Página 1
SPECIAL COUNCIL MEETING - BUDGET REVIEW
AGENDA
MAY 24, 2016 - 6:00 P.M.
CITY HALL COUNCIL CHAMBERS, 15 LOOCKERMAN PLAZA, DOVER, DELAWARE
PUBLIC COMMENTS ARE WELCOMED ON ANY ITEM AND WILL BE PERMITTED AT APPROPRIATE TIMES. WHEN
POSSIBLE, PLEASE NOTIFY THE CITY CLERK (736-7008 OR E-MAIL AT CITYCLERK@DOVER.DE.US) SHOULD
YOU WISH TO BE RECOGNIZED.
AGENDA ADDITIONS/DELETIONS
MAY 24, 2016 - 6:00 P.M.
1. INTRODUCTION AND PRESENTATION
2. SUMMARIES OF FUND REVENUE AND EXPENSES
BREAK. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . (7:15 - 7:30 P.M.)
3. PERSONNEL INFORMATION
4. REVENUE REVIEW
5. RECESS BY 9:00 P.M.
MAY 25, 2016 - 6:00 P.M. (CONTINUATION OF RECESSED MEETING OF MAY 24, 2016)
AGENDA ADDITIONS/DELETIONS
1. DIVISION BUDGET REVIEWS
BREAK. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . (7:15 - 7:30 P.M.)
2. REVIEW OF CAPITAL INVESTMENT PLAN (CIP)
3. RECESS BY 9:00 P.M.
MAY 26, 2016 - 6:00 P.M. (CONTINUATION OF RECESSED MEETING OF MAY 25, 2016)
AGENDA ADDITIONS/DELETIONS
1. FINANCIAL FORECAST BY FUND.. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . (6:00 - 6:45 P.M.)
A. GENERAL FUND
B. WATER/WASTEWATER FUND
C. ELECTRIC FUND
Página 2
SPECIAL COUNCIL - BUDGET REVIEW AGENDA - 2016 Page 2
MAY 26, 2016 - 6:00 P.M. (CONTINUATION OF RECESSED MEETING OF MAY 25, 2016)(CONTINUED)
2. CITY POLICIES AND PROCEDURES. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . (6:45 - 7:15 P.M.)
A. FINANCIAL POLICY
B. BUDGET AMENDMENT PROCEDURE
BREAK. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . (7:15 - 7:30 P.M.)
3. QUESTIONS, ANSWERS, OPEN DISCUSSION, AND MARKUP. . . . . . . . . . . . . . . . . . . . . . . . . . 7:30 P.M.
4. RECESS BY 8:00 P.M.
JUNE 1, 2016 - 6:00 P.M. (CONTINUATION OF RECESSED MEETING OF MAY 26, 2016, IF NECESSARY)
AGENDA ADDITIONS/DELETIONS
1. QUESTIONS, ANSWERS, OPEN DISCUSSION, AND MARKUP. . . . . . . . . . . . . . . . . . . . . . . . . . 6:00 P.M.
BREAK. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . (7:15 - 7:30 P.M.)
2. ADJOURNMENT BY 9:00 P.M.
(ALL OF THE ABOVE TIMES ARE ESTIMATED AND ARE SUBJECT TO CHANGE BASED ON LENGTH OF
DISCUSSION)
EXECUTIVE SESSION PURSUANT TO:
29 DEL. C. §10004(B)(2) - PRELIMINARY DISCUSSIONS ON SITE ACQUISITIONS FOR ANY PUBLICLY FUNDED CAPITAL
IMPROVEMENTS, OR SALES OR LEASES OF REAL PROPERTY;
29 DEL. C. §10004(B)(4) - STRATEGY SESSIONS, INCLUDING THOSE INVOLVING LEGAL ADVICE OR OPINION FROM
AN ATTORNEY-AT-LAW, WITH RESPECT TO COLLECTIVE BARGAINING OR PENDING OR POTENTIAL LITIGATION,
BUT ONLY WHEN AN OPEN MEETING WOULD HAVE AN ADVERSE EFFECT ON THE BARGAINING OR LITIGATION
POSITION OF THE PUBLIC BODY;
29 DEL. C. §10004(B)(6) - DISCUSSION OF THE CONTENT OF DOCUMENTS, EXCLUDED FROM THE DEFINITION OF
"PUBLIC RECORD" IN §10002 OF THIS TITLE WHERE SUCH DISCUSSION MAY DISCLOSE THE CONTENTS OF SUCH
DOCUMENTS;
29 DEL. C. §10004(B)(9) - PERSONNEL MATTERS IN WHICH THE NAMES, COMPETENCY AND ABILITIES OF
INDIVIDUAL EMPLOYEES ARE DISCUSSED, UNLESS THE EMPLOYEE REQUESTS THAT SUCH A MEETING BE OPEN
/TM
S:\AGENDAS-MINUTES-PACKETS-PRESENTATIONS-ATT&EXH\COUNCIL-AGENDAS\2016\05-24-2016 SPECIAL COUNCIL-BUDGET REVIEW.WPD
THE AGENDA ITEMS AS LISTED MAY NOT BE CONSIDERED IN SEQUENCE. PURSUANT TO 29 DEL. C. §10004(E)(2), THIS
AGENDA IS SUBJECT TO CHANGE TO INCLUDE THE ADDITION OR THE DELETION OF ITEMS, INCLUDING EXECUTIVE
SESSIONS, WHICH ARISE AT THE TIME OF THE MEETING.
Página 4
FY 2016 – 2017 Draft Budget for the City of Dover, Delaware
Table of Contents
CITY OF DOVER, DELAWARE
FY 2016 – 2017 DRAFT BUDGET
WITH 2017 – 2021 CAPITAL INVESTMENT PLANS
SECTION PAGE
INTRODUCTORY SECTION
City Manager’s Letter............................... 3
City of Dover Vision................................ 5
City Organizational Chart........................... 6
BUDGET SUMMARY
Highlights of Overall Budget....................... 7
Rate & Fee Trends............................. 22
FUND SUMMARIES & RESERVE ACCOUNTS
All Funds Summary................................... 24
General Fund
Cash Receipt Summary........................... 25
Expense Summary................................ 26
Governmental Capital Projects....................... 31
Water/Wastewater.................................... 32
Electric............................................ 37
Charter Article IV, Sec44 & Financial Policies
Sec. 44 – Annual Budget............................. 43
Financial Policies.................................. 44
Budget Administration Guidelines.................... 53
PERSONNEL INFORMATION
Personnel Table..................................... 57
Personnel Cost Summary.............................. 58
Overtime Trends
FY14 through FY17 Comparison................... 59
FIVE YEAR FORECAST SUMMARY
General Fund........................................ 62
Water/Wastewater Fund............................... 72
Electric Revenue Fund............................... 85
i
For online viewing, click on a topic to go to that page
Página 5
FY 2016 – 2017 Draft Budget for the City of Dover, Delaware
Table of Contents
CAPITAL INVESTMENT PLAN
Total City Summary.................................. 101
General
Funding Source Summary FY17-FY21 ................... 104
Projects by Department FY17-FY21 ................... 105
Water/Wastewater (Water/WW)
Funding Source Summary FY17-FY21 ................... 120
Projects by Department FY17-FY21 ................... 121
Electric
Funding Source Summary FY17-FY21 ................... 141
Projects by Department FY17-FY21 ................... 142
Vehicle Replacements
General FY17-FY21 .................................. 184
Water/WW FY17-FY21 ................................. 189
Electric FY17-FY21 ................................. 192
DEBT SERVICE
Debt Limit
Legal Debt Margin .................................. 195
Debt Service Schedules
Projected Debt Service ............................. 196
Water/WW Revenue Bonds ............................. 197
Electric Revenue Fund .............................. 199
GENERAL
Budget Review FY 2016-2017.......................... 202
FY 2017 Annual Operating Budget
Mayor............................................... 234
Economic Development........................... 235
City Council........................................ 237
City Manager........................................ 239
City Clerk.......................................... 241
Customer Services................................... 243
Finance............................................. 245
Procurement & Inventory........................ 246
Fire................................................ 248
Human Resources..................................... 250
Information Technology.............................. 252
Parks & Recreation.................................. 254
Library............................................. 256
Police.............................................. 258
ii
For online viewing, click on a topic to go to that page
Página 6
FY 2016 – 2017 Draft Budget for the City of Dover, Delaware
Table of Contents
GENERAL - CONTINUED PAGE
Tax Assessor........................................ 261
Planning & Inspections
Planning/CDBG....................................... 263
Life Safety......................................... 264
Code Enforcement.................................... 265
Inspections......................................... 266
Public Works
Administration...................................... 268
Public Works Engineering............................ 269
Facilities Management............................... 270
Fleet Maintenance................................... 271
Grounds............................................. 272
Sanitation.......................................... 273
Street.............................................. 274
PUBLIC UTILITIES
Water/Wastewater Budget Review ........................ 277
Water/WW Engineering................................ 283
Water Management.................................... 284
Wastewater Management............................... 285
Water Treatment Plant............................... 286
Electric Budget Review ................................ 288
Power Plant Operations.............................. 298
Power Supply........................................ 299
Transmission & Distribution......................... 300
Electric Engineering................................ 301
Administration...................................... 302
Meter Reading....................................... 303
System Operations................................... 304
OTHER FUNDS
Municipal Street Aid................................ 306
Electric Red Light Program.......................... 307
Realty Transfer Tax................................. 308
Workers Compensation................................ 309
Community Transportation............................ 310
Library Grants...................................... 311
Police Grants....................................... 312
Community Development Block Grant (CDBG)............ 313
Substance Abuse Prevention Program.................. 314
iii
For online viewing, click on a topic to go to that page
Página 7
CITY MANAGER’S LETTER
CITY OF DOVER VISION
CITY ORGANIZATIONAL CHART
Página 11
FY 2017 DRAFT ANNUAL OPERATING BUDGET – DOVER, DELAWARE
VISION
The City of Dover is a place where people want to live! Through the team effort of its elected
officials, employees, and citizens, Dover is a clean and safe community, with a future of
balanced growth and opportunity where all citizens are heard, enjoy a high quality of life, and
diversity is valued.
5
Página 12
FY 2017 ANNUAL OPERATING BUDGET – DOVER, DELAWARE
CITY OF DOVER
FISCAL YEAR 2017 ORGANIZATION CHART
CITIZENS OF DOVER
MAYOR & COUNCIL
ECONOMIC DEVELOPMENT MAYOR COUNCIL
POLICE CITY SOLICITOR
PLANNING & COMMUNITY
CITY MANAGER CITY CLERK FINANCE FIRE TAX ASSESSOR
ENHANCEMENT SERVICES
ASSISTANT CITY MANAGER LIFE SAFETY
LIBRARY PROCUREMENT/INVENTORY
LIBRARY CUSTOMER SERVICES CODE ENFORCEMENT
CUSTOMER SERVICE INSPECTIONS/
PUBLIC WORKS PERMITTING
METER READING
PUBLIC WORKS
PLANNING
ADMINISTRATION INFORMATION
TECHNOLOGY
ENGINEERING & INSPECTIONS
COMMUNITY
HUMAN RESOURCES DEVELOPMENT
GROUNDS
ELECTRIC
SANITATION PARKS & RECREATION
ELECTRIC
STREETS ADMINISTRATION
FACILITIES MANAGEMENT
SYSTEM OPERATIONS
FLEET MAINTENANCE
WATER/WASTEWATER ELECTRIC ENGINEERING
ENGINEERING
WASTEWATER
MANAGEMENT ELECTRIC TRANSMISSION &
DISTRIBUTION
WATER MANAGEMENT
WATER TREATMENT
6
Página 13
City of Dover
Fiscal Year 2017
Proposed Budget
Highlights of Overall Budget
May 24, 2016
7
Página 14
General Fund Services
Police*Fire*Life Safety*Code Enforcement*Planning
Public Inspections*Library*Recreation*Streets
Sanitation*Grounds*Facilities Management
Fleet Maintenance*Public Works Administration
Public Works Engineering*Mayor*Customer Service
Procurement & Inventory*City Council*City Manager
City Clerk*Economic Development*Tax Assessor
Finance*Information Technology*Human Resources
8
Página 15
Water/Wastewater Utility
Engineering & Inspection
Water Distribution & Well Maintenance
Wastewater Distribution & Pump Station Maintenance
Water Treatment Plant
Capital Project Management
Electric Utility
Administration
Engineering & Inspection
Transmission & Distribution Maintenance
System Operations
Metering
Capital Project Management
9
Página 16
Policy Compliance
• Revenue Policy
• #7 – The City will project current revenues on a conservative basis so the actual revenues will
consistently meet or exceed budgeted revenues. Revenues greater or less than the original
budget will flow through to the audited Ending Budget Balance.
• Expenditure Policy
• #2 – The City will adopt a balanced budget, by fund, for all funds maintained by the City, in
which total anticipated revenues must equal or exceed the budgeted expenditures. The
Beginning Budget Balance will not be considered a revenue source.
• Budget Balance Policy – General Fund
• #1 – The City will strive to maintain a minimum Budget Balance, of at least 8% and no greater
than 12% of the current year operating revenues for the General Fund, excluding the carry
forward balance. (8.33% = 1 month, 12% = 45 days)
• Budget Balance Policy – Water & Wastewater Fund
• #1 – The City will strive to maintain a minimum Budget Balance, of at least 8% and no greater
than 17% of the current year operating revenues for the Water/Wastewater, excluding the
carry forward balance. (17% = 2 months)
• Budget Balance Policy – Electric Fund
• #1 – The City will strive to maintain a minimum Budget Balance, of at least 12% of the current
year operating revenues for the Electric Fund, excluding the carry forward balance.
10
Página 17
Policy Compliance (continued)
General Water Wastewater Water/Wastewater Electric
Fund Utility Utility Fund Fund
Revenus $42,261,300 $6,459,700 $9,007,500 $15,467,200 $81,259,600
Expenses (42,261,300) (5,826,900) (8,408,200) (14,235,100) (79,123,800)
Surplus/(Deficit) $0 $632,800 $599,300 $1,232,100 $2,135,800
Ending Budget Balance $4,493,900 $1,181,500 $1,280,500 $2,462,000 $15,218,200
% of Revenue 10.6% 18.3% 14.2% 15.9% 18.7%
Policy Requirement % 8% - 12% 8% - 17% Min. 12%
Beginning Budget Balance $4,493,900 $548,700 $681,200 $1,229,900 $13,082,400
11
Página 18
City Revenue – Rates & Fees
• General Fund
No proposed changes
• Water/Wastewater Fund
No proposed changes
• Electric Fund
No proposed fee changes
12
Página 19
All Major Operating Funds
Personnel
• Pay increases in accordance with collective bargaining agreements
• Proposed increase for Non-Bargaining employees 2.5%
• Total Headcount – Reduced 2 full-time with outsourcing janitors and added 2 part-time
relief fire dispatchers with no budget impact
• General Fund was reduced ($48,900) for 1 full-time position for a Key Accounts position
that is transferred to the Electric Fund $64,100 in this budget. The job description was
revised to follow the recommendation of the American Public Power Association (APPA),
the position was originally budgeted at Customer Service Representative.
• General Fund was reduced ($19,100) for 1 part-time position in Finance for budget
preparation.
• Electric Fund added 1 part-time Engineering intern $10,600.
• (See Personnel Section and individual Division pages for details)
• Personnel Cost Increases – $1,176,700 over the original FY16 budget
• Salary and wages increased $1,021,100
• Employer’s benefit cost increased $155,600 as follows
• FICA $119,300
• Health Care Premiums $260,400
• Worker’s Compensation $213,300 (Phasing in new rates over 3 years, 2 nd year)
• Pension $56,100 (The affects of the actuarial valuation by Fund was presented earlier in the year)
• Other Post Employment Benefits (retirement medical) ($493,500) (Actuarial valuation presented earlier)
• Aggregates all vacation sell-back, retirement payouts, and education assistance in Other
Employment Expenses
13
Página 20
General Fund Revenues
• Revenue increase over FY16 original Budget – $934,200 or 2.3%
• Major increases/(decreases) affecting revenues
• Transfer Taxes – $332,700 (average last 3 years)
• Extra Duty Grant Revenue – $184,200
• Planning/Inspections Permits & Fees – $225,800
• Municipal Street Aid – $108,900
• Fines & Police Revenue – $61,000
• Investment Income - $55,000
• Library Revenues & County Reciprocal Borrowing – ($137,400)
• Verizon Grant – ($50,000)
14
Página 21
General Fund Expenditures
• Expense increase over FY16 Original Budget – $1,060,000 or 2.6%
• Major increases/(decreases) affecting expenditures (+/- 5.0%)
(see Division summaries for details)
• Council – $26,000
• City Clerk – $28,900
• Library - $125,000
• Law Enforcement – $932,600
• Police Extra Duty – $181,200
• Streets - $489,000
• Sanitation – ($125,100)
• City Manager – ($66,800)
• Public Works Administration – $53,200
• Facilities Maintenance – ($100,400)
• Public Works Engineering – $25,600
• Retiree Health Care Premiums – $144,100
• Other Employment Expenses – ($127,900) *
• Transfer to the Capital Project Fund – ($766,000)
• Appropriation to Police Pension Fund - $100,000
15
Página 22
FY16 Adopted Budget - General Fund Program Receipts & Expenditures
Outlays and Receipts (Incl. Property Taxes) for Governmental Activities
Receipts Outlays
$25
$20
$15
Millions
$10
$5
$0
General Public Safety Public Works Library & Community & Central Financial Other Post
Government Recreation Economic Services Administration Employment
Development Benefits
For the Year Ended June 30, 2016
16
Página 23
FY17 Proposed Budget - General Fund Program Receipts & Expenditures
17
Página 24
Property Taxes
CITY OF DOVER
PROPERTY ASSESSMENT PROJECTION
2016 BASE YEAR
TOTAL ASSESSED VALUE AS OF DECEMBER 31, 2015 $3,075,403,900
Supplemental Billing (April) & new construction estimated to be complete by June Estimate Only 15,000,000
Annual Appeals (Exemption Requests that have been submitted) Estimate Only (9,200,000)
(Habitat for Humanity; Whatcoat; open space - estimate based on previous year)
Senior Citizen/Disability Exemption(approx 425 approved; revenue loss $89,100) Estimate Only (22,000,000)
TAXABLE ASSESSED VALUE $3,059,203,900
CITY OF DOVER
PROJECTED PROPERTY TAX RECEIPTS
7/01/16 - 6/30/17
Rate
$0.4050
Using a tax rate of $0.4050 per $100 of assessment, the estimated gross 7/01/16 billing will be $12,389,800
Penalties 70,000
Estimated Quarterly Billing 22,000
PROJECTED PROPERTY TAX RECEIPT SUBTOTAL $12,481,800
BID 1 - Using a rate of $0.0644 per $100 of assessment, the estimated gross 7/01/16 billing will be $24,700
BID 2 - Using a rate of $0.0325 per $100 of assessment, the estimated gross 7/01/16 billing will be 19,700
BID 3 - Using a rate of $0.0128 per $100 of assessment, the estimated gross 7/01/16 billing will be 4,600
PROJECTED BID RECEIPT TOTAL $49,000
Pay In Lieu of Taxes
Luther Towers $27,200; State of Delaware $312,200; $402,100
Delaware State Housing Authority $5,200; Dover Housing Authority $50,000
Walker Woods $7,500; Farmland Roll Back Taxes
PROJECTED PROPERTY TAX RECEIPTS FOR FY 2017 $12,932,900
$0.01 of tax rate equates to: $305,920.39
18
Página 25
City of Dover, Delaware
Computation of Legal Debt Margin
General Obligation Bonds
(amounts expressed in thousands)
Estimated Estimated
2017 2016 2015 2014 2013 2012 2011 2010
Debt Limit $ 152,960 $ 152,516 $ 158,485 $ 157,995 $ 159,075 $ 158,465 $ 156,832 $ 145,351
Net (Taxable) Assessed Value on Books 3,059,204 3,050,322 3,169,707 3,159,894 3,181,496 3,169,308 3,136,639 2,907,011
Total net debt applicable to limit 7,926 8,587 7,337 4,050 4,479 1,550 1,820 2,080
Legal Debt Margin $ 143,929 $ 151,148 $ 153,945 $ 154,596 $ 156,915 $ 155,012 $ 143,271
Total Net Debt applicable to limit
as a percentage of debt limit 5.18% 5.63% 4.63% 2.56% 2.82% 0.98% 1.00% 1.44%
Legal Debt Margin Calculation for Fiscal Year 2017
Net (Taxable) Assessed Value on Books $ 3,059,204 $ 3,050,322 $ 3,169,707 $ 3,159,894 $ 3,181,496 $ 3,169,308
Debt Limit - 5 Percent of Total Assessed Value $ 152,960 $ 152,516 $ 158,485 $ 157,995 $ 159,075 $ 158,465
DEBT
(For which the City's full faith and credit has been pledged)
Gross Bonded Debt 7,926 8,587 7,337 4,050 4,479 1,550
LEGAL DEBT MARGIN $ 145,034 $ 143,929 $ 151,148 $ 153,945 $ 154,596 $ 156,915
IMPORTANT NOTE: The Total Net Debt applicable to the debt limit includes the remaining Series 2014 A & B Bonds (PNC) and the 2012 Bonds (PNC)
Source: City of Dover Financial Reports, City of Dover Charter, Section 50(b), and Tax Assessor's Office
New Bonds without referendum cannot exceed 1/4 of 1% of taxable assessed value and shall not cause the total aggregate principal outstanding at any one time to exceed 1% of
total taxable assessment for a general tax at the time of issue or $7,648,000 based on the 2017 Estimate.
19
Página 26
Water/Wastewater Fund
• Revenue decrease over FY16 Budget – ($260,500) or -1.7%
• Expenses decrease over FY16 Budget – ($1,015,900) or -6.7%
• Major increases/(decreases) affecting revenues
• Water Service fees – ($400,000) (related to Garrison Energy Center)
• Wastewater Service Fees – $72,000
• Wastewater Treatment Fees – ($26,500)
• Groundwater Inflow Adjustment – $73,700
• Major increases/(decreases) affecting expenses
• Water Treatment Plant – ($182,600) electricity and chemicals attributed
Garrison Energy Center
• Internal Service allocations – $161,100
• Debt Service – $95,100 SRF Loans
• Transfer to Contingency Reserves - $138,000 to comply with policy
• Capital Project Appropriations – ($1,300,000)
• Bond financing several projects
20
Página 27
Electric Fund
• Revenue decrease over original FY16 Budget – $2,276,400) or -2.7%
• Expense decrease by ($1,444,900) or -1.8%
• Major contributing factors to revenues
• Prior year included a transfer from the Rate Stabilization Reserve – $3,000,000 that is not included in
the FY17 Proposed Budget
• Customer sales - increase of $712,000
• Major contributing factors to expenses
• Power Supply –
• Power Supply Cost decreased ($2,846,400)
• Capacity Credits (generating revenue) decreased by ($3.1 million) – offsetting the power
supply decrease
Net of Generation Revenue ($1,293,200) under FY15 Budget
• Division expenses ($470,400) – attributed to significant decreases in pension and OPEB cost for
the Electric Fund
• Utility Bank & Credit Card Fees increase $32,700
• Internal service allocations – $265,200
• Debt Service decrease – ($1,784,000) (2010 Bonds paid in full)
• OPEB Appropriation to fully fund prior liability calculation removed – ($1,030,000)
• Transfers to other accounts as follows –
• Transfer to Capital Projects – decreased $1.0 million (FY16 included $2.1 million transfer from
Bond Reserve)
• Transfer to Depreciation and & Future Capacity Reserves $1.5M for land acquisition for DAFB
Substation
• Transfer to Rate Stabilization Reserve to cover potential power supply fluctuations or forced
outage penalties
21
Página 28
City of Dover
Major Rate & Fee Trends
Actual Actual Actual Actual Actual Actual Actual Actual Budget Budget
GENERAL FUND 2007/08 2008/09 2009/10 2010/11 2011/12 2012/13 2013/14 2014/15 2015/16 2016/17
Rolled Back/(Up) Property Tax Rate @ 100% value $0.3108 ($0.3499)
Property Tax Rate Approved $0.3300 $0.3300 $0.3300 $0.3378 $0.3378 $0.3378 $0.3378 $0.3378 $0.4050 $0.4050
Property Tax Rate Increase Proposed for revenue requirement $0.0551
Property Tax Rate Increase/(Decrease) (excluding 100% rollback/up) $0.0270 $0.0121
Trash Fees (in City) - implemented FY2000 $5.85 $5.85 $5.85 $11.70 $11.70 $17.00 $17.00 $17.00 $17.00 $17.00
Trash Fees (outside City) $23.00 $29.00 $29.00 $42.75 $42.75 $42.75 $42.75 $42.75 $42.75 $42.75
Transfer from Electric Utility 7.2% 6.6% 6.5% 8.0% 8.0% $8 million $8 million $10 million $10 million $10 million
% of Electric Fund Revenues 8.3% 9.6% 12.5% 12.2% 12.3%
% of General Fund Revenues 22.3% 22.5% 25.7% 23.9% 23.7%
Transfer from Water/Wastewater Utility 4.6% 5.0% 4.5% 0.0% 4.5% $500,000 $500,000 $500,000 $850,000 $875,000
% of Water/Wastewater Fund Revenues 3.7% 3.6% 3.4% 5.7% 5.6%
% of General Fund Revenues 1.4% 1.4% 1.3% 2.0% 1.2%
WATER/WASTEWATER FUND
Water per 1,000 gal $2.45 $2.45 $2.70 $3.00 $3.00 $3.00 $3.00 $3.00 $3.00 $3.00
Water per 1,000 gal (Outside City) $3.68 $3.68 $4.05 $4.50 $4.50 $4.50 $4.50 $4.50 $4.50 $4.50
Water Flat Rate Charge (new source) $1.25 $1.25 $1.25 $1.25 $1.25 $1.25 $1.25 $2.50 $2.50 $2.50
Wastewater per 1,000 gal. Charge $2.10 $2.10 $2.10 $2.65 $2.65 $2.65 $2.65 $2.65 $2.65 $2.65
Wastewater per 1,000 gal (Outside City) $3.15 $3.15 $3.15 $3.98 $3.98 $3.98 $3.98 $3.98 $3.98 $3.98
Wastewater Flat Rate Charge (new source) $1.25 $1.25 $1.25 $1.25 $1.25 $1.25 $1.25 $2.50 $2.50 $2.50
Kent County Sewer Treatment Fee - Rate set by County $2.34 $2.34 $2.34 $2.34 $2.34 $2.34 $2.34 $2.34 $2.34 $2.34
Kent County Sewer Adjustment (new source for I & I - City) $1.05 $1.05 $1.05 $1.05 $1.50 $1.50 $1.50
ELECTRIC FUND
Residential Rate Changes (includes any PCA adj.) $0.1343 $0.1450 $0.1450 $0.1407 $0.1364 $0.1316 $0.1204 $0.1204 $0.1203 $0.1203
Increase % 10.3% 8.0% 0.0% -3.0% -3.1% -3.5% -8.5% 0.0% -0.1% 0.0%
Electric Fund Customer Charge $5.00 $5.00 $5.00 $5.00 $5.00 $5.00 $5.00 $5.00 $7.50 $8.50
Reconnect Fees $50 - $100 $50 - $100 $50 - $100 $50 - $100 $50 - $100 $50 - $100 $50 - $100 $50 - $100 $50 - $100 $50 - $100
Return Check Fees $25 $25 $25 $25 $25 $25 $25 $25 $40 $40
22
Página 29
ALL FUNDS SUMMARY
GENERAL FUND
WATER/WASTEWATER FUND
ELECTRIC FUND
CHARTER ARTICLE IV SEC44
& FINANCIAL POLICIES
Página 30
FY 2017 DRAFT OPERATING BUDGET - DOVER, DELAWARE
City of Dover
All Funds Summary
Fiscal 2017 Proposed Budget
Fund or Beginning Revenues/ Expenses/ Ending
Reserve Account Balances Transfers In Transfers Out Balances
General Fund
Operating Fund $ 4,493,900 $ 42,261,300 $ (42,261,300) $ 4,493,900
Contingency Account 731,000 10,000 - 741,000
Capital Project Fund 383,900 2,049,400 (2,044,400) 388,900
Capital Asset Reserve 1,022,700 6,000 - 1,028,700
Parkland Reserve 324,900 3,000 (80,000) 247,900
Total General Fund 6,956,400 44,329,700 (44,385,700) 6,900,400
Water/Wastewater Fund
Operating Fund 1,229,900 15,467,200 (14,235,100) 2,462,000
Contingency Account 329,600 172,500 - 502,100
I & E Fund 2,132,500 5,706,000 (4,590,400) 3,248,100
Capital Asset Reserve 1,028,000 7,800 - 1,035,800
Impact Fee Reserve 2,021,600 15,400 (402,000) 1,635,000
Total Water Fund 6,741,600 21,368,900 (19,227,500) 8,883,000
Electric Fund
Operating Fund 13,082,400 81,259,600 (79,123,800) 15,218,200
Contingency Account 841,900 6,400 - 848,300
Insurance Reserve 756,300 5,700 - 762,000
Rate Stabilization Reserve 7,207,100 1,304,800 - 8,511,900
I & E Fund 5,349,700 3,445,000 (5,770,300) 3,024,400
Depreciation Reserve 10,083,600 826,600 - 10,910,200
Future Capacity Reserve 10,134,700 827,000 - 10,961,700
Total Electric Fund 47,455,700 87,675,100 (84,894,100) 50,236,700
Less:
Interfund Operating Transfers (10,875,000) 10,875,000
Capital and Reserve Transfers (6,841,400) 6,841,400
Interfund Allocations 5,218,700 (5,218,700)
Subtotal Major Operating Funds 61,153,700 140,876,000 (136,009,600) 66,020,100
Workers Compensation 1,256,300 880,400 (644,500) 1,492,200
Community Transportation Fund 92,100 500,000 (500,000) 92,100
Police Grants 642,700 319,000 (720,100) 241,600
Library Grants 17,300 308,000 (325,300) -
CDBG 2,100 272,800 (272,500) 2,400
Total All Funds & Reserves $ 63,164,200 $ 143,156,200 $ (138,472,000) $ 67,848,400
Notes: Special Revenue Funds with receipts that pass over to the General Fund are not individually included.
These are Municipal Street Aid, Civil Traffic Penalties, and Transfer Taxes.
24
Página 31
FY 2017 DRAFT OPERATING BUDGET - DOVER, DELAWARE
GENERAL FUND
CASH RECEIPT SUMMARY
$ DIFFERENCE % CHG
2014/15 2015/16 2015/16 2016/17 FY 17 PP VS FY17 VS
ACTUAL BUDGET REVISED PROPOSED FY16 BUDGET FY16
1 BEGINNING BALANCE 4,362,491 3,977,500 4,820,400 4,529,400 551,900 13.9%
2 FINES AND POLICE REVENUE 666,694 702,300 651,400 763,300 61,000 8.7%
3 LIBRARY REVENUES 68,056 72,000 67,000 70,300 (1,700) -2.4%
4 KENT COUNTY BOOK REIMBURSEMENT 412,767 450,000 312,600 312,600 (137,400) -30.5%
5 BUSINESS LICENSES 1,403,100 1,425,000 1,472,000 1,467,000 42,000 2.9%
6 PERMITS AND OTHER FEES 1,490,182 1,436,300 1,436,300 1,662,100 225,800 15.7%
7 MISCELLANEOUS CHARGES 135,415 22,700 56,600 56,800 34,100 150.2%
8 POLICE EXTRA DUTY 503,043 533,000 461,500 525,000 (8,000) -1.5%
9 PROPERTY TAXES 11,176,763 12,894,200 12,833,500 12,932,900 38,700 0.3%
10 RECREATION REVENUE 149,318 149,000 149,000 150,000 1,000 0.7%
11 FRANCHISE FEE 683,354 672,300 682,300 680,000 7,700 1.1%
12 SANITATION FEES 2,578,892 2,580,000 2,530,000 2,538,300 (41,700) -1.6%
13 RENT REVENUE - GARRISON FARM 92,294 93,700 93,900 94,500 800 0.9%
14 COURT OF CHANCERY FEES 1,118,680 1,065,100 1,090,400 1,100,000 34,900 3.3%
15 INVESTMENT INCOME 29,326 35,000 140,000 90,000 55,000 157.1%
16 RECEIPTS SUBTOTAL 20,507,884 22,130,600 21,976,500 22,442,800 312,200 1.4%
17 INTERFUND SERVICE RECEIPTS
18 INTRAFUND SERVICE RECEIPTS W/WW 1,341,640 1,492,700 1,417,400 1,653,800 161,100 10.8%
19 INTRAFUND SERVICE RECEIPTS ELECTRIC 3,478,806 3,738,500 3,573,500 3,564,900 (173,600) -4.6%
20 INTERFUND SERVICE RECEIPTS SUBTOTAL 4,820,446 5,231,200 4,990,900 5,218,700 (12,500) -0.2%
21 GRANTS:
22 POLICE RELATED/EXTRA DUTY 127,130 74,400 172,700 258,600 184,200 247.6%
23 POLICE PENSION GRANT 629,910 500,000 500,000 500,000 - 0.0%
24 GREEN ENERGY GRANT 98,500 98,500 98,500 98,500 - 0.0%
25 MISC GRANT REVENUE 5,494 25,000 25,000 25,000 - 0.0%
26 VERIZON RESERVE - 50,000 50,000 - (50,000) -100.0%
27 GRANTS SUBTOTAL 861,034 747,900 846,200 882,100 134,200 17.9%
28 TRANSFERS FROM:
29 TRANSFER TAX 1,713,788 1,340,000 2,090,200 1,672,700 332,700 24.8%
30 MUNICIPAL STREET AID 664,266 564,200 673,100 673,100 108,900 19.3%
31 CIVIL TRAFFIC PENALTIES 495,182 450,000 480,000 496,900 46,900 94.4%
32 WATER/WASTEWATER 500,000 850,000 850,000 875,000 25,000 0.0%
33 ELECTRIC 10,000,000 10,000,000 10,000,000 10,000,000 - 0.0%
34 OTHER RESERVES 58,733 13,200 13,200 - (13,200) -100.0%
35 2003 GO BOND REDEMPTION 475,000 - - - - 0.0%
36 TRANSFERS FROM SUBTOTAL 13,906,969 13,217,400 14,106,500 13,717,700 500,300 3.8%
37 TOTAL REVENUES 40,096,333 41,327,100 41,920,100 42,261,300 934,200 2.3%
38 TOTAL BEGINNING BALANCE & REVENUE 44,458,824 45,304,600 46,740,500 46,790,700 1,486,100 3.3%
25
Página 32
FY 2017 DRAFT OPERATING BUDGET - DOVER, DELAWARE
GENERAL FUND
EXPENSE SUMMARY
$ DIFFERENCE % CHG
2014/15 2015/16 2015/16 2016/17 FY 17 PP VS FY17 VS
ACTUAL BUDGET REVISED PROPOSED FY16 BUDGET FY16
1 DEPARTMENT EXPENSES:
2 CITY CLERK 377,564 383,400 382,800 412,300 28,900 7.5%
3 COUNCIL 92,870 118,100 113,600 144,100 26,000 22.0%
4 TAX ASSESSOR 303,440 234,800 239,800 244,000 9,200 3.9%
5 FIRE 681,170 745,400 735,400 721,700 (23,700) -3.2%
6 GROUNDS MAINTENANCE 952,159 1,210,300 1,133,000 1,201,300 (9,000) -0.7%
7 LIBRARY 1,380,437 1,510,000 1,456,000 1,635,000 125,000 8.3%
8 RECREATION 658,615 729,500 723,200 747,900 18,400 2.5%
9 LIFE SAFETY 504,840 482,200 479,800 485,200 3,000 0.6%
10 CODE ENFORCEMENT 392,859 419,400 412,700 421,100 1,700 0.4%
11 PLANNING 450,400 534,000 532,800 546,800 12,800 2.4%
12 INSPECTIONS 581,480 664,700 749,000 697,900 33,200 5.0%
13 ECONOMIC DEVELOPMENT 226,308 238,000 245,000 237,700 (300) -0.1%
14 POLICE 14,789,684 15,159,000 15,921,400 16,091,600 932,600 6.2%
15 POLICE EXTRA DUTY 557,432 602,400 634,200 783,600 181,200 30.1%
16 STREETS 543,832 674,500 658,500 1,163,500 489,000 72.5%
17 SANITATION 2,185,408 2,157,900 2,151,100 2,032,800 (125,100) -5.8%
18 CITY MANAGER 553,558 750,300 909,300 683,500 (66,800) -8.9%
19 INFORMATION TECHNOLOGY 730,046 704,800 625,500 716,300 11,500 1.6%
20 FINANCE 946,618 978,500 990,200 1,008,600 30,100 3.1%
21 PUBLIC WORKS - ADMINISTRATION 522,935 626,800 580,300 680,000 53,200 8.5%
22 FACILITIES MANAGEMENT 688,162 707,500 692,200 607,100 (100,400) -14.2%
23 PUBLIC WORKS - ENGINEERING 26,996 181,400 173,400 207,000 25,600 14.1%
24 PROCUREMENT & INVENTORY 534,298 560,200 569,300 585,100 24,900 4.4%
25 FLEET MAINTENANCE 786,500 768,500 760,000 776,300 7,800 1.0%
26 CUSTOMER SERVICE 1,045,588 1,120,100 1,082,000 1,143,800 23,700 2.1%
27 HUMAN RESOURCES 361,384 383,900 376,700 392,500 8,600 2.2%
28 MAYOR 77,861 76,100 76,100 74,000 (2,100) -2.8%
29 DEPARTMENT SUBTOTALS 30,952,444 32,721,700 33,403,300 34,440,700 1,719,000 5.3%
30 OTHER EXPENDITURES:
31 DEBT SERVICE 962,312 660,800 669,400 685,300 24,500 3.7%
32 CONTRIBUTION TO DDP 70,000 70,000 70,000 70,000 - 0.0%
33 MISCELLANEOUS GRANT RELATED EXP - 25,000 25,000 25,000 - 0.0%
34 INSURANCE 674,775 690,000 690,000 700,000 10,000 1.4%
35 RETIREES HEALTH CARE 1,636,500 1,895,600 1,567,700 2,039,700 144,100 7.6%
36 OTHER EMPLOYMENT EXPENSES - 520,100 52,000 392,200 (127,900) -24.6%
37 BANK & CREDIT CARD FEES - 15,000 10,600 15,000 - 0.0%
38 UNCOLLECTIBLES - TRASH AND OTHER 50,113 50,000 50,000 50,000 - 0.0%
39 STREET LIGHTS 775,197 797,700 797,700 804,000 6,300 0.8%
40 NEW STREET PROPERTIES ACQUISITIONS - - 240,400 - - 0.0%
41 OTHER EXPENSE SUBTOTAL 4,168,897 4,724,200 4,172,800 4,781,200 57,000 1.2%
42 TRANSFERS
43 TRANSFER TO CAPITAL ASSET RESERVE 60,000 - 229,600 - - 0.0%
44 TRANSFER TO CAPITAL FUND - PROJECTS 2,196,000 2,625,400 2,625,400 1,859,400 (766,000) -29.2%
45 APPROP. TO THE POLICE PENSION FUND 755,000 570,000 676,500 670,000 100,000 17.5%
46 APPROP. POLICE PENSION - STATE GRANT 629,910 500,000 500,000 500,000 - 0.0%
47 APPROP. TO THE GENERAL PENSION FUND 543,000 - 594,300 - - 0.0%
48 TRANSFER TO CONTINGENCY RESERVE 300,000 - - - - 0.0%
49 TRANSFER TO PARKLAND RESERVE 25,000 - - - - 0.0%
50 TRANSFER TO OTHER/VERIZON RESERVE - 50,000 50,000 - (50,000) -100.0%
51 TRANSFER TO INVENTORY WRITE-OFFS - 10,000 10,000 10,000 - 0.0%
52 TRANSFERS SUBTOTAL 4,508,910 3,755,400 4,685,800 3,039,400 (716,000) -19.1%
53 TOTAL EXPENDITURES 39,630,251 41,201,300 42,261,900 42,261,300 1,060,000 2.6%
54 BUDGET BALANCE 4,828,573 4,103,300 4,493,900 4,493,900 390,600 9.5%
55 TOTAL BUDGET BALANCE & EXPENDITURES 44,458,824 45,304,600 46,755,800 46,755,200 1,450,600 3.2%
56 EXCEEDS/(REMAINS)TO MEET REQUIREMENT 1,620,900 797,100 1,139,100 1,113,000
$ DIFFERENCE
2014/15 2015/16 2015/16 2016/17 FY 17 PP VS
57 RESERVE BALANCES ACTUAL BUDGET REVISED PROPOSED FY16 BUDGET POLICY
58 CONTINGENCY 720,334 467,900 731,000 741,000 10,000 $700K
26
Página 33
FY 2017 DRAFT OPERATING BUDGET - DOVER, DELAWARE
Fiscal Year 2016/2017
General Fund Revenue
COURT OF
GRANTS CHANCERY FEES
3.7% 2.6%
POLICE FINES &
FEES
LICENSES & FRANCHISE FEES
4.2%
PERMITS 1.6%
7.4% LIBRARY &
RECREATION FEES
TRANSFER TAXES 1.3%
4.0% OTHER
MISCELLANEOUS
RECEIPTS
SANITATION FEES 0.6%
6.0%
INTERFUND
SERVICE FEES
12.3%
PROPERTY TAXES
30.6%
UTILITY TRANSFERS
25.7%
27
Página 34
FY 2017 DRAFT OPERATING BUDGET - DOVER, DELAWARE
Fiscal Year 2016/2017
General Fund Expenditures
By Major Function
TRANSFER TO
CAPITAL PROJECTS
4.4%
DEBT SERVICE CITY
1.6% ADMINISTRATION
INSURANCE
1.7% OTHER 4.6%
STREET 1.2%
LIGHTS LIBRARY &
RETIREE PENSION 1.9% RECREATION
CONTRIBUTIONS 5.6%
2.8%
PLANNING &
RETIREE MEDICAL INSPECTIONS
CONTRIBUTIONS 5.1%
4.8%
PUBLIC WORKS
15.8%
FINANCIAL
ADMINISTRATION
8.9% POLICE & FIRE
41.6%
Several General Fund Departments service all City operations. The General Fund bills the utility funds
services provided. The receipts are reported as revenue in the General Fund and not netted against the
expenditures.
