UTILITY COMMITTEE
The Utility Committee Meeting was held on September 28, 2015 at 5:03 p.m. with
Chairman Hutchison presiding. Members present were Mr. Cole, Mr. Neil, Mr. Blakeman, and
Ms. Stewart. Members of Council present were Mr. Hosfelt (arrived at 5:16 p.m.; departed at 5:24 p.m.;
and returned at 5:39 p.m.), and Mr. Slavin.
AGENDA ADDITIONS/DELETIONS
Mr. Neil moved for approval of the agenda, seconded by Mr. Blakeman and unanimously
carried.
Critical Repair - VanSant Exhaust Plenum
Mr. Scott Koenig, City Manager, stated that due to time constraints, this item had been placed on the
City Council agenda for the meeting being held later in the evening.
Mr. Koenig informed members that the VanSant Frame 6B Combustion Turbine (CT) exhaust
plenum, transition piece, and expansion joint have degraded over time and now require replacement.
Since beginning commercial operation in 1991, there have been occasional upkeep repairs made to
the referenced components with the latest repairs in the fall of 2014 and the summer of 2015. He
stated that an Infrared Thermograph Inspection Report was completed by Compliance
Environmental, Inc. Mr. Koenig advised that the depleted condition of the plenum wall(s) allows
heat infusion into the CT compartment which has started to cause damage to the ignitors, flame
scanners, and other associated control wiring instruments, which could affect the unit reliability and
availability. He explained that the exhaust system was not properly ventilating the heat generated
from the CT due to the age of the parts.
Mr. Koenig indicated that the repair would be completed during the current outage. He stated that
staff was requesting expedited processing of this request to allow North American Energy Services
(NAES) to complete the necessary engineering, obtain contractor quotes, and make the contractor
selection to manufacture the new plenum and install the plenum, transition piece and expansion joint
before the 2016/2017 PJM Capacity Performance operational period, which begins in the spring.
Mr. Koenig stated that a Request for Proposal (RFP) package was advertised by NAES and NAES
is currently reviewing the submissions. He explained that this work is an Original Equipment
Manufacturers specialty item with a limited number of organizations familiar enough with
the installation requirements to support the City’s desired replacement schedule. The estimate
received for the above work is from the original manufacturer of the plenum for VanSant, Braden
Manufacturing, LLC. The preliminary estimate from Braden, in the amount of $430,000, did
not include replacement of the transition piece or expansion joint. In addition to
Braden Manufacturing, LLC, NAES will obtain at least three (3) proposals from other contractors
familiar with this work, Consolidated Fabricators and Universal Acoustics and Emissions
Technology. NAES will continue to research additional resources capable of performing this work
to ensure the best capable contractor and cost estimate(s). NAES would like approval and
permission to proceed and select the highest evaluated bidder to immediately award the project once
the bids are received and reviewed. This request is only to promulgate the expeditious manufacture
of the material component parts necessary to perform these repairs, without further review by City
Página 2
UTILITY COMMITTEE MEETING OF SEPTEMBER 28, 2015 PAGE 2
Council. The proposals will be evaluated using cost, experience, and completeness of bid to select
the contractor who will perform the work, and all work must be completed prior to June 1, 2016.
Mr. Koenig reminded members that staff was requesting authorization from City Council during
their meeting being held later in the evening because of the time line associated with the repair;
however, staff felt that it was important to advise members of the Utility Committee as well.
Mr. Koenig advised that, to fund this repair, the City would delay the inspection and repairs on the
Unit 3 cooling water line, noting that these critical repairs at VanSant were more important in the
hierarchy of the utility than the cooling water lines. He explained that the Unit 3 cooling water line
repair was budgeted at $469,000, and that money would be moved to fund the proposed replacement
of the parts associated with the CT unit, which was currently estimated at $430,000.
Staff recommended delaying inspection and repairs on the Unit 3 cooling water line and funding the
critical repairs needed on the VanSant exhaust plenum, transition piece, and expansion joint in
accordance with the completion date of June 1, 2016.
Mr. Neil asked how critical the Unit 3 cooling water line problem would be if it were deferred,
questioning whether it would need emergency repair in the future. Responding, Mr. Koenig
explained that the inspection and repairs for the Unit 3 cooling water line was routine maintenance,
and staff would keep an eye on it. He stated that the VanSant exhaust plenum was a higher priority
and, as the City finishes projects this fiscal year, staff will determine whether there is additional
money for the Unit 3 inspection and repairs. Mr. Koenig noted that if there is not funding available
this fiscal year, the Unit 3 inspection and repairs would be re-budgeted next fiscal year.