28
Página 35
FY 2017 DRAFT OPERATING BUDGET - DOVER, DELAWARE
Fiscal Year 2016/2017
General Fund Expenditures
By Expenditure Category
RETIREE PENSION
CONTRIBUTIONS STREET LIGHTS DEBT SERVICE
2.8% 1.9% 1.6%
INSURANCE
RETIREE MEDICAL 1.7%
CONTRIBUTIONS
4.8%
CAPITAL
ADMINISTRATIVE
4.4%
EXPENSES
OTHER
7.0%
0.4%
MATERIALS &
SUPPLIES
3.3%
PERSONNEL SERVICES
72.2%
29
Página 36
FY 2017 DRAFT OPERATING BUDGET - DOVER, DELAWARE
PROJECTED COST PER CAPITA BY FUNCTION
Fiscal Year 2016-2017
OTHER $13.24
TRANSFER TO CAPITAL PROJECTS $49.53
INSURANCE $18.65
DEBT SERVICE $18.26
STREET LIGHTS $21.42
RETIREE PENSION CONTRIBUTIONS $31.17
RETIREE MEDICAL CONTRIBUTIONS $54.33
PUBLIC WORKS $177.62
FINANCIAL ADMINISTRATION $100.23
$468.75
POLICE & FIRE
PLANNING & INSPECTIONS $57.30
LIBRARY & RECREATION $63.48
$51.79
CITY ADMINISTRATION
$0.00 $100.00 $200.00 $300.00 $400.00 $500.00
Total per capita based on population estimate of 37,540 = $1,125.77
30
Página 37
FY 2017 DRAFT OPERATING BUDGET - DOVER, DELAWARE
GOVERNMENTAL CAPITAL PROJECTS FUND SUMMARY
$ DIFFERENCE % CHG
2014/15 2015/16 2015/16 2016/17 FY 17 PP VS FY17 VS
ACTUAL BUDGET REVISED PROPOSED FY16 BUDGET FY16
1 BEGINNING BALANCE - PROJECTS 2,654,625 154,800 2,926,700 383,900 229,100 148.0%
2 REVENUES
3 STATE GRANTS - Other 70,609 - 80,500 105,000 105,000 0.0%
4 BUDGET BOND/BANK PROCEEDS 3,660,000 - - - - 0.0%
5 INCOME FROM SALE OF ASSETS 86,491 20,300 120,800 - (20,300) -100.0%
6 MISCELLANEOUS RECEIPTS - - 74,700 - - 0.0%
7 INTEREST EARNINGS 1,773 5,000 5,000 5,000 - 0.0%
8 TRANSFER FROM GENERAL FUND 2,196,000 2,625,400 2,625,400 1,859,400 (766,000) -29.2%
9 TRANSFER FROM PARKLAND RESERVE 104,000 - - 80,000 80,000 0.0%
10 SUBTOTAL CAPITAL PROJECT FUNDING SOURCES 6,118,873 2,650,700 2,906,400 2,049,400 (601,300) -22.7%
11 TOTAL BEGINNING BALANCE & FUNDING SOURCES 8,773,498 2,805,500 5,833,100 2,433,300 (372,200) -13.3%
12 EXPENDITURES
13 FIRE 526,617 145,600 445,800 145,700 100 0.1%
14 GROUNDS 65,947 201,100 185,200 58,200 (142,900) -71.1%
15 RECREATION 207,323 - 73,900 165,000 165,000 0.0%
16 LIFE SAFETY - 55,700 55,700 29,500 (26,200) -47.0%
17 POLICE 581,012 262,100 302,700 299,800 37,700 14.4%
18 STREETS 3,597,163 1,428,500 3,735,000 1,026,000 (402,500) -28.2%
19 SANITATION 247,858 449,000 449,000 261,500 (187,500) -41.8%
20 CITY MANAGER - 24,700 24,700 - (24,700) -100.0%
21 FACILITIES MANAGEMENT - - - 27,700 27,700 0.0%
22 PROCUREMENT & INVENTORY 49,672 - - - - 0.0%
23 FLEET MAINTENANCE - 84,000 84,500 31,000 (53,000) -63.1%
24 DEPARTMENT SUBTOTAL 5,275,592 2,650,700 5,356,500 2,044,400 (606,300) -22.9%
25 TRANSFERS & MISCELLANEOUS EXPENSES
26 BOND/LOAN ISSUANCE COST 60,668 - - - - 0.0%
27 TRANSFER TO PARKLAND RESERVE 180,000 - - - - 0.0%
28 TRANSFER TO CAPITAL ASSET RESERVE 330,500 - 92,700 - - 0.0%
29 TRANSFERS & MISCELLANEOUS SUBTOTAL 571,168 - 92,700 - - 0.0%
30 TOTAL EXPENDITURES 5,846,760 2,650,700 5,449,200 2,044,400 (606,300) -22.9%
31 BUDGET BALANCE 2,926,738 154,800 383,900 388,900 234,100 151.2%
32 TOTAL BUDGET BALANCE & EXPENDITURES 8,773,498 2,805,500 5,833,100 2,433,300 (372,200) -13.3%
$ DIFFERENCE
2014/15 2015/16 2015/16 2016/17 FY 17 PP VS
RESERVE BALANCES ACTUAL BUDGET REVISED PROPOSED FY16 BUDGET POLICY
33 CAPITAL ASSET RESERVE 915,129 512,300 1,022,700 1,028,700 6,000 Min $500K
34 PARKLAND/RECREATION 320,796 304,800 324,900 247,900 (77,000) N/A
31
Página 38
FY 2017 DRAFT OPERATING BUDGET - DOVER, DELAWARE
WATER/WASTEWATER FUND SUMMARY
$ DIFFERENCE % CHG
2014/15 2015/16 2015/16 2016/17 FY 17 PP VS FY17 VS
ACTUAL BUDGET REVISED PROPOSED FY16 BUDGET FY16
1 BEGINNING BALANCE - WATER 550,768 861,600 1,072,900 566,700 (294,900) -34.2%
2 BEGINNING BALANCE - WASTEWATER 69,989 293,400 206,900 663,200 369,800 126.0%
3 TOTAL BEGINNING BALANCES 620,757 1,155,000 1,279,800 1,229,900 74,900 6.5%
4 BASE REVENUE:
5 WATER SERVICES 4,889,046 6,200,000 5,366,600 5,800,000 (400,000) -6.5%
6 WASTEWATER SERVICES 3,735,855 3,728,000 3,823,800 3,800,000 72,000 1.9%
7 WASTEWATER TREATMENT SERVICES 2,952,857 3,026,500 2,997,600 3,000,000 (26,500) -0.9%
8 GROUNDWATER INFLOW ADJUSTMENT 1,831,784 1,864,300 1,965,600 1,938,000 73,700 4.0%
9 WATER TANK SPACE LEASING 344,842 341,900 341,900 366,200 24,300 7.1%
10 SEWER IMPACT FEES 482,236 250,000 222,400 228,000 (22,000) -8.8%
11 WATER IMPACT FEES 536,922 250,000 253,400 252,000 2,000 0.8%
12 INTEREST - WATER (396) 1,000 5,000 10,000 9,000 900.0%
13 INTEREST - WASTEWATER (620) 2,000 5,000 10,000 8,000 400.0%
14 MISCELLANEOUS SERVICE FEE 74,982 64,000 56,200 63,000 (1,000) -1.6%
15 TOTAL REVENUES 14,847,508 15,727,700 15,037,500 15,467,200 (260,500) -1.7%
16 TOTAL BEGINNING BALANCE & REVENUES 15,468,265 16,882,700 16,317,300 16,697,100 (185,600) -1.1%
No salaries included
17 DIRECT EXPENSES:
18 ENGINEERING & INSPECTION 468,706 517,500 512,500 516,500 (1,000) -0.2%
19 WATER CONSTRUCTION 260,383 - - - - 0.0%
20 WATER DEPARTMENT 399,530 673,300 650,900 655,400 (17,900) -2.7%
21 WASTEWATER DEPARTMENT 790,525 968,600 840,600 962,400 (6,200) -0.6%
22 WATER TREATMENT PLANT 1,452,318 1,910,000 1,743,100 1,727,400 (182,600) -9.6%
23 DIRECT EXPENDITURE SUBTOTAL 3,371,462 4,069,400 3,747,100 3,861,700 (207,700) -5.1%
24 OTHER EXPENSES:
25 DEBT SERVICE - WATER 486,635 545,200 521,100 590,300 45,100 8.3%
26 DEBT SERVICE - WASTEWATER 650,647 586,900 611,300 636,900 50,000 8.5%
27 RETIREES HEALTH CARE 200,000 178,600 60,200 192,400 13,800 7.7%
28 OTHER EMPLOYMENT EXPENSES - 20,000 142,300 60,000 40,000 200.0%
29 KENT COUNTY TREATMENT CHARGE 4,127,919 4,130,000 4,130,000 4,130,000 - 0.0%
30 INTRAFUND SERVICE FEES 1,341,640 1,492,700 1,420,000 1,653,800 161,100 10.8%
31 BANK & CREDIT CARD FEES - 46,200 25,000 25,000 (21,200) -45.9%
32 BOND ISSUANCE COSTS - - - 40,000
33 OTHER EXPENSES SUBTOTAL 6,806,841 6,999,600 6,909,900 7,328,400 328,800 4.7%
34 TRANSFER TO:
35 GENERAL FUND FROM WATER 250,000 550,000 550,000 500,000 (50,000) -9.1%
36 GENERAL FUND FROM WASTEWATER 250,000 300,000 300,000 375,000 75,000 25.0%
37 WATER IMP AND EXT 1,205,285 1,800,000 1,800,000 1,000,000 (800,000) -44.4%
38 WASTEWATER IMP AND EXT 1,803,104 1,500,000 1,500,000 1,000,000 (500,000) -33.3%
39 SEWER IMPACT FEE RESERVE 275,279 - - - - 0.0%
40 WATER IMPACT FEE RESERVE 226,485 - - - - 0.0%
41 CONTINGENCY RESERVE WATER - 32,000 32,000 110,000 78,000 243.8%
42 CONTINGENCY RESERVE WASTEWATER - - - 60,000 60,000 0.0%
43 GENERAL EMPLOYEES PENSION - - 248,400 - - 0.0%
44 TRANSFER TO SUBTOTAL 4,010,153 4,182,000 4,430,400 3,045,000 (1,137,000) -27.2%
45 TOTAL EXPENSES 14,188,456 15,251,000 15,087,400 14,235,100 (1,015,900) -6.7%
46 BUDGET BALANCES
47 BUDGET BALANCE WATER 1,072,915 1,048,600 566,700 1,199,500 150,900 14.4%
48 BUDGET BALANCE WASTEWATER 206,894 583,100 663,200 1,262,500 679,400 116.5%
49 BUDGET BALANCE SUBTOTALS 1,279,809 1,631,700 1,229,900 2,462,000 830,300 50.9%
50 TOTAL BUDGET BALANCES & EXPENSES 15,468,265 16,882,700 16,317,300 16,697,100 (185,600) -1.1%
51 EXCEEDS/(REMAINS)TO MEET REQMNT 1,279,809 373,500 26,900 1,224,600
$ DIFFERENCE
2014/15 2015/16 2015/16 2016/17 FY 17 PP VS
52 RESERVE BALANCES ACTUAL BUDGET REVISED BUDGET FY16 BUDGET POLICY
53 CONTINGENCY - WATER 105,189 107,700 138,000 249,000 111,000 $250K
54 CONTINGENCY - WATER/WASTEWATER 190,209 194,800 191,600 253,100 61,500 $250K
32
Página 39
FY 2017 DRAFT OPERATING BUDGET - DOVER, DELAWARE
Fiscal Year 2016/2017
Water/Wastewater Fund
Revenue
WATER TANK SPACE
GROUNDWATER LEASING
INFLOW 2.4% IMPACT FEES
ADJUSTMENT 3.1%
12.5%
MISCELLANEOUS
SERVICE FEE
0.5%
WASTEWATER WATER SERVICES
TREATMENT 37.5%
SERVICES
19.4%
WASTEWATER
SERVICES
24.6%
33
Página 40
FY 2017 DRAFT OPERATING BUDGET - DOVER, DELAWARE
2016/2017 Budget
Water/Wastewater Fund Expenses
By Major Function
INTRAFUND
SERVICE FEES
11.8%
TRANSFER TO
GENERAL FUND
6.1%
TRANSFER TO
CAPITAL PROJECTS
14.1%
TRF TO
CONTINGENCY
KENT COUNTY WATER
TREATMENT FEES 0.8%
29.7%
ENGINEERING &
INSPECTION
3.6%
WATER
CONSTRUCTION
0.0%
DEBT SERVICE
8.6% WATER
RETIREE MEDICAL WATER TREATMENTDEPARTMENT
CONTRIBUTIONS PLANT 4.6%
1.4% 12.6%
WASTEWATER
DEPARTMENT
6.8%
34
Página 41
FY 2017 DRAFT OPERATING BUDGET - DOVER, DELAWARE
2016/2017 Budget
Water/Wastewater Fund Expenses
By Expense Category
INTRAFUND
SERVICE FEES
11.5%
TRANSFER TO
GENERAL FUND
6.1%
TRANSFER TO
CAPITAL PROJECTS
14.7%
KENT COUNTY
TREATMENT FEES
28.8%
PERSONNEL
SERVICES
18.9%
RETIREE MEDICAL MATERIALS &
CONTRIBUTIONS DEBT SERVICE SUPPLIES
1.3% 8.6% 2.4%
ADMINISTRATIVE
EXPENSES
7.7%
35
Página 42
FY 2017 DRAFT OPERATING BUDGET - DOVER, DELAWARE
WATER/WASTEWATER IMPROVEMENT & EXTENSION FUND SUMMARY
$ DIFFERENCE % CHG
2014/15 2015/16 2015/16 2016/17 FY 17 PP VS FY17 VS
ACTUAL BUDGET REVISED PROPOSED FY16 BUDGET FY16
1 BEGINNING BALANCE - WATER 7,178,064 833,500 4,990,300 1,179,900 346,400 41.6%
2 BEGINNING BALANCE - WASTEWATER 5,677,607 1,027,600 4,551,700 952,600 (75,000) -7.3%
3 TOTAL BEGINNING BALANCES 12,855,671 1,861,100 9,542,000 2,132,500 (5,419,735) 14.6%
4 REVENUES
5 STATE LOAN FUND - WATER - - - 2,400,000 2,400,000 0.0%
6 STATE LOAN FUND - WASTEWATER - - - 884,000 884,000 0.0%
7 TRANS FR OPERATING FUND - WATER 1,205,285 1,800,000 1,800,000 1,000,000 1,600,000 -44.4%
8 TRANS FR OPERATING FUND - WASTEWATER 1,803,104 1,500,000 1,500,000 1,000,000 1,800,000 -33.3%
9 TRANSFER FR WATER IMPACT FEE - - - 190,800 190,800 0.0%
10 TRANSFER FR WASTEWATER IMPACT FEE 1,315,600 165,000 165,000 211,200 211,200 28.0%
11 FEDERAL/STATE GRANTS - - 20,300 - - 0.0%
12 PROCEEDS FROM SALE OF ASSETS 27,283 - - - - 0.0%
13 INTEREST INCOME 39,883 25,000 69,900 20,000 (5,000) -20.0%
14 MISCELLANEOUS RECEIPTS - - 61,400 - - 0.0%
15 TOTAL REVENUES 4,391,155 3,490,000 3,616,600 5,706,000 2,216,000 63.5%
16 TOTAL BEGINNING BALANCES & REVENUES 17,246,826 5,351,100 13,158,600 7,838,500 2,487,400 46.5%
17 EXPENSES
18 W/WW ENGINEERING - - - 30,400 30,400 0.0%
19 WATER 3,392,546 2,028,600 5,442,600 1,338,800 (689,800) -34.0%
20 WASTEWATER 4,277,921 1,822,100 5,299,100 2,021,200 199,100 10.9%
21 WATER TREATMENT PLANT 33,771 - 284,400 1,200,000 - 0.0%
22 TOTAL EXPENSES 7,704,238 3,850,700 11,026,100 4,590,400 739,700 19.2%
23 BUDGET BALANCE - WATER 4,990,615 617,400 1,179,900 2,226,700 1,609,300 260.7%
24 BUDGET BALANCE - WASTEWATER 4,551,973 883,000 952,600 1,021,400 138,400 15.7%
25 TOTAL ENDING BUDGET BALANCES 9,542,588 1,500,400 2,132,500 3,248,100 1,747,700 116.5%
26 TOTAL BUDGET BALANCES & EXPENSES 17,246,826 5,351,100 13,158,600 7,838,500 2,487,400 46.5%
$ DIFFERENCE
2014/15 2015/16 2015/16 2016/17 FY 17 PP VS
27 RESERVE BALANCES ACTUAL BUDGET REVISED PROPOSED FY16 BUDGET POLICY
28 CAPITAL ASSET RESERVE-WATER 510,681 522,700 514,600 518,500 (4,200) MIN $500K
29 CAPITAL ASSET RESERVE-WASTEWATER 509,513 521,600 513,400 517,300 (4,300) MIN $500K
30 IMPACT FEE RESERVE - WATER 427,523 203,900 430,700 243,200 39,300 20% of Rev.
31 IMPACT FEE RESERVE - WASTEWATER 1,742,652 1,552,300 1,590,900 1,391,800 (160,500) 20% of Rev.
36
Página 43
FY 2017 DRAFT OPERATING BUDGET - DOVER, DELAWARE
ELECTRIC REVENUE FUND SUMMARY
$ DIFFERENCE % CHG
2014/15 2015/16 2015/16 2016/17 FY 17 PP VS FY17 VS
ACTUAL BUDGET REVISED PROPOSED FY16 BUDGET FY16
1 BEGINNING BALANCE 6,602,899 6,177,600 8,117,200 13,095,100 6,917,500 112.0%
2 BASE REVENUE:
3 DIRECT SALES TO CUSTOMER 77,011,592 78,279,200 78,493,800 78,991,200 712,000 0.9%
4 UTILITY TAX 1,266,872 1,281,100 1,309,600 1,320,900 39,800 3.1%
5 MISCELLANEOUS REVENUE 1,038,372 597,200 911,400 548,600 (48,600) -8.1%
6 RENT REVENUE 223,065 202,600 202,600 223,000 20,400 10.1%
7 GREEN ENERGY 128,090 128,000 128,000 128,000 - 0.0%
8 INTEREST EARNINGS 5,909 47,900 35,000 47,900 - 0.0%
9 TRANSFER FROM RATE STABILIZATION 3,000,000 3,000,000 750,000 - (3,000,000) -100.0%
10 TOTAL REVENUES 82,673,900 83,536,000 81,830,400 81,259,600 (2,276,400) -2.7%
11 TOTAL BEGINNING BALANCE & REVENUES 89,276,799 89,713,600 89,947,600 94,354,700 4,641,100 5.2%
12 EXPENSES:
13 POWER SUPPLY 26,170,504 23,402,600 23,402,600 16,557,600 (6,845,000) -29.2%
14 SOLAR ENERGY 1,976,577 2,313,900 2,313,900 2,313,900 - 0.0%
15 SOLAR RENEWAL ENERGY CREDITS 372,329 363,400 363,400 363,400 - 0.0%
16 POWER SUPPLY MANAGEMENT 996,000 996,000 996,000 996,000 - 0.0%
17 REC'S (Renewable Energy Credits) 572,515 673,400 673,400 673,400 - 0.0%
18 PJM CHARGES - ENERGY 5,389,169 7,932,500 7,932,500 12,357,900 4,425,400 55.8%
19 PJM CHARGES - TRANSMISSION & FEES 8,681,190 7,966,100 7,966,100 7,603,800 (362,300) -4.5%
20 CAPACITY CHARGES 9,617,562 10,225,100 10,225,100 10,160,600 (64,500) -0.6%
21 SUB-TOTAL POWER SUPPLY 53,775,846 53,873,000 53,873,000 51,026,600 (2,846,400) -5.3%
22 PLANT OPERATIONS 5,968,784 6,434,600 6,382,900 6,217,100 (217,500) -3.4%
23 GENERATIONS FUELS 1,729,044 1,342,300 1,342,300 431,900 (910,400) -67.8%
24 PJM SPOT MARKET ENERGY (2,560,292) (1,708,300) (1,708,300) (804,900) 903,400 -52.9%
25 PJM CREDITS (560,450) (360,000) (360,000) (360,000) - 0.0%
26 CAPACITY CREDITS (8,706,981) (10,472,100) (10,472,100) (7,355,100) 3,117,000 -29.8%
27 GENERATION SUBTOTAL (4,129,895) (4,763,500) (4,815,200) (1,871,000) 2,892,500 -60.7%
28 POWER SUPPLY & GENERATION SUBTOTAL 49,645,950 49,109,500 49,057,800 49,155,600 46,100 0.1%
29 DIRECT EXPENDITURES
30 TRANSMISSION/DISTRIBUTION 3,625,462 4,068,600 3,610,300 3,605,700 (462,900) -11.4%
31 ELECTRICAL ENGINEERING 1,166,201 1,335,800 1,243,300 1,247,900 (87,900) -6.6%
32 ADMINISTRATION 609,819 839,300 881,800 929,700 90,400 10.8%
33 METER READING 371,658 360,500 322,200 378,600 18,100 5.0%
34 SYSTEMS OPERATIONS 703,431 679,800 612,700 651,700 (28,100) -4.1%
35 DIRECT EXPENDITURE SUBTOTALS 6,476,572 7,284,000 6,670,300 6,813,600 (470,400) -6.5%
36 OTHER EXPENSES:
37 UTILITY TAX 1,266,872 1,281,100 1,309,600 1,320,900 39,800 3.1%
38 ALLOW FOR UNCOLLECTIBLES 200,000 200,000 200,000 250,000 50,000 25.0%
39 CONTRACTUAL SERVICES - RFP'S 266,856 - - - - 0.0%
40 RETIREES HEALTH CARE 513,300 537,800 57,700 600,000 62,200 11.6%
41 OTHER EMPLOYMENT EXPENSES - 72,000 40,300 128,200 56,200 78.1%
42 OPEB UNFUNDED LIABILITY 1,009,800 1,030,000 - - (1,030,000) -100.0%
43 GREEN ENERGY PAYMENT TO DEMEC 128,161 128,000 128,000 128,000 - 0.0%
44 INTRAFUND SERVICE FEES 3,478,806 3,738,500 3,573,500 3,564,900 (173,600) -4.6%
45 INTEREST ON DEPOSITS 18,098 20,500 20,500 21,000 500 2.4%
46 BANK & CREDIT CARD FEES - 242,300 259,300 275,000 32,700 13.5%
47 DEBT SERVICE 3,405,202 3,402,000 1,617,700 1,618,000 (1,784,000) -52.4%
48 OTHER EXPENSES SUBTOTAL 10,287,095 10,652,200 7,206,600 7,906,000 (2,746,200) -25.8%
49 TRANSFER TO:
50 IMPROVEMENT & EXTENSION 4,750,000 3,500,000 3,500,000 2,500,000 (1,000,000) -28.6%
51 GENERAL FUND 10,000,000 10,000,000 10,000,000 10,000,000 - 0.0%
52 TRANSFER TO FUTURE CAPACITY RESERVE - - - 750,000 750,000 0.0%
53 TRANSFER TO DEPRECIATION RESERVE - - - 750,000 750,000 0.0%
54 TRANSFER INSURANCE RESERVE - 10,000 10,000 - (10,000) -100.0%
55 TRANSFER CONTINGENCY RESERVE - 13,000 13,000 - (13,000) -100.0%
56 RATE STABILIZATION RESERVE - - 394,800 1,250,000 1,250,000 0.0%
57 TRANSFER TO SUBTOTAL 14,750,000 13,523,000 13,917,800 15,250,000 1,727,000 12.8%
58 TOTAL EXPENSES 81,159,617 80,568,700 76,852,500 79,125,200 (1,443,500) -1.8%
59 BUDGET BALANCE - WORKING CAPITAL 8,117,182 9,144,900 13,095,100 15,229,500 6,084,600 66.5%
60 TOTAL BUDGET BALANCE & EXPENSES 89,276,799 89,713,600 89,947,600 94,354,700 4,641,100 5.2%
61 EXCEEDS/(REMAINS)TO MEET REQUIREMENT (1,291,618) (365,700) 3,522,600 5,636,900
$ DIFFERENCE
2014/15 2015/16 2015/16 2016/17 FY 17 PP VS
62 RESERVE BALANCES ACTUAL BUDGET REVISED PROPOSED FY16 BUDGET POLICY
63 CONTINGENCY RESERVE 822,677 826,000 841,900 848,300 22,300 $750K
64 INSURANCE RESERVE 740,641 743,600 756,300 762,000 18,400 $750K
65 RATE STABILIZATION RESERVE 7,505,354 8,583,000 7,207,100 8,511,900 (71,100) 10% - 20%
37
Página 44
FY 2017 DRAFT OPERATING BUDGET - DOVER, DELAWARE
Electric Fund
Fiscal Year 2016/2017
Revenue
DIRECT SALES TO
CUSTOMER
97.2%
TRANSFER FROM
UTILITY TAX
RATE STABILIZATION
1.6%
0.0%
MISCELLANEOUS
REVENUE
1.2%
38
Página 45
FY 2017 DRAFT OPERATING BUDGET - DOVER, DELAWARE
Electric Fund
Fiscal Year 2016/2017
Expense by Function
ADMINISTRATION METER READING
1.2% 0.5%
ENGINEERING SYSTEMS
1.6% OPERATIONS
T&D 0.9%
4.7%
TRANSFER TO
GENERAL FUND
13.1%
TRANSFER TO
CAPITAL PROJECTS
3.3%
INTERFUND
SERVICE FEES
4.7%
DEBT SERVICE
POWER SUPPLY & 2.1%
GENERATION
64.5%
RETIREE MEDICAL
CONTRIBUTIONS
MISCELLANEOUS 0.8%
EXPENSES
0.9%
STATE UTILITY
TAXES
1.7%
39
Página 46
FY 2017 DRAFT OPERATING BUDGET - DOVER, DELAWARE
Electric Fund
Fiscal Year 2016/2017
Expense by Category
POWER SUPPLY &
GENERATION
64.0%
ADMINISTRATIVE
EXPENSES TRANSFER TO
1.4% GENERAL FUND
13.0%
MATERIALS &
SUPPLIES TRANSFER TO
0.9% CAPITAL PROJECTS
PERSONNEL DEBT SERVICE 3.3%
SERVICES 2.1%
7.4% INTERFUND
SERVICE FEES
4.6%
RETIREE MEDICAL
CONTRIBUTIONS
0.8%
MISCELLANEOUS STATE UTILITY
EXPENSES TAXES
0.9% 1.7%
40
Página 47
FY 2017 DRAFT OPERATING BUDGET - DOVER, DELAWARE
ELECTRIC IMPROVEMENT & EXTENSION FUND SUMMARY
$ DIFFERENCE % CHG
2014/15 2015/16 2015/16 2016/17 FY 17 PP VS FY17 VS
ACTUAL BUDGET REVISED PROPOSED FY16 BUDGET FY16 REV
1 BEGINNING BALANCE 5,847,854 3,623,600 6,904,500 5,349,700 1,726,100 47.6%
2 REVENUES
3 TRANSFER FROM ELECTRIC 4,750,000 3,500,000 3,500,000 2,500,000 (1,000,000) -28.6%
4 TRANSFER FROM BOND RESERVE - - 2,108,000 - - 0.0%
5 GENERAL SERVICE BILLING 95,045 1,900,000 1,900,000 900,000 (1,000,000) -52.6%
6 DEVELOPMENT GRANTS - - 15,000 5,000 5,000 0.0%
7 INCOME FROM SALE OF ASSETS 39,637 - - - - 0.0%
8 INTEREST EARNINGS 1,047 26,700 57,900 40,000 13,300 49.8%
9 TOTAL REVENUES 4,885,729 5,426,700 7,580,900 3,445,000 (1,981,700) -36.5%
10
11 TOTALS 10,733,583 9,050,300 14,485,400 8,794,700 (255,600) -2.8%
12 EXPENSES
13 ELECTRIC GENERATION 1,899,229 1,655,000 2,299,800 1,842,800 187,800 11.3%
14 TRANSMISSION AND DISTRIBUTION 1,078,077 2,887,600 3,524,900 1,975,000 (912,600) -31.6%
15 ELECTRICAL ENGINEERING 851,740 1,724,300 3,288,000 910,700 (813,600) -47.2%
16 METER READING - - 23,000 41,800 41,800 0.0%
17 ERP SYSTEM - - - 1,000,000 1,000,000 0.0%
18 TOTAL EXPENSES 3,829,046 6,266,900 9,135,700 5,770,300 (496,600) -7.9%
19 BUDGET BALANCE 6,904,537 2,783,400 5,349,700 3,024,400 241,000 8.7%
20 TOTAL BUDGET BALANCE & EXPENSES 10,733,583 9,050,300 14,485,400 8,794,700 (255,600) -2.8%
$ DIFFERENCE
2014/15 2015/16 2015/16 2016/17 FY 17 PP VS
ACTUAL BUDGET REVISED PROPOSED FY16 BUDGET POLICY
21 RESERVE BALANCES
22 DEPRECIATION RESERVE 9,957,873 9,998,200 10,083,600 10,910,200 912,000 Min $10M
23 FUTURE CAPACITY RESERVE 10,107,899 10,148,700 10,108,400 10,908,900 760,200 Min $10M
41
Página 49
FY 2017 ANNUAL OPERATING BUDGET – DOVER, DELAWARE
Sec. 44. - Annual budget.
On or before the second Monday of May of each year, the city manager shall prepare and submit to
the council, a budget, presenting a financial plan for conducting the affairs of the city for the ensuing fiscal
year. The total of proposed expenditures shall not exceed the total of anticipated income.
The budget shall include the following information:
1. A detailed statement showing the expenses of conducting each department and office of the
city for the current year and last preceding fiscal year.
2. A detailed estimate of the expenses of conducting each department and office of the city for the
ensuing fiscal year with reasons for the increases and decreases recommended.
3. The amount of the debt of the city together with a schedule of maturities of bond issues.
4. A statement showing the amount required for interest on the city debt and for paying off any
bonds maturing during the year and the amount required for the sinking fund.
5. An itemized statement of all anticipated income of the city with a comparative statement of the
amounts received by the city from each of the same or similar sources for the last preceding and
current fiscal years.
6. An estimate of the amount of money to be received from taxes.
7. Such other information as the city manager may think desirable or as may be required by the
council.
The council shall on or before the second Monday in the month of June in each year adopt a budget
for the succeeding fiscal year. The council shall, so far as possible, adhere to the budget so adopted in the
making of appropriations.
(Amd. of 7-12-2005 (S.B. 126))
43
Página 50
CITY OF DOVER
FINANCIAL POLICIES
Amended October 12, 2015
44
Página 51
CITY OF DOVER, DELAWARE
FINANCIAL POLICIES
The purpose of these policies is to present a standardized set of principles that the City follows in
managing its financial and budgetary affairs. These are general statements of policies, which
represent long-standing principles, traditions, and practices that will be used to guide the City in
maintaining financial stability. It will be the responsibility of the Finance Department to ensure the
financial objectives of these policies are maintained.
Revenue Policy
1. The City will strive to maintain a broad and diversified revenue base that will equitably
distribute the burden of supporting City services and will protect the City from short-term
fluctuations in any one revenue source.
2. The City will actively support economic and industrial development recruitment and
retention efforts to provide for a solid revenue base.
3. The City will maintain timely collection systems and implement necessary enforcement
strategies to collect revenues from available sources.
4. The City will establish user fees and charges for services, when feasible, at levels related to
the cost of providing the services. The City will review the fees and charges every three to
five years to determine modifications needed to keep pace with the cost of providing the
services. Property Tax Rates are set annually
5. The City will establish, when feasible, self-supporting enterprise funds and intergovernmental
service funds in which a relationship between revenues and expenditures clearly exists.
6. The City will project current revenues on a conservative basis so the actual revenues will
consistently meet or exceed budgeted revenues. Revenues greater or less than the original
budget will flow through to the audited Ending Budget Balance.
7. The City will maintain a budgetary control system and will prepare reports, which compare
actual revenues to budgeted amounts.
8. The City will limit the designation of General Fund revenues for specified purposes to
maximize flexibility in budgeting and revenue utilization.
9. The City will review annually and revise, where necessary, its cost allocation formulas, i.e.
internal service departments.
10. Upon satisfying all rate covenants the City will provide operating transfers to the General
Fund. From the Water/Wastewater Utility no greater than $1,000,000 and from the Electric
Utility no greater than $10,000,000.
45
Página 52
Expenditure Policy
1. Basic and essential services provided by the City will receive first priority for funding, i.e.
Public Safety & Health, Utilities, Streets, & Sanitation.
2. A report of the expenses of the Public Safety categories that have been identified will be
presented to City Council two (2) times; once upon delivery of the proposed budget in May
and the other upon the adoption of the budget in July. The report will map the revenues that
have been identified to support the expenses, how much of a gap there is, and what the trend is
for closing the gap over a 20 year period. The revenues will be the direct revenues of those
programs and the Property Tax Revenue, excluding BID taxes.
3. The City will adopt a balanced budget, by fund, for all funds maintained by the City, in which
total anticipated revenues must equal or exceed the budgeted expenditures for each fund. The
Beginning Budget Balance will not be considered a revenue source.
4. The City will maintain a budgetary control system to ensure adherence to the original adopted
budget and will prepare reports, which compare actual expenditures to budgeted amounts.
Expenditures greater or less than the original adopted budget will flow through the audited
Ending Budget Balance.
5. The City will restrict the use of appropriations as follows:
• Funds appropriated for personnel expenses shall be restricted to use as personnel
expenses; Any personnel savings at the end of each fiscal year will be re-appropriated in
the next fiscal year to be transferred to the City’s unfunded retirement liabilities;
• Funds appropriated as capital expenses shall be restricted to use as capital expenses;
• Funds appropriated as operating expenses shall be restricted to use as operating
expenses;
• All requests for additional personnel shall be accompanied with a five-year estimate on
the costs of such position(s), including salaries and other employment costs (OEC’s);
6. The City will refrain from budgeting revenues derived from infrequent and unanticipated
transactions for ongoing expenses. These revenues will be set aside for asset replacement or
as otherwise directed by Council.
7. The City will provide access to medical, dental, vision, life, AD & D, and short-term disability
insurance for its employees. The cost for these benefits will be a shared responsibility
between the City and its employees as outlined in the City Personnel Handbook or collective
bargaining agreements
8. The City will provide access to medical and dental insurance for its retirees and their families.
The cost for these benefits will be a shared responsibility between the City and its retirees as
outlined in the City Personnel Handbook or collective bargaining agreements.
9. The City will provide access to appropriate retirement plans for its employees. The City will
make contributions for eligible employees at the actuarial determined percentage defined for
each of the respective retirement plans.
46
Página 53
10. The City will establish an Other Post-Employment Benefit Fund (OPEB). The City will make
contributions for eligible employees and retirees at the actuarial determined rates or
percentages to fund future retiree medical benefits.
Debt Policy
1. The City will maintain a debt management policy and full disclosure on financial reports.
2. The City will maintain communications with bond rating agencies and continue to strive for
improvements in the City’s bond rating.
3. The City will adhere to its debt covenants.
4. The City will review its debt capacity every three (3) years.
5. The City will pay for all capital projects and capital improvements on a pay-as-you-go basis
using current revenues if possible. If a project or improvement cannot be financed with current
revenues, long-term debt or use of reserves will be recommended.
6. The City will refrain from issuing long-term debt for a period in excess of the expected useful
life of the capital project.
7. The City will use special assessment revenue or other self-supporting bonds instead of general
obligation bonds, when practical.
8. The City will seek refinancing of outstanding debt if it is determined that the City will benefit
by reduced interest expense over the remaining life of the bonds.
Budget Balance/Reserve Policy – General Fund
1. The City will strive to maintain a minimum Budget Balance, of at least 8% and no greater than
12% of the current year operating revenues for the General Fund, excluding the carry forward
balance. The purpose of the budget balance is to meet temporary fluctuations in cash flows and
to provide a cushion for loss of revenues until operating changes can be implemented. If the
final Budget Balance exceeds the amount as approved in the budget ordinance, such funds shall
be used to provide for unfunded retirement liabilities or as otherwise designated by City
Council. The City may use monies in the Budget Balance only in times of fiscal and economic
hardship.
2. Once achieved, at no time should the City’s budget balances fall below their specified
percentages. If a shortfall occurs in the budget balance and immediately restoring the balances
to the specified percentage would cause an extreme burden on the taxpayers, the budget balance
may, with the City Council’s approval, be restored to the specified percentage within one (1)
year, but in any case, no longer than three (3) years.
3. The City will maintain a minimum reserve, in a contingency account, of at least $700,000. The
City may only use monies in the contingency accounts to cover emergencies of a non-recurring
nature that are over and above the normal course of operations. Examples are uninsured losses,
47
Página 54
storms or hurricane damages. The Contingency Reserve will not be used to balance the
operating budget.
4. The total of the General Fund budget and contingency balances shall not exceed 17% (~ 2
months) of Budgeted Operating Revenues.
5. The City will create a Capital Asset Replacement account for Governmental Fund asset
procurements. Optimally, the amount set aside for future asset replacements should equal the
annual depreciation of the current assets. (Annual Depreciation is approximately $2.5 million
per year) The City will appropriate excess (amounts greater than budgeted) revenues to fund
this account, or if the balance is less than the $500,000 minimum, $200,000 per annum until
such time the minimum balance is replenished.
6. The City will create a General Capital Project Fund to account for all General Government asset
procurements and projects. The City will provide operating fund transfers and/or debt proceeds
for each fiscal year’s Capital Investment Plan. All vehicle and equipment purchases under
$25,000 will be budgeted on a pay as you go basis.
Budget Balance/Reserve Policy – Water/Wastewater Fund
1. The City will strive to maintain a minimum Budget Balance, of at least 8% and no greater than
17% (two months) of the current year operating revenues for each of the Water & Wastewater
Utility Funds, excluding the carry forward balance. The purpose of the budget balance is to
meet temporary fluctuations in cash flows and to provide a cushion for loss of revenues until
operating changes can be implemented. If the final Budget Balance exceeds the amount as
approved in the budget ordinance, such funds shall be used to provide for unfunded retirement
liabilities or as otherwise designated by City Council. The City may use monies in the Budget
Balance only in times of fiscal and economic hardship.
2. Once achieved, at no time should the City’s budget balances fall below their specified
percentages. If a shortfall occurs in the budget balance and immediately restoring the balances
to the specified percentage would cause an extreme burden on the ratepayers, the budget balance
may, with the City Council’s approval, be restored to the specified percentage within one (1)
year, but in any case, no longer than three (3) years.
3. The City will maintain a minimum reserve, in a contingency account, of at least $250,000 for
each the Water & Wastewater Fund. The City may only use monies in the contingency accounts
to cover emergencies of a non-recurring nature that are over and above the normal course of
operations. Examples are uninsured losses, storms or hurricane damages. The Contingency
Reserve will not be used to balance the operating budget.
4. The total of the combined Water & Wastewater Fund budget and contingency balances shall not
exceed 25% (3 months) of Budgeted Operating Revenues.
5. The City will maintain a Capital Asset Replacement account to cover replacement or
procurement of assets of the utility. Optimally, the amount set aside for future asset
replacements should equal the annual depreciation of the current assets. The City will maintain
a minimum balance of $500,000 for each utility for Capital Asset Replacements. The City will
48
Página 55
appropriate excess revenues to fund this account, or if the balance is less than the minimum
$100,000 per annum for each utility until such time the minimum balance is achieved.
6. The City established by ordinance on December 17, 1996 the Wastewater Impact Fee Reserve to
provide for future expansion of the City’s wastewater system due to increased demand. The
ordinance further provides for debt service payments attributed to wastewater expansion
projects to be funded by the current year’s collection of Impact Fees and the remainder to be
deposited into the reserve account. The City shall maintain a minimum of 20% of wastewater
revenues in the Impact Fee Reserve account. Amounts used to finance projects shall be
replenished by the operating revenues of the Wastewater Fund over the succeeding seven years
of any project completion.
7. The City established by ordinance on February 1, 2008 the Water Impact Fee Reserve to
provide for future expansion of the City’s water system due to increased demand. The
ordinance further provides for debt service payments attributed to water system expansion
projects to be funded by the current year’s collection of Impact Fees and the remainder to be
deposited into the reserve account. The City shall maintain a minimum of $1.5 million of water
revenues in the Impact Fee Reserve account. Amounts used to finance projects shall be
replenished by the operating revenues of the Water Fund over the succeeding seven (7) years of
any project completion.
8. The Water & Wastewater Improvement & Extension Fund budget balance shall be no less than
$200,000 of the current fiscal year’s appropriation for water and wastewater projects to allow
for project variances and change orders; a 10% contingency shall be included in project budgets
greater than $250,000 if the Department Head determines it to be appropriate. All vehicle and
equipment purchases under $25,000 will be budgeted on a pay as you go basis. The City
Manager shall make the necessary budget amendments in accordance with the City of Dover
Purchasing & Budget Amendment Policies.
Budget Balance/Reserve Policy – Electric Revenue Fund
1. The City will strive to maintain a minimum Budget Balance, of at least 12% (45 days) of the
current year operating revenues for the Electric Revenue Fund, excluding the carry forward
balance and power cost adjustments. The purpose of the budget balance is to meet temporary
fluctuations in cash flows and to provide a cushion for loss of revenues until operating changes
can be implemented. If the final Budget Balance exceeds the amount as approved in the budget
ordinance, such funds shall be used to provide for unfunded retirement liabilities or as otherwise
designated by City Council. The City may use monies in the Budget Balance only in times of
fiscal and economic hardship.
2. Once achieved, at no time should the City’s budget balances fall below their specified
percentages. If a shortfall occurs in the budget balance and immediately restoring the balances
to the specified percentage would cause an extreme burden on the ratepayers, the budget balance
may, with the City Council’s approval, be restored to the specified percentage within one year,
but in any case, no longer than three years.
3. The City will maintain a minimum reserve, in a contingency account, of at least $750,000 for
the Electric Revenue Fund. The City may only use monies in the contingency accounts to cover
emergencies of a non-recurring nature that are over and above the normal course of operations.
49
Página 56
Examples are uninsured losses, storms or hurricane damages. The Contingency Reserve will
not be used to balance the operating budget.
4. The total of the combined Electric Revenue Fund budget and contingency balances shall not
exceed 25% (3 months) of Budgeted Operating Revenues.
5. The City has established by bond covenant an account to cover insurance deductibles on the
electric transmission and distribution system or the generating plants. The City shall maintain a
minimum balance of $750,000 to cover various deductibles.
6. Recognizing price fluctuations in the wholesale power markets the City has established a rate
stabilization reserve. The purpose of using such a reserve is to level off the fluctuations in the
wholesale power supply market and in turn provide stable rates to our customers. In those
instances where the actual cost of power supply and generation are less/more than the budgeted
cost of power supply and generation, the City will transfer the difference to/from the Rate
Stabilization Reserve. The balance shall be maintained at a minimum of 10% not to exceed
20% of the purchase power cost in any given year. If the reserve balance exceeds the 20%
maximum, a credit will be applied to the power cost adjustment.
7. The Electric Improvement & Extension Fund budget balance shall be no less than $200,000 of
the current fiscal year’s appropriation for electric system projects to allow for project variances
and change orders; a 10% contingency shall be included in project budgets greater than
$250,000 if the Department Head determines it to be appropriate. All vehicle and equipment
purchases under $25,000 will be budgeted on a pay as you go basis. The City Manager shall
make the necessary budget amendments in accordance with the City of Dover Purchasing &
Budget Amendment Policies.
8. The City has established an account to provide for capital financing of Future Capacity or
system expansion. The City shall maintain a balance equivalent to the value of 10% growth in
capacity at any given time, or no less than $10,000,000. Amounts used to finance projects shall
be replenished by the operating revenues of the Electric Revenue Fund over the succeeding
seven years of any project completion.
9. The City has established an account to provide for replacement or procurement of utility system
assets, otherwise known as Depreciation Reserve. Optimally, the amount set aside for future
asset replacements should equal the annual depreciation of the current assets. The City will
maintain a minimum balance of $10,000,000. The primary purpose of this account is to provide
partial or all financing of major capital projects and minimize debt service payments. The
account is also intended to cover unforeseen capital replacements due to equipment breakdowns,
storms or hurricane damages. Amounts used to finance projects shall be replenished by the
operating revenues of the Electric Revenue Fund over the succeeding seven (7) years of any
project completion
10. The total of the combined Electric Revenue and Electric Improvement & Extension Fund budget
and reserve balances shall be benchmarked at 50% Budgeted Operating Revenues. Operating
Fund Budget Balance and Reserves shall be adjusted to appropriate levels through adjustments
in the operating budget. Improvement & Extension Fund Budget Balance and Reserves shall be
adjusted in accordance with the Capital Improvement Plan.
50
Página 57
Investment and Cash Management Policy
1. The City will deposit all receipts on a timely basis in interest bearing accounts.
2. The City will strive to maximize the return on its investment portfolio without jeopardizing
principal amounts.
3. The City will limit its investments to the types of securities provided for by Delaware statutes.
4. The City will diversify its investments by maturity date to protect against market fluctuations.
5. The City will purchase securities from qualified institutions based on competitive bids in an
effort to obtain the highest available rates.
6. The City will maintain an Investment Policy based on prudent investment practices and will
monitor all investment managers’ compliance with policy objectives.
Capital Improvement Policy
1. The City will prepare and update, as needed a five-year Capital Improvements Program (CIP)
which will provide for the orderly maintenance, replacement, and expansion of capital assets.
2. The CIP will identify long-range capital projects and capital improvements of all types, which
will be coordinated with the annual operating budget to maintain full utilization of available
revenue sources.
3. When preparing the CIP, the City will seek to identify all viable capital projects and capital
improvements required during the subsequent five-year period. These projects and
improvements will be prioritized by year and by funding source.
4. Every attempt will be made to match projects and improvements with available funding sources.
Future operating costs and savings associated with a project or an improvement will also be
given consideration in the establishment of priorities.
5. When appropriate, the City will seek Federal, State, and other funding to assist in financing
capital projects and capital improvements.
6. The City will incorporate the reasonable findings and recommendations of other cities’ Boards,
Commissions, Committees, and Citizen Task Forces, as they relate to capital projects and
improvements.
7. The City will seek input from the public by holding public hearings in relation to the
establishment of projects and project priorities.
Financial Reporting Policy
1. The City’s accounting system will maintain records in accordance with accounting standards
and principles outlined by the Governmental Accounting Standards Board (GASB), Financial
Accounting Standards Board (FASB), and the State of Delaware.
51
Página 58
2. The City will employ an independent accounting firm to perform an annual audit of the City’s
finances and make the annual audit available to all required and interested parties.
3. The City will produce monthly and quarterly financial statements reporting the current periods’
activity for all funds maintained by the City.
4. The City will prepare an annual budget document that provides a basic understanding of the
City’s planned financial operations for the coming fiscal year. Copies of the proposed and final
budget will be made available to all interested parties and opportunities will be provided for
citizen input prior to final decisions on the budget.
5. The City will place continued emphasis on review and maintenance of an accounting system
which provides strong internal budgetary and accounting controls designed to provide
reasonable assurance, but not absolute, assurance regarding:
(a) the safeguarding of assets against loss from unauthorized use or disposition and,
(b) the reliability of financial records for preparing financial statements and reports, and the
maintaining accountability for assets.
6. The City will seek annual renewal of the Government Finance Officers Association’s (GFOA)
Certificate of Achievement for Excellence in Financial Reporting.
7.
Adoption:
Approval by City Council: January 28, 2002
Most recent amendments:
1. Amended by City Council on June 11, 2014
2. Amended by City Council on September 8, 2014
3. Amended by City Council on October 12, 2015
52
Página 59
CITY OF DOVER
DEPARTMENT OF FINANCE
POLICY MANUAL
TITLE: Budget Administration – Policy
for Operating Departments DATE: September 8, 2014
Each Department Head is responsible for managing their overall budgets for account variances
created by routine operating expenses. This policy is intended to permit the redistribution of funds in
departmental budgets when unexpected events or transactions occur. It establishes the procedure to
be followed when the approval of a supplemental appropriation is requested. It restricts the
redistribution of personnel and capital outlay accounts. All redistributions are to be rounded to the
nearest hundred dollars (no cents).
1. Definitions, as used in this policy:
“Fund”: In governmental accounting, a fund is a fiscal and accounting entity with a self-
balancing set of accounts, created and maintained for a particular purpose and having
transactions subject to legal or administrative restrictions. A separate budget is provided for
each fund.
“Department”: Departments are the major organizational sub-divisions. They have a broad
overall purpose. The City of Dover is organized into twelve (12) departments: City Clerk,
City Manager, Customer Services, Electric, Information Services, Finance and Procurement
& Inventory, Human Resources, Planning & Inspections and Parks & Recreation & Library,
Police, Public Works, and Tax Assessor.
“Division”: Is the major operational areas of the City. Each Division has been assigned to
one of the Departments listed above according to the type of activity it performs. For
example, the Electric Engineering Division is part of the Electric Department.
“Category”: Within each division, each expenditure line item is grouped into a category of
related expenditures. The budget for each line item is listed by categorical total. Examples of
a category include personnel services, materials & supplies, administrative expenditures,
capital outlay, project accounts, and depreciation.
2. Department Managers may redistribute monies “within” a group of accounts in a particular
category, except salary/benefits, and capital outlay accounts to address unexpected events or
transactions. Form COD #98 shall be used to request the transfer of funds. The monies shall
not be encumbered until the Controller/Treasurer has returned a copy of Form COD #98
advising the manager that the redistribution has been entered into the budget software.
3. Transfers between categories material/supplies and administrative are permitted.
4. Transfers from salary and benefit accounts are permitted upon the approval of the City
Council to cover unanticipated expenses created by vacancies. Budget savings from these
line items will transferred to the pension and OPEB funds towards the City’s unfunded
liability.
53
Página 60
5. The redistribution request must be submitted to the Finance Department for verification and
confirmation, and then Finance will forward to the City Manager. Confirmation of the change
will be made to the originating department by the Finance Department once the change has
been approved.
6. No funds authorized in capital outlay may be encumbered unless said purchase was detailed
in the “approved” budget.
Any Capital Improvement Project (CIP) deferrals due to cost over-runs in other CIP items
shall be communicated to the Council and the Controller/Treasurer.
The City Manager may approve transfers of savings from completed CIP items to non-
completed CIP items. Any transfers that cause the particular item or project to exceed its
original budget 10% or greater will be communicated to Council and the Controller/Treasurer.
To request an exception in capital outlay or project categories, submit a written memorandum
explaining the request and attach a copy of the original budget submission. The memorandum
must explain the reason for not purchasing the authorized items. A copy noting the action
taken on the request by the City Manager will be returned to the respective department.
Council and the Controller/Treasurer will be copied on all exception request approvals.
All capital outlay change requests must be accompanied by a Capital Improvement Project
worksheet in the following instances:
- Scrap a CIP and create a new CIP
- Reduce approved CIP and create a new CIP
- New funded CIP (grant)
The Controller/Treasurer will adjust project budgets each year to include prior year project
balances before finalizing the Carry Forward Budget Balances for multi-year projects or
projects not completed due to unforeseen circumstances. This process will be followed only
on projects that were approved by City Council in a prior year CIP.
7. The City Manager may approve intra-fund transfers (i.e., within the General Fund) of up to
five percent per annum, Form COD #98, with the exception of line items associated with
salary and benefits.
8. All personnel positions will receive and be adhered to, the documented increases as approved
through the budget process. Any exceptions require Council approval.
9. Budget amendments exceeding that authorized above or that affect budget balances shall be
referred to the City Council.
54
Página 61
CITY OF DOVER
COST CENTER REQUEST FOR BUDGET AMENDMENT
Department: Fiscal Year:
From Account #: Date of Request:
To Account #: (Check Only One)
Change Within Budget
Supplemental Appropriation
By: Departmental Transfers
(Signature)
Net Current Requested
Element Account Original Previous Revised Change or Adjusted YTD
Object Name Budget Changes Budget Supplement Budget Expense
FROM
TO
1 2 3 4 5 6 7 8
Request Justification:
Instructions: Complete all appropriate items. Figures in columns four and seven must be preceded by a "plus"
or a "minus" sign. Round all figures to nearest one hundred dollar. Use the reverse side of this form if additional
space is needed to justify request. Form must bear the live signature(s) of cost center manager(s). Before
submitting request to Finance Department for consideration, obtain verification from the accounting department that
all figures are correct. Submit copy of request to the City Manager. A copy will be returned noting the action taken.
Approval:
City Manager Controller/Treasurer
Date of Action:
Approved as: Requested Approved as Modified Denied
Deferred Until:
For Finance Department Use Only Processed: By:
COD FINANCE FORM 98
55
Página 62
PERSONNEL TABLE
PERSONNEL COST SUMMARY
OVERTIME TRENDS
FY 14 THROUGH FY 17 COMPARISON
Página 63
FY 2017 DRAFT ANNUAL OPERATING BUDGET - DOVER, DELAWARE
City of Dover
Fiscal Year 2017 Proposed Budget
2014-2015 2015-2016 2016-2017
DEPT/DIVISION
BUDGET BUDGET BUDGET CHANGE
CITY CLERK 4.0 4.0 4.0 0.0
CITY MANAGER 4.0 4.0 4.0 0.0
CODE ENFORCEMENT 5.0 5.0 5.0 0.0
CUSTOMER SERVICES 14.0 14.0 13.0 (1.0)
ECONOMIC DEVELOPMENT 3.0 3.0 3.0 0.0
FACILITIES MANAGEMENT 7.0 7.0 5.0 (2.0)
FINANCE 8.0 8.0 8.0 0.0
FIRE DEPARTMENT 6.0 5.0 5.0 0.0
FLEET MAINTENANCE 6.0 6.0 6.0 0.0
GROUNDS 13.0 13.0 13.0 0.0
HUMAN RESOURCES 3.0 3.0 3.0 0.0
INFORMATION TECHNOLOGY 5.0 4.0 4.0 0.0
INSPECTIONS 6.0 6.0 6.0 0.0
LIBRARY 13.0 13.0 13.0 0.0
LIFE SAFETY 3.0 3.0 3.0 0.0
MAYOR 1.0 1.0 1.0 0.0
PARKS AND RECREATION 5.0 5.0 5.0 0.0
PLANNING 5.0 6.0 6.0 0.0
POLICE - TOTAL* 124.0 134.0 134.0 0.0
PROCUREMENT AND INVENTORY 3.0 3.0 3.0 0.0
PUBLIC WORKS - ADMINISTRATION 5.0 6.0 6.0 0.0
PUBLIC WORKS - ENGINEERING 3.0 3.0 3.0 0.0
SANITATION 11.0 10.0 10.0 0.0
STREETS 8.0 8.0 8.0 0.0
TAX ASSESSOR 3.0 3.0 3.0 0.0
GENERAL FUND AND CDBG TOTAL 268.0 277.0 274.0 (3.0)
ELECTRIC ADMINISTRATION 3.0 4.0 5.0 1.0
ELECTRIC SYSTEM OPERATIONS 5.0 5.0 5.0 0.0
ELECTRIC ENGINEERING 10.0 10.0 10.0 0.0
ELECTRIC T & D 24.0 24.0 24.0 0.0
METER READING - CUSTOMER SERVICE 3.0 4.0 4.0 0.0
ELECTRIC FUND TOTAL 45.0 47.0 48.0 1.0
WATER/WASTEWATER ENGINEERING 5.0 5.0 5.0 0.0
WATER CONSTRUCTION 3.0 0.0 0.0 0.0
WATER MANAGEMENT 4.0 6.0 6.0 0.0
WASTEWATER MANAGEMENT 11.0 11.0 11.0 0.0
WATER TREATMENT PLANT 11.0 13.0 13.0 0.0
WATER/WASTEWATER FUND TOTAL 34.0 35.0 35.0 0.0
TOTAL FULL-TIME PERSONNEL 347.0 359.0 357.0 (2.0)
*101 Officers; 33 Civilians - 134 Total Employees
2014-2015 2015-2016 2016-2017
DEPT/DIVISION
BUDGET BUDGET BUDGET CHANGE
PART-TIME PERSONNEL
CITY COUNCIL COMMITTEES 17.0 17.0 17.0 0.0
CITY MANAGER 0.0 4.0 4.0 0.0
PLANNING COMMISSION 14.0 14.0 14.0 0.0
FIRE (4 On Call Dispatchers & Chief's Assistant) 2.0 3.0 5.0 2.0
GROUNDS 1.0 0.0 0.0 0.0
PARKS AND RECREATION 14.0 14.0 14.0 0.0
LIBRARY 13.0 19.0 19.0 0.0
PROCUREMENT AND INVENTORY 1.0 1.0 1.0 0.0
CUSTOMER SERVICES 1.0 4.0 4.0 0.0
FINANCE 0.0 1.0 0.0 (1.0)
INFORMATION TECHNOLOGY 0.0 1.0 1.0 0.0
ELECTRIC ENGINEERING 0.0 0.0 1.0 1.0
COMMUNITY DEVELOPMENT GRANT 0.0 0.0 0.0 0.0
SUBSTANCE ABUSE GRANT 15.0 10.0 10.0 0.0
POLICE CADET - GRANT 0.0 6.0 6.0 0.0
TOTAL PART-TIME PERSONNEL 78.0 94.0 96.0 2.0
TOTAL PERSONNEL 425.0 453.0 453.0 0.0
57
Página 64
FY 2017 DRAFT ANNUAL OPERATING BUDGET - DOVER, DELAWARE
City of Dover
Personnel Budget
Fiscal Year 2017
Total City by Fund
Dept/Div Division Base Pay Bonus/Allow./SD Overtime Part Time/Temp Total Total Total
Number Title 10-11 On Call 10-11 10-12 10-13 Wages Benefits Personnel
1100-511 City Clerk $ 228,300 $ - $ - $ - $ 228,300 $ 144,500 $ 372,800
1200-512 City Council - - - 84,300 84,300 6,700 91,000
1300-513 Assessor 132,200 - - - 132,200 85,700 217,900
1400-514 Fire 207,500 600 43,000 37,100 288,200 149,500 437,700
1500-522 Grounds 493,200 2,200 12,200 - 507,600 445,800 953,400
1500-523 Library 616,300 - 3,700 271,200 891,200 477,800 1,369,000
1500-525 Recreation 234,400 - 1,600 122,100 358,100 141,400 499,500
1600-531 Life Safety 150,300 8,500 8,000 - 166,800 64,800 231,600
1600-532 Code Enforcement 222,700 - 2,500 - 225,200 171,100 396,300
1600-533 Planning 380,300 (36,000) 1,000 15,000 360,300 152,800 513,100
1600-534 Building Inspections 277,500 - 2,000 - 279,500 224,100 503,600
1600-535 Economic Development 151,700 - - - 151,700 62,700 214,400
1700-542 Civilian Police 1,467,600 26,100 70,900 - 1,564,600 1,029,100 2,593,700
1700-543 Law Enforcement 7,291,700 212,100 450,600 - 7,954,400 4,298,500 12,252,900
1700-544 Police Extra Duty 704,300 - - - 704,300 97,400 801,700
1800-554 Streets 306,800 1,700 7,900 - 316,400 272,600 589,000
1800-555 Sanitation 380,800 1,300 17,500 - 399,600 333,300 732,900
2100-515 City Manager 345,500 6,000 2,000 11,500 365,000 138,300 503,300
2200-516 Information Technology 250,200 - - 13,800 264,000 177,400 441,400
2300-517 Finance 515,800 - - - 515,800 295,800 811,600
2400-551 Public Works Admin 370,500 500 - - 371,000 290,600 661,600
2500-552 Facilities 234,900 700 6,400 - 242,000 217,500 459,500
2600-553 Public Works Engineering 132,400 400 500 - 133,300 70,300 203,600
2700-571 Procurement & Inventory 165,800 - 1,000 21,400 188,200 125,800 314,000
2800-572 Fleet Maintenance 280,100 3,300 6,700 - 290,100 176,100 466,200
2900-529 Customer Service 556,100 - - 82,700 638,800 438,400 1,077,200
3100-518 Human Resources 187,100 - - - 187,100 158,000 345,100
3200-519 Mayor 45,000 - - - 45,000 12,300 57,300
Total General Fund $ 16,329,000 $ 227,400 $ 637,500 $ 659,100 $ 17,853,000 $ 10,258,300 $ 28,111,300
Dept/Div Division Base Pay Bonus/Allow./SD Overtime Part Time/Temp Total Total Total
Number Title 10-11 On Call 10-11 10-12 10-13 Wages Benefits Personnel
2600-553 Engineering $ 310,900 $ 900 $ 1,000 $ - $ 312,800 $ 140,800 $ 453,600
6800-568 Water 281,000 8,200 12,000 - 301,200 226,200 527,400
6900-569 Wastewater 383,400 12,700 25,000 - 421,100 233,300 654,400
7600-576 Water Treatment 583,400 6,000 30,000 - 619,400 420,700 1,040,100
Total Water/Wastewater Fund $ 1,558,700 $ 27,800 $ 68,000 $ - $ 1,654,500 $ 1,021,000 $ 2,675,500
Dept/Div Division Base Pay Bonus/Allow./SD Overtime Part Time/Temp Total Total Total
Number Title 10-11 On Call 10-11 10-12 10-13 Wages Benefits Personnel
8200-562 T&D $ 1,513,300 $ 49,200 $ 106,800 $ - $ 1,669,300 $ 983,200 $ 2,652,500
8300-563 Engineering 605,200 10,800 11,100 10,600 637,700 303,800 941,500
8400-564 Administration 346,700 - - - 346,700 133,000 479,700
8500-565 Meter Reading 185,100 8,100 19,100 12,500 224,800 125,800 350,600
8600-526 System Operators 338,800 5,200 72,900 - 416,900 234,800 651,700
Total Electric Fund $ 2,989,100 $ 73,300 $ 209,900 $ 23,100 $ 3,295,400 $ 1,780,600 $ 5,076,000
Dept/Div Division Base Pay Bonus/Allow./SD Overtime Part Time/Temp Total Total Total
Number Title 10-11 On Call 10-11 10-12 10-13 Wages Benefits Personnel
9900-596 CDBG $ - $ 36,000 $ - $ - $ 36,000 $ - $ 36,000
9900-542 Police Cadet Program - - - 71,400 71,400 9,700 81,100
1500-581 Substance Abuse Grant - - - 59,600 59,600 4,700 64,300
Total Grant Funds $ - $ 36,000 $ - $ 131,000 $ 167,000 $ 14,400 $ 181,400
GRAND TOTAL $ 20,876,800 $ 364,500 $ 915,400 $ 813,200 $ 22,969,900 $ 13,074,300 $ 36,044,200
58
Página 65
FY 2017 DRAFT ANNUAL OPERATING BUDGET - DOVER, DELAWARE
CITY OF DOVER
OVERTIME COMPARISON
FISCAL YEAR 2014 THROUGH 2017
2014 2015 2016 THROUGH APRIL (83.0%) 2017
DEPARTMENT Orig. Budget Actual Variance % To Date Orig. Budget Actual Variance % To Date Orig. Budget Actual Variance % To Date Proposed
CITY CLERK - - - --- - - - --- - - - --- -
FIRE 48,800 45,836 2,964 93.9% 32,000 43,706 (11,706) 136.6% 43,000 27,699 15,301 64.4% 43,000
GROUNDS 14,900 15,057 (157) 101.1% 11,100 12,002 (902) 108.1% 8,300 11,925 (3,625) 143.7% 12,200
PARKS & RECREATION - 102 (102) --- - 398 (398) --- 1,500 1,271 229 84.7% 1,600
LIBRARY 3,700 5,496 (1,796) 148.5% 3,900 3,714 186 95.2% 5,600 2,892 2,708 51.6% 3,700
LIFE SAFETY 7,000 9,523 (2,523) 136.0% 7,600 8,683 (1,083) 114.2% 8,600 3,380 5,220 39.3% 8,000
CODE ENFORCEMENT 2,000 1,179 821 58.9% 2,000 1,891 109 94.5% 5,000 1,025 3,975 20.5% 2,500
PLANNING - 377 (377) --- - 282 (282) --- 700 729 (29) 104.2% 1,000
PUBLIC INSPECTIONS 1,000 1,840 (840) --- 1,800 2,084 (284) 115.8% 1,800 2,975 (1,175) 165.3% 2,000
POLICE CIVILIAN 66,200 83,514 (17,314) 126.2% 50,000 82,711 (32,711) 165.4% 66,400 71,029 (4,629) 107.0% 70,900
POLICE LAW ENFORCEMENT 500,000 355,468 144,532 71.1% 400,000 433,344 (33,344) 108.3% 445,000 357,336 87,664 80.3% 450,400
STREET 8,800 10,867 (2,067) 123.5% 4,700 7,574 (2,874) 161.1% 4,100 6,836 (2,736) 166.7% 7,900
SANITATION 13,200 26,215 (13,015) 198.6% 12,100 17,988 (5,888) 148.7% 12,100 14,932 (2,832) 123.4% 17,500
CITY MANAGER 1,500 2,513 (1,013) 167.5% 2,000 517 1,483 25.9% 2,000 1,192 808 59.6% 2,000
FINANCE - 104 (104) --- - 37 (37) --- - 12 (12) #DIV/0! -
PW ADMINISTRATION - - - --- - - - --- - - - #DIV/0! -
FACILITIES MANAGEMENT 7,600 14,238 (6,638) 187.3% 10,500 11,771 (1,271) 112.1% 10,500 7,990 2,510 76.1% 6,400
PROCUREMENT & INVENTORY - 2,132 (2,132) --- 1,600 756 844 47.2% 1,000 423 577 42.3% 1,000
VEHICLE MAINTENANCE 2,400 10,451 (8,051) 435.5% 1,000 6,302 (5,302) 630.2% 1,000 6,021 (5,021) 602.1% 6,700
HUMAN RESOURCES - - - --- - - - --- - 159 (159) #DIV/0! -
WATER ENGINEERING 3,300 927 2,373 28.1% 1,600 943 657 58.9% 800 - 800 0.0% 1,000
CONSTRUCTION & MAINT 15,000 12,178 2,822 81.2% 7,100 6,743 357 95.0% - - - #DIV/0! -
WATER 11,200 11,755 (555) 105.0% 9,100 8,632 468 94.9% 13,400 12,374 1,026 92.3% 12,000
WASTE-WATER 27,100 24,351 2,749 89.9% 27,000 23,559 3,441 87.3% 27,000 11,467 15,533 42.5% 25,000
WATER TREATMENT PLANT 19,700 24,591 (4,891) 124.8% 34,800 26,750 8,050 76.9% 32,300 38,011 (5,711) 117.7% 30,000
TRANSMISSION/DISTRIBUTION 127,800 110,376 17,424 86.4% 115,000 111,864 3,136 97.3% 115,000 87,458 27,542 76.1% 106,800
ELECTRIC ENGINEERING 15,000 10,912 4,088 72.7% 11,000 7,792 3,208 70.8% 11,000 4,387 6,613 39.9% 11,100
ELECTRIC ADMINISTRATION - - - --- 2,000 91 1,909 4.6% 2,000 - 2,000 0.0% -
ELECTRIC METERING 8,800 9,377 (577) 106.6% 5,000 13,155 (8,155) 263.1% 11,100 13,700 (2,600) 123.4% 19,100
ELECTRIC SYSTEMS OPERATIONS 50,300 68,038 (17,738) 135.3% 50,000 77,426 (27,426) 154.9% 50,000 58,374 (8,374) 116.7% 72,900
TOTAL 955,300 857,416 97,884 89.8% 802,900 910,713 (107,813) 113.4% 879,200 743,596 135,604 84.6% 914,700
ELECTRIC PLANT OPERATIONS 229,500 226,536 2,964 98.7% 198,700 230,378 (31,678) 115.9% 209,200 196,978 12,222 94.2% 185,500
POLICE EXTRA DUTY 690,400 588,971 101,429 85.3% 633,300 478,834 154,466 75.6% 529,200 357,071 172,129 67.5% 704,300
59
Página 66
GENERAL FUND
WATER/WASTEWATER FUND
ELECTRIC REVENUE FUND
Página 68
City of Dover
General Fund
Financial Projections
2017 – 2021
Budget Meetings
May 24, 2016
62
Página 69
Key Assumptions
• The FY17 – FY21 Forecast continues to be short on revenues to cover projected expenses incorporating the
current growth assumptions.
• Projected Revenues
Miscellaneous Revenue – includes Franchise fees, rental income, recreation revenues, administration fees for collecting
County impact fees, sale of assets, and other miscellaneous items
Transfers In Other (Funds) – includes transfer of revenues from Transfer Taxes, and Police Grants for Extra Duty
reimbursements
Growth Assumptions on slide #4
• Projected Operating Expenses
Other Charges represents the set aside for vacation sell back, retirements, and education assistance
Fund Expense – includes Insurance, bad debt expense, City Police Pension Plan appropriations, miscellaneous grant
expenses and DDP contributions
Growth assumptions as indicated on slide #5
• Water/Wastewater Fund Transfer
Phases-in increase for Wastewater each year through 2020
• Funds Capital projects through operating transfers, reserves, and grants
Exceptions are the Tar Ditch storm water project, estimated at $7.7 million, and redevelopment of Schutte Park $3.5
million. Total $11.2 million; Will require debt issuance and/or grants; See slide #9
63
Página 70
Revenues, Expenditures & Fund Balance
2016B 2017B 2018F 2019F 2020F 2021F
FUND BALANCE-BEGINNING 4,400,300 4,073,800 4,073,800 2,719,400 950,600 (1,004,000)
REVENUES AND SOURCES
01-PROPERTY TAXES 12,833,500 12,932,900 13,094,600 13,258,300 13,424,000 13,598,500
02-LICENSES AND PERMITS 2,908,300 3,129,100 3,156,000 3,219,100 3,283,500 3,349,100
03-GRANTS RECEIVED 1,346,600 1,296,600 1,296,600 1,296,600 1,296,600 1,296,600
04-COURT OF CHANCERY FEES 1,090,400 1,100,000 1,122,000 1,144,400 1,167,300 1,190,600
05-SANITATION FEES AND REBATES 2,530,000 2,538,300 2,551,000 2,563,700 2,576,600 2,589,400
06-LIBRARY REVENUE - GENERAL 379,600 382,900 384,800 386,700 388,700 390,600
07-FINES AND POLICE REVENUE 1,112,900 1,288,300 1,301,200 1,314,200 1,327,300 1,340,600
08-INVESTMENT INCOME (LOSS) 140,000 90,000 90,500 90,900 91,400 91,800
09-MISCELLANEOUS SERVICES 981,800 981,300 996,000 1,015,900 1,036,300 1,057,000
10-INDIRECT SERVICES BILLING 5,006,200 5,218,700 5,375,300 5,536,500 5,702,600 5,873,700
11-TRANSFERS IN-ELECTRIC 10,000,000 10,000,000 10,000,000 10,000,000 10,000,000 10,000,000
12-TRANSFERS IN-WATER/WW 850,000 875,000 900,000 950,000 1,000,000 1,000,000
13-TRANSFERS IN-OTHER 2,756,100 2,428,200 2,471,600 2,515,900 2,561,000 2,607,000
TOTAL REVENUES AND SOURCES 41,935,400 42,261,300 42,739,600 43,292,200 43,855,300 44,384,900
EXPENDITURES AND USES
01-SALARIES AND WAGES 17,437,800 17,838,500 18,270,300 18,727,100 19,195,300 19,675,100
02-FICA 1,315,600 1,366,700 1,400,900 1,435,900 1,471,800 1,508,600
03-HEALTH INSURANCE 3,009,500 3,401,400 3,605,500 3,821,800 4,051,100 4,294,200
04-OTHER-BENEFITS 650,800 715,500 722,700 729,900 737,200 744,600
05-RETIREE HEALTHCARE 1,567,700 2,039,700 2,121,300 2,206,100 2,294,400 2,386,200
07-PENSION 2,689,700 3,262,800 3,344,400 3,428,000 3,513,700 3,601,500
08-OPEB 1,773,100 1,508,300 1,538,500 1,569,200 1,600,600 1,632,600
09-MATERIALS & SUPPLIES 1,364,600 1,380,700 1,394,500 1,408,500 1,422,500 1,436,800
10-ADMIN EXPENDITURES 5,172,800 4,981,800 5,056,500 5,132,400 5,209,400 5,287,500
11-FUND EXPENSE 2,251,100 2,025,000 2,025,000 2,025,000 2,025,000 2,025,000
12-STREET LIGHT 797,700 804,000 808,000 812,100 816,100 820,200
13-OTHER-CHARGES 342,400 392,200 392,200 392,200 392,200 392,200
14-TRANSFER-TO-DEBT 669,400 685,300 428,700 428,700 428,700 428,700
15-TRANSFER-TO-CIP 2,625,400 1,859,400 2,985,500 2,944,100 2,652,100 3,332,200
TOTAL REVENUES AND SOURCES 42,261,900 42,261,300 44,094,000 45,061,000 45,810,100 47,565,400
SURPLUS/(DEFICIT) (326,500) - (1,354,400) (1,768,800) (1,954,800) (3,180,500)
% REVENUE -1% 0% -3% -4% -4% -7%
FUND BALANCE-ENDING 4,073,754 4,073,800 2,719,400 950,600 (1,004,000) (4,184,600)
% OF REVENUES AND SOURCES 9.7% 9.6% 6.4% 2.2% -2.3% -9.4%
Additional Funds Needed (718,900) (692,900) 699,800 2,512,800 4,512,400 7,735,400
64
Página 71
Revenue Assumptions
REVENUES AND SOURCES
ACCTTYPE 2016B 2017B 2018F 2019F 2020F 2021F
ACCTTYPE 1.3% 1.3% 1.3% 1.3%
01-PROPERTY TAXES 12,833,500 12,932,900 13,094,600 13,258,300 13,424,000 13,598,500
01-PROPERTY TAXES 14.4% 0.8% 1.3% 1.3% 1.2% 1.3%
ACCTTYPE 2.0% 2.0% 2.0% 2.0%
03-LICENSES AND PERMITS 2,908,300 3,129,100 3,191,700 3,255,500 3,320,600 3,387,000
03-LICENSES AND PERMITS 0.5% 7.6% 2.0% 2.0% 2.0% 2.0%
ACCTTYPE 0.0% 0.0% 0.0% 0.0%
04-GRANTS RECEIVED 1,427,100 1,401,600 1,401,600 1,401,600 1,401,600 1,401,600
04-GRANTS RECEIVED -1.9% -1.8% 0.0% 0.0% 0.0% 0.0%
ACCTTYPE 2.0% 2.0% 2.0% 2.0%
05-COURT OF CHANCERY FEES 1,090,400 1,100,000 1,122,000 1,144,400 1,167,300 1,190,600
05-COURT OF CHANCERY FEES -2.5% 0.9% 2.0% 2.0% 2.0% 2.0%
ACCTTYPE 0.5% 0.5% 0.5% 0.5%
06-SANITATION FEES AND REBATES 2,530,000 2,538,300 2,550,992 2,563,746 2,576,565 2,589,448
06-SANITATION FEES AND REBATES -1.9% 0.3% 0.5% 0.5% 0.5% 0.5%
ACCTTYPE 0.5% 0.5% 0.5% 0.5%
07-LIBRARY REVENUE - GENERAL 379,600 382,900 384,815 386,739 388,672 390,616
07-LIBRARY REVENUE - GENERAL -21.1% 0.9% 0.5% 0.5% 0.5% 0.5%
ACCTTYPE 1.0% 1.0% 1.0% 1.0%
08-FINES 1,112,900 1,288,300 1,301,183 1,314,195 1,327,337 1,340,610
08-FINES -4.9% 15.8% 1.0% 1.0% 1.0% 1.0%
ACCTTYPE 0.5% 0.5% 0.5% 0.5%
09-INVESTMENT INCOME (LOSS) 145,000 95,000 95,475 95,952 96,432 96,914
09-INVESTMENT INCOME (LOSS) 89.6% -34.5% 0.5% 0.5% 0.5% 0.5%
ACCTTYPE 1.5% 2.0% 2.0% 2.0%
10-MISCELLANEOUS SERVICES 1,177,300 981,300 996,020 1,015,940 1,036,259 1,056,984
10-MISCELLANEOUS SERVICES 0.8% -16.6% 1.5% 2.0% 2.0% 2.0%
ACCTTYPE 3.0% 3.0% 3.0% 3.0%
11-INDIRECT SERVICES BILLING 5,006,200 5,218,700 5,375,261 5,536,519 5,702,614 5,873,693
11-INDIRECT SERVICES BILLING 3.9% 4.2% 3.0% 3.0% 3.0% 3.0%
ACCTTYPE 0.0% 0.0% 0.0% 0.0%
12-TRANSFERS IN-OTHER 185,900 258,600 258,600 258,600 258,600 258,600
12-TRANSFERS IN-OTHER 0.0% 39.1% 0.0% 0.0% 0.0% 0.0%
ACCTTYPE 0.0% 0.0% 0.0% 0.0%
12-TRANSFERS IN-ELECTRIC FUND (480) 10,000,000 10,000,000 10,000,000 10,000,000 10,000,000 10,000,000
12-TRANSFERS IN-ELECTRIC FUND (480) 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%
ACCTTYPE 0.0% 0.0% 0.0% 0.0%
12-TRANSFERS IN-WATER/WW FUND (412) 850,000 875,000 900,000 950,000 1,000,000 1,000,000
12-TRANSFERS IN-WATER/WW FUND (412) 70.0% 2.9% 2.9% 5.6% 5.3% 0.0%
ACCTTYPE 2.0% 2.0% 2.0% 2.0%
12-TRANSFERS IN-ERLSP (212) 480,000 496,900 506,838 516,975 527,314 537,861
12-TRANSFERS IN-ERLSP (212) -3.1% 3.5% 2.0% 2.0% 2.0% 2.0%
ACCTTYPE 2.0% 2.0% 2.0% 2.0%
12-TRANSFERS IN-REALTY TRANSFER TAX 2,090,200 1,672,700 1,706,154 1,740,277 1,775,083 1,810,584
12-TRANSFERS IN-REALTY TRANSFER TAX 22.0% -20.0% 2.0% 2.0% 2.0% 2.0%
65
Página 72
Expenditure Assumptions
EXPENDITURES AND USES
ACCTTYPE 2016B 2017B 2018F 2019F 2020F 2021F
ACCTTYPE 2.5% 2.5% 2.5% 2.5%
01-SALARIES AND WAGES 17,437,800 17,838,500 18,284,463 18,741,574 19,210,113 19,690,366
01-SALARIES AND WAGES 5.4% 2.3% 2.5% 2.5% 2.5% 2.5%
ACCTTYPE 2.5% 2.5% 2.5% 2.5%
02-FICA 1,315,600 1,366,700 1,400,868 1,435,889 1,471,786 1,508,581
02-FICA 7.7% 3.9% 2.5% 2.5% 2.5% 2.5%
ACCTTYPE 6.0% 6.0% 6.0% 6.0%
03-HEALTH INSURANCE 3,009,500 3,401,400 3,605,484 3,821,813 4,051,122 4,294,189
03-HEALTH INSURANCE 22.4% 13.0% 6.0% 6.0% 6.0% 6.0%
ACCTTYPE 1.0% 1.0% 1.0% 1.0%
04-OTHER-BENEFITS 650,800 715,500 722,655 729,882 737,180 744,552
04-OTHER-BENEFITS 26.7% 9.9% 1.0% 1.0% 1.0% 1.0%
ACCTTYPE 4.0% 4.0% 4.0% 4.0%
05-RETIREE HEALTHCARE 1,567,700 2,039,700 2,121,288 2,206,140 2,294,385 2,386,161
05-RETIREE HEALTHCARE -4.2% 30.1% 4.0% 4.0% 4.0% 4.0%
ACCTTYPE 2.5% 2.5% 2.5% 2.5%
07-PENSION 2,689,700 3,262,800 3,344,370 3,427,979 3,513,679 3,601,521
07-PENSION 1.7% 21.3% 2.5% 2.5% 2.5% 2.5%
ACCTTYPE 2.0% 2.0% 2.0% 2.0%
08-OPEB 1,773,100 1,508,300 1,538,466 1,569,235 1,600,620 1,632,632
08-OPEB 6.5% -14.9% 2.0% 2.0% 2.0% 2.0%
ACCTTYPE 1.0% 1.0% 1.0% 1.0%
09-MATERIALS & SUPPLIES 1,364,600 1,380,700 1,394,507 1,408,452 1,422,537 1,436,762
09-MATERIALS & SUPPLIES 9.4% 1.2% 1.0% 1.0% 1.0% 1.0%
ACCTTYPE 1.5% 1.5% 1.5% 1.5%
10-ADMIN EXPENDITURES 5,172,800 4,981,800 5,056,527 5,132,375 5,209,361 5,287,501
10-ADMIN EXPENDITURES 12.3% -3.7% 1.5% 1.5% 1.5% 1.5%
ACCTTYPE 0.0% 0.0% 0.0% 0.0%
11-FUND EXPENSE 2,251,100 2,025,000 2,025,000 2,025,000 2,025,000 2,025,000
11-FUND EXPENSE -11.6% -10.0% 0.0% 0.0% 0.0% 0.0%
ACCTTYPE 0.5% 0.5% 0.5% 0.5%
12-STREET LIGHT 797,700 804,000 808,020 812,060 816,120 820,201
12-STREET LIGHT 2.9% 0.8% 0.5% 0.5% 0.5% 0.5%
ACCTTYPE 0.0% 0.0% 0.0% 0.0%
13-OTHER-CHARGES 742,600 392,200 392,200 392,200 392,200 392,200
13-OTHER-CHARGES 115.6% -47.2% 0.0% 0.0% 0.0% 0.0%
ACCTTYPE
14-TRANSFER-TO-DEBT 669,400 685,300 428,700 428,700 428,700 428,700
14-TRANSFER-TO-DEBT -30.4% 2.4% -37.4% 0.0% 0.0% 0.0%
ACCTTYPE
15-TRANSFER-TO-CIP 2,625,400 1,859,400 2,985,500 2,944,100 2,652,100 3,332,200
15-TRANSFER-TO-CIP 19.6% -29.2% 60.6% -1.4% -9.9% 25.6%
66
Página 73
Capital Projects - Funding Sources
CAPITAL IMPROVEMENTS PROGRAM 2016B 2017B 2018F 2019F 2020F 2021F
BEGINNING BALANCE 2,926,700 383,900 388,900 390,800 390,800 390,800
APPROPRIATIONS & RECEIPTS
APPROPRIATION FROM GENERAL FUND 2,625,400 1,859,400 2,985,500 2,944,100 2,652,100 3,332,200
TRANSFER FROM PARKLAND RESERVE - 80,000 50,000 15,000 55,000
TRANSFER FROM COM TRANSP FUND - - 30,000
BOND PROCEEDS - - 3,710,000 3,710,000 3,710,000
RECREATION GRANTS - 105,000 68,000 - 73,000
PUBLIC WORKS GRANTS - DNREC 80,500 - - - -
SALE OF ASSETS & AUCTION RECEIPTS 120,800 - - - -
DONATIONS FOR SPECIFIC PROJECTS 74,700 - - -
INTEREST EARNINGS 5,000 5,000 5,000 5,000 5,000 5,000
TOTAL RECEIPTS 2,906,400 2,049,400 6,848,500 6,674,100 6,495,100 3,337,200
TOTAL BEGINNING BALANCE & REVENUES 5,833,100 2,433,300 7,237,400 7,064,900 6,885,900 3,728,000
67
Página 74
Capital Projects – Use of Funds (See CIP section for details)
CAPITAL IMPROVEMENTS PROGRAM 2016B 2017B 2018F 2019F 2020F 2021F
PROGRAM OPERATING EXPENDITURES
541 POLICE ADMINISTRATION 302,700 299,800 451,500 399,100 364,700 367,400
PUBLIC SERVICES
522 GROUNDS 185,200 58,200 59,800 188,000 153,000 151,000
531 LIFE SAFETY 55,700 29,500 - - - -
534 PUBLIC INSPECTIONS - - 16,000 - - 34,000
551 P W ADMINISTRATION - - - - - 42,000
554 STREET 3,735,000 1,026,000 5,245,400 5,258,900 5,353,000 1,872,500
555 SANITATION 449,000 261,500 431,700 429,100 204,900 627,000
TOTAL PUBLIC SERVICES 4,424,900 1,375,200 5,752,900 5,876,000 5,710,900 2,726,500
PLANNING & CODE ENFORCEMENT
533 PLANNING - - 16,000 - - -
532 CODE ENFORCEMENT - - 23,800 - - 17,000
TOTAL PLANNING & CODE ENFORCEMENT - - 39,800 - - 17,000
514 FIRE DEPARTMENT 445,800 145,700 295,200 295,200 226,300 226,300
525 RECREATION 73,900 165,000 241,000 15,000 161,000 -
TOTAL PROGRAM EXPENDITURES 5,247,300 1,985,700 6,780,400 6,585,300 6,462,900 3,337,200
ADMINISTRATIVE & SUPPORT EXPENDITURES
515 CITY MANAGER 24,700 - - - - -
552 FACILITIES MANAGEMENT - 27,700 28,200 28,800 32,200 -
572 VEHICLE MAINTENANCE 84,500 31,000 38,000 60,000 - -
TOTAL ADMINISTRATIVE & SUPPORT EXPENDITURES 109,200 58,700 66,200 88,800 32,200 -
TOTAL CAPITAL INVESTMENT 5,356,500 2,044,400 6,846,600 6,674,100 6,495,100 3,337,200
TRANSFERS TO RESERVES
CAPITAL ASSET RESERVE 92,700 - - - - -
BUDGET BALANCE - WORKING CAPITAL 383,900 388,900 390,800 390,800 390,800 390,800
TOTAL BUDGET BALANCE & EXPENDITURES 5,833,100 2,433,300 7,237,400 7,064,900 6,885,900 3,728,000
68
Página 75
General Fund Projected Debt Service
City of Dover
General Fund
Projected Debt Service
2012 $3,660,000 2014 SeriesB Green Energy
Fiscal Year Total Debt Net Debt
Tax- Exempt 2014 Series A Refunding Debt Service
Ending Service Service
Loan * Bonds Bond Contribution
6/30/2017 $ 224,700 $ 204,000 $ 249,400 $ 678,100 $ (98,500) $ 579,600
6/30/2018 224,700 204,000 - 428,700 (98,500) 330,200
6/30/2019 224,700 204,000 - 428,700 (98,500) 330,200
6/30/2020 224,700 204,000 - 428,700 (98,500) 330,200
6/30/2021 224,700 204,000 - 428,700 (98,500) 330,200
6/30/2022 224,700 204,000 - 428,700 (98,500) 330,200
6/30/2023 224,700 204,000 - 428,700 (98,500) 330,200
6/30/2024 224,700 204,000 - 428,700 (98,500) 330,200
6/30/2025 224,700 204,000 - 428,700 (98,500) 330,200
6/30/2026 224,700 204,000 - 428,700 (98,500) 330,200
6/30/2027 224,700 204,000 - 428,700 (98,500) 330,200
6/30/2028 224,700 204,000 - 428,700 (98,500) 330,200
6/30/2029 224,700 204,000 - 428,700 (98,500) 330,200
6/30/2030 224,700 204,000 - 428,700 (98,500) 330,200
6/30/2031 224,700 204,000 - 428,700 (98,500) 330,200
6/30/2032 224,700 204,000 - 428,700 (98,500) 330,200
6/30/2033 205,800 204,000 - 409,800 (98,500) 311,300
6/30/2034 - 204,000 - 204,000 - 204,000
6/30/2035 - 204,000 - 204,000 - 204,000
Totals $ 3,801,000 $ 3,876,000 $ 249,400 $ 7,926,400 $ (1,674,500) $ 6,251,900
Library & Garrison Farm 2003 Bond Library
Streets & Equipment Refinanced
69
Página 76
Debt Financing – Old PW2/Schutte Park Redevelopment
• The project estimates total $11.3 million
• Annual debt service estimated at $760,000
• Equals a $.025 tax rate increase
• Debt limitations per Charter Section 50
▫ Total debt borrowed cannot exceed a sum equal to 5% of the total assessed value of real
property within the bounds of the City (Currently estimated $152,960,000)
▫ Bonds may be authorized and issued, without a referendum vote, by a resolution of the
Council which shall have the affirmative vote of three-fourths of the members thereof and
approval of the Mayor
▫ To finance capital projects, including, but not limited to, public storm sewers, water mains,
sewer mains, streets and public buildings provided that no more than ¼ of one percent (.25%)
of taxable assessed value of real property of aggregate principal amount of general obligation
bonds may be issued at any one time pursuant to this clause ($7,648,000)
▫ and any new bonds issued pursuant to this clause may not cause the total aggregate principal
amount of general obligation bonds outstanding at any one time to exceed one percent of the
total taxable assessment for a general tax at the time such new bonds are issued
($30,592,000);
70
Página 78
City of Dover
Water and Wastewater Fund
Financial Projections
2017 – 2021
Budget Meetings
May 24, 2016
72
Página 79
Financial Projections
• An informational tool provided to those charged with
governance and management of the City.
• A planning tool used for setting future goals and
objectives to meet the City’s financial requirements.
• A tool to insure we are meeting three main objectives.
▫ Positive net income as measured by audited generally accepted
accounting principles (GAAP accounting)
▫ Sufficient revenues to cover debt service covenants and ratios as
measured by GAAP accounting
▫ Sufficient (positive) cash balances to cover items not included in
the income statement as measured by budgetary accounting
73
Página 80
FY17 – FY21 Key Assumptions
• T/Gallons Growth & Revenues
FY17 reduces the FY16 projected revenue for the Calpine Generating Station
Forecast includes an assumed .5% growth rate in FY17 and FY20
Water Tank space leases projected to increase at 2 1/2% each year
• Projected Operating Expenses includes the following assumptions:
Pay increases included for applicable Collective Bargaining Agreements
Growth in Division expenses 2017 – 2020 = 3% annual
Increased retiree health insurance premiums - 6.0% annual
Growth in expenses is greater than the assumptions in revenue growth
• Continues to increase the General Fund Transfer each year for Wastewater through 2019.
• Maintains transfers to the Capital Project Fund each year for water quality and inflow/infiltration projects
• Includes systematic write off of current water meters to be replaced with new meters where applicable
• Emphasis on level of capital improvements to replace failing infrastructure
• Impact Fees are projected to be used to pay debt service and partial wastewater project financing
• Includes Transfers to the Electric I & E Fund for allocation of estimated cost for ERP system $231,100
• The Wastewater Utility experiences a negative cash position starting in FY18 and the Water Utility in FY19.
Unless greater growth occurs or realized costs reductions are sustained the rates would need to be increased to
maintain positive net income and cash, assuming all the above assumptions are met. We would recommend a
cost of service study for the Water/Wastewater Utility to determine appropriate rates and if the current rate
structure is equitable among all users.
74
Página 81
Net Income – Combined Water & Wastewater
Revised Proposed Projection Projection Projection Projection
2016 2017 2018 2019 2020 2021
Net Income - Combined Water & Wastewater
Water Fees $ 5,366,600 $ 5,800,000 $ 5,829,000 $ 5,858,100 $ 5,887,401 $ 5,916,802
Wastewater Fees 3,823,800 3,800,000 3,819,000 3,838,100 3,857,301 3,876,602
Treatment Fees - Kent County 2,997,600 3,000,000 3,015,000 3,030,100 3,045,300 3,060,500
Groundwater Inflow Adjustment 1,965,600 1,938,000 1,947,700 1,957,400 1,967,200 1,977,000
Miscellaneous Income - Water 370,000 397,700 406,900 416,300 425,900 435,800
Miscellaneous Income - Wastewater 28,100 31,500 31,500 31,500 31,500 31,500
Impact Fees - Water 253,400 252,000 252,000 252,000 252,000 252,000
Impact Fees - Wastewater 222,400 228,000 228,000 228,000 228,000 228,000
Total Revenue 15,027,500 15,447,200 15,529,100 15,611,500 15,694,602 15,778,204
Treatment Fees - Kent County (4,130,000) (4,130,000) (4,150,700) (4,171,500) (4,192,400) (4,213,400)
Operating Expenses - Water (3,685,600) (3,714,100) (3,790,600) (3,897,600) (4,008,000) (4,122,100)
Operating Expenses - Wastewater (2,132,400) (2,293,800) (2,340,800) (2,407,500) (2,466,200) (2,537,000)
Operating Transfers - Out Water (550,000) (500,000) (500,000) (500,000) (500,000) (500,000)
Operating Transfers - Out Wastewater (300,000) (375,000) (400,000) (450,000) (500,000) (500,000)
Total Operating Expenses (10,798,000) (11,012,900) (11,182,100) (11,426,600) (11,666,600) (11,872,499)
Operating Income 4,229,500 4,434,300 4,347,000 4,184,900 4,028,002 3,905,705
Non-Oper. Rev. - Interest on Operating 10,000 20,000 12,000 12,000 12,000 12,000
Non-Oper. Rev. - Interest on Reserves 26,400 25,700 24,000 24,000 23,400 23,500
Income Available For Debt Service 4,265,900 4,480,000 4,383,000 4,220,900 4,063,402 3,941,205
Interest for Long-Term Debt (370,400) (382,300) (396,100) (379,400) (369,300) (354,800)
Cash From Operations 3,895,500 4,097,700 3,986,900 3,841,500 3,694,102 3,586,405
Non Cash Investment Income/(Loss)
Depreciation Expense (3,237,800) (3,465,300) (3,774,500) (4,062,400) (4,288,300) (4,482,200)
Net Income ($) $ 657,700 $ 632,400 $ 212,400 $ (220,900) $ (594,198) $ (895,795)
Debt Service Coverage
Income Avail. for Debt Service $ 4,265,900 $ 4,480,000 $ 4,383,000 $ 4,220,900 $ 4,063,402 $ 3,941,204
Total Debt Service $ 1,132,400 $ 1,227,200 $ 1,339,300 $ 1,368,400 $ 1,375,000 $ 1,379,000
Debt Service Coverage Ratio (1.20) 3.77 3.65 3.27 3.08 2.96 2.86
Transfer to I & E Fund - Combined $ 3,300,000 $ 2,000,000 $ 2,600,000 $ 3,400,000 $ 3,400,000 $ 3,400,000
Transfer to Impact Fee Reserve - Combined - - - - - -
Transfer to Cap Asset & Cont. Reserve - Combined 32,000 401,200 231,100 - - -
Reinvestment of Reserve Interest - Combined 26,400 25,700 24,000 24,000 23,400 23,500
Debt Service Principal - Combined 762,000 844,900 943,200 989,000 1,000,200 1,011,600
Total Cash Budget Requirements - Combined $ 4,120,400 $ 3,271,800 $ 3,798,300 $ 4,413,000 $ 4,423,600 $ 4,435,100
Net Positive/(Negative Cash) $ (224,900) $ 825,900 $ 188,600 $ (571,500) $ (729,498) $ (848,695)
75
Página 82
Net Income - Water
Revised Proposed Projection Projection Projection Projection
2016 2017 2018 2019 2020 2021
Net Income - Water
Water Fees $ 5,366,600 $ 5,800,000 $ 5,829,000 $ 5,858,100 $ 5,887,401 $ 5,916,802
Miscellaneous Income - Water 370,000 397,700 406,900 416,300 425,900 435,800
Impact Fees - Water 253,400 252,000 252,000 252,000 252,000 252,000
Total Revenue 5,990,000 6,449,700 6,487,900 6,526,400 6,565,301 6,604,602
Operating Expenses - Water (3,685,600) (3,714,100) (3,790,600) (3,897,600) (4,008,000) (4,122,100)
Operating Transfers - Out (550,000) (500,000) (500,000) (500,000) (500,000) (500,000)
Total Operating Expenses (4,235,600) (4,214,100) (4,290,600) (4,397,600) (4,508,000) (4,622,100)
Operating Income 1,754,400 2,235,600 2,197,300 2,128,800 2,057,301 1,982,502
Non-Oper. Rev. - Interest on Operating 5,000 10,000 10,000 10,000 10,000 10,000
Non-Oper. Rev. - Interest on Reserves 7,900 8,200 7,600 7,400 6,700 6,800
Income Available For Debt Service 1,767,300 2,253,800 2,214,900 2,146,200 2,074,001 1,999,302
Interest for Long-Term Debt (184,700) (198,400) (211,000) (198,700) (189,100) (179,300)
Cash From Operations 1,582,600 2,055,400 2,003,900 1,947,500 1,884,901 1,820,002
Depreciation Expense (1,579,700) (1,706,400) (1,888,700) (1,999,800) (2,116,900) (2,196,600)
Net Income ($) $ 2,900 $ 349,000 $ 115,200 $ (52,300) $ (231,999) $ (376,598)
Debt Service Coverage
Income Avail. for Debt Service $ 1,767,300 $ 2,253,800 $ 2,214,900 $ 2,146,200 $ 2,074,001 $ 1,999,302
Total Debt Service $ 521,100 $ 590,300 $ 663,400 $ 666,700 $ 662,600 $ 665,400
Debt Service Coverage Ratio 3.39 3.82 3.34 3.22 3.13 3.00
Transfer to I & E Fund - Water $ 1,800,000 $ 1,000,000 $ 1,200,000 $ 1,600,000 $ 1,600,000 $ 1,600,000
Transfer to Impact Fee Reserve - Water - - - - - -
Transfer to Capital Asset & Contingency Reserves 32,000 225,600 115,500 - - -
Reinvestment of Reserve Interest 7,900 8,200 7,600 7,400 6,700 6,800
Debt Service Principal 336,400 391,900 452,400 468,000 468,000 473,500
Total Cash Budget Requirements 2,176,300 1,625,700 1,775,500 2,075,400 2,074,700 2,080,300
Net Positive/(Negative Cash) $ (593,700) $ 429,700 $ 228,400 $ (127,900) $ (189,799) $ (260,298)
76
Página 83
Net Income - Wastewater
Revised Proposed Projection Projection Projection Projection
2016 2017 2018 2019 2020 2021
Net Income - Wastewater
Wastewater Fees $ 3,823,800 $ 3,800,000 $ 3,819,000 $ 3,838,100 $ 3,857,301 $ 3,876,602
Treatment Fees - Kent County 2,997,600 3,000,000 3,015,000 3,030,100 3,045,300 3,060,500
Groundwater Inflow Adjustment 1,965,600 1,938,000 1,947,700 1,957,400 1,967,200 1,977,000
Miscellaneous Income - Wastewater 28,100 31,500 31,500 31,500 31,500 31,500
Impact Fees - Wastewater 222,400 228,000 228,000 228,000 228,000 228,000
Total Revenue 9,037,500 8,997,500 9,041,200 9,085,100 9,129,301 9,173,602
Treatment Expense - Kent County (4,130,000) (4,130,000) (4,150,700) (4,171,500) (4,192,400) (4,213,400)
Operating Expenses - Wastewater (2,132,400) (2,293,800) (2,340,800) (2,407,500) (2,466,200) (2,537,000)
Operating Transfers - Out (300,000) (375,000) (400,000) (450,000) (500,000) (500,000)
Total Operating Expenses (6,562,400) (6,798,800) (6,891,500) (7,029,000) (7,158,600) (7,250,400)
Operating Income 2,475,100 2,198,700 2,149,700 2,056,100 1,970,701 1,923,202
Non-Oper. Rev. - Interest on Operating 5,000 10,000 2,000 2,000 2,000 2,000
Non-Oper. Rev. - Interest on Reserves 18,500 17,500 16,400 16,600 16,700 16,700
Income Available For Debt Service 2,498,600 2,226,200 2,168,100 2,074,700 1,989,401 1,941,902
Interest for Long-Term Debt (185,700) (183,900) (185,100) (180,700) (180,200) (175,500)
Cash From Operations 2,312,900 2,042,300 1,983,000 1,894,000 1,809,201 1,766,402
Depreciation Expense (1,658,100) (1,758,900) (1,885,800) (2,062,600) (2,171,400) (2,285,600)
Net Income ($) $ 654,800 $ 283,400 $ 97,200 $ (168,600) $ (362,199) $ (519,198)
Debt Service Coverage
Income Avail. for Debt Service $ 2,498,600 $ 2,226,200 $ 2,168,100 $ 2,074,700 $ 1,989,401 $ 1,941,902
Total Debt Service $ 611,300 $ 636,900 $ 675,900 $ 701,700 $ 712,400 $ 713,600
Debt Service Coverage Ratio 4.09 3.50 3.21 2.96 2.79 2.72
Transfer to I & E Fund - Wastewater $ 1,500,000 $ 1,000,000 $ 1,400,000 $ 1,800,000 $ 1,800,000 $ 1,800,000
Transfer to Impact Fee Reserve - Wastewater - - - - - -
Transfer to Electric I & E Fund - 175,600 115,600 - - -
Reinvestment of Reserve Interest 18,500 17,500 16,400 16,600 16,700 16,700
Debt Service Principal 425,600 453,000 490,800 521,000 532,200 538,100
Total Cash Budget Requirements $ 1,944,100 $ 1,646,100 $ 2,022,800 $ 2,337,600 $ 2,348,900 $ 2,354,800
Net Positive/(Negative Cash) $ 368,800 $ 396,200 $ (39,800) $ (443,600) $ (539,699) $ (588,398)
77
Página 84
Capital Improvement Plan
Revised Proposed Projection Projection Fiscal Year Fiscal Year 5 Yr Projctd
CAPITAL PROJECTS 2016 2017 2018 2019 2020 2021 Total
Vehicles & Equipment (Split W/WW 50%) $ - $ 30,400 $ 31,000 $ 23,000 $ 28,000 $ - $ 112,400
Water, Water Construction & Water Treatment
Vehicles & Equipment - Water 106,000 145,000 339,700 224,300 240,700 25,000 974,700
Meter Reading - Radio Read Meters (Split W/WW 50%) 150,000 200,000 200,000 200,000 200,000 200,000 1,000,000
1.0 MG Elevated Storage Tank 2,468,200 - - - - - -
West Dover Connector - Design 76,400 - - - - - -
Garrison Oak Technical Park - Water Tower 1,297,300 - - - - - -
New Burton Road - Kent County Water Main 30,000 - - - - - -
Shallow Well #7 Abondonment 15,000 - - - - - -
Fence at Bayard Avenue Water Tower 84,200 - - - - - -
Projects with Locations to be Determined -
Future Well Installation 80,000 100,000 1,098,300 - - - 1,198,300
Wellhead Redevelopment 82,500 85,000 87,500 90,000 92,500 95,000 450,000
Water Quality Improvements 895,000 645,800 265,800 881,000 919,000 1,167,000 3,878,600
Emergency Repairs - line breaks 75,000 75,000 77,000 79,000 81,000 83,000 395,000
SCADA Upgrades 83,000 88,000 - - - - 88,000
Treatment Plant Improvements 284,400 1,200,000 1,200,000 - - - 2,400,000
Total Water 5,727,000 2,538,800 3,268,300 1,474,300 1,533,200 1,570,000 10,384,600
Wastewater
Vehicles & Equipment - Wastewater 310,900 47,200 119,000 437,400 78,400 110,000 792,000
Meter Reading - Radio Read Meters (Split W/WW 50%) 150,000 200,000 200,000 200,000 200,000 200,000 1,000,000
Tar Ditch Interceptor Upgrade - - 250,000 - - - 250,000
Brandywine Pump Station Replacement 101,200 - - - - - -
Garrison Oak Technical Park - PS & force main 628,500 - - - -
Lepore Road Pump Station Replacement - 50,000 250,000 - - - 300,000
Rolling Acres Pump Station Replacement 52,000 372,000 - - - - 372,000
Turnberry Pump Station - - - - - 60,000 60,000
DelTech Pump Station Replacement - 52,000 384,000 - - - 436,000
Westover Pump Station & Force Main Upgrade 1,292,400 - - - - - -
Lakeview Drive Pump Station Replacement 359,600 - - - - - -
Sliver Lake Pump Station Replacement - 52,000 - 396,000 - - 448,000
US Rt. 113 East Pump Station Repair 140,000 - - - - - -
Hazlettville Road Interceptor - Impact Fees 774,100 - - - - - -
Walker Woods Pump Station Replacement - 52,000 - - 408,000 - 460,000
College Road Pump Station Replacement - - - - 55,000 420,000 475,000
Retreat Pump Station Replacement 447,700 - - - - - -
McKee Tax Ditch Sewer Repair 27,300 - - - - - -
St Jones River Sewer Repair 47,300 - - - - - -
Puncheon Run Pump Station Upgrade/Repair 160,000 - - - - - -
West Dover Connector 387,300 - - - - - -
Delaware Avenue Sanitary Sewer Extension 25,000 - - - - - -
US Rt. 113 East PS # 7 Repair - Controller 97,000 - - - - - -
Location/Pump Station to be Determined -
Inflow/Infiltration Removal/System Improvements 223,800 1,121,000 1,173,000 1,171,000 1,169,000 1,167,000 5,801,000
Misc. Sewer System Improvements 75,000 75,000 77,000 79,000 81,000 83,000 395,000
Total Wastewater $ 5,299,100 $ 2,021,200 $ 2,453,000 $ 2,283,400 $ 1,991,400 $ 2,040,000 $ 10,789,000
Total Water/Wastewater Improvements $ 11,026,100 $ 4,590,400 $ 5,752,300 $ 3,780,700 $ 3,552,600 $ 3,610,000 $ 21,286,000
78
Página 85
Capital Improvement Plan – Funding Sources
Revised Proposed Projection Projection Projection Projection 5 Yr Projctd
FUNDING SOURCES 2016 2017 2018 2019 2020 2021 Total
I & E Fund Budget Balance - Water $ 4,990,300 $ 1,179,900 $ 2,226,700 $ 201,600 $ 412,200 $ 475,000
I & E Fund Budget Balance - Wastewater $ 4,551,700 $ 952,600 $ 1,021,400 $ 358,900 $ 282,000 $ 108,600
Transfer from Operating Fund - Water 1,800,000 1,000,000 1,200,000 1,600,000 1,600,000 1,600,000 7,000,000
Transfer from Operating Fund - Wastewater 1,500,000 1,000,000 1,400,000 1,800,000 1,800,000 1,800,000 7,800,000
Transfer from Impact Fee Reserve - Water - 190,800 48,700 86,400 - - 325,900
Transfer from Impact Fee Reserve - Wastewater 165,000 211,200 - - 22,000 192,000 425,200
State Loan Fund - Water 2017 - 2,400,000 - - - - 2,400,000
State Loan Fund - Wastewater 2017 - 884,000 396,000 408,000 - - 1,688,000
Interest Income 69,900 20,000 20,000 20,000 20,000 20,000 100,000
Grants/State Reimbursements 20,300 - - - - - -
Miscellaneous Receipts 61,400 - - - - - -
Total Funding Sources $ 3,616,600 $ 5,706,000 $ 3,064,700 $ 3,914,400 $ 3,442,000 $ 3,612,000 $ 19,739,100
Total Sources of Funds (incl. Budget Balances) $ 13,158,600 $ 7,838,500 $ 6,312,800 $ 4,474,900 $ 4,136,200 $ 4,195,600
Water $ 1,179,900 $ 2,226,700 $ 201,600 $ 412,200 $ 475,000 $ 515,000
Wastewater $ 952,600 $ 1,021,400 $ 358,900 $ 282,000 $ 108,600 $ 70,600
Total Budget Balances $ 2,132,500 $ 3,248,100 $ 560,500 $ 694,200 $ 583,600 $ 585,600
79
Página 86
Debt Issues
• Forecast includes the following proposed State Revolving Fund
Loans @ 2.0% interest. Revenue Bonds $4.088M.
• Increases needed for bond reserves not included.
• Impact Fees are sometimes used to supplement the project cost
related to growth and design fees.
▫ FY17
Lepore Road Sanitary Sewer Upgrade $250,000
Tar Ditch Interceptor $250,000
Del Tech Pump Station Replacement $384,000
Water Treatment Plant Improvements $2.4 million
▫ FY18
Silver Lake Pump Station Replacement $396,000
▫ FY19
Walker Woods Pump Station Replacement $408,000
80
Página 87
Water/Wastewater Fund Projected Debt Service - Existing
City of Dover
Water/Wastewater Revenue Bonds
Current Debt Service - Table 1
Series 2013
Series 2013 Revenue Total
Fiscal Year Series 2000 Series 2009 Series 2010 Series 2011 Revenue Bonds - Total Water Wastewater Total Debt
Ending Wastewater Wastewater Water Wastewater Bonds - Water Wastewater Debt Service Debt Service Service
6/30/2017 $ 53,000 $ 347,100 $ 161,300 $ 58,200 $ 355,900 $ 151,800 $ 517,200 $ 610,100 $ 1,127,300
6/30/2018 53,000 347,100 161,300 58,200 355,800 151,800 517,100 610,100 1,127,200
6/30/2019 53,000 347,100 161,300 58,200 359,100 153,100 520,400 611,400 1,131,800
6/30/2020 53,000 347,100 161,300 58,200 355,100 151,400 516,400 609,700 1,126,100
6/30/2021 - 347,100 161,300 58,200 357,900 152,600 519,200 557,900 1,077,100
6/30/2022 - 347,100 161,300 58,200 356,900 152,200 518,200 557,500 1,075,700
6/30/2023 - 347,100 161,300 58,200 355,700 151,700 517,000 557,000 1,074,000
6/30/2024 - 347,100 161,300 58,200 357,700 152,600 519,000 557,900 1,076,900
6/30/2025 - 347,100 161,300 58,200 214,400 91,500 375,700 496,800 872,500
6/30/2026 - 347,100 161,300 58,200 213,300 91,000 374,600 496,300 870,900
6/30/2027 - 347,100 161,300 58,200 211,800 90,300 373,100 495,600 868,700
6/30/2028 - 347,100 161,300 58,200 213,300 91,000 374,600 496,300 870,900
6/30/2029 - 347,100 161,300 58,200 214,000 91,300 375,300 496,600 871,900
6/30/2030 - 347,100 161,300 58,200 214,000 91,300 375,300 496,600 871,900
6/30/2031 - 347,100 80,700 58,200 214,400 91,500 295,100 496,800 791,900
6/30/2032 - 173,600 - 29,100 213,200 90,900 213,200 293,600 506,800
6/30/2033 - - - - 212,300 90,600 212,300 90,600 302,900
6/30/2034 - - - - 211,100 90,000 211,100 90,000 301,100
Total $ 212,000 $ 5,380,100 $ 2,338,900 $ 902,100 $ 4,985,900 $ 2,126,600 $ 7,324,800 $ 8,620,800 $ 15,945,600
SRF SRF SRF SRF PNC Loan PNC Loan
81
Página 88
Water/Wastewater Fund Projected Debt Service - New
City of Dover
Water/Wastewater Revenue Bonds
Projected Debt Service - Table 2
New State of Delaware Revolving Fund Loans
Total Tables 1 & 2
Fiscal Year Series 2017 Series 2017 Series 2018 Series 2019 Total Water Wastewater Total Debt
Ending Water Wastewater Wastewater Wastewater Debt Service Debt Service Service
6/30/2017 $ 73,100 $ 27,000 $ - $ - $ 73,100 $ 27,000 $ 1,227,400
6/30/2018 146,200 53,900 12,100 - 146,200 66,000 1,339,400
6/30/2019 146,200 53,900 24,200 12,500 146,200 90,600 1,368,600
6/30/2020 146,200 53,900 24,200 24,900 146,200 103,000 1,375,300
6/30/2021 146,200 53,900 24,200 24,900 146,200 103,000 1,326,300
6/30/2022 146,200 53,900 24,200 24,900 146,200 103,000 1,324,900
6/30/2023 146,200 53,900 24,200 24,900 146,200 103,000 1,323,200
6/30/2024 146,200 53,900 24,200 24,900 146,200 103,000 1,326,100
6/30/2025 146,200 53,900 24,200 24,900 146,200 103,000 1,121,700
6/30/2026 146,200 53,900 24,200 24,900 146,200 103,000 1,120,100
6/30/2027 146,200 53,900 24,200 24,900 146,200 103,000 1,117,900
6/30/2028 146,200 53,900 24,200 24,900 146,200 103,000 1,120,100
6/30/2029 146,200 53,900 24,200 24,900 146,200 103,000 1,121,100
6/30/2030 146,200 53,900 24,200 24,900 146,200 103,000 1,121,100
6/30/2031 146,200 53,900 24,200 24,900 146,200 103,000 1,041,100
6/30/2032 146,200 53,900 24,200 24,900 146,200 103,000 756,000
6/30/2033 146,200 53,900 24,200 24,900 146,200 103,000 552,100
6/30/2034 146,200 53,900 24,200 24,900 146,200 103,000 550,300
6/30/2035 146,200 53,900 24,200 24,900 146,200 103,000 249,200
6/30/2036 146,200 53,900 24,200 24,900 146,200 103,000 249,200
6/30/2037 73,100 26,900 24,200 24,900 73,100 76,000 149,100
6/30/2038 - - 12,100 24,900 - 37,000 37,000
6/30/2039 - - - 12,400 - 12,400 12,400
Total $ 2,924,000 $ 1,078,000 $ 484,000 $ 498,000 $ 2,924,000 $ 2,060,000 $ 20,929,600
(1) Maximum annual debt service on City of Dover, Water/Wastewater Revenue Bonds measured on fiscal year basis.
SRF SRF SRF SRF
82
Página 89
Reserve Account Projections
Revised Proposed Projection Projection Projection Projection
2016 2017 2018 2019 2020 2021
Contingency Reserve Account - Water ($250,000) $119,800 $250,000 $250,000 $250,000 $250,000 $250,000
Balance in Account on July 1 $105,200 $138,000 $249,000 $250,900 $252,800 $254,700
Receipts
Interest Earned 800 1,000 1,900 1,900 1,900 1,900
Appropriations 32,000 110,000 - - - -
Total Funds Available $138,000 $249,000 $250,900 $252,800 $254,700 $256,600
Disbursements
Balance in Account on June 30 $138,000 $249,000 $250,900 $252,800 $254,700 $256,600
Contingency Reserve - Wastewater ($250,000) $180,800 $250,000 $250,000 $250,000 $250,000 $250,000
Balance in Account on July 1 $190,200 $191,600 $253,100 $255,000 $256,900 $258,900
Receipts
Appropriations - 60,000 - - - -
Interest Earned 1,400 1,500 1,900 1,900 2,000 2,000
Total Funds Available $191,600 $253,100 $255,000 $256,900 $258,900 $260,900
Disbursements
Balance in Account on June 30 $191,600 $253,100 $255,000 $256,900 $258,900 $260,900
Impact Fee Reserve - Water (20% of Revenue) $1,073,300 $1,160,000 $1,165,800 $1,171,600 $1,177,500 $1,183,400
Balance in Account on July 1 $427,500 $430,700 $243,200 $196,300 $111,400 $112,200
Receipts
Interest Earned 3,200 3,300 1,800 1,500 800 900
Total Funds Available $430,700 $434,000 $245,000 $197,800 $112,200 $113,100
Disbursements
Transfer to Capital Improvements - 190,800 48,700 86,400 - -
Balance in Account on June 30 $430,700 $243,200 $196,300 $111,400 $112,200 $113,100
Impact Fee Reserve - Wastewater (20% of Rev) $764,800 $760,000 $763,800 $767,600 $771,500 $775,300
Balance in Account on July 1 $1,742,700 $1,590,900 $1,391,800 $1,402,400 $1,413,100 $1,401,800
Receipts
Interest Earned 13,200 12,100 10,600 10,700 10,700 10,700
Total Funds Available $1,755,900 $1,603,000 $1,402,400 $1,413,100 $1,423,800 $1,412,500
Disbursements
Transfer to Capital Improvements 165,000 211,200 - - 22,000 192,000
Balance in Account on June 30 $1,590,900 $1,391,800 $1,402,400 $1,413,100 $1,401,800 $1,220,500
Capital Asset Reserve - Water (Min. $500K)
Balance in Account on July 1 $510,700 $514,600 $518,500 $522,400 $526,400 $530,400
Receipts
Interest Earned 3,900 3,900 3,900 4,000 4,000 4,000
Total Funds Available $514,600 $518,500 $522,400 $526,400 $530,400 $534,400
Disbursements
Balance in Account on June 30 $514,600 $518,500 $522,400 $526,400 $530,400 $534,400
Capital Asset Resrv - Wastewater (Min $500K)
Balance in Account on July 1 $509,500 $513,400 $517,300 $521,200 $525,200 $529,200
Receipts
Interest Earned 3,900 3,900 3,900 4,000 4,000 4,000
Total Funds Available $513,400 $517,300 $521,200 $525,200 $529,200 $533,200
Disbursements
Balance in Account on June 30 $513,400 $517,300 $521,200 $525,200 $529,200 $533,200
Total All Reserves at June 30 $3,379,200 $3,172,900 $3,148,200 $3,085,800 $3,087,200 $2,918,700
83
Página 91
City of Dover
Electric Revenue Fund
Financial Projections
2017 – 2021
Budget Meetings
May 24, 2016
85
Página 92
Financial Projections
• An informational tool provided to those charged with
governance and management of the City.
• A planning tool used for setting future goals and
objectives to meet the City’s financial requirements.
• A tool to insure we are meeting three main objectives.
▫ Positive net income as measured by audited generally accepted
accounting principles (GAAP accounting)
▫ Sufficient revenues to cover debt service covenants and ratios as
measured by GAAP accounting
▫ Sufficient (positive) cash balances to cover items not included in
the income statement as measured by budgetary accounting
86
Página 93
FY17 – FY21 Key Assumptions
• kWh demand for FY17 – FY21 approximately 1.0% annual growth
• No rate increases in current forecast
• General Fund Transfer each fiscal year remains $10.0 million
• Includes billed revenues for new services & improvements in the
Improvement & Extension Fund to offset cost of the improvements
($.9 million annually); Funds will be restricted to
developer/contractor applications for service;
• Forecasted Operating Expenses as follows:
Growth in Division expenses 2018 – 2021 at 3.0% annual
Increased retiree health insurance premiums 6.0%
Reduced annual appropriations for inventory reserve and increased
appropriation for bad debt
Power Supply includes cost of Non-Solar Renewable Energy credits as
mandated to fulfill the City’s Renewable Portfolio Standard
Increased transfer to the capital project fund to cover replacement cost
of current assets. To be adjusted upon decommissioning of Units 1 & 2.
87
Página 94
Net Income
Revised Proposed Projected Projected Projected Projected
2016 2017 2018 2019 2020 2021
Net Income
Revenue from Current Electric Rates $ 78,493,800 $ 78,991,200 $ 79,768,300 $ 80,778,700 $ 81,642,700 $ 82,518,500
Utility Tax 1,309,600 1,320,900 1,333,900 1,350,800 1,365,200 1,379,800
Miscellaneous Receipts 1,242,000 1,799,600 1,885,000 1,887,000 1,889,000 1,891,000
Total Operating Revenue 81,045,400 82,111,700 82,987,200 84,016,500 84,896,900 85,789,300
Power Supply & Production (49,057,800) (49,155,600) (50,499,900) (44,857,000) (47,306,800) (47,755,500)
Operating Expenses (12,409,200) (13,251,600) (13,615,300) (13,995,400) (14,385,900) (14,790,100)
Operating Transfers - Out (General Fund) (10,000,000) (10,000,000) (10,000,000) (10,000,000) (10,000,000) (10,000,000)
Total Operating Expenses (71,467,000) (72,407,200) (74,115,200) (68,852,400) (71,692,700) (72,545,600)
Operating Income 9,578,400 9,704,500 8,872,000 15,164,100 13,204,200 13,243,700
Non-Oper. Rev. - Interest on Operating 92,900 88,600 97,500 85,400 94,700 108,700
Non-Oper. Rev. - Interest on Reserves 221,400 220,500 243,100 244,900 231,700 256,300
Operating Transfers - In - - - - - -
Income Available For Debt Service 9,892,700 10,013,600 9,212,600 15,494,400 13,530,600 13,608,700
Interest on Long-Term Debt (922,700) (888,000) (851,600) (819,800) (785,800) (750,000)
Cash From Operations 8,970,000 9,125,600 8,361,000 14,674,600 12,744,800 12,858,700
Non Cash Income/Loss & Reserve Transfers
Depreciation Expense (5,477,200) (5,720,600) (5,974,800) (6,203,400) (6,442,200) (6,672,000)
Net Income $ 3,492,800 $ 3,405,000 $ 2,386,200 $ 8,471,200 $ 6,302,600 $ 6,186,700
88
Página 95
Debt Service Coverage
Revised Proposed Projected Projected Projected Projected
2016 2017 2018 2019 2020 2021
Debt Service Coverage
Income Avail. for Debt Service $ 9,892,700 $ 10,013,600 $ 9,212,600 $ 15,494,400 $ 13,530,600 $ 13,608,700
Total Debt Service $ 3,287,700 $ 1,583,000 $ 1,581,600 $ 1,584,800 $ 1,585,800 $ 1,590,000
Debt Service Coverage Ratio 3.01 6.33 5.82 9.78 8.53 8.56
Debt Service Coverage Requirement 1.25 1.25 1.25 1.25 2.25 1.25
Debt Service Coverage Requirement Status Met Met Met Met Met Met
Debt Service Safety Margin 8.12% 10.23% 9.16% 16.49% 14.02% 13.95%
Cash Flow Position
Revised Proposed Projected Projected Projected Projected
CASH SUMMARY 2016 2017 2018 2019 2020 2021
Cash from Operations $ 8,970,000 $ 9,125,600 $ 8,361,000 $ 14,674,600 $ 12,744,800 $ 12,858,700
Transfer to I & E Fund $ 3,500,000 $ 3,400,000 $ 5,400,000 $ 5,900,000 $ 5,900,000 $ 5,900,000
Transfer (from)/to Reserves (773,000) 2,750,000 - 4,000,000 3,000,000 -
Reinvestment of Reserve Interest 279,300 261,200 266,100 254,900 250,200 380,200
Debt Service Principal 2,365,000 695,000 730,000 765,000 800,000 840,000
Total Cash Budget Requirements 5,371,300 7,106,200 6,396,100 10,919,900 9,950,200 7,120,200
Net Positive/(Negative Cash) $ 3,598,700 $ 2,019,400 $ 1,964,900 $ 3,754,700 $ 2,794,600 $ 5,738,500
89
Página 96
Purchased Power Expense
Revised Proposed Projected Projected Projected Projected
2016 2017 2018 2019 2020 2021
Purchased Power [1] - kWh - - kWh - - kWh - - kWh - - kWh - - kWh -
Long Term Energy Supply 741,304,000 763,129,600 774,465,000 795,728,000 795,839,000 795,596,000
Annual Variation -2.11% 2.94% 1.49% 2.75% 0.01% -0.03%
Total Energy Purchases 741,304,000 763,129,600 774,465,000 795,728,000 795,839,000 795,596,000
Purchased Power Expense
Power Supply (Hedged) $ 23,402,600 $ 16,557,600 $ 15,625,700 $ 24,421,800 $ 20,881,700 $ 15,076,000
Dover Sun Park - Energy 2,313,900 2,313,900 2,446,700 2,551,500 2,580,200 2,639,700
Dover Sun Park - Solar Recs 363,400 363,400 362,400 373,500 397,800 408,600
Renewable Energy Credits (incl DEMEC) 673,400 673,400 875,300 1,097,700 1,199,000 1,306,500
Regional Greenhouse Gas Initiative 175,000 129,300 129,000 129,500 135,000 162,900
Power Supply Management 996,000 996,000 996,000 996,000 996,000 996,000
PJM Charges - Load Market Purchases 7,966,100 12,357,900 13,654,400 4,262,400 6,245,500 11,964,500
PJM Charges - Trans, ARR, and Fees 7,932,500 7,603,800 7,755,900 7,911,000 8,069,200 8,230,600
Capacity Charges 10,225,100 10,160,600 10,089,400 9,968,200 11,156,100 11,119,000
Generation Fuels 1,167,300 302,600 238,200 219,500 236,100 210,500
PJM Spot Market Energy Revenue (1,708,300) (804,900) (588,300) (540,000) (571,700) (493,300)
PJM Credits - Reactive Power Supply (360,000) (360,000) (367,200) (374,500) (382,000) (389,700)
Capacity Credits (10,472,100) (7,355,100) (6,434,300) (12,004,400) (9,611,900) (9,585,600)
Total Purchase Power Expense $ 42,674,900 $ 42,938,500 $ 44,783,200 $ 39,012,200 $ 41,331,000 $ 41,645,700
Purchased Power Cost per MWh [2] $ 57.57 $ 56.27 $ 57.82 $ 49.03 $ 51.93 $ 52.35
Current Hedge Percentage 76.0% 63.0% 56.0% 88.0% 80.0% 0.0%
90
Página 97
Net Electric Generation Benefit
City of Dover
Net Electric Generation Benefit
FY16 FY17 FY18 FY19 FY20 FY21 FY17 thru
Revised Proposed Projected Projected Projected Projected FY21
Plant Operations $ 6,382,900 $ 6,217,100 $ 5,716,700 $ 5,844,800 $ 5,975,800 $ 6,109,800 $ 29,864,200
Capacity Credits (10,472,100) (7,355,100) (6,434,300) (12,004,400) (9,611,900) (9,585,600) (44,991,300)
PJM Spot Market Energy (Net of Fuel) (2,875,600) (502,300) (826,500) (759,500) (335,600) (703,800) (3,127,700)
PJM Credits (360,000) (360,000) (367,200) (374,500) (382,000) (389,700) (1,873,400)
Net Generation - Operations (7,324,800) (2,000,300) (1,911,300) (7,293,600) (4,353,700) (4,569,300) (20,128,200)
Capital Cost 2,299,800 1,842,800 2,770,000 1,668,000 964,000 715,000 7,959,800
Net Generation - Cash Flow $ (5,025,000) $ (157,500) $ 858,700 $ (5,625,600) $ (3,389,700) $ (3,854,300) $ (12,168,400)
The City receives PJM capacity credits for our generating plant capacity. This revenue off-sets PJM's capacity charges which are required to serve approximately
180 MWH of our load plus reserves. If we did not have the ability to generate, we would loose the capacity credit but still have to pay the capacity charges to
PJM for our load requirements. The forecast reflects the 40 MHW of capacity purchase with Calpine.
Capacity Charges $ 10,225,100 $ 10,160,600 $ 10,089,400 $ 9,968,200 $ 11,156,100 $ 11,119,000 $ 52,493,300
$15.0
Costs $10.0
$5.0
Million Dollars
$0.0 Cap acity Credits
Cap acity Charges
($5.0)
Net Generation - Cash Flow
($10.0)
Benefits ($15.0)
($20.0)
FY16 FY17 FY18 FY19 FY20 FY21
91
Página 98
Capital Investment Plan 2017 – 2021
Revised Proposed Projected Projected Projected Projected Yr 1 - Yr 5
CAPITAL PROJECTS 2016 2017 2018 2019 2020 2021 Total
Electric Engineering Projects
Ann Avenue - Underground $ - $ - $ 126,000 $ - $ - $ - $ 126,000
Beeechwood Avenue - Underground - - 80,000 - - - 80,000
Farmview - Underground - - - 110,000 - - 110,000
The Greens - Underground - - - 90,000 - - 90,000
Townpoint Distribution Upgrades 350,000 350,000 350,000 350,000 350,000 350,000 1,750,000
Distribution System Upgrades - Unidentified - - - 300,000 600,000 - 900,000
Substation Relay Upgrade - 125,000 150,000 75,000 - - 350,000
Oak Grove Trailer Park Distribution Upgrade 78,500 - - - - - -
Lakeland Laurel Point - Distribution Upgrade 63,000 - - - - - -
Rt 8/ Mifflin Road Crossing - Distribution Upgrade 51,500 - - - - - -
Route 8/Taps - Distribution Upgrade 38,500 - - - - - -
Townsend Brothers - Distribution Upgrade 14,500 - - - - - -
Persimmon Tree Apartments - Distribution Upgrade 62,000 - - - - - -
North Street OH to UG (Governors to Queen) - - 170,000 - - - 170,000
Dover East Estates - Distribution Upgrade 130,000 - - - - - -
Lighting Project and Rehabilitation 67,000 50,000 50,000 50,000 50,000 50,000 250,000
LED Lighting - 17,500 - - - - 17,500
Ampacity Standardization - 25,000 25,000 25,000 25,000 25,000 125,000
Satellite Syncrhonized Substation Clocks 30,000 - - - - - -
Horsepond Road URD - Distribution Feeders 67,000 - - - - - -
SCADA Master Hardware Replacement - 150,000 - - - - 150,000
Transmission Line Maintenance Program 75,000 75,000 75,000 75,000 75,000 75,000 375,000
GOTP Transmission Line Relocation 408,500 - 120,000 - - - 120,000
GOTP Substation - - 50,000 - 6,000,000 - 6,050,000
Distribution Capacitors - Overhead 25,000 25,000 25,000 25,000 25,000 25,000 125,000
Distribution Capacitors - Underground 25,000 25,000 25,000 25,000 25,000 25,000 125,000
Fault Indicators 10,000 10,000 10,000 10,000 10,000 - 40,000
Horsepond SS to Cartanza 69kv Rebuild 318,500 - - - - - -
69kv Substation Cable Replacement North Street 135,000 - 480,700 - - - 480,700
Weyant Hall Roof Refurbishment 151,800 - - - - - -
Weyant Hall Security Improvements 50,000 - - - - - -
General Scott Switchgear 1,097,200 - - - - - -
Dover Air Force Base Substation Relocation 30,000 - - - -
System Operations Voice Recorder - - - 18,000 - - 18,000
System Automation - - 150,000 150,000 150,000 150,000 600,000
Uninterruptible Power Supply (UPS) System Replmnt - 25,000 - - - - 25,000
Vehicles, Trucks, & Equipment 10,000 33,200 83,200 - - - 116,400
Subtotal Electric Engineering Division $ 3,288,000 $ 910,700 $ 1,969,900 $ 1,303,000 $ 7,310,000 $ 700,000 $ 12,193,600
Electric Transmission & Distribution Projects
New Developments - UG Transformers $ 516,100 $ 500,000 $ 500,000 $ 500,000 $ 500,000 $ 500,000 $ 2,500,000
New Developments - UG Conductors/Devices 2,295,600 900,000 900,000 900,000 900,000 900,000 4,500,000
DNREC R & R Metering 41,000 - - - - - -
NBR Properties, LLC 11,500 - - - - - -
PWII/Tar Ditch - Relocation of utility poles & lines - 450,000 - - - - 450,000
Meter Replacements & System upgrades 60-46 & 40-25 263,100 100,000 100,000 100,000 100,000 100,000 500,000
Vehicles, Trucks, & Equipment 397,600 25,000 553,000 325,000 400,000 310,000 1,613,000
Subtotal Electric Transmission Division $ 3,524,900 $ 1,975,000 $ 2,053,000 $ 1,825,000 $ 1,900,000 $ 1,810,000 $ 9,563,000
92
Página 99
Capital Investment Plan 2017 – 2021 continued
Revised Proposed Projected Projected Projected Projected Yr 1 - Yr 5
CAPITAL PROJECTS 2016 2017 2018 2019 2020 2021 Total
Electric Generation Projects
McKee Run & VanSant Preservation of Structures $ 215,000 $ 131,000 $ 130,000 $ 100,000 $ 100,000 125,000 586,000
McKee Run Building Equipment Replacements 42,000 59,000 99,000 27,000 66,000 175,000 426,000
Unit 3 Software & Compupter Upgrades - CEMS 4,500 - - - - - -
Unit 3 - Stack Repairs 485,000 - - - - - -
Unit 3 Boiler Systems 122,800 382,000 160,000 299,000 80,000 235,000 1,156,000
Unit 3 Auxillary System Components 135,000 128,000 261,000 277,000 213,000 65,000 944,000
Unit 3 Turbine Outage - Inspections & Repairs 53,500 - - - - - -
Unit 3 Turbine Repairs - Intercept Valves - - - 438,000 25,000 - 463,000
Unit 3 Turbine Outage - Generator - - - 438,000 25,000 25,000 488,000
Unit 3 Cooling Water Line Replacement/Repairs - 469,000 - - - - 469,000
Unit 3 Fast Start Upgrade - - 200,000 - - - 200,000
Units 1, 2 & 3 Hydrogen Purity Analyzers - 96,000 - - - - 96,000
VanSant Plenum Replacement 469,000 - - - - - -
VanSant Capacity Increase 492,200 - - - - - -
VanSant Software & Compupter Upgrades - CEMS 4,500 - - - - - -
VanSant Major Overhaul & Inspection - 400,000 1,548,000 - 150,000 - 2,098,000
VanSant Component replacements 21,000 - - 89,000 305,000 90,000 484,000
VanSant Fire Suppression System Upgrade - - 285,000 - - - 285,000
Metering System Upgrades 80,000 - - - - - -
Hyrdogren Generator - - 50,000 - - - 50,000
Safety & Compliance Improvements 175,300 112,000 37,000 - - - 149,000
Vehicles, Trucks & Equipment - 65,800 - - - - 65,800
Subtotal Electric Generation Division $ 2,299,800 $ 1,842,800 $ 2,770,000 $ 1,668,000 $ 964,000 $ 715,000 $ 7,959,800
Electric Administration Projects
Vehicles, Trucks, & Equipment $ - $ - $ 30,000 $ - $ - $ - $ 30,000
Subtotal Electric Administration Division $ - $ - $ 30,000 $ - $ - $ - $ 30,000
Electric Metering Division
Vehicles, Trucks, & Equipment $ 23,000 $ 41,800 $ - $ - $ - $ - $ 41,800
Subtotal Electric Administration Division $ 23,000 $ 41,800 $ - $ - $ - $ - $ 64,800
ERP Consulting and Systems (Finance project) $ - $ 1,000,000 $ 1,300,000 $ - $ - $ - $ 2,300,000
Total Electric Improvements $ 9,135,700 $ 5,770,300 $ 8,122,900 $ 4,796,000 $ 10,174,000 $ 3,225,000 $ 32,088,200
93
Página 100
Capital Improvement Plan Funding 2017 – 2021
Revised Proposed Projected Projected Projected Projected Yr 1 - Yr 5
2016 2017 2018 2019 2020 2021 Total
Funding Sources
Electric I & E Fund Beginning Budget Balance $ 6,904,500 $ 5,349,700 $ 3,025,100 $ 1,357,700 $ 2,470,700 $ 4,214,200
Transfer from Operating Fund 3,500,000 2,500,000 4,500,000 5,000,000 5,000,000 5,000,000 22,000,000
Transfer from Other Funds - - 862,500 - - - 862,500
Elecric Future Capacity Reserve - - - - 6,000,000 - 6,000,000
Electric Revenue Fund Bond Reserve 2,108,000 - - - - - -
General Service Billing 1,900,000 900,000 900,000 900,000 900,000 900,000 4,500,000
Grants 15,000 5,000 170,000 - - - 175,000
Interest Earnings 57,900 40,700 23,000 9,000 17,500 30,700 120,900
Total Funding Sources 7,580,900 3,445,700 6,455,500 5,909,000 11,917,500 5,930,700 35,308,600
Total Beginning Balance & Funding Sources $ 14,485,400 $ 8,795,400 $ 9,480,600 $ 7,266,700 $ 14,388,200 $ 10,144,900 $ 54,416,300
Electric I & E Fund Ending Budget Balance $ 5,349,700 $ 3,025,100 $ 1,357,700 $ 2,470,700 $ 4,214,200 $ 6,919,900
94
Página 101
Projected Debt Service
City of Dover
Electric Revenue Fund
Projected Debt Service
Electric Revenue Fund
Fiscal Year 2008 Revenue Bonds Total Debt
6/30/2017 695,000 918,704 1,613,704
6/30/2018 730,000 883,954 1,613,954
6/30/2019 765,000 847,454 1,612,454
6/30/2020 800,000 815,706 1,615,706
6/30/2021 840,000 781,706 1,621,706
6/30/2022 880,000 746,006 1,626,006
6/30/2023 925,000 707,506 1,632,506
6/30/2024 970,000 665,881 1,635,881
6/30/2025 1,015,000 622,231 1,637,231
6/30/2026 1,065,000 576,555 1,641,555
6/30/2027 1,120,000 527,300 1,647,300
6/30/2028 1,175,000 475,500 1,650,500
6/30/2029 1,230,000 416,750 1,646,750
6/30/2030 1,290,000 355,250 1,645,250
6/30/2031 1,355,000 290,750 1,645,750
6/30/2032 1,420,000 223,000 1,643,000
6/30/2033 1,485,000 152,000 1,637,000
6/30/2034 1,555,000 77,750 1,632,750
Total $ 19,315,000 $ 10,084,003 $ 29,399,003
95
Página 102
FY17 – FY21 Reserve Account Projections
Revised Proposed Projected Projected Projected Projected
2016 2017 2018 2019 2020 2021
De pre cia tion Re se rve Account (Policy $10 mil)
Balance in Account on July 1 $ 9,957,900 $ 10,083,600 $ 10,910,200 $ 10,993,100 $ 11,076,600 $ 11,160,800
Receipts
Interest Earned 75,700 76,600 82,900 83,500 84,200 84,800
Transfer from Future Capacity Reserve 50,000 - - - - -
Appropriations - 750,000 - - - -
Total Funds Available $ 10,083,600 $ 10,910,200 $ 10,993,100 $ 11,076,600 $ 11,160,800 $ 11,245,600
Disbursements
Transfer to Capital Improvements (CIP) - - - - - -
Balance in Account on June 30 $ 10,083,600 $ 10,910,200 $ 10,993,100 $ 11,076,600 $ 11,160,800 $ 11,245,600
Future Ca pa city Account (Policy $10 mil)
Balance in Account on July 1 $ 10,107,900 $ 10,134,700 $ 10,961,700 $ 11,045,000 $ 15,128,900 $ 12,198,300
Receipts
Interest Earned 76,800 77,000 83,300 83,900 69,400 92,700
Appropriations - 750,000 - 4,000,000 3,000,000 -
Total Funds Available $ 10,184,700 $ 10,961,700 $ 11,045,000 $ 15,128,900 $ 18,198,300 $ 12,291,000
Disbursements
Transfer to Capital Improvements - - - - 6,000,000 -
Transfer to Depreciation Reserve (50,000) - - - - -
Balance in Account on June 30 $ 10,134,700 $ 10,961,700 $ 11,045,000 $ 15,128,900 $ 12,198,300 $ 12,291,000
Insura nce Sta biliza tion Account (Policy min $750K)
Balance in Account on July 1 $ 740,700 $ 756,300 $ 762,000 $ 767,800 $ 773,600 $ 779,500
Receipts
Interest Earned 5,600 5,700 5,800 5,800 5,900 5,900
Appropriations 10,000 - - - - -
Total Funds Available $ 756,300 $ 762,000 $ 767,800 $ 773,600 $ 779,500 $ 785,400
Disbursements
Transfer (to)/from Operations - - - - - -
Balance in Account on June 30 $ 756,300 $ 762,000 $ 767,800 $ 773,600 $ 779,500 $ 785,400
Ra te Sta biliza tion Account
Balance in Account on July 1 $ 7,505,300 $ 7,207,100 $ 8,511,900 $ 8,576,600 $ 8,641,800 $ 8,707,500
Receipts
Interest Earned 57,000 54,800 64,700 65,200 65,700 66,200
Appropriations 394,800 1,250,000 - - - -
Total Funds Available $ 7,957,100 $ 8,511,900 $ 8,576,600 $ 8,641,800 $ 8,707,500 $ 8,773,700
Disbursements
Transfer to Operations (750,000) - - - - -
Balance in Account on June 30 $ 7,207,100 $ 8,511,900 $ 8,576,600 $ 8,641,800 $ 8,707,500 $ 8,773,700
Reserve Requirement - (10% - 20% of Purchased Power) 16.89% 19.82% 19.15% 22.15% 21.07% 21.07%
Reserve Requirement Status Exceeds 10% Exceeds 10% Exceeds 10% Exceeds 10% Exceeds 10% Exceeds 10%
Continge ncy Re se rve Account
Balance in Account on July 1 $ 822,637 $ 841,937 $ 848,337 $ 854,737 $ 861,237 $ 867,737
Receipts
Interest Earned 6,300 6,400 6,400 6,500 6,500 6,600
Appropriations 13,000 - - - - -
Total Funds Available $ 841,937 $ 848,337 $ 854,737 $ 861,237 $ 867,737 $ 874,337
Disbursements
Transfer (to)/from Operations - - - - - -
Balance in Account on June 30 $ 841,937 $ 848,337 $ 854,737 $ 861,237 $ 867,737 $ 874,337
Reserve Requirement - (Min. $750,000) 810,454 821,087 829,842 840,135 848,939 857,863
Reserve Requirement Status OK OK OK OK OK OK
Total All Reserves at June 30 $ 29,023,637 $ 31,994,137 $ 32,237,237 $ 36,482,137 $ 33,713,837 $ 33,970,037
96
Página 103
Alternative Budget & Forecast
• Incorporates $.00252 Power Cost Adjustment (PCA) credit
• Financial estimates in FY17 – FY21
• Propose to reset PCA each year based on the annual budgets and reserve
levels
• Potential for lower sales growth
• Potential changes to power supply cost for unhedged supply
• Potential for forced outage penalties greater than rate stabilization reserve
• Not included in current Capital Investment Plan
▫ DAFB Substation relocation and rebuild (FY17 includes $1.5M transfer to reserve for land acquisition)
▫ Decommissioning plan for Units 1 & 2
▫ Integrated Resource Plan
• We would recommend a discussion of our current rate model design to determine if
a reset is necessary before any future rate changes are presented. This would
include winter/summer rates and customer charge increases to cover fixed cost,
which in turn would affect energy and demand charges.
97
Página 104
Net Income with PCA Credit
Revised Proposed Projected Projected Projected Projected Yr 1 - Yr 5
2016 2017 2018 2019 2020 2021 Total
Net Income
Revenue from Current Electric Rates $ 78,493,800 $ 78,991,200 $ 79,768,300 $ 80,778,700 $ 81,642,700 $ 82,518,500 $ 403,699,400
Revenue from Power Cost Adjustments (PCA) - (1,798,000) (1,817,400) (1,840,700) (1,860,600) (1,880,800) (7,316,700)
Utility Tax 1,309,600 1,287,900 1,300,500 1,317,000 1,331,100 1,345,400 6,581,900
Miscellaneous Receipts 1,242,000 1,799,600 1,885,000 1,887,000 1,889,000 1,891,000 9,351,600
Total Operating Revenue 81,045,400 80,280,700 81,136,400 82,142,000 83,002,200 83,874,100 407,606,700
Power Supply & Production (49,057,800) (49,155,600) (50,499,900) (44,857,000) (47,306,800) (47,755,500) (239,574,800)
Operating Expenses (12,409,200) (13,218,600) (13,581,900) (13,961,600) (14,351,800) (14,755,700) (69,869,600)
Operating Transfers - Out (General Fund) (10,000,000) (10,000,000) (10,000,000) (10,000,000) (10,000,000) (10,000,000) (50,000,000)
Total Operating Expenses (71,467,000) (72,374,200) (74,081,800) (68,818,600) (71,658,600) (72,511,200) (358,400,200)
Operating Income 9,578,400 7,906,500 7,054,600 13,323,400 11,343,600 11,362,900 50,991,000
Non-Oper. Rev. - Interest on Operating 92,900 88,600 97,500 85,400 94,600 108,700 474,800
Non-Oper. Rev. - Interest on Reserves 221,400 220,500 243,100 244,900 231,700 256,300 1,196,500
Operating Transfers - In - - - - - - -
Income Available For Debt Service 9,892,700 8,215,600 7,395,200 13,653,700 11,669,900 11,727,900 50,827,100
Interest on Long-Term Debt (922,700) (888,000) (851,600) (819,800) (785,800) (750,000) (4,095,200)
Cash From Operations 8,970,000 7,327,600 6,543,600 12,833,900 10,884,100 10,977,900 48,567,100
Non Cash Income/Loss & Reserve Transfers
Depreciation Expense (5,477,200) (5,720,600) (5,974,800) (6,203,400) (6,442,200) (6,672,000) (31,013,000)
Net Income $ 3,492,800 $ 1,607,000 $ 568,800 $ 6,630,500 $ 4,441,900 $ 4,305,900 $ 16,741,000
98
Página 105
Revised Proposed Projected Projected Projected Projected Yr 1 - Yr 5
2016 2017 2018 2019 2020 2021 Total
Debt Service Coverage
Income Avail. for Debt Service $ 9,892,700 $ 8,215,600 $ 7,395,200 $ 13,653,700 $ 11,669,900 $ 11,727,900 $ 50,827,100
Total Debt Service $ 3,287,700 $ 1,583,000 $ 1,581,600 $ 1,584,800 $ 1,585,800 $ 1,590,000 $ 9,622,900
Debt Service Coverage Ratio 3.01 5.19 4.68 8.62 7.36 7.38 5.28
Debt Service Coverage Requirement 1.25 1.25 1.25 1.25 2.25 1.25
Debt Service Coverage Requirement Status Met Met Met Met Met Met
Debt Service Safety Margin 8.12% 8.23% 7.14% 14.63% 12.10% 12.03%
Revised Proposed Projected Projected Projected Projected Yr 1 - Yr 5
CASH SUMMARY 2016 2017 2018 2019 2020 2021 Total
Cash from Operations $ 8,970,000 $ 7,327,600 $ 6,543,600 $ 12,833,900 $ 10,884,100 $ 10,977,900
Transfer to I & E Fund $ 3,500,000 $ 3,400,000 $ 5,400,000 $ 5,900,000 $ 5,900,000 $ 5,900,000 $ 26,500,000
Transfer (from)/to Reserves (773,000) 2,750,000 - 4,000,000 3,000,000 - 9,750,000
Reinvestment of Reserve Interest 279,300 261,200 266,100 254,900 250,100 380,100 1,412,400
Debt Service Principal 2,365,000 695,000 730,000 765,000 800,000 840,000 3,830,000
Total Cash Budget Requirements 5,371,300 7,106,200 6,396,100 10,919,900 9,950,100 7,120,100 41,492,400
Net Positive/(Negative Cash) $ 3,598,700 $ 221,400 $ 147,500 $ 1,914,000 $ 934,000 $ 3,857,800 $ 7,074,700
99
Página 106
REVENUE SOURCES & FUNDS
TOTAL CITY SUMMARY
GENERAL
WATER/WASTEWATER
ELECTRIC
VEHICLE REPLACEMENTS
Página 107
City of Dover, Delaware
FY 2017 Capital Investment Plan
FY 17 thru FY 21
FUNDING SOURCE SUMMARY
Source FY 17 FY 18 FY 19 FY 20 FY 21 Total
Bond Proceeds 3,710,000 3,710,000 3,710,000 11,130,000
Community Transportation Fund 30,000 30,000
DE Sewer Revolving Loan Fund 884,000 396,000 408,000 1,688,000
DE Water Revolving Loan Fund 1,200,000 1,200,000 2,400,000
Developer Contribution 900,000 900,000 900,000 900,000 900,000 4,500,000
Development Grant 5,000 5,000
Electric I & E Fund 1,000,000 437,500 1,437,500
Electric Revenue 3,870,300 5,872,900 3,896,500 3,274,000 2,325,000 19,238,700
Future Capacity Reserve Fund 50,000 6,000,000 6,050,000
General Fund 1,919,400 3,328,800 2,949,100 2,657,100 3,337,200 14,191,600
Impact Fee Reserve 402,000 48,700 86,400 22,000 192,000 751,100
Parkland Reserve Fund 80,000 50,000 15,000 55,000 200,000
State Grant 45,000 128,000 73,000 246,000
Water/Wastewater Fund 2,988,400 4,081,900 3,298,300 3,122,600 3,418,000 16,909,200
GRAND TOTAL 12,410,100 20,721,800 15,251,300 20,221,700 10,172,200 78,777,100
Thursday, May 12, 2016
101
Página 108
City of Dover, Delaware
FY 2017 Capital Investment Plan
FY 17 thru FY 21
DEPARTMENT SUMMARY
Department FY 17 FY 18 FY 19 FY 20 FY 21 Total
Code Enforcement 23,800 17,000 40,800
Electric Admin 30,000 30,000
Electric Engineering 910,700 1,969,900 1,303,000 7,310,000 700,000 12,193,600
Electric Meter Reading 41,800 41,800
Electric T & D 1,975,000 2,053,000 1,825,500 1,900,000 1,810,000 9,563,500
Facilities Management 27,700 28,200 28,800 32,200 116,900
Finance 1,000,000 1,000,000 300,000 2,300,000
Fire/Robbins Hose 145,700 295,200 295,200 226,300 226,300 1,188,700
Fleet Maintenance 31,000 38,000 60,000 129,000
Life Safety (Fire Marshal) 29,500 29,500
Parks and Recreation 165,000 241,000 15,000 161,000 582,000
Permtting and Inspections 16,000 34,000 50,000
Planning 16,000 16,000
Police 299,800 451,500 399,100 364,700 367,400 1,882,500
Power Plant 1,842,800 2,770,000 1,668,000 964,000 715,000 7,959,800
Public Works - Grounds 58,200 59,800 188,000 153,000 151,000 610,000
Public Works - Sanitation 261,500 431,700 429,100 204,900 627,000 1,954,200
Public Works - Streets 1,026,000 5,245,400 5,258,900 5,353,000 1,872,500 18,755,800
Public Works Admin 42,000 42,000
W/WW Engineering 30,400 31,000 23,000 28,000 112,400
Wastewater Management 2,021,200 2,453,000 2,283,400 1,991,400 2,040,000 10,789,000
Water Management 1,338,800 2,042,300 1,424,300 1,450,900 1,570,000 7,826,300
Water Treatment Plant 1,200,000 1,226,000 50,000 82,300 2,558,300
TOTAL 12,405,100 20,421,800 15,551,300 20,221,700 10,172,200 78,772,100
Thursday, May 12, 2016
102
Página 110
City of Dover, Delaware
FY 2017 Capital Investment Plan
FY 17 thru FY 21
FUNDING SOURCE SUMMARY
Source FY 17 FY 18 FY 19 FY 20 FY 21 Total
Bond Proceeds 3,710,000 3,710,000 3,710,000 11,130,000
Community Transportation Fund 30,000 30,000
General Fund 1,078,500 1,176,200 1,395,700 1,290,500 1,215,500 6,156,400
Parkland Reserve Fund 80,000 50,000 15,000 55,000 200,000
State Grant 45,000 128,000 73,000 246,000
GRAND TOTAL 1,203,500 5,094,200 5,120,700 5,128,500 1,215,500 17,762,400
Thursday, May 12, 2016
104
Página 111
City of Dover, Delaware
FY 2017 Capital Investment Plan
FY 17 thru FY 21
PROJECTS BY DEPARTMENT
Department Project# Priority FY 17 FY 18 FY 19 FY 20 FY 21 Total
Parks and Recreation
Dover Park - Master Plan PR1701 1 50,000 50,000
Schutte Park Land Improvements PR1702 1 100,000 90,000 190,000
Park and Playground Improvement Program PR1703 3 66,000 66,000 132,000
Small Park Improvements PR1704 4 15,000 15,000 15,000 15,000 60,000
Silver Lake Park - Master Plan&Plan Implementation PR1801 1 70,000 80,000 150,000
Parks and Recreation Total 165,000 241,000 15,000 161,000 582,000
Police
Video Storage Array for In-Car Video Recordings PD1701 1 12,500 12,500
Server Consolidation PD1801 1 43,200 43,200 86,400
Police Total 12,500 43,200 43,200 98,900
Public Works - Streets
Stormwater/Old PW2 Site Improvements ST1602 1 2,550,000 2,550,000 2,550,000 7,650,000
Street, Concrete and Alley Program ST1701 2 900,000 1,050,000 1,102,500 1,157,500 1,215,500 5,425,500
Silver Lake Dam Improvements ST1703 3 126,000 126,000
Redevelopment of Schutte Park ST1801 1 1,160,000 1,160,000 1,160,000 3,480,000
Dover Library Conveyance System Improvements ST1803 1 50,000 200,000 250,000
Water Street Flooding Improvements ST1904 4 50,000 100,000 150,000
Public Works - Streets Total 1,026,000 4,810,000 5,062,500 4,967,500 1,215,500 17,081,500
GRAND TOTAL 1,203,500 5,094,200 5,120,700 5,128,500 1,215,500 17,762,400
Thursday, May 12, 2016
105
Página 112
FY 2017 Capital Investment Plan FY 17 thru FY 21 Department Parks and Recreation
City of Dover, Delaware Contact Parks & Recreation Director
Type Improvement
Project # PR1701
Useful Life
Project Name Dover Park - Master Plan Category General
New Project: No Account Number: 147-1500-525.40-31 Priority 1
Time-Line: FY16-FY18 Status Active
Total Project Cost: $50,000
Description
Hire a consultant to develop a master plan for Dover Park that includes a vegetation management plan and lighting plan, and also addresses the
needs identified in the Recreation Needs Assessment, including walking paths, restrooms, a skate parks, splash pad, and reserves a location for a
recreation center building in the event that one is constructed at a future date.
Justification
With the demolition of the old recreation center building and the concern about the need to improve access to recreation opportunities on the east
side of Dover, the City Council allocated funds for improvements to Dover Park. The Recreation Needs Assessment identified a number of
priorities and issues to be addressed. In order to appropriately allocate resources, a park plan that addresses the priorities and issues brought forth
in the Recreation Needs Assessment is necessary. The planning process will include input from the public and address the phasing of
improvements.
Expenditures FY 17 FY 18 FY 19 FY 20 FY 21 Total
Planning/Design 50,000 50,000
Total 50,000 50,000
Funding Sources FY 17 FY 18 FY 19 FY 20 FY 21 Total
Parkland Reserve Fund 25,000 25,000
State Grant 25,000 25,000
Total 50,000 50,000
Budget Impact/Other
Thursday, May 12, 2016
106
Página 113
FY 2017 Capital Investment Plan FY 17 thru FY 21 Department Parks and Recreation
City of Dover, Delaware Contact Public Works Director
Type Improvement
Project # PR1702
Useful Life 50 years
Project Name Schutte Park Land Improvements Category General
New Project: No Account Number: 147-1500-525.40-31 Priority 1
Time-Line: FY17 Status Active
Total Project Cost: $190,000
Description
This project includes a plan to develop multipurpose fields on the lands on the west side of the park and to complete the multipurpose pathway
around the park’s perimeter. It will also include other amenities that are consistent with the Recreation Needs Assessment. Once plans are
complete, the improvements will be constructed in FY 17.
Justification
Currently, the Schutte Park addition is unusable. There is constant demand for field space, and we have 14 acres of unusable space.
Expenditures FY 17 FY 18 FY 19 FY 20 FY 21 Total
Construction/Maintenance 100,000 90,000 190,000
Total 100,000 90,000 190,000
Funding Sources FY 17 FY 18 FY 19 FY 20 FY 21 Total
Community Transportation 30,000 30,000
Fund
General Fund 40,000 40,000
Parkland Reserve Fund 40,000 40,000
State Grant 20,000 60,000 80,000
Total 100,000 90,000 190,000
Budget Impact/Other
Thursday, May 12, 2016
107
Página 114
FY 2017 Capital Investment Plan FY 17 thru FY 21 Department Parks and Recreation
City of Dover, Delaware Contact Public Works Director
Type Improvement
Project # PR1703
Useful Life 10-15 years
Project Name Park and Playground Improvement Program Category General
New Project: No Account Number: 147-1500-525.40-31 Priority 3
Time-Line: FY17-FY20 Status Active
Total Project Cost: $132,000
Description
This project provides for a regular replacement of playground equipment and other park amenities throughout the park system. It could also
potentially include installation of playground equipment in parks without equipment. This is important to ensure that equipment is replaced as old
equipment deteriorates and becomes less safe. All newly installed equipment will meet the standards of the Consumer Product Safety Commission.
Justification
As equipment ages it deteriorates and can become unsightly and/or unsafe. Replacement of dated equipment is important to ensure that our parks
meet the needs of the population and provides a safe play environment.
Expenditures FY 17 FY 18 FY 19 FY 20 FY 21 Total
Construction/Maintenance 66,000 66,000 132,000
Total 66,000 66,000 132,000
Funding Sources FY 17 FY 18 FY 19 FY 20 FY 21 Total
General Fund 33,000 33,000 66,000
State Grant 33,000 33,000 66,000
Total 66,000 66,000 132,000
Budget Impact/Other
Thursday, May 12, 2016
108
Página 115
FY 2017 Capital Investment Plan FY 17 thru FY 21 Department Parks and Recreation
City of Dover, Delaware Contact Parks & Recreation Director
Type Improvement
Project # PR1704
Useful Life 10-15 years
Project Name Small Park Improvements Category General
New Project: No Account Number: 147-1500-525.40-31 Priority 4
Time-Line: FY17-FY20 Status Active
Total Project Cost: $60,000
Description
Under this project, the City would fund small capital improvements in parks citywide. This could include improvements to pavilions, fencing and
other structures in the park that require investment over time but exceed the thresholds for non-capital investments.
Justification
There are a number of amenities in the City’s park that deteriorate over time and require small capital investments to be safe and attractive. As our
park investments age, we need to make sure that we are maintaining the properties, which may require small capital projects.
Expenditures FY 17 FY 18 FY 19 FY 20 FY 21 Total
Construction/Maintenance 15,000 15,000 15,000 15,000 60,000
Total 15,000 15,000 15,000 15,000 60,000
Funding Sources FY 17 FY 18 FY 19 FY 20 FY 21 Total
Parkland Reserve Fund 15,000 15,000 15,000 15,000 60,000
Total 15,000 15,000 15,000 15,000 60,000
Budget Impact/Other
Thursday, May 12, 2016
109
Página 116
FY 2017 Capital Investment Plan FY 17 thru FY 21 Department Parks and Recreation
City of Dover, Delaware Contact Parks & Recreation Director
Type Improvement
Project # PR1801
Useful Life
Project Name Silver Lake Park - Master Plan&Plan Implementation Category General
New Project: No Account Number: 147-1500-525.40-31 Priority 1
Time-Line: FY18-FY20 Status Active
Total Project Cost: $150,000
Description
Hire a consultant to develop a master plan for Silver Lake Park that includes a vegetation management plan and lighting plan, and also addresses
the needs identified in the Recreation Needs Assessment, including paths, restrooms, a splash pad, and other general park improvements such as
parking lot improvements and delineation and preservation of the African American Cemetery on the property. The Silver Lake Commission and
DNREC would be part of the planning process.
Justification
The plan for Silver Lake Park needs to be updated based on current need as identified in the Recreation Needs Assessment.
Expenditures FY 17 FY 18 FY 19 FY 20 FY 21 Total
Planning/Design 70,000 80,000 150,000
Total 70,000 80,000 150,000
Funding Sources FY 17 FY 18 FY 19 FY 20 FY 21 Total
Parkland Reserve Fund 35,000 40,000 75,000
State Grant 35,000 40,000 75,000
Total 70,000 80,000 150,000
Budget Impact/Other
Thursday, May 12, 2016
110
Página 117
FY 2017 Capital Investment Plan FY 17 thru FY 21 Department Police
City of Dover, Delaware Contact Capt Stump
Type Technology
Project # PD1701
Useful Life 1-5 years
Project Name Video Storage Array for In-Car Video Recordings Category General
New Project: Yes Account Number: 147-1700-541.40-28 Priority 1
Time-Line: Status Active
Total Project Cost: $12,500
Description
The current disk storage for the police department in-car recordings is beyond the city’s life-cycle term of 5 years. It was originally sized to meet
the needs of the old I-COP video system, but now stores the ICOP plus two newer video systems’ recordings as well. The storage is at maximum
capacity requiring a constant manual deletion of the oldest recordings to make space for the new video footage.
The current storage space is approximately 5.4 Terabytes. The new disk storage array, which will be a Dell PowerVault NX3230, will total 48
Terabytes of disk space with a final redundancy configuration allowing for 36 Terabytes of storage. This will greatly increase the amount of
recordings as well as the length of time they can be kept.
Justification
In-car and body-camera footage serves to protect both the officer and the persons they contact. There is a push to have a two-year retention for
videos as an in-house standard which exceeds the State of Delaware retention requirements. The department is also anticipating the body-camera
technology to be implemented in the near future which will raise the current storage space requirements. This project will satisfy current storage
needs in addition to putting the police department into a position to support any future officer related video projects that may be implemented.
Expenditures FY 17 FY 18 FY 19 FY 20 FY 21 Total
Equip/Vehicle/Furnishings 12,500 12,500
Total 12,500 12,500
Funding Sources FY 17 FY 18 FY 19 FY 20 FY 21 Total
General Fund 12,500 12,500
Total 12,500 12,500
Budget Impact/Other
The purchase price above includes a five year warranty period, which is the expected life cycle for these servers. As a result, we would hope to
replace them every five years so there are no expected recurring budget costs for this project. However, it may be possible to extend the life of the
systems, but maintenance costs would be incurred for additional years to keep the systems operational. We do not know what the maintenance cost
would be for that point in time.
Thursday, May 12, 2016
111
Página 118
FY 2017 Capital Investment Plan FY 17 thru FY 21 Department Police
City of Dover, Delaware Contact Capt Stump
Type Technology
Project # PD1801
Useful Life 5 years
Project Name Server Consolidation Category Information Technology
New Project: Yes Account Number: 147-1700-541.40-26 Priority 1
Time-Line: FY18-FY19 Status Active
Total Project Cost: $86,400
Description
The Police Department regular server hardware currently consists of 9 physical server computers, with one of them serving as a virtualized host of
3 virtualized servers, totaling 11 windows server environments. This number is dynamic as the need for separate servers changes every few years.
The cost of an individual server includes both the physical hardware as well as the operating system installed on such servers, and licenses for
clients to connect to each of those operating systems. The idea behind virtualized server environments is to reduce operating costs over time by
purchasing one robust physical server which can handle the virtualized load of operating systems normally housed on individual and less robust
server hardware. The initial cost of the robust virtual host is a fraction of what would be spent in multiple years of physical server costs. This,
combined with a Datacenter Edition of Windows Server allows for unlimited licenses of virtual servers, limited only by the hardware capabilities
of that one robust host. There will be exceptions where a physical machine is required by a vendor or is necessary due to workload (such as SQL
database host), but most environments can be of a virtual type.
Justification
The City’s IT Department is also migrating the rest of the city computer systems to this type of set-up so we would like to follow their example. In
addition, this project will simplify the internal server structure by:
1.Reducing the number of physical servers
2.Reducing costs of operating systems purchased over time
3.Reducing costs of multiple physical server purchases
4.Reducing electrical use of physical servers which in turn reduces electrical costs as well as increasing the run-time on our server battery backup
unit
5.Reducing the amount of heat generated otherwise by multiple physical servers which in turn requires more cooling of server room
6.Reduces the necessary cabling/wiring necessary to control and network multiple servers
7.Allows us to duplicate the virtual machines to a future, identical machine to facilitate redundancy, reducing or eliminating downtime of server
maintenance (FY18)
Expenditures FY 17 FY 18 FY 19 FY 20 FY 21 Total
Equip/Vehicle/Furnishings 43,200 43,200 86,400
Total 43,200 43,200 86,400
Funding Sources FY 17 FY 18 FY 19 FY 20 FY 21 Total
General Fund 43,200 43,200 86,400
Total 43,200 43,200 86,400
Budget Impact/Other
The purchase price above includes a five year warranty period, which is the expected life cycle for these servers. As a result, we would hope to
replace them every five years so there are no expected recurring budget costs for this project. However, it may be possible to extend the life of the
systems, but maintenance costs would be incurred for additional years to keep the systems operational. We do not know what the maintenance cost
would be for that point in time.
Thursday, May 12, 2016
112
Página 119
FY 2017 Capital Investment Plan FY 17 thru FY 21 Department Public Works - Streets
City of Dover, Delaware Contact Public Works Director
Type Improvement
Project # ST1602
Useful Life 90+ years
Project Name Stormwater/Old PW2 Site Improvements Category General
New Project: No Account Number: 147-1800-554.40-31 Priority 1
Time-Line: FY17-FY21 Status Active
Total Project Cost: $7,650,000
Description
Due to the environmental concerns, the PW 2 site will be redeveloped to increase stormwater quality entering Silver Lake. The improvements
include relocating the greenhouse, grounds office, equipment garage (including small engine repair) to Schutte Park. The existing water
production well will remain on site. The site will be converted to a stabilized park with water quality improvements for stormwater.
Estimates provided by URS, Corp., Consulting Engineer.
Justification
Stringent environmental regulations will require improvements on the site. Relocation of existing city facility to Schutte Park.
Expenditures FY 17 FY 18 FY 19 FY 20 FY 21 Total
Construction/Maintenance 2,550,000 2,550,000 2,550,000 7,650,000
Total 2,550,000 2,550,000 2,550,000 7,650,000
Funding Sources FY 17 FY 18 FY 19 FY 20 FY 21 Total
Bond Proceeds 2,550,000 2,550,000 2,550,000 7,650,000
Total 2,550,000 2,550,000 2,550,000 7,650,000
Budget Impact/Other
Thursday, May 12, 2016
113
Página 120
FY 2017 Capital Investment Plan FY 17 thru FY 21 Department Public Works - Streets
City of Dover, Delaware Contact Public Works Director
Type Improvement
Project # ST1701
Useful Life 20-25 years
Project Name Street, Concrete and Alley Program Category General
New Project: No Account Number: 147-1800-554.40-31 Priority 2
Time-Line: FY17-FY21 Status Active
Total Project Cost: $5,425,500
Description
This project will rehabilitate approximately three to five percent (3-5%) of the street and alley network each year. The estimated capital
maintenance costs are $33.7 million over a 20-year planning horizon in Fiscal Year 2005 dollars. This estimate is based on the needs survey
conducted by Public Services in Fiscal Year 2004. Continuous maintenance on these assets will prevent more costly reconstruction in the future.
This project combines the former Street Resurfacing Program, the Alley Program and the Barrier Free Access Ramp Program. Locations will be
determined by the priority listing and by potential legislator contributions. Additionally, this program replaces and rehabilitates deteriorated
sidewalks and curbs throughout the City using in-house labor and private contractors. This is in accordance with the ADA. Delaying or
eliminated the project will result in continued complaints and insurance claims from citizens and visitors. In addition, further deterioration of the
sidewalk network will occur.
Justification
The program identifies maintenance costs for the 84.79 miles of streets and 15.24 miles of alleys as of June 30, 2010. Replacement of deteriorated
curbs, gutters, and sidewalks provides improved use, drainage, and the appearance of the pavement section. The Street and Alley Program
schedule is driven by funding and road ratings. Total street mileage is growing as more roads and alleys are dedicated for public maintenance due
to growth. Additionally, this program promotes the interconnection of the sidewalk network to conform to ISTEA (Intermodal Surface
Transportation Efficiency Act) and rehabilitates sidewalks that have root damage from City street trees. This program also facilitates compliance
with the Americans with Disabilities Act as it relates to the pedestrian network as well as improving localized drainage issues.
Expenditures FY 17 FY 18 FY 19 FY 20 FY 21 Total
Construction/Maintenance 900,000 1,050,000 1,102,500 1,157,500 1,215,500 5,425,500
Total 900,000 1,050,000 1,102,500 1,157,500 1,215,500 5,425,500
Funding Sources FY 17 FY 18 FY 19 FY 20 FY 21 Total
General Fund 900,000 1,050,000 1,102,500 1,157,500 1,215,500 5,425,500
Total 900,000 1,050,000 1,102,500 1,157,500 1,215,500 5,425,500
Budget Impact/Other
Thursday, May 12, 2016
114
Página 121
FY 2017 Capital Investment Plan FY 17 thru FY 21 Department Public Works - Streets
City of Dover, Delaware Contact Public Works Director
Type Improvement
Project # ST1703
Useful Life 50 years
Project Name Silver Lake Dam Improvements Category General
New Project: Yes Account Number: 147-1800-554.40-31 Priority 3
Time-Line: FY16-FY20 Status Active
Total Project Cost: $126,000
Description
The proposed project, identified by the 2014 Silver Lake Dam Inspection report, will stabilize the east wing wall of the dam, remove large trees,
repair the boat ramp, install stone rip rap on the upstream slope and repair the concrete supports of the pedestrian walkway. Preliminary estimates
provided by JMT, Consulting Engineer
Justification
The improvements are necessary to maintain the existing dam in normal working conditions. Failure to maintain the dam could lead to failure and
downstream flooding.
Expenditures FY 17 FY 18 FY 19 FY 20 FY 21 Total
Construction/Maintenance 126,000 126,000
Total 126,000 126,000
Funding Sources FY 17 FY 18 FY 19 FY 20 FY 21 Total
General Fund 126,000 126,000
Total 126,000 126,000
Budget Impact/Other
Thursday, May 12, 2016
115
Página 122
FY 2017 Capital Investment Plan FY 17 thru FY 21 Department Public Works - Streets
City of Dover, Delaware Contact Public Works Director
Type Improvement
Project # ST1801
Useful Life 90+ years
Project Name Redevelopment of Schutte Park Category General
New Project: No Account Number: 147-1800-554.40-31 Priority 1
Time-Line: FY18-FY20 Status Active
Total Project Cost: $3,480,000
Description
In conjunction with the PW2 site improvements, operations will be relocated to Schutte Park. The improvements include relocating the
greenhouse, grounds office, equipment garage (including small engine repair).
Estimates provided by AECOM, Corp., Consulting Engineer.
Justification
Relocation of existing city facility to Schutte Park will create a centralized location for divisions and increase operational efficiency.
Expenditures FY 17 FY 18 FY 19 FY 20 FY 21 Total
Construction/Maintenance 1,160,000 1,160,000 1,160,000 3,480,000
Total 1,160,000 1,160,000 1,160,000 3,480,000
Funding Sources FY 17 FY 18 FY 19 FY 20 FY 21 Total
Bond Proceeds 1,160,000 1,160,000 1,160,000 3,480,000
Total 1,160,000 1,160,000 1,160,000 3,480,000
Budget Impact/Other
Thursday, May 12, 2016
116
Página 123
FY 2017 Capital Investment Plan FY 17 thru FY 21 Department Public Works - Streets
City of Dover, Delaware Contact Public Works Director
Type Improvement
Project # ST1803
Useful Life 50 years
Project Name Dover Library Conveyance System Improvements Category General
New Project: Yes Account Number: 147-2500-552.40-31 Priority 1
Time-Line: FY18 Status Active
Total Project Cost: $250,000
Description
This project, identified by staff, will upgrade the existing stormwater infrastructure that begins in the northeast corner of the Dover Public Library
parking lot and travels due east to mirror lake and eventually St. Jones River.
Justification
This will provide improved capacity and conveyance of stormwater from the City owned parking lot. Failure to improve this system will result in
continued flooding in the area.
Expenditures FY 17 FY 18 FY 19 FY 20 FY 21 Total
Planning/Design 50,000 50,000
Construction/Maintenance 200,000 200,000
Total 50,000 200,000 250,000
Funding Sources FY 17 FY 18 FY 19 FY 20 FY 21 Total
General Fund 50,000 200,000 250,000
Total 50,000 200,000 250,000
Budget Impact/Other
Thursday, May 12, 2016
117
Página 124
FY 2017 Capital Investment Plan FY 17 thru FY 21 Department Public Works - Streets
City of Dover, Delaware Contact Public Works Director
Type Improvement
Project # ST1904
Useful Life 50 years
Project Name Water Street Flooding Improvements Category General
New Project: Yes Account Number: 147-1800-554.40-31 Priority 4
Time-Line: FY19 Status Active
Total Project Cost: $150,000
Description
This project, identified by staff, will upgrade the existing stormwater infrastructure that is in Water Street, near the intersection of Governors
Avenue. This area consistently floods with a moderate rain event in the City.
Justification
This will provide improved capacity and conveyance of stormwater from this intersection. Failure to improve this system will result in continued
flooding in the area.
Expenditures FY 17 FY 18 FY 19 FY 20 FY 21 Total
Planning/Design 50,000 50,000
Construction/Maintenance 100,000 100,000
Total 50,000 100,000 150,000
Funding Sources FY 17 FY 18 FY 19 FY 20 FY 21 Total
General Fund 50,000 100,000 150,000
Total 50,000 100,000 150,000
Budget Impact/Other
Thursday, May 12, 2016
118
Página 126
City of Dover, Delaware
FY 2017 Capital Investment Plan
FY 17 thru FY 21
FUNDING SOURCE SUMMARY
Source FY 17 FY 18 FY 19 FY 20 FY 21 Total
DE Sewer Revolving Loan Fund 884,000 396,000 408,000 1,688,000
DE Water Revolving Loan Fund 1,200,000 1,200,000 2,400,000
Impact Fee Reserve 402,000 48,700 86,400 22,000 192,000 751,100
Water/Wastewater Fund 2,765,800 3,129,900 2,613,600 2,775,500 3,283,000 14,567,800
GRAND TOTAL 4,367,800 5,262,600 3,096,000 3,205,500 3,475,000 19,406,900
Thursday, May 12, 2016
120
Página 127
City of Dover, Delaware
FY 2017 Capital Investment Plan
FY 17 thru FY 21
PROJECTS BY DEPARTMENT
Department Project# Priority FY 17 FY 18 FY 19 FY 20 FY 21 Total
Wastewater Management
Rolling Acres Pump Station Replacement WW1603 1 372,000 372,000
Meter Replacement Program WW1700 1 200,000 200,000 200,000 200,000 200,000 1,000,000
Inflow/Infiltration Removal WW1701 1 1,121,000 1,173,000 1,171,000 1,169,000 1,167,000 5,801,000
Miscellaneous Emergency Sanitary Sewer Repairs WW1702 2 75,000 77,000 79,000 81,000 83,000 395,000
Lepore Road Sanitary Sewer Upgrade WW1704 4 50,000 250,000 300,000
Delaware Tech Pump Station Replacement WW1705 5 52,000 384,000 436,000
Silver Lake Pump Station Replacement WW1706 6 52,000 396,000 448,000
Walker Woods Pump Station Replacement WW1707 7 52,000 408,000 460,000
Tar Ditch Interceptor WW1805 5 250,000 250,000
College Road Pump Station Replacement WW2004 4 55,000 420,000 475,000
Turnberry Pump Station Replacement WW2104 4 60,000 60,000
Wastewater Management Total 1,974,000 2,334,000 1,846,000 1,913,000 1,930,000 9,997,000
Water Management
Future Well Installation WD1605 5 100,000 1,098,300 1,198,300
Meter Replacement Project WD1700 1 200,000 200,000 200,000 200,000 200,000 1,000,000
Wellhead Redevelopment Program WD1701 1 85,000 87,500 90,000 92,500 95,000 450,000
SCADA Equipment Technology Upgrade WD1705 5 88,000 88,000
Water Quality Improvements WQ1702 2 645,800 265,800 881,000 919,000 1,167,000 3,878,600
Miscellaneous Emergency Water Repairs WQ1703 3 75,000 77,000 79,000 81,000 83,000 395,000
Water Management Total 1,193,800 1,728,600 1,250,000 1,292,500 1,545,000 7,009,900
Water Treatment Plant
Water Treatment Plant Process Improvements WD1609 4 1,200,000 1,200,000 2,400,000
Water Treatment Plant Total 1,200,000 1,200,000 2,400,000
GRAND TOTAL 4,367,800 5,262,600 3,096,000 3,205,500 3,475,000 19,406,900
Thursday, May 12, 2016
121
Página 128
FY 2017 Capital Investment Plan FY 17 thru FY 21 Department Wastewater Management
City of Dover, Delaware Contact Public Works Director
Type Improvement
Project # WW1603
Useful Life 20-25 years
Project Name Rolling Acres Pump Station Replacement Category Water/Wastewater
New Project: No Account Number: 417-6900-569.40-31 Priority 1
Time-Line: FY16-FY17 Status Active
Total Project Cost: $372,000
Description
This project calls for replacement of the Smith & Loveless package pumping station installed in 1973 in order to handle the commercial areas from
Harrington Realty Shopping Center to the Howard Johnson Hotel. The station has exceeded its life anticipated expectancy of 20-25 years and is in
need of a capacity upgrade due to the high peak inflow rates. This station experiences periods of high inflow rates due to the hotel occupancy and
is susceptible to possible inflow/infiltration. Staff has observed numerous pump high wet well alarms due to high inflows and increased runtimes
during wet months.
Justification
Replace the aged station with a completely new station to prevent the need for costly unbudgeted repairs to maintain operation. Pump failure
resulting in a sewage spill into waterway or backup in a residence. Due to the age of the station, certain parts are no longer obtainable, and
replacement of equipment is costly. Design and bid in Fiscal 2016; construction in Fiscal 2017
Expenditures FY 17 FY 18 FY 19 FY 20 FY 21 Total
Construction/Maintenance 372,000 372,000
Total 372,000 372,000
Funding Sources FY 17 FY 18 FY 19 FY 20 FY 21 Total
Impact Fee Reserve 148,800 148,800
Water/Wastewater Fund 223,200 223,200
Total 372,000 372,000
Budget Impact/Other
Thursday, May 12, 2016
122
Página 129
FY 2017 Capital Investment Plan FY 17 thru FY 21 Department Wastewater Management
City of Dover, Delaware Contact Public Works Director
Type Improvement
Project # WW1700
Useful Life 20 years
Project Name Meter Replacement Program Category Water/Wastewater
New Project: Yes Account Number: 417-6900-569.40-31 Priority 1
Time-Line: FY17-FY21 Status Active
Total Project Cost: $1,000,000
Description
This project will be an ongoing project to replace our aged water meters in the system. A portion of water meters will be replaced each year. A
majority of the water meters have exceeded their life expectancy of 15-20 years. The industry standard is to replace 20% of the meter inventory for
five years. The City will benefit from this project by having a more efficient system which will recover maximum revenue to the water utility.
Additionally, expenses of maintaining, stocking and operating the out dated meters are greatly reduced. This project will begin in Fiscal 2016.
Justification
This project will provide the City of Dover with accurate readings of our water users, thus creating accurate revenue from the customers. Delaying
or eliminating this project would result in the age of the water meters increasing, and consequently the meters will not read the correct volume of
water being consumed. Additionally, older water meters typically require more maintenance.
Expenditures FY 17 FY 18 FY 19 FY 20 FY 21 Total
Equip/Vehicle/Furnishings 200,000 200,000 200,000 200,000 200,000 1,000,000
Total 200,000 200,000 200,000 200,000 200,000 1,000,000
Funding Sources FY 17 FY 18 FY 19 FY 20 FY 21 Total
Water/Wastewater Fund 200,000 200,000 200,000 200,000 200,000 1,000,000
Total 200,000 200,000 200,000 200,000 200,000 1,000,000
Budget Impact/Other
Over time, the capabilities of a water meter to read accurate volumes of water deteriorates, typically registering less water than actually being
consumed. With installation of new meters, accurate readings will increase the actual revenue from this utility.
Thursday, May 12, 2016
123
Página 130
FY 2017 Capital Investment Plan FY 17 thru FY 21 Department Wastewater Management
City of Dover, Delaware Contact Public Works Director
Type Improvement
Project # WW1701
Useful Life 50-80
Project Name Inflow/Infiltration Removal Category Water/Wastewater
New Project: No Account Number: 417-6900-569.40-31 Priority 1
Time-Line: FY17-FY21 Status Active
Total Project Cost: $5,801,000
Description
This project identifies and corrects areas in the sanitary sewer collection system that are deteriorating and allowing groundwater to enter the
sanitary sewer system through cracked pipes and/or joints. Video investigations of the lines are performed by in-house crews to determine the
condition of subject pipes which may also help with the identification of sump pumps and other illicit connections to the system which will have to
be removed by individual property owners. Investigations are occurring systematically through the sewer basins to establish projects for the
following year. Sanitary sewer lines are also being inspected in conjunction with water quality improvement project areas to determine main
condition. Smoke testing, pipe relining and or replacement are to occur each year.
The wet weather which was experienced in both 2003 and 2009/2010/2011, exemplified the fact that the aging and deteriorating sanitary sewer
system allows groundwater and rain water to enter the system. This in turn results in higher treatment charges from Kent County. In FY 2011 a
new groundwater inflow adjustment charge was established as a result. It is critical to continue making improvements on a regular and planned
basis to improve the integrity of the wastewater system. Weather occurs in a cyclical fashion and discrepancies between fees collected and charges
received will likely happen again when groundwater and precipitation levels rise. FY 16 projects include rehabilitating the White Oak Farms
Basin #5.
Justification
The wet weather experienced in both 2003 and 2009/2010/2011, highlighted the fact that we have an aging wastewater system that requires more
attention to the condition of the old pipe network and more monitoring of illicit connections to the system. Inflow and infiltration are problems that
all customers pay for since they are costs that are not assigned to an individual customer. Therefore, all customers are affected by expenses related
to inflow and infiltration.
Delaying or eliminating this project will result in continued higher treatment charges for wastewater flow to Kent County than is necessary. In
addition, the reduction in available capacity in the City and county systems due to inflow and infiltration will reduce the capacity available for
future growth.
Expenditures FY 17 FY 18 FY 19 FY 20 FY 21 Total
Construction/Maintenance 1,121,000 1,173,000 1,171,000 1,169,000 1,167,000 5,801,000
Total 1,121,000 1,173,000 1,171,000 1,169,000 1,167,000 5,801,000
Funding Sources FY 17 FY 18 FY 19 FY 20 FY 21 Total
Water/Wastewater Fund 1,121,000 1,173,000 1,171,000 1,169,000 1,167,000 5,801,000
Total 1,121,000 1,173,000 1,171,000 1,169,000 1,167,000 5,801,000
Budget Impact/Other
The project will reduce the operating budget over time due to the reduction in costs for sewage treatment paid to Kent County. All savings are
cumulative.
Thursday, May 12, 2016
124
Página 131
FY 2017 Capital Investment Plan FY 17 thru FY 21 Department Wastewater Management
City of Dover, Delaware Contact Public Works Director
Type Improvement
Project # WW1702
Useful Life 50-80
Project Name Miscellaneous Emergency Sanitary Sewer Repairs Category Water/Wastewater
New Project: Yes Account Number: 417-6900-569.40-31 Priority 2
Time-Line: FY17-FY21 Status Active
Total Project Cost: $395,000
Description
This project will repair failing sanitary sewer infrastructure. The work will focus on emergency repair situations on City owned infrastructure. No
specific locations for this work have been identified.
Justification
This project is necessary to address failing or deteriorated infrastructure in the City. If these repairs are not conducted, significant impacts to
property, life and environment could arise. Delaying these repairs could result in road failure, sink holes and environmental contamination.
Expenditures FY 17 FY 18 FY 19 FY 20 FY 21 Total
Construction/Maintenance 75,000 77,000 79,000 81,000 83,000 395,000
Total 75,000 77,000 79,000 81,000 83,000 395,000
Funding Sources FY 17 FY 18 FY 19 FY 20 FY 21 Total
Water/Wastewater Fund 75,000 77,000 79,000 81,000 83,000 395,000
Total 75,000 77,000 79,000 81,000 83,000 395,000
Budget Impact/Other
Thursday, May 12, 2016
125
Página 132
FY 2017 Capital Investment Plan FY 17 thru FY 21 Department Wastewater Management
City of Dover, Delaware Contact Public Works Director
Type Improvement
Project # WW1704
Useful Life 90+ years
Project Name Lepore Road Sanitary Sewer Upgrade Category Water/Wastewater
New Project: No Account Number: 417-6900-569.40-31 Priority 4
Time-Line: FY17-FY18 Status Active
Total Project Cost: $300,000
Description
This project calls for the replacement of approximately 374 linear feet of 8 inch gravity sewer main. Currently, the sewer main operates in a
reverse slope condition, which overloads the pipe. The proposed upgrade will provide slope and adequate capacity for current flow to be carried to
discharge. Estimates provided by Pennoni Associates, Consulting Engineer.
Justification
This project will allow for proper capacity and slope to handle the current flow. Delaying or eliminating this project could result in overflow of
wastewater material. Design and bid in Fiscal 2017; construction in Fiscal 2018.
Expenditures FY 17 FY 18 FY 19 FY 20 FY 21 Total
Planning/Design 50,000 50,000
Construction/Maintenance 250,000 250,000
Total 50,000 250,000 300,000
Funding Sources FY 17 FY 18 FY 19 FY 20 FY 21 Total
DE Sewer Revolving Loan 250,000 250,000
Fund
Water/Wastewater Fund 50,000 50,000
Total 50,000 250,000 300,000
Budget Impact/Other
Thursday, May 12, 2016
126
Página 133
FY 2017 Capital Investment Plan FY 17 thru FY 21 Department Wastewater Management
City of Dover, Delaware Contact Public Works Director
Type Improvement
Project # WW1705
Useful Life 20-25 years
Project Name Delaware Tech Pump Station Replacement Category Water/Wastewater
New Project: No Account Number: 417-6900-569.40-31 Priority 5
Time-Line: FY17-FY18 Status Active
Total Project Cost: $436,000
Description
This project calls for replacement of the Smith & Loveless package pumping station installed in 1975 in order to handle the increased flows from
the area. The station has exceeded its life anticipated expectancy of 20-25 years and is in need of a capacity upgrade due to anticipated increase
flow. Estimates provided by Pennoni Associates, Consulting Engineer.
Justification
Replace the aged station with a completely new station to prevent the need for costly unbudgeted repairs to maintain operation. Pump failure
resulting in a sewage spill into waterway or backup in a residence. Due to the age of the station, certain parts are no longer obtainable, and
replacement of equipment is costly. Design in Fiscal 2017; construction in Fiscal 2018
Expenditures FY 17 FY 18 FY 19 FY 20 FY 21 Total
Planning/Design 52,000 52,000
Construction/Maintenance 384,000 384,000
Total 52,000 384,000 436,000
Funding Sources FY 17 FY 18 FY 19 FY 20 FY 21 Total
DE Sewer Revolving Loan 384,000 384,000
Fund
Impact Fee Reserve 20,800 20,800
Water/Wastewater Fund 31,200 31,200
Total 52,000 384,000 436,000
Budget Impact/Other
The construction phase of this project has a potential to be funded by a Clean Water State Revolving Fund Loan.
Thursday, May 12, 2016
127
Página 134
FY 2017 Capital Investment Plan FY 17 thru FY 21 Department Wastewater Management
City of Dover, Delaware Contact Public Works Director
Type Improvement
Project # WW1706
Useful Life 20-25 years
Project Name Silver Lake Pump Station Replacement Category Water/Wastewater
New Project: No Account Number: 417-6900-569.40-31 Priority 6 --
Time-Line: FY17 - FY19 Status Active
Total Project Cost: $448,000
Description
This project calls for replacement of the Smith & Loveless package pumping station installed in 1982 in order to handle development in the area,
as well as completely rehabilitate the wet well side of the pump station using a poly-triplex system liner. The station has exceeded its life
expectancy of 20-25 years and is in need of a capacity upgrade to handle anticipated growth in the basin.
Justification
Replace the aged station with a completely new station to prevent the need for costly unbudgeted repairs to maintain operation. Pump failure
resulting in a sewage spill into waterway or backup in a residence. Due to the age of the station, certain parts are no longer obtainable and
replacement of equipment is costly. Design in Fiscal 2017; construction in Fiscal 2019.
Expenditures FY 17 FY 18 FY 19 FY 20 FY 21 Total
Planning/Design 52,000 52,000
Construction/Maintenance 396,000 396,000
Total 52,000 396,000 448,000
Funding Sources FY 17 FY 18 FY 19 FY 20 FY 21 Total
DE Sewer Revolving Loan 396,000 396,000
Fund
Impact Fee Reserve 20,800 20,800
Water/Wastewater Fund 31,200 31,200
Total 52,000 396,000 448,000
Budget Impact/Other
The construction phase of this project has a potential to be funded by a Clean Water State Revolving Fund Loan.
Thursday, May 12, 2016
128
Página 135
FY 2017 Capital Investment Plan FY 17 thru FY 21 Department Wastewater Management
City of Dover, Delaware Contact Public Works Director
Type Improvement
Project # WW1707
Useful Life 20-25 years
Project Name Walker Woods Pump Station Replacement Category Water/Wastewater
New Project: Yes Account Number: 417-6900-569.40-31 Priority 7 --
Time-Line: FY19-FY20 Status Active
Total Project Cost: $460,000
Description
This project calls for replacement of the Smith & Loveless package pumping station installed in 1989 in order to handle development in the area,
as well as completely rehabilitate the wet well side of the pump station using a poly-triplex system liner. The station has exceeded its life
expectancy of 20-25 years and is in need of a capacity upgrade to handle anticipated growth in the basin.
Justification
Replace the aged station with a completely new station to prevent the need for costly unbudgeted repairs to maintain operation. Pump failure
resulting in a sewage spill into waterway or backup in a residence. Due to the age of the station, certain parts are no longer obtainable and
replacement of equipment is costly. Design in Fiscal 2017; construction in Fiscal 2020.
Expenditures FY 17 FY 18 FY 19 FY 20 FY 21 Total
Planning/Design 52,000 52,000
Construction/Maintenance 408,000 408,000
Total 52,000 408,000 460,000
Funding Sources FY 17 FY 18 FY 19 FY 20 FY 21 Total
DE Sewer Revolving Loan 408,000 408,000
Fund
Impact Fee Reserve 20,800 20,800
Water/Wastewater Fund 31,200 31,200
Total 52,000 408,000 460,000
Budget Impact/Other
Thursday, May 12, 2016
129
Página 136
FY 2017 Capital Investment Plan FY 17 thru FY 21 Department Wastewater Management
City of Dover, Delaware Contact Public Utilities Director
Type Improvement
Project # WW1805
Useful Life 20-25 years
Project Name Tar Ditch Interceptor Category Water/Wastewater
New Project: Yes Account Number: 417-6900-569.40-31 Priority 5
Time-Line: FY18 Status Active
Total Project Cost: $250,000
Description
This project, identified in the 2009 Wastewater Master Plan, requires approximately 300 linear feet of fifteen (15”) gravity sanitary sewer
replacement. It has been identified that the subject pipe is flowing with a reverse slope, which can cause a surcharge during peak flow periods.
Estimates provided by AECOM, Corp., Consulting Engineer.
Justification
Delaying this project will result in preventing growth, as well as environmental issues with sewage surcharging onto the ground. Additionally, not
addressing this issue could result in sewage backups to residences. Construction in Fiscal 2018.
Expenditures FY 17 FY 18 FY 19 FY 20 FY 21 Total
Construction/Maintenance 250,000 250,000
Total 250,000 250,000
Funding Sources FY 17 FY 18 FY 19 FY 20 FY 21 Total
DE Sewer Revolving Loan 250,000 250,000
Fund
Total 250,000 250,000
Budget Impact/Other
The construction phase of this project has a potential to be funded by a Clean Water State Revolving Fund Loan.
Thursday, May 12, 2016
130
Página 137
FY 2017 Capital Investment Plan FY 17 thru FY 21 Department Wastewater Management
City of Dover, Delaware Contact Public Works Director
Type Improvement
Project # WW2004
Useful Life 20-25 years
Project Name College Road Pump Station Replacement Category Water/Wastewater
New Project: Yes Account Number: 417-6900-569.40-31 Priority 4
Time-Line: FY20-FY21 Status Active
Total Project Cost: $475,000
Description
This project calls for replacement of the Smith & Loveless package pumping station installed in 1987 in order to handle development in the area,
as well as completely rehabilitate the wet well side of the pump station using a poly-triplex system liner. The station has exceeded its life
expectancy of 20-25 years and is in need of a capacity upgrade to handle anticipated growth in the basin.
Justification
Replace the aged station with a completely new station to prevent the need for costly unbudgeted repairs to maintain operation. Pump failure
resulting in a sewage spill into waterway or backup in a residence. Due to the age of the station, certain parts are no longer obtainable and
replacement of equipment is costly. Design and bid in Fiscal 2020; construction in Fiscal 2021.
Expenditures FY 17 FY 18 FY 19 FY 20 FY 21 Total
Planning/Design 55,000 420,000 475,000
Total 55,000 420,000 475,000
Funding Sources FY 17 FY 18 FY 19 FY 20 FY 21 Total
Impact Fee Reserve 22,000 168,000 190,000
Water/Wastewater Fund 33,000 252,000 285,000
Total 55,000 420,000 475,000
Budget Impact/Other
Thursday, May 12, 2016
131
Página 138
FY 2017 Capital Investment Plan FY 17 thru FY 21 Department Wastewater Management
City of Dover, Delaware Contact
Type Improvement
Project # WW2104
Useful Life 20-25 years
Project Name Turnberry Pump Station Replacement Category Water/Wastewater
New Project: Yes Account Number: 417-6900-569.40-31 Priority 4
Time-Line: FY21 Status Active
Total Project Cost: $60,000
Description
This project calls for replacement of the Smith & Loveless package pumping station installed in 1989 in order to handle development in the area,
as well as completely rehabilitate the wet well side of the pump station using a poly-triplex system liner. The station has exceeded its life
expectancy of 20-25 years and is in need of a capacity upgrade to handle anticipated growth in the basin.
Justification
Replace the aged station with a completely new station to prevent the need for costly unbudgeted repairs to maintain operation, thus reducing
pump failure resulting in a sewage spill into waterway or backup in a residence. Due to the age of the station, certain parts are no longer obtainable
and replacement of equipment is costly. Design and bid in Fiscal 2021; construction in Fiscal 2022.
Expenditures FY 17 FY 18 FY 19 FY 20 FY 21 Total
Planning/Design 60,000 60,000
Total 60,000 60,000
Funding Sources FY 17 FY 18 FY 19 FY 20 FY 21 Total
Impact Fee Reserve 24,000 24,000
Water/Wastewater Fund 36,000 36,000
Total 60,000 60,000
Budget Impact/Other
Thursday, May 12, 2016
132
Página 139
FY 2017 Capital Investment Plan FY 17 thru FY 21 Department Water Management
City of Dover, Delaware Contact Public Works Director
Type Improvement
Project # WD1605
Useful Life 100+
Project Name Future Well Installation Category Water/Wastewater
New Project: Yes Account Number: 417-6800-568.40-31 Priority 5
Time-Line: FY16-FY18 Status Active
Total Project Cost: $1,198,300
Description
The proposed project, identified by staff will drill a new well to increase production capacity for the Water Department. Estimates provided by
URS, Consulting Engineer
Justification
To meet increased water demand and fire suppression requirements. Delaying or eliminating this project would result in the continued reduction in
our production capabilities under our permitted allocation, as well as limiting the City’s growth. Initial planning is proposed for FY15, site
procurement planned for FY16 and construction in FY17.
Expenditures FY 17 FY 18 FY 19 FY 20 FY 21 Total
Land Acquisition 100,000 100,000
Construction/Maintenance 1,098,300 1,098,300
Total 100,000 1,098,300 1,198,300
Funding Sources FY 17 FY 18 FY 19 FY 20 FY 21 Total
Impact Fee Reserve 100,000 100,000
Water/Wastewater Fund 1,098,300 1,098,300
Total 100,000 1,098,300 1,198,300
Budget Impact/Other
Thursday, May 12, 2016
133
Página 140
FY 2017 Capital Investment Plan FY 17 thru FY 21 Department Water Management
City of Dover, Delaware Contact Public Works Director
Type Improvement
Project # WD1700
Useful Life 20 years
Project Name Meter Replacement Project Category Water/Wastewater
New Project: Yes Account Number: 417-6800-568.40-31 Priority 1
Time-Line: FY17-FY21 Status Active
Total Project Cost: $1,000,000
Description
This project will be an ongoing project to replace our aged water meters in the system. A portion of water meters will be replaced each year. A
majority of the water meters have exceeded their life expectancy of 15-20 years. The industry standard is to replace 20% of the meter inventory for
five years. The City will benefit from this project by having a more efficient system which will recover maximum revenue to the water utility.
Additionally, expenses of maintaining, stocking and operating the out dated meters are greatly reduced. This project will begin in Fiscal 2016.
Justification
This project will provide the City of Dover with accurate readings of our water users, thus creating accurate revenue from the customers. Delaying
or eliminating this project would result in the age of the water meters increasing, and consequently the meters will not read the correct volume of
water being consumed. Additionally, older water meters typically require more maintenance.
Expenditures FY 17 FY 18 FY 19 FY 20 FY 21 Total
Equip/Vehicle/Furnishings 200,000 200,000 200,000 200,000 200,000 1,000,000
Total 200,000 200,000 200,000 200,000 200,000 1,000,000
Funding Sources FY 17 FY 18 FY 19 FY 20 FY 21 Total
Water/Wastewater Fund 200,000 200,000 200,000 200,000 200,000 1,000,000
Total 200,000 200,000 200,000 200,000 200,000 1,000,000
Budget Impact/Other
Over time, the capabilities of a water meter to read accurate volumes of water deteriorates, typically registering less water than actually being
consumed. With installation of new meters, accurate readings will increase the actual revenue from this utility.
Thursday, May 12, 2016
134
Página 141
FY 2017 Capital Investment Plan FY 17 thru FY 21 Department Water Management
City of Dover, Delaware Contact Public Works Director
Type Improvement
Project # WD1701
Useful Life 20-25 years
Project Name Wellhead Redevelopment Program Category Water/Wastewater
New Project: No Account Number: 417-6800-568.40-31 Priority 1
Time-Line: FY17-FY21 Status Active
Total Project Cost: $450,000
Description
This project will provide for rehabilitation and repair of each deep wellhead in an effort to maintain operations and/or increase/maintain the yield
of each well as it relates to the permitted allocation. FY 2008; total well inspection and testing performed. FY 2009: Motors at Wells #6A and #9
were rebuilt, and wells #13R and #15 were redeveloped. FY 2010: Well #10. FY 2011: Well #4 redevelopment and well piping improvements at
various well locations, as well as continued well testing. FY 2012: Well #1 redevelopment. FY2013: complete repair of Well #10. FY2014:
complete repair of well #14. FY2015 inspected: 2, 3, 11, 13R, 15, PW2 & PW4B. FY 2016 scheduled: 4, 6, 8R, 9, 10, PW6A & PW8A.
Justification
The well screening and gravel pack requires cleaning over time due to a buildup of mineral deposits and foreign materials such as clay and silt.
This maintenance effort is critical to ensure that production can continue to meet demand. It is also necessary to maintain the operational aspects of
each well and provide repairs as needed to minimize downtime to maintain system capacity. Delaying or eliminating this project would result in
the continued deterioration of the well screen, gravel pack, and well yield over time. It would also result in increased well downtime, emergency
repairs, and decreased capacity. These issues can lead to increased flow pattern changes and water quality concerns.
Expenditures FY 17 FY 18 FY 19 FY 20 FY 21 Total
Construction/Maintenance 85,000 87,500 90,000 92,500 95,000 450,000
Total 85,000 87,500 90,000 92,500 95,000 450,000
Funding Sources FY 17 FY 18 FY 19 FY 20 FY 21 Total
Water/Wastewater Fund 85,000 87,500 90,000 92,500 95,000 450,000
Total 85,000 87,500 90,000 92,500 95,000 450,000
Budget Impact/Other
Thursday, May 12, 2016
135
Página 142
FY 2017 Capital Investment Plan FY 17 thru FY 21 Department Water Management
City of Dover, Delaware Contact Public Works Director
Type Improvement
Project # WD1705
Useful Life 10-12 years
Project Name SCADA Equipment Technology Upgrade Category Water/Wastewater
New Project: No Account Number: 417-6800-568.40-31 Priority 5
Time-Line: FY17 Status Active
Total Project Cost: $88,000
Description
This project involves the replacement of antiquated and/or obsolete equipment related to the SCADA (Supervisory Control and Data Acquisition)
system, which controls water production. This equipment includes, but is not limited to, Remote Telemetry Units (RTUs), Master Telemetry Unit
(MTU) and Radios. SCADA is used for reporting, on a constant basis, the status of the City of Dover’s water production wells as well as the
Water Treatment Plant. The equipment being replaced would be outdated, or unable to be repaired. It is estimated that upgrades will be made at
deep well sites and the Water Treatment Plant, as part of this program.
Justification
Replace failing and antiquated equipment to improve monitoring ability and system control to comply with regulatory and reporting requirements
and to prevent the need for costly non budgeted emergency repairs. Due to the age of some of the equipment, only used parts are available. Lack
of alarms regarding problems at water production wells and the water treatment plant. Failures would provide no advance warnings of failures in
the field at water production sites.
Expenditures FY 17 FY 18 FY 19 FY 20 FY 21 Total
Equip/Vehicle/Furnishings 88,000 88,000
Total 88,000 88,000
Funding Sources FY 17 FY 18 FY 19 FY 20 FY 21 Total
Water/Wastewater Fund 88,000 88,000
Total 88,000 88,000
Budget Impact/Other
Thursday, May 12, 2016
136
Página 143
FY 2017 Capital Investment Plan FY 17 thru FY 21 Department Water Management
City of Dover, Delaware Contact Public Works Director
Type Improvement
Project # WQ1702
Useful Life 90+ years
Project Name Water Quality Improvements Category Water/Wastewater
New Project: No Account Number: 417-6800-568.40-31 Priority 2
Time-Line: FY17-FY21 Status Active
Total Project Cost: $3,878,600
Description
This project was first identified by staff and the 2006 Water Master Plan Update, and has since become further refined with the FY 2006 Water
Quality Evaluation. Projects to be included under this category primarily consist of replacement or relining of old unlined cast iron water main
within the City’s water distribution system; system upgrades to improve system control; and utilization of a consultant to provide additional design
and evaluation services, as needed. Recent research and data collection has produced a Water Main Rehabilitation Priority List, based on several
criteria to identify water mains that are in need of replacement or relining. Pipes will be upgraded according to the severity of the pipe condition,
as well as coordination with the City of Dover’s Public Services Street Rehabilitation Program. Between FY 2008 and FY 2010, the deep well
contact chambers were designed and installed. Between FY 2008 and FY 2011 the water mains that were replaced include, Washington Street,
Pennsylvania Avenue, South Street, Pear Street, West Street, Hazel Road, Maryland Avenue, American Avenue, Bayard Avenue, Greenhill
Avenue, Bayard Avenue Alley and Loockerman Street. Operational efforts, such as flushing, will continue to occur on a routine basis. FY 2012
improvements include, N. Pennsylvania Ave., American Ave. Ext., Madison St., Rodney Rd., New Street, Ross Street and Bradford Street (near
Wesley College). FY 2013 improvements included North Street. As part of the Water Main Rehabilitation Priority List, water lines were
identified throughout the City that requires replacement/relining. FY 2014 improvements included West Dover Connector. Using this as a guide,
FY 2015 roads include New Street, William Street and West Street Alley.
Justification
Water quality complaints have eroded consumer confidence in the City’s water supply as the water is perceived to be aesthetically unpleasant. In
order to reduce complaints and potentially alleviate this problem, it is necessary to implement the improvements identified by staff, the 2006 Water
Master Plan Update, and the FY 2006 Water Quality Evaluation. Delaying or eliminating this project will prolong customer dissatisfaction and
further erode confidence in the City’s water supply. In addition, main rehabilitation and replacement, ensuring pipes do not significantly exceed
the expected life cycle, is critical to provide a reliable supply of water for our customers and for fire suppression. Water leaks and breaks on older
lines can have a significant impact on our ability to serve over time. Addressing the brown water and associated water quality concerns of the
City’s water system will not only require capital improvements to the system but also operational changes. Some operation changes will result in
no net effect on the operating budget, while others will need to be addressed in the development of future operating budgets. Such items include
tools and supplies necessary to improve system sampling and monitoring as well as tools and supplies necessary to improve system-wide flushing
operations.
Expenditures FY 17 FY 18 FY 19 FY 20 FY 21 Total
Construction/Maintenance 645,800 265,800 881,000 919,000 1,167,000 3,878,600
Total 645,800 265,800 881,000 919,000 1,167,000 3,878,600
Funding Sources FY 17 FY 18 FY 19 FY 20 FY 21 Total
Impact Fee Reserve 90,800 48,700 86,400 225,900
Water/Wastewater Fund 555,000 217,100 794,600 919,000 1,167,000 3,652,700
Total 645,800 265,800 881,000 919,000 1,167,000 3,878,600
Budget Impact/Other
Thursday, May 12, 2016
137
Página 144
FY 2017 Capital Investment Plan FY 17 thru FY 21 Department Water Management
City of Dover, Delaware Contact Public Works Director
Type Improvement
Project # WQ1703
Useful Life 50-80
Project Name Miscellaneous Emergency Water Repairs Category Water/Wastewater
New Project: Yes Account Number: 417-6800-568.40-31 Priority 3
Time-Line: FY17-FY21 Status Active
Total Project Cost: $395,000
Description
This project will repair failing water infrastructure. The work will focus on emergency repair situations on City owned infrastructure. No specific
locations for this work have been identified.
Justification
This project is necessary to address failing or deteriorated infrastructure in the City. If these repairs are not conducted, significant impacts to
property, life and environment could arise. Delaying these repairs could result in road failure, sink holes and environmental impacts.
Expenditures FY 17 FY 18 FY 19 FY 20 FY 21 Total
Construction/Maintenance 75,000 77,000 79,000 81,000 83,000 395,000
Total 75,000 77,000 79,000 81,000 83,000 395,000
Funding Sources FY 17 FY 18 FY 19 FY 20 FY 21 Total
Water/Wastewater Fund 75,000 77,000 79,000 81,000 83,000 395,000
Total 75,000 77,000 79,000 81,000 83,000 395,000
Budget Impact/Other
Thursday, May 12, 2016
138
Página 145
FY 2017 Capital Investment Plan FY 17 thru FY 21 Department Water Treatment Plant
City of Dover, Delaware Contact Public Works Director
Type Improvement
Project # WD1609
Useful Life 20-25 years
Project Name Water Treatment Plant Process Improvements Category Water/Wastewater
New Project: No Account Number: 417-7600-576.40-31 Priority 4
Time-Line: FY15-FY18 Status Active
Total Project Cost: $2,684,400
Description
This project, identified in the 2006 Water Master Plan Update, proposes process improvements to the existing Water Treatment Plant. Due to
limitations with the Ozone Contactors, the capacity at the Water Treatment Plant is below the original design capacity. A consultant will be
utilized to determine the best means and improvements necessary to rehabilitate the infrastructure. Planning is proposed for Fiscal Year 2015-
2016; construction to begin in Fiscal 2017.
Justification
Process improvements will allow for improved ability to meet regulatory requirements. Delaying or eliminating this project can result in
deteriorating infrastructure, which could limit growth, and/or cause regulatory incompliance.
Prior Expenditures FY 17 FY 18 FY 19 FY 20 FY 21 Total
284,400 Construction/Maintenance 1,200,000 1,200,000 2,400,000
Total Total 1,200,000 1,200,000 2,400,000
Prior Funding Sources FY 17 FY 18 FY 19 FY 20 FY 21 Total
284,400 DE Water Revolving Loan 1,200,000 1,200,000 2,400,000
Fund
Total
Total 1,200,000 1,200,000 2,400,000
Budget Impact/Other
Thursday, May 12, 2016
139
Página 147
City of Dover, Delaware
FY 2017 Capital Investment Plan
FY 17 thru FY 21
FUNDING SOURCE SUMMARY
Source FY 17 FY 18 FY 19 FY 20 FY 21 Total
Developer Contribution 900,000 900,000 900,000 900,000 900,000 4,500,000
Development Grant 5,000 5,000
Electric I & E Fund 1,000,000 437,500 1,437,500
Electric Revenue 3,704,500 5,206,700 3,571,000 2,874,000 2,015,000 17,371,200
Future Capacity Reserve Fund 50,000 6,000,000 6,050,000
General Fund 400,200 400,200
Water/Wastewater Fund 462,300 462,300
GRAND TOTAL 5,609,500 7,456,700 4,471,000 9,774,000 2,915,000 30,226,200
Thursday, May 12, 2016
141
Página 148
City of Dover, Delaware
FY 2017 Capital Investment Plan
FY 17 thru FY 21
PROJECTS BY DEPARTMENT
Department Project# Priority FY 17 FY 18 FY 19 FY 20 FY 21 Total
Electric Engineering
Townpoint Development ~ Distribution Feeders EE1513 1 350,000 350,000 350,000 350,000 350,000 1,750,000
69 kV Cable Replacement North Street EE1605 1 480,700 480,700
Fault Indicators EE1610 2 10,000 10,000 10,000 10,000 40,000
North Street OH to UG (Governors to Queen) EE1631 n/a 170,000 170,000
SCADA Master Hardware Replacement EE1700 1 150,000 150,000
UPS System Replacement EE1701 1 25,000 25,000
Transmission Line Maintenance Program EE1703 2 75,000 75,000 75,000 75,000 75,000 375,000
Lighting Project and Rehabilitation EE1704 1 50,000 50,000 50,000 50,000 50,000 250,000
Distribution Capacitors and Controls EE1706 2 50,000 50,000 50,000 50,000 50,000 250,000
LED Lighting Upgrade EE1707 1 17,500 17,500
Ampacity Standardization EE1708 2 25,000 25,000 25,000 25,000 25,000 125,000
Substation Relay Upgrade EE1709 2 125,000 150,000 75,000 350,000
Garrision Oak / Sun Park Substation EE1801 5 50,000 6,000,000 6,050,000
College Road Consolidation EE1809 6 120,000 120,000
Distribution Upgrades EE1810 1 300,000 600,000 900,000
Ann Avenue Underground Upgrade EE1811 2 126,000 126,000
Beechwood Avenue Underground Upgrade EE1812 3 80,000 80,000
System Automation EE1813 4 150,000 150,000 150,000 150,000 600,000
System Operations Voice Recorder EE1900 1 18,000 18,000
Farmview Underground Upgrade EE1901 2 110,000 110,000
The Greens Underground Upgrade EE1902 3 90,000 90,000
Electric Engineering Total 877,500 1,886,700 1,303,000 7,310,000 700,000 12,077,200
Electric T & D
Public Works Wetlands Project (Tar Ditch) EE1710 1 450,000 450,000
New Developments EE1717 1 1,500,000 1,500,000 1,500,000 1,500,000 1,500,000 7,500,000
Electric T & D Total 1,950,000 1,500,000 1,500,000 1,500,000 1,500,000 7,950,000
Finance
Enterprise Resource Planning (ERP) Solution FN1701 1 1,000,000 1,000,000 300,000 2,300,000
Finance Total 1,000,000 1,000,000 300,000 2,300,000
Power Plant
McKee Run Unit #3 Boiler Systems EG1504 1 382,000 160,000 299,000 80,000 235,000 1,156,000
McKee Run Building Equipment Replacement EG1601 3 59,000 99,000 27,000 66,000 175,000 426,000
McKee Run Unit 3 Auxiliary System Components EG1607 2 128,000 261,000 277,000 213,000 65,000 944,000
Van Sant Unit 11 Component Replacements EG1609 4 89,000 305,000 90,000 484,000
Plant Systems Safety & Compliance Improvements EG1610 6 112,000 37,000 149,000
McKee Run & VanSant - Preservation of Structures EG1611 5 131,000 130,000 100,000 100,000 125,000 586,000
Van Sant Unit 11 Major Inspection EG1701 2 400,000 1,548,000 150,000 2,098,000
McKee Run Unit 3 Hydrogen Purity Analyzer EG1704 1 96,000 96,000
Unit #3 Fast Start Upgrade EG1706 2 200,000 200,000
Unit 3 Cooling Water Line Repairs EG1709 3 469,000 469,000
Thursday, May 12, 2016
142
Página 149
Department Project# Priority FY 17 FY 18 FY 19 FY 20 FY 21 Total
VanSant Fire Suppression System Upgrade EG1711 4 285,000 285,000
Hydrogen Generator EG1807 1 50,000 50,000
McKee Run Unit #3 Turbine Repairs - Generator EG1901 1 438,000 25,000 25,000 488,000
McKee Run Unit 3 Turbine Repairs Intercept Valves EG1902 2 438,000 25,000 463,000
Power Plant Total 1,777,000 2,770,000 1,668,000 964,000 715,000 7,894,000
GRAND TOTAL 5,604,500 7,156,700 4,771,000 9,774,000 2,915,000 30,221,200
Thursday, May 12, 2016
143
Página 150
FY 2017 Capital Investment Plan FY 17 thru FY 21 Department Electric Engineering
City of Dover, Delaware Contact Electric Director
Type Improvement
Project # EE1513
Useful Life 20-25 years
Project Name Townpoint Development ~ Distribution Feeders Category Electric
New Project: Yes Account Number: 487-8300-563.90-25 Priority 1
Time-Line: Multi-year Status Active
Total Project Cost: $2,350,000
Description
FY17 - This project will continue to remove troublesome overhead distribution wiring and replace with underground installations. Current plan is
broken into 4 phases dependent on rate structure of boring, electrician services and landscaping fees and was initially approved for a four year
completion. Due to changes in prices, this request will be for a funding out to 2021 at the same $350,000 per year allocated. Current activity has
completed 75% of the first of five phases planned across the next five years (FY17-21). Phases will be completed as funding dictates during the
associated FY accounting for contractor costs and associated expenses.
FY16 - This project involves the systemic replacement of overhead lines with underground lines. Whenever services are being moved, wire is
damaged, trees cause a high number of outages, or development is in progress, and when it is beneficial to the Utility to convert to underground.
This can involve a single line section or an entire residential neighborhood. Annual outage records are reviewed and selected areas are scheduled
for upgrade to underground service. Additionally, this program funds the replacement of existing underground conductors and equipment that
have reached their useful life and have started failing and require replacement.
Justification
FY17 - The conversion from overhead to underground will improve reliability and stability of electric service to the residents of the subdivision.
FY16 - The number of storm and tree-related outages has been greatly reduced under this program and further improvements can be made to insure
the most reliable electric service possible. Reliability has become one of most important factors to electric customers, second only to safety. The
utility has responded by attempting to provide the most reliable system possible. Underground cable replacements are necessary as the useful,
reliable, life of the original underground cable was 20-30 years. By proactively replacing this cable we will minimize outages and improve system
reliability. In addition to cable replacement, overhead lines are replaced with underground to minimize outages caused by tree growth or animal
contact. Lastly, overhead lines that have reached the end of their useful life are replaced with underground instead of rebuilding the overhead.
CONSEQUENCES OF DELAYING OR ELIMINATING THIS PROJECT: Continued outages lead to increased complaints from our customers
and will lead to customer dissatisfaction. There will be increased costs for repairs made under outage conditions as well as loss of electric revenue.
Prior Expenditures FY 17 FY 18 FY 19 FY 20 FY 21 Total
600,000 Construction/Maintenance 350,000 350,000 350,000 350,000 350,000 1,750,000
Total Total 350,000 350,000 350,000 350,000 350,000 1,750,000
Prior Funding Sources FY 17 FY 18 FY 19 FY 20 FY 21 Total
600,000 Electric Revenue 350,000 350,000 350,000 350,000 350,000 1,750,000
Total Total 350,000 350,000 350,000 350,000 350,000 1,750,000
Budget Impact/Other
FY17 - Previously approved for $1,350,000 over 4 years starting FY2015 ($250,000/$350,000/$350,000/$350,000) with approximately $600,000
spent on initial installation and phased in progress through the development. This request would extend initial request from 4 years to 7 years for
an additional $1,050,000 in funding from FY 2019-2021.
Thursday, May 12, 2016
144
Página 151
FY 2017 Capital Investment Plan FY 17 thru FY 21 Department Electric Engineering
City of Dover, Delaware Contact Electric Director
Type Improvement
Project # EE1605
Useful Life 30+ years
Project Name 69 kV Cable Replacement North Street Category Electric
New Project: No Account Number: 487-8300-563.50-83 Priority 1
Time-Line: FY15-FY18 Status Active
Total Project Cost: $615,700
Description
Replace the aging 69 KV underground cables from North Street switching yard to Kraft’s and Proctor & Gamble’s (customer owned) substations.
TIME-LINE/CURRENT STATUS: Engineering is scheduled for FY15/FY16 with completion in FY18.
COMMENTS: Proactively replacing cables that have reached their anticipated life.
Justification
Proctor & Gamble and Kraft are two (2) of the City of Dover’s 69 KV customers and it is our obligation to provide them with adequate and
reliable service. The cables were installed in 1973 and have had two repairs. The first repair was in 1986 and the second repair was in 1992.
CONSEQUENCES OF DELAYING OR ELIMINATING THIS PROJECT: Customer outages due to failing conductor. Additionally, the limited
capacity of a single circuit could restrict the possible generation of NRG and the production of Proctor & Gamble and Kraft Foods. This project
will take some time as the old cable is buried in concrete which will require rerouting.
Prior Expenditures FY 17 FY 18 FY 19 FY 20 FY 21 Total
135,000 Construction/Maintenance 480,700 480,700
Total Total 480,700 480,700
Prior Funding Sources FY 17 FY 18 FY 19 FY 20 FY 21 Total
135,000 Electric Revenue 480,700 480,700
Total Total 480,700 480,700
Budget Impact/Other
Thursday, May 12, 2016
145
Página 152
FY 2017 Capital Investment Plan FY 17 thru FY 21 Department Electric Engineering
City of Dover, Delaware Contact Electric Director
Type Improvement
Project # EE1610
Useful Life 15-20 years
Project Name Fault Indicators Category Electric
New Project: Yes Account Number: 487-8300-563.90-25 Priority 2
Time-Line: FY16-FY20 Status Active
Total Project Cost: $40,000
Description
Replacing fault indicators for overhead and underground primaries.
Justification
Aids in restoring power during an outage and finding the causes of said outages.
Expenditures FY 17 FY 18 FY 19 FY 20 FY 21 Total
Construction/Maintenance 10,000 10,000 10,000 10,000 40,000
Total 10,000 10,000 10,000 10,000 40,000
Funding Sources FY 17 FY 18 FY 19 FY 20 FY 21 Total
Electric Revenue 10,000 10,000 10,000 10,000 40,000
Total 10,000 10,000 10,000 10,000 40,000
Budget Impact/Other
Thursday, May 12, 2016
146
Página 153
FY 2017 Capital Investment Plan FY 17 thru FY 21 Department Electric Engineering
City of Dover, Delaware Contact Electric Director
Type Improvement
Project # EE1631
Useful Life
Project Name North Street OH to UG (Governors to Queen) Category Electric
New Project: Yes Account Number: 487-8300-563.90-25 Priority n/a
Time-Line: Status Active
Total Project Cost: $170,000
Description
This project is to bury the overhead electric lines on W. North Street from S. Governors Avenue to S. Queen Street. All poles will be removed and
16 street lights installed.
Verizon and Comcast lines will also have to be buried in order for the poles to be removed.
Justification
Expenditures FY 17 FY 18 FY 19 FY 20 FY 21 Total
Construction/Maintenance 170,000 170,000
Total 170,000 170,000
Funding Sources FY 17 FY 18 FY 19 FY 20 FY 21 Total
Electric Revenue 170,000 170,000
Total 170,000 170,000
Budget Impact/Other
Thursday, May 12, 2016
147
Página 154
FY 2017 Capital Investment Plan FY 17 thru FY 21 Department Electric Engineering
City of Dover, Delaware Contact Electric Director
Type Improvement
Project # EE1652
Useful Life 10-15 years
Project Name South New Street Lighting Project Category Electric
New Project: Yes Account Number: 487-8200-562.60-34 Priority 1
Time-Line: FY16-FY17 Status Active
Total Project Cost: $70,000
Description
This project is to provide improvements to the street lights on South New Street from Loockerman Street to several hundred north of Reed Street.
It would replace a series of Victorian lights and overhead light fixtures and replace them with a uniform standard and lighting head to help
aesthetically improve the area.
Justification
This project is a Restoring Central Dover Steering Committee recommendation and will provide continuity in the installation of street lights in the
redevelopment area.
Prior
70,000
Total
Prior Funding Sources FY 17 FY 18 FY 19 FY 20 FY 21 Total
65,000 Development Grant 5,000 5,000
Total Total 5,000 5,000
Budget Impact/Other
Thursday, May 12, 2016
148
Página 155
FY 2017 Capital Investment Plan FY 17 thru FY 21 Department Electric Engineering
City of Dover, Delaware Contact Electric Director
Type Equipment
Project # EE1700
Useful Life 5-10 years
Project Name SCADA Master Hardware Replacement Category Electric
New Project: Yes Account Number: 487-8300-563.80-38 Priority 1
Time-Line: FY17 Status Active
Total Project Cost: $150,000
Description
This project will replace the Master Station hardware and associated enclosures/desks. The Master Station receives all the analog data, door
alarms, and control for all electrical substations and wastewater lift stations. The Master Station is comprised of dual host servers, dual operator
consoles, paging systems, web server, two firewalls for DMZ and one remote access/support firewall. The Master Station also allows the operators
to modify and control the city’s electrical grid remotely reducing the amount of time outages affect the residents and reduce harm to the city’s
populace. Requested amount includes $130,000 for master hardware replacement and associated training for 2 personnel who are tasked with the
day to day maintenance of the SCADA system. This also accounts for modifications to the workstation enclosures to account for new equipment.
TIME-LINE/CURRENT STATUS: Equipment will be ordered and replaced during the FY17 budget year.
Justification
The equipment will reach the end of its life expectancy. It should be noted that the systems runs continuously 24 hours a day seven days a weeks
to monitor and track anomalies in the electrical and wastewater systems. The additional firewalls will be required to conform to upcoming
implementations of NERC CIP Cyber Security Standards.
CONSEQUENCES OF DELAYING OR ELIMINATING THIS PROJECT: If the system fails, we will not be able to monitor or control electrical
substations and view alarms for wastewater lift stations. This could result in prolonged outages and/or outages in wastewater removal as well as
overflows.
Expenditures FY 17 FY 18 FY 19 FY 20 FY 21 Total
Equip/Vehicle/Furnishings 150,000 150,000
Total 150,000 150,000
Funding Sources FY 17 FY 18 FY 19 FY 20 FY 21 Total
Electric Revenue 150,000 150,000
Total 150,000 150,000
Budget Impact/Other
Thursday, May 12, 2016
149
Página 156
FY 2017 Capital Investment Plan FY 17 thru FY 21 Department Electric Engineering
City of Dover, Delaware Contact Electric Director
Type Equipment
Project # EE1701
Useful Life 5-10 years
Project Name UPS System Replacement Category Electric
New Project: Yes Account Number: 487-8300-563.40-25 Priority 1
Time-Line: FY17 Status Active
Total Project Cost: $25,000
Description
Uninterruptible Power Supplies (UPS) is an electrical device that provides emergency power to a load when the input power source, typically main
power fails. The primary role of the UPS is to provide short term power unitl the back up generator comes on when the input power source fails.
Justification
The existing system is 12 years old and will be due for replacement as the unit has reached it's life expectancy.
Expenditures FY 17 FY 18 FY 19 FY 20 FY 21 Total
Equip/Vehicle/Furnishings 25,000 25,000
Total 25,000 25,000
Funding Sources FY 17 FY 18 FY 19 FY 20 FY 21 Total
Electric Revenue 25,000 25,000
Total 25,000 25,000
Budget Impact/Other
Thursday, May 12, 2016
150
Página 157
FY 2017 Capital Investment Plan FY 17 thru FY 21 Department Electric Engineering
City of Dover, Delaware Contact Electric Director
Type Maintenance
Project # EE1703
Useful Life 20-25 years
Project Name Transmission Line Maintenance Program Category Electric
New Project: No Account Number: 487-8300-563.70-35 Priority 2
Time-Line: On Going Maint. Status Active
Total Project Cost: $375,000
Description
FY17 Note – While there has been no major maintenance required this FY due to higher priority projects, this funding can be critical to restoration
of power due to storm loss or catastrophic component failure. Certain areas have 795 ASCR cable in overhead applications and have one wire per
phase. Unit of issue for the wire is by the spool and each spool is 3,470 feet so to replace 3 phases of 795 cable across 3,470 feet would cost
approximately $18,600 not including associated hardware.
FY16 - Replace aging porcelain insulators and related components on the transmission system with new polymer insulators and components.
Justification
IInsulators have a defined equipment life due to sun and weather conditions breaking down the porcelain and base bonding cement. Insulators
installed in 1960's and 1970's are due for replacement because of this deterioration. We have experienced several transmission outages due to
insulator failure. Replacing the insulators should extend the life an additional 30 years.
CONSEQUENCES OF DELAYING OR ELIMINATING THIS PROJECT: Outages may occur if insulators are not replaced and fail due to
deterioration.
Expenditures FY 17 FY 18 FY 19 FY 20 FY 21 Total
Construction/Maintenance 75,000 75,000 75,000 75,000 75,000 375,000
Total 75,000 75,000 75,000 75,000 75,000 375,000
Funding Sources FY 17 FY 18 FY 19 FY 20 FY 21 Total
Electric Revenue 75,000 75,000 75,000 75,000 75,000 375,000
Total 75,000 75,000 75,000 75,000 75,000 375,000
Budget Impact/Other
Thursday, May 12, 2016
151
Página 158
FY 2017 Capital Investment Plan FY 17 thru FY 21 Department Electric Engineering
City of Dover, Delaware Contact Electric Director
Type Maintenance
Project # EE1704
Useful Life 10-12 years
Project Name Lighting Project and Rehabilitation Category Electric
New Project: No Account Number: 487-8300-563.50-76 Priority 1
Time-Line: Continuous Status Active
Total Project Cost: $250,000
Description
FY17 - Continual replacement of existing lighting and upgrade of lighting to more energy efficient LED lights. There were 25 lights on RT 13 that
were converted to LED. Coordinating with Dover Police Department to install LEDs in several alleys to provide better lighting for residents and
emergency responders.
FY16 -This fund was developed to replace and repair existing street lights or install new lights upon customer request.
COMMENTS: This fund will remain active as long as there are improvements to be made. Private area lighting requests are a source of revenue
for the City. Areas completed are White Oak Apartments, Westfield, Fairview, Cranberry Run, Millcreek, Independence Village and Governors
Avenue (South 100 Block), Deerfield, Central Middle School, Fox Hall, Hidden Oaks, a portion of North Governors Ave, The Meadows,
Turnberry, Baltray,
Bicentennial, The Overlook and Woodcrest. Areas to be completed this budget year include Old Mill Acres and Eagles Nest.
Justification
FY17 -radual conversion of existing lights to LED lights will provide a longer useful life and reduce replacement costs as well as monthly electric
consumption for the City.
FY16 - The Electric Division receives numerous requests for lighting improvements. These requests are due to the lights aging, and as they age
they put out less light and become unreliable. There are many developments that are in need of street light improvements. This fund would also
provide funding for new private security light requests.
CONSEQUENCES OF DELAYING OR ELIMINATING THIS PROJECT: Constant complaints of poor street lighting and multiple failures due
to antiquated lights.
Expenditures FY 17 FY 18 FY 19 FY 20 FY 21 Total
Construction/Maintenance 50,000 50,000 50,000 50,000 50,000 250,000
Total 50,000 50,000 50,000 50,000 50,000 250,000
Funding Sources FY 17 FY 18 FY 19 FY 20 FY 21 Total
Electric Revenue 50,000 50,000 50,000 50,000 50,000 250,000
Total 50,000 50,000 50,000 50,000 50,000 250,000
Budget Impact/Other
Thursday, May 12, 2016
152
Página 159
FY 2017 Capital Investment Plan FY 17 thru FY 21 Department Electric Engineering
City of Dover, Delaware Contact Electric Director
Type Improvement
Project # EE1706
Useful Life 15-20 years
Project Name Distribution Capacitors and Controls Category Electric
New Project: No Account Number: 487-8300-563.60-82 Priority 2
Time-Line: Continuous Status Active
Total Project Cost: $250,000
Description
Install distribution capacitors throughout the system to correct poor power factor on distribution circuits. Install capacitor controllers capable of
two-way communication to provide real-time monitoring and remote control operation. These controllers will be capable of switching the
capacitors on and off to comply with system requirements. This project will also replace outdated substation equipment, capable of advanced
metering such as power factor and harmonics to further analyze system performance remotely. Lastly, distribution line recorders will be purchased
and installed to provide power factor recordings to fine tune this operation.
COMMENTS: The required substation equipment installation will be completed in two phases. FY2016 will upgrade the required communication
equipment installed 20 years ago. FY2017 will install equipment capable of extracting system data, for enhanced performance analyzing. The
completion of these two phases will ultimately reduce engineering time and costs because of remote access to all substations. In addition to this
advanced metering, event report extraction and analysis, relay settings review and installation, and advancements to our 24 hour system operation
center will be also be realized. FY2016 -FY2020 will be the addition of capacitor banks and controllers into the distribution system.
Justification
Additional capacitance is required in order to meet system power factor requirements at the Delmarva Power and Light interchange point. This was
substantiated through a load-flow study conducted by Shaw in early 2004 and distribution study by Wilson & Wilson in 2006. The current
capacitor controls are not providing the granularity required to turn them off and on as required to meet both the power quality requirements of our
customers and DP&L requirements. Additional controls are required to fine tune the systems operation.
CONSEQUENCES OF DELAYING OR ELIMINATING THIS PROJECT: Without the additional capacitor banks and more importantly controls,
the City may experience a low/high voltage problem at the customer level and/or the possibility of having to pay power factor penalties to
Delmarva Power and Light.
Expenditures FY 17 FY 18 FY 19 FY 20 FY 21 Total
Construction/Maintenance 50,000 50,000 50,000 50,000 50,000 250,000
Total 50,000 50,000 50,000 50,000 50,000 250,000
Funding Sources FY 17 FY 18 FY 19 FY 20 FY 21 Total
Electric Revenue 50,000 50,000 50,000 50,000 50,000 250,000
Total 50,000 50,000 50,000 50,000 50,000 250,000
Budget Impact/Other
Thursday, May 12, 2016
153
Página 160
FY 2017 Capital Investment Plan FY 17 thru FY 21 Department Electric Engineering
City of Dover, Delaware Contact Electric Director
Type Improvement
Project # EE1707
Useful Life 7 - 10 years
Project Name LED Lighting Upgrade Category Electric
New Project: Yes Account Number: 487-8300-563.40-31 Priority 1
Time-Line: FY17 Status Active
Total Project Cost: $17,500
Description
Replace selected alley way lighting from mercury vapor & high pressure sodium lights to LED lights.
Justification
In coordination with the Dover Police Department, specific alleys were designated for a test program using LED lights to replace existing mercury
vapor & high pressure sodium lights. The utilization of LED lighting will produce more illumination in the alley at a reduced cost to the City.
Current reduction in wattage would be from 100 to 400 watt conventional fixtures to 91 watt LED fixtures. The end goal of the project is to
replace the lighting in 4 alleys and then evaluate the impact of the lighting on criminal activity. This could lead to more alleys being changed over
but further maintenance actions will be driven at the request of the Police Department.
Expenditures FY 17 FY 18 FY 19 FY 20 FY 21 Total
Construction/Maintenance 17,500 17,500
Total 17,500 17,500
Funding Sources FY 17 FY 18 FY 19 FY 20 FY 21 Total
Electric Revenue 17,500 17,500
Total 17,500 17,500
Budget Impact/Other
Thursday, May 12, 2016
154
Página 161
FY 2017 Capital Investment Plan FY 17 thru FY 21 Department Electric Engineering
City of Dover, Delaware Contact Electric Director
Type Improvement
Project # EE1708
Useful Life 15-20 years
Project Name Ampacity Standardization Category Electric
New Project: Yes Account Number: 487-8300-563.40-31 Priority 2
Time-Line: FY17-FY21 Status Active
Total Project Cost: $125,000
Description
Standardize the primary overhead and underground distribution wiring to allow consistent ampacity throughout the City’s feeders.
Justification
This project will replace segments of overhead and underground wiring to allow for a consistent ampacity rating throughout the City. Currently
there are several sections of primary distribution wiring that lower the overall ampacity of the circuit which can hinder growth, cause equipment
failure and cause outages due to increased demand. This project will be worked in conjunction with other projects to increase reliability and
stability of the City’s infrastructure.
Expenditures FY 17 FY 18 FY 19 FY 20 FY 21 Total
Construction/Maintenance 25,000 25,000 25,000 25,000 25,000 125,000
Total 25,000 25,000 25,000 25,000 25,000 125,000
Funding Sources FY 17 FY 18 FY 19 FY 20 FY 21 Total
Electric Revenue 25,000 25,000 25,000 25,000 25,000 125,000
Total 25,000 25,000 25,000 25,000 25,000 125,000
Budget Impact/Other
Thursday, May 12, 2016
155
Página 162
FY 2017 Capital Investment Plan FY 17 thru FY 21 Department Electric Engineering
City of Dover, Delaware Contact Electric Director
Type Improvement
Project # EE1709
Useful Life 25 - 30 years
Project Name Substation Relay Upgrade Category Electric
New Project: Yes Account Number: 487-8300-563.40-31 Priority 2
Time-Line: FY17 - FY19 Status Active
Total Project Cost: $350,000
Description
Replacement of selected relay components to standardize the entire COD system by converting to an all Schweitzer relaying and protection
configuration. Replace out dated substation Relaying (protection) equipment and upgrade RTAC (Real-Time Automation Controller)
Justification
This upgrade will greatly improve the monitoring capabilities of the city’s distribution system and add the capability of monitoring power factor at
all substations. This upgrade will also help in analyzing the fault and determining the causes of outages and anomalies. It will also improve the
system reliability with the upgrade to the RTAC by providing more dependable and real time monitoring of the COD power grid through the
SCADA system.
Expenditures FY 17 FY 18 FY 19 FY 20 FY 21 Total
Planning/Design 50,000 50,000 100,000
Construction/Maintenance 75,000 100,000 75,000 250,000
Total 125,000 150,000 75,000 350,000
Funding Sources FY 17 FY 18 FY 19 FY 20 FY 21 Total
Electric Revenue 125,000 150,000 75,000 350,000
Total 125,000 150,000 75,000 350,000
Budget Impact/Other
Thursday, May 12, 2016
156
Página 163
FY 2017 Capital Investment Plan FY 17 thru FY 21 Department Electric Engineering
City of Dover, Delaware Contact Electric Director
Type Equipment
Project # EE1801
Useful Life 30 Years
Project Name Garrision Oak / Sun Park Substation Category Electric
New Project: Yes Account Number: Priority 5
Time-Line: FY18-FY20 Status Active
Total Project Cost: $6,050,000
Description
FY18 - Requested funding for initial planning and engineering for design and construction of a new electric substation located at Garrison Oak
Park. Amount includes $50,000 for engineering service and associated costs with design and estimation of layout and capabilities of new
substation.
Justification
FY18 - As occupancy of Garrison Oak Technology Park increases, the amount of power drawn will exceed the capabilities of the current City of
Dover Transmission and Distribution system. We currently have 2 megawatts of reserve power for contingency situations for Calpine and we
estimate approximately 500 to 2000 kilowatts of demand per lot. This additional load will not be attainable without a new substation to dedicate to
the park and allow distribution to a limited amount of customers outside the park in residential areas.
Expenditures FY 17 FY 18 FY 19 FY 20 FY 21 Total
Planning/Design 50,000 50,000
Construction/Maintenance 6,000,000 6,000,000
Total 50,000 6,000,000 6,050,000
Funding Sources FY 17 FY 18 FY 19 FY 20 FY 21 Total
Electric Revenue 50,000 50,000
Future Capacity Reserve Fund 6,000,000 6,000,000
Total 50,000 6,000,000 6,050,000
Budget Impact/Other
Thursday, May 12, 2016
157
Página 164
FY 2017 Capital Investment Plan FY 17 thru FY 21 Department Electric Engineering
City of Dover, Delaware Contact Electric Director
Type Improvement
Project # EE1809
Useful Life 25 - 30 years
Project Name College Road Consolidation Category Electric
New Project: Yes Account Number: 487-8300-563.40-31 Priority 6 --
Time-Line: FY18 Status Active
Total Project Cost: $120,000
Description
The high-side of the substation will be upgraded to include transmission line protection breakers.
Justification
This project will consolidate the College Road substation into one existing building instead of the current configuration taking up two buildings.
The metal clad switchgear has eight distribution circuits breakers and all the distribution protection relays. All the 69kv transmission line
protection relays are in the old College Road building, which is about 25 years old. We would like to move the 69kv transmission line protection
relays in to the metal clad switchgear with all the other relays so we will have all the protection relays in one location. By keeping all the relays in
one location, this will help us reduce the restoration time during an outage as well as cut down the maintenance cost by eliminating the extra
building. Subsequent removal of the unused building will also allow for further expansion of the substation as required.
Expenditures FY 17 FY 18 FY 19 FY 20 FY 21 Total
Planning/Design 60,000 60,000
Construction/Maintenance 60,000 60,000
Total 120,000 120,000
Funding Sources FY 17 FY 18 FY 19 FY 20 FY 21 Total
Electric Revenue 120,000 120,000
Total 120,000 120,000
Budget Impact/Other
Thursday, May 12, 2016
158
Página 165
FY 2017 Capital Investment Plan FY 17 thru FY 21 Department Electric Engineering
City of Dover, Delaware Contact Electric Director
Type Improvement
Project # EE1810
Useful Life 20-25 years
Project Name Distribution Upgrades Category Electric
New Project: No Account Number: 487-8300-563.90-25 Priority 1
Time-Line: On Going Maint. Status Active
Total Project Cost: $900,000
Description
This project involves the systemic replacement of overhead lines with underground lines whenever services are being moved, wire is damaged,
trees cause a high number of outages, or development is in progress, and when it is beneficial to the Utility to convert to underground. This can
involve a single line section or an entire residential neighborhood. Annual outage records are reviewed and selected areas are scheduled for
upgrade to underground service. Additionally, this program funds the replacement of existing underground conductors and equipment that have
reached their useful life and have started failing and require replacement.
This account is used to upgrade any trouble areas during the year.
Justification
The number of storm and tree-related outages have been greatly reduced under this program and further improvements can be made to insure the
most reliable electric service possible. Reliability has become one of most important factors to electric customers, second only to safety. The utility
has responded by attempting to provide the most reliable system possible. Underground cable replacements are necessary as the useful, reliable,
life of the original underground cable was 20-30 years. By proactively replacing this cable we will minimize outages and improve system
reliability. In addition to cable replacement, overhead lines are replaced with underground to minimize outages caused by tree growth or animal
contact. Lastly, overhead lines that have reached the end of their useful life are replaced with underground instead of rebuilding the overhead.
CONSEQUENCES OF DELAYING OR ELIMINATING THIS PROJECT: Continued outages lead to increased complaints from our customers
and will lead to customer dissatisfaction. There will be increased costs for repairs made under outage conditions as well as loss of electric revenue.
Expenditures FY 17 FY 18 FY 19 FY 20 FY 21 Total
Construction/Maintenance 300,000 600,000 900,000
Total 300,000 600,000 900,000
Funding Sources FY 17 FY 18 FY 19 FY 20 FY 21 Total
Electric Revenue 300,000 600,000 900,000
Total 300,000 600,000 900,000
Budget Impact/Other
Thursday, May 12, 2016
159
Página 166
FY 2017 Capital Investment Plan FY 17 thru FY 21 Department Electric Engineering
City of Dover, Delaware Contact Electric Director
Type Improvement
Project # EE1811
Useful Life 15-20 years
Project Name Ann Avenue Underground Upgrade Category Electric
New Project: Yes Account Number: 110-2700-571.40-31 Priority 2
Time-Line: FY18 Status Active
Total Project Cost: $126,000
Description
Replace the original underground primary cabling in the Ann Avenue Development and convert from direct bury to bored installation.
Justification
This project will replace the original direct buried primary cable and replace it with new cable installed by boring. The underground wiring and
equipment has been in place for over 15 years and is direct buried. Utilizing boring the new cable will be placed in conduit and better protected
from the elements and unintentional damage. The original cable also has an external neutral wrapped around the cable while the new cable has the
neutral internal to the cable offering a more stable and dependable system to the customer.
Expenditures FY 17 FY 18 FY 19 FY 20 FY 21 Total
Construction/Maintenance 126,000 126,000
Total 126,000 126,000
Funding Sources FY 17 FY 18 FY 19 FY 20 FY 21 Total
Electric Revenue 126,000 126,000
Total 126,000 126,000
Budget Impact/Other
Thursday, May 12, 2016
160
Página 167
FY 2017 Capital Investment Plan FY 17 thru FY 21 Department Electric Engineering
City of Dover, Delaware Contact Electric Director
Type Improvement
Project # EE1812
Useful Life 15-20 years
Project Name Beechwood Avenue Underground Upgrade Category Electric
New Project: Yes Account Number: 487-8300-563.40-31 Priority 3
Time-Line: FY18 Status Active
Total Project Cost: $80,000
Description
Replace the original underground primary cabling in the Beechwood Development and convert from direct bury to bored installation.
Justification
This project will replace the original direct buried primary cable and replace it with new cable installed by boring. The underground wiring and
equipment has been in place for over 15 years and is direct buried. Utilizing boring the new cable will be placed in conduit and better protected
from the elements and unintentional damage. The original cable also has an external neutral wrapped around the cable while the new cable has the
neutral internal to the cable offering a more stable and dependable system to the customer.
Expenditures FY 17 FY 18 FY 19 FY 20 FY 21 Total
Construction/Maintenance 80,000 80,000
Total 80,000 80,000
Funding Sources FY 17 FY 18 FY 19 FY 20 FY 21 Total
Electric Revenue 80,000 80,000
Total 80,000 80,000
Budget Impact/Other
Thursday, May 12, 2016
161
Página 168
FY 2017 Capital Investment Plan FY 17 thru FY 21 Department Electric Engineering
City of Dover, Delaware Contact Electric Director
Type Improvement
Project # EE1813
Useful Life 5-10 years
Project Name System Automation Category Electric
New Project: No Account Number: 487-8300-563.70-28 Priority 4
Time-Line: FY17-FY21 Status Active
Total Project Cost: $600,000
Description
Design, develop, and install a self-healing or "smart" distribution system.
Justification
This project will include an engineering study to be performed using a system model to develop a scheme that will allow the distribution system to
be self-healing in the event of a fault. Following the study, automation equipment will be purchased to detect problems on the system, isolate the
affected area, and reenergize lines not affected. This will improve the reliability of the city’s local electric grid, minimize customer outages, and
increase customer satisfaction.
Expenditures FY 17 FY 18 FY 19 FY 20 FY 21 Total
Planning/Design 150,000 150,000 150,000 150,000 600,000
Total 150,000 150,000 150,000 150,000 600,000
Funding Sources FY 17 FY 18 FY 19 FY 20 FY 21 Total
Electric Revenue 150,000 150,000 150,000 150,000 600,000
Total 150,000 150,000 150,000 150,000 600,000
Budget Impact/Other
Thursday, May 12, 2016
162
Página 169
FY 2017 Capital Investment Plan FY 17 thru FY 21 Department Electric Engineering
City of Dover, Delaware Contact Electric Director
Type Equipment
Project # EE1900
Useful Life 5-10 years
Project Name System Operations Voice Recorder Category Electric
New Project: Yes Account Number: 487-8300-563.40-25 Priority 1
Time-Line: FY19 Status Active
Total Project Cost: $18,000
Description
Replace aging System Operations voice recorder
Justification
The voice recorder is used to tape all System Operations phone calls and radio traffic. These recordings contain switching schedule and outage
radio traffic which may be required for litigation purposes.
Expenditures FY 17 FY 18 FY 19 FY 20 FY 21 Total
Equip/Vehicle/Furnishings 18,000 18,000
Total 18,000 18,000
Funding Sources FY 17 FY 18 FY 19 FY 20 FY 21 Total
Electric Revenue 18,000 18,000
Total 18,000 18,000
Budget Impact/Other
Thursday, May 12, 2016
163
Página 170
FY 2017 Capital Investment Plan FY 17 thru FY 21 Department Electric Engineering
City of Dover, Delaware Contact Electric Director
Type Improvement
Project # EE1901
Useful Life 15-20 years
Project Name Farmview Underground Upgrade Category Electric
New Project: Yes Account Number: 487-8300-563.40-31 Priority 2
Time-Line: FY19 Status Active
Total Project Cost: $110,000
Description
Replace the original underground primary cabling in the Farmview Development and convert from direct bury to bored installation.
Justification
This project will replace the original direct buried primary cable and replace it with new cable installed by boring. The underground wiring and
equipment has been in place for over 15 years and is direct buried. Utilizing boring the new cable will be placed in conduit and better protected
from the elements and unintentional damage. The original cable also has an external neutral wrapped around the cable while the new cable has the
neutral internal to the cable offering a more stable and dependable system to the customer.
Expenditures FY 17 FY 18 FY 19 FY 20 FY 21 Total
Construction/Maintenance 110,000 110,000
Total 110,000 110,000
Funding Sources FY 17 FY 18 FY 19 FY 20 FY 21 Total
Electric Revenue 110,000 110,000
Total 110,000 110,000
Budget Impact/Other
Thursday, May 12, 2016
164
Página 171
FY 2017 Capital Investment Plan FY 17 thru FY 21 Department Electric Engineering
City of Dover, Delaware Contact Electric Director
Type Improvement
Project # EE1902
Useful Life 15-20 years
Project Name The Greens Underground Upgrade Category Electric
New Project: Yes Account Number: 487-8300-563.40-31 Priority 3
Time-Line: FY19 Status Active
Total Project Cost: $90,000
Description
Replace the original underground primary cabling in the Greens Development and convert from direct bury to bored installation.
Justification
This project will replace the original direct buried primary cable and replace it with new cable installed by boring. The underground wiring and
equipment has been in place for over 15 years and is direct buried. Utilizing boring the new cable will be placed in conduit and better protected
from the elements and unintentional damage. The original cable also has an external neutral wrapped around the cable while the new cable has the
neutral internal to the cable offering a more stable and dependable system to the customer.
Expenditures FY 17 FY 18 FY 19 FY 20 FY 21 Total
Construction/Maintenance 90,000 90,000
Total 90,000 90,000
Funding Sources FY 17 FY 18 FY 19 FY 20 FY 21 Total
Electric Revenue 90,000 90,000
Total 90,000 90,000
Budget Impact/Other
Thursday, May 12, 2016
165
Página 172
FY 2017 Capital Investment Plan FY 17 thru FY 21 Department Electric T & D
City of Dover, Delaware Contact Electric Director
Type Improvement
Project # EE1710
Useful Life 20-25 years
Project Name Public Works Wetlands Project (Tar Ditch) Category Electric
New Project: Yes Account Number: 487-8200-562.60-34 Priority 1
Time-Line: FY16-FY17 Status Active
Total Project Cost: $450,000
Description
This project will redevelop the old Public Works 2 (PW2) site and increase storm runoff capability from the area in and around S. State Street,
direct benefit will be seen to the parking lots of Kent General Hospital during heavy rains. Additional benefit will be to the storm water entering
the St. Jones River and eventually into Silver Lake. Actions required from the Electric Department will include converting the existing overhead
line to underground and possible relocation of existing switchgear.
Justification
This project is a request from Public Works Department to address environmental concerns entering waterways and to address storm runoff on and
around S. State Street.
Expenditures FY 17 FY 18 FY 19 FY 20 FY 21 Total
Construction/Maintenance 450,000 450,000
Total 450,000 450,000
Funding Sources FY 17 FY 18 FY 19 FY 20 FY 21 Total
Electric Revenue 450,000 450,000
Total 450,000 450,000
Budget Impact/Other
Thursday, May 12, 2016
166
Página 173
FY 2017 Capital Investment Plan FY 17 thru FY 21 Department Electric T & D
City of Dover, Delaware Contact Public Works Director
Type Improvement
Project # EE1717
Useful Life 30+ years
Project Name New Developments Category Electric
New Project: No Account Number: 4878200-562.Several Priority 1
Time-Line: Continuous Status Active
Total Project Cost: $7,500,000
Description
This project purchases materials and equipment that are used to provide electric service to new housing developments, businesses, and industrial
developments. Additionally, a portion of this expense is offset by the extension payments whereby new developers pay a $1,600 per residential lot
connection fee, or business and industrial developers pay the total material expense for line extensions.
This is an ongoing project and affects three separate accounts:
487-8200-562.60-31
487-8200-562.60-34
487-8200-562.60-46
COMMENTS: Not all new development projects are known during budget preparation, as some will arise during the year.
Justification
During the course of each budget year, new developers request line extensions for new electric projects. Some are new projects, while other
projects may have received plan approval previously but were not completed for any number of reasons.
Expenditures FY 17 FY 18 FY 19 FY 20 FY 21 Total
Construction/Maintenance 1,500,000 1,500,000 1,500,000 1,500,000 1,500,000 7,500,000
Total 1,500,000 1,500,000 1,500,000 1,500,000 1,500,000 7,500,000
Funding Sources FY 17 FY 18 FY 19 FY 20 FY 21 Total
Developer Contribution 900,000 900,000 900,000 900,000 900,000 4,500,000
Electric Revenue 600,000 600,000 600,000 600,000 600,000 3,000,000
Total 1,500,000 1,500,000 1,500,000 1,500,000 1,500,000 7,500,000
Budget Impact/Other
Thursday, May 12, 2016
167
Página 174
FY 2017 Capital Investment Plan FY 17 thru FY 21 Department Finance
City of Dover, Delaware Contact Controller/Treasurer
Type Technology
Project # FN1701
Useful Life 10 years
Project Name Enterprise Resource Planning (ERP) Solution Category Electric
New Project: Yes Account Number: 480-9900-582.90-23 Priority 1
Time-Line: FY17-FY21 Status Active
Total Project Cost: $2,300,000
Description
This project involves consulting services and purchase of Enterprise Resource Planning (ERP) Solution to support the business processes of the
City of Dover.
Justification
The City's current ERP software is Sungard Public Sector's Select/Naviline version 8.0.2.0. It is an IBM System powered environment (iSeries).
This system is a legacy system that came out of the Y2K era, when previous systems were not programmed for the year 2000. The Sungard Public
Sector system was purchased in April 1997.
The technology for ERP systems have evolved from mainframe based systems (AS400) to Personal Computer (PC) based systems either hosted by
the software provider through the internet or hosted by the customer on file servers. The industry trend is to drive access to customers with web
and app based delivery models.
Project Strategy & Objectives:
- The City requires an integrated environment where any user can access the data they need.
- The City will emphasize a self-service environment with technology enabling and not hindering the users to easily access data with the proper
controls at the point of data entry.
- The City desires to utilize rational data base technology plus easy report and query writing tools to accomplish this.
- The City realizes that this goal will not be accomplished through new technology alone but also requires extensive process changes and
organizational support.
- Management requires better access to data, information and reporting that is currently unavailable or significantly restricted.
- As a result of current limitations to functionallity and access to data, City personnel have developed work-around processes that are impacting
City business.
- Third-party software integrations with the current system are extremely difficult, limited or unvailable.
Expenditures FY 17 FY 18 FY 19 FY 20 FY 21 Total
Consulting 300,000 300,000
ERP System 700,000 1,000,000 300,000 2,000,000
Total 1,000,000 1,000,000 300,000 2,300,000
Funding Sources FY 17 FY 18 FY 19 FY 20 FY 21 Total
Electric I & E Fund 1,000,000 437,500 1,437,500
General Fund 400,200 400,200
Water/Wastewater Fund 462,300 462,300
Total 1,000,000 1,300,000 2,300,000
Budget Impact/Other
Annual Operating impact is being evaluated to determine the net difference with the current ERP/ancillary systems and support versus the
recommended solution. The current estimate for the new fully integrated ERP solution is approximately $300,000 annuallly. Current cost is being
evaluated as above.
Thursday, May 12, 2016
168
Página 175
FY 2017 Capital Investment Plan FY 17 thru FY 21 Department Power Plant
City of Dover, Delaware Contact Power Plant Manager
Type Maintenance
Project # EG1504
Useful Life Unknown
Project Name McKee Run Unit #3 Boiler Systems Category Electric
New Project: No Account Number: 487-8101-591.40-31 Priority 1
Time-Line: Multi-year Status Active
Total Project Cost: $1,278,800
Description
This Project was developed to perform inspections and repairs to the Unit 3 boiler on a predetermined frequency based on unit operating hours,
required regulatory inspection intervals, and known equipment condition. In general, most work activities are those requiring planned outages and
therefore will be scheduled to coincide with planned outages. The work identified includes the following:
Replacement of water wall tubes as needed.
Replacement of super heater and re-heater boiler clips.
Air preheater inspection and repairs.
De-aerator heater and storage tank inspection.
Note: Project costs in years beyond 2018 are shown for expense planning purposes and represent future projects related to this equipment that are
anticipated based on expected operation.
Justification
Critical system equipment represents components that, if they fail, will result in loss of generation and or capacity. Routine evaluation of the
condition of critical components will allow for proper prioritization of maintenance activities and resources. Delaying this project could result in
the failure of critical unit equipment and subsequent loss of generation and or capacity. More importantly, component failure could also result in
safety risk to personnel.
Prior Expenditures FY 17 FY 18 FY 19 FY 20 FY 21 Total
122,800 Construction/Maintenance 382,000 160,000 299,000 80,000 235,000 1,156,000
Total Total 382,000 160,000 299,000 80,000 235,000 1,156,000
Prior Funding Sources FY 17 FY 18 FY 19 FY 20 FY 21 Total
122,800 Electric Revenue 382,000 160,000 299,000 80,000 235,000 1,156,000
Total Total 382,000 160,000 299,000 80,000 235,000 1,156,000
Budget Impact/Other
Thursday, May 12, 2016
169
Página 176
FY 2017 Capital Investment Plan FY 17 thru FY 21 Department Power Plant
City of Dover, Delaware Contact Power Plant Manager
Type Maintenance
Project # EG1601
Useful Life Unknown
Project Name McKee Run Building Equipment Replacement Category Electric
New Project: No Account Number: 487-8101-591.40-31 Priority 3
Time-Line: Multi-year Status Active
Total Project Cost: $426,000
Description
This project includes the replacement of certain building support systems that are expected to reach the end of their useful life. The specific
building systems to be addressed in 2017 include:
-Supervisor’s Office roof top Air Conditioners
-Contractor rebuild for the 2A Air Compressor
-Administrative Building heating and cooling systems.
-Roof repairs.
-DI Room modifications.
Note: Project costs in years beyond 2017 are shown for expense planning purposes and represent future projects related to this equipment that are
anticipated based on expected operation.
Justification
This project is required to fund the replacement of equipment that has reached the end of its design life. Continued increases in the costs to
maintain this equipment will result if the listed equipment is not kept up to date or replaced in a timely manner. In addition, critical temperature
control is necessary to keep plant instrumentation located in the control room at acceptable operating conditions. Replacement of the control room
air conditioners is scheduled for 2017. Waiting for the air conditioning to fail and allowing the temperatures in the control room to exceed control
conditions could contribute to reduced control equipment life and reduced unit reliability.
Expenditures FY 17 FY 18 FY 19 FY 20 FY 21 Total
Construction/Maintenance 59,000 99,000 27,000 66,000 175,000 426,000
Total 59,000 99,000 27,000 66,000 175,000 426,000
Funding Sources FY 17 FY 18 FY 19 FY 20 FY 21 Total
Electric Revenue 59,000 99,000 27,000 66,000 175,000 426,000
Total 59,000 99,000 27,000 66,000 175,000 426,000
Budget Impact/Other
Thursday, May 12, 2016
170
Página 177
FY 2017 Capital Investment Plan FY 17 thru FY 21 Department Power Plant
City of Dover, Delaware Contact Power Plant Manager
Type Maintenance
Project # EG1607
Useful Life
Project Name McKee Run Unit 3 Auxiliary System Components Category Electric
New Project: No Account Number: 487-8101-591.40-31 Priority 2
Time-Line: Multi-year Status Active
Total Project Cost: $944,000
Description
This project will perform inspections and repairs of Unit 3 auxiliary system components focusing on critical components. Components identified
that will be addressed in 2017 include the #3 and 4 service water pumps, heat exchanger and piping safety valves.
Hot water system circulating pumps.
Cooling water booster pump.
Unit #3 vacuum pump inspections.
Unit #3 vacuum pump motive air valve replacement.
Unit #3 vacuum pump seal water pump inspections.
Unit #3 lube oil cooler piping and temperature control valve refurbishment.
Note: Project costs in years beyond 2017 are shown for expense planning purposes and represent future projects related to this equipment that are
anticipated based on expected operation.
Justification
Critical auxiliary systems components are those components that, if they were to fail, their failure could result in unit