In response to Mr. Blakeman, Mr. Koenig stated that he did not think that there was evidence that
this problem was as critical in the fall of 2014. He explained that some repairs were completed in
the fall of 2014 and then there were additional problems in the spring of 2015. Mr. Koenig informed
members that this was becoming more important because the utility is changing. Generation assets
are changing and, in the past four (4) years, the City had gone from a more passive running of the
system to a more active engagement of running the system. He noted that the City now wants these
generation assets to run whenever the economics say that the City can get a return on its investments
and the City is actively pushing both The Energy Authority (TEA) and NAES to ensure this happens.
Mr. Koenig advised that the VanSant repairs were on the horizon but, as the market has changed and
this unit has deteriorated more since last fall, these replacements and repairs have become more
critical. He explained that there used to be a little more float in whether entities could produce or
not, noting that if an entity had an issue and could not, they probably would not get penalized as long
as another entity could pick up the loss; however, as the market tightens up and the new capacity
requirements come in to play, if entities cannot run, they will get penalized.
Mr. Blakeman noted that the $430,000 estimate did not include the additional equipment that may
be required and asked what the estimated cost of the additional equipment would be. Responding,
Mr. Koenig stated that the $430,000 included the plenum, the transition piece, and the expansion
joints; however, it did not include any type of instrumentation that may have been damaged by heat,
since staff did not currently know whether there was additional damage.
Página 3
UTILITY COMMITTEE MEETING OF SEPTEMBER 28, 2015 PAGE 3
In response to Mr. Blakeman, Mr. Koeing stated that the additional equipment had not yet been
priced and it was his understanding that, in some cases, the different contractors may be able to
provide all three (3) components.
Mr. Blakeman, referring to the seven (7) repairs listed as critical on the Infrared Thermography
Inspection, asked if there were any previous indications that there were that many critical problems
or if they were only detected with this inspection. Responding, Mr. Harry Maloney, Electric
Director, explained that the steel inside the exhaust stack was corroding and very thin, so it was
patched as best as possible and put back together. After that, the unit did not run very much and the
problem was not realized until after staff started testing for the newly installed water injection
system. He stated that staff ran the unit a lot and then, all of a sudden, it would not start, which they
realized was because the flame scanner was melted. After the water injection was installed and the
unit ran more frequently, they realized the patches were not holding. Mr. Maloney stated that staff
did some other minor repairs, patched more holes, and moved some things around this past August
and September.
In response to Mr. Blakeman, Mr. Maloney stated that he did not know which problems were
category one (1) or category two (2); however, he did know that it was leaking and they could not
start the unit. He explained that it is a fast start unit; however, repairs are necessary to enable it to
start within ten or fifteen minutes instead of an hour.
Mr. Blakeman agreed that the problem is critical and has to be fixed; however, he expressed concern
with using the money for the cooling water line repairs for Unit 3. Responding to Mr. Blakeman,
Mr. Maloney stated that the cooling water line pipe was a 40-year old, four (4) to six (6) foot, cast-
iron pipe that was in the ground and corroding inside. Mr. Maloney stated that he had briefly
discussed this problem with Mr. Vince Scire, former Plant Manager, McKee Run Generating Station,
before he left, and Mr. Scire indicated that this type of problem was typically addressed by putting
in a liner.
Mr. Blakeman informed members that this pipe had leaked before at the joints. Referring to Page
194 of the FY 2015/2016 Budget, he informed members that the Capital Investments Plan (CIP)
stated that “delaying this project beyond 2016 will increase the risk of a failure causing extended unit
outage to repair or replace the failed pipe, as well as incurring water spillage to the surrounding
ground. Additional budget dollars will need to be allocated to make the repairs of the failed piping.”
Mr. Blakeman noted that no estimates were provided for these additional costs. He shared his
concern that if the City cannot cool the water, the unit cannot be run and the City would be taking
out 102 megawatts (MW). He asked if there was another funding source for the repairs to the
VanSant exhaust plenum that would not delay the Unit 3 cooling water line repairs.
In response to Mr. Blakeman, Mr. Maloney stated that he would revisit the CIP and talk to
Mrs. Donna Mitchell, Controller/Treasurer, about other funding sources and the possibility of
postponing or moving a less critical project. He indicated that it was mainly a matter of accelerating
the repairs, noting that the money would eventually be in a future budget; however, the City was
running out of time.
Página 4
UTILITY COMMITTEE MEETING OF SEPTEMBER 28, 2015 PAGE 4
Mr. Blakeman noted that, years ago, the City had scuba divers go through this pipe and it is a huge
pipe with a lot of water. He stated that if this pipe leaks, it will flood the field out and shut the unit
down.
Mr. Hutchison asked if, in the future, the City would be required to use the VanSant plant more often
than not. Responding, Mr. Maloney stated that the way Dover is situated, the CT should be a quick
start unit since it gets dispatched first for unusual circumstances. He explained that staff typically
knows a day ahead of time when the steam unit will need to run. Mr. Maloney reiterated that the CT
is dispatched for emergencies and, although it currently takes an hour to start, it should be a ten-
minute start, which he is working on changing. He stated that it is important to be able to get the CT
on line in a hurry because it might end up with more run hours than the 100 MW unit and noted that
it has to be set up correctly so it does not burn itself out, which is currently happening with the
equipment.
Mr. Blakeman noted that although PJM does not call the VanSant Unit on that often, it must be
available when called upon. In response, Mr. Maloney stated that the use of the VanSant Unit has
increased because the City is able to get 500 dekatherms (Dth) of gas for it, which is more efficient
to dispatch because the City does not get enough gas to run the 100 MW unit.
Responding to Mr. Hutchison, Mr. Koenig reiterated that Staff recommended delaying inspection
and repairs on the Unit 3 cooling water line and funding the critical repairs needed on the VanSant
exhaust plenum, transition piece, and expansion joint in accordance with the completion date of
June 1, 2016. He stated that if the Committee endorses Staff’s recommendation, Staff would then
look at the CIP again, in case the re-prioritization of Unit 3 is necessary, and bring forward any
changes that need to be made.
In response to Mr. Hutchison, Mr. Koenig explained that the City’s contract with Calpine is for
capacity, and does not take effect until the City takes Units 1 and 2 offline.
Mr. Neil moved to recommend delaying the inspection and repairs on the Unit 3 cooling water
line and funding the critical repairs needed on the VanSant exhaust plenum, transition piece,
and expansion joint in accordance with the completion date of June 1, 2016, as recommended
by Staff. The motion was seconded by Mr. Blakeman and unanimously carried.
Review of PJM Capacity Performance Auction
Mrs. Donna Mitchell, Controller/Treasurer, reviewed a presentation entitled “The Energy Authority -
Review of PJM Capacity Performance Auction,” explaining that PJM had entered into a new
capacity performance market and the effect on the City. She noted that this presentation would also
be reviewed during the review of financial policies during the Legislative, Finance, and
Administration Committee meeting scheduled for later in the evening.
Responding to Mr. Blakeman, Mrs. Mitchell stated that the contract between the City and Calpine
would take effect when Units 1 and 2 are removed from the capacity list, which would take place
in May 2017 which would be Power Year 2017/2018.
Página 5
UTILITY COMMITTEE MEETING OF SEPTEMBER 28, 2015 PAGE 5
Referring to Page 4, Mrs. Mitchell noted that the PJM Capacity Market Overview was very technical
and explained that the City bids its capacity in and also purchases capacity through PJM, so there
is a price differential between what goes in and out.
Mrs. Mitchell stated that PJM’s new capacity performance product was implemented for Delivery
Year (DY) 2018/2019. She noted that there was a partial implementation with partial-market
“transition auctions” for DY 2016/2017 and DY 2017/2018, and the City had already been through
those transitional auctions.
Mr. Blakeman asked what the likelihood was of the City continuing to maintain a profit margin. In
response, Mrs. Mitchell explained that the City would continue to maintain a profit as long as the
City does not get penalties. She stated that Staff was redoing the City’s five-year forecast to include
these new prices and all of these changes.
Referring to Page 6, Mrs. Mitchell reminded members that the City incurred a penalty of $562,994
for generation short-falls during February 2015 peak hours and the North American Energy Services
(NAES) performance incentive was decreased by $423,000 as a result of this inability to run.
Mr. Blakeman noted that the Comprehensive Annual Financial Report (CAFR) listed 191 MW of
operating capacity and questioned why the City was only using 175 MW. He stated that the CAFR
changed in 2007 from 175 to 191. Responding, Mrs. Mitchell indicated that she would look into this
matter.
Referring to Page 7, Mrs. Mitchell explained that the way a transitional auction works, if the City
does not clear the auction, the old rules still apply. She stated that the City would be subject to the
new rules in DY 2018/2019.
Mr. Blakeman, referring to Page 9, asked what a stop-loss limit was and how it would kick-in. In
response, Mr. Harry Maloney, Electric Director, explained that PJM does not want to drive people
that far into bankruptcy so they put a stop in place and once an entity reaches the limit, PJM will stop
penalizing. He stated that it is a dollar cap.
Mrs. Mitchell reviewed the Capacity Revenue at Risk for Dover’s 145 MW of Generation
(DY 2018/19) on Page 10. She reminded members that in February of 2015 the City had a short-fall
of 11.2 megawatts which resulted in a $562,000 penalty; however, under the new rules, the City
would have a penalty between $5M and $7.5M for the same short-fall.
Mrs. Mitchell reviewed the list of Pro-Active Mitigation Measures on Page 11 and noted that the
Calpine plant had put some restrictions on the gas line and made it more difficult for other generators
to get gas. She informed members that the City had received good cooperation from both Eastern
Shore and Chesapeake Utilities in getting gas and they will have what the City needs to start the
units. Mrs. Mitchell stated that the City was very close to completing the transition of McKee 3 to
oil but gas would still be needed to start the burners. She indicated that it might be a little higher
cost, since the City might have to pay a premium for that gas but it would be much cheaper than what
the City would pay in penalties.
Página 6
UTILITY COMMITTEE MEETING OF SEPTEMBER 28, 2015 PAGE 6
Mr. Hutchison noted that the City was training staff and asked if staff was also reaching out to the
City’s larger customers to educate them on better ways for operation. Responding, Mrs. Mitchell
stated that staff was talking to the City’s large customers about their load profiles to determine how
the City can help. She indicated that staff was examining many different ideas to determine how
these customers and the City can help each other.
In response to Mr. Blakeman’s question regarding the possibilities of expanding the Rate
Stabilization Reserve account to lower the impact to electric customers, Mrs. Mitchell advised
members that currently the reserve is a minimum of 3% and a maximum of 10%, and her
recommendation was for a minimum of 10% and a maximum of 20%. She explained that the City
usually gets income when generating, and as the City gets favorability and power supply the City
puts the money in the Rate Stabilization Reserve. Mrs. Mitchell stated that she would never
recommend a rate increase to fund a reserve.
Referring to Page 8, Ms. Stewart asked if the enhanced demand-side participation was from the City
of Dover or the entire DPL South Zone. Responding, Mrs. Mitchell advised that the graph indicated
when this change in the PJM regulations was implemented, noting her belief that it was the enhanced
demand-side participation for the whole PJM grid.
In response to Ms. Stewart, Mrs. Mitchell stated that the City does not currently do anything for
demand response. Mr. Maloney confirmed that the City does not do anything directly; however,
through the Delaware Municipal Electric Corporation (DMEC) and CPower, the City’s customers
can participate in the PJM demand response. He indicated that a few of the City’s large industrial
customers participate in this program. Mr. Maloney explained that these customers will receive a
phone call alert that they have a specific amount of time to reduce their load and then they share in
the savings.
Mr. Blakeman asked if the City participates in the demand response program through the City’s rate
structure. Responding, Mr. Maloney stated that the City does not participate and is not involved in
any of the money or the transactions. He advised that the customer releases the information and the
City gives the information to the contractor, CPower.
Mr. Scott Koenig, City Manager, stated that Staff brought this forward as an informational item and
to support some of the recommended changes to the financial policy, which will be discussed during
the Legislative, Finance, and Administration Committee meeting scheduled for later in the evening.
He reiterated that the utility was changing and getting more complicated, which was leading the City
to a more active and participatory management of the electric system, including the City’s energy
supply, its larger customers, being able to participate in the energy efficiency programs, how to
replace capacity, behind the meter renewables, net metering, etc. Mr. Koenig stated that all of these
things are playing a role as the City moves forward and these things equate to and influence either
the City’s power supply costs or the final electric rate costs to the City’s customers.
Mr. Koenig stated that as the PJM grid and the electric utility become more complicated, timing is
a big issue. For the City to be able to compete, the City has to be able to bring its units up quickly,
know the status of the units, be able to maintain the units, have adequate reserves to pay potential
penalties, etc.
Página 7
UTILITY COMMITTEE MEETING OF SEPTEMBER 28, 2015 PAGE 7
Mr. Blakeman moved for adjournment, seconded by Mr. Neil and unanimously carried.
Meeting adjourned at 5:40 p.m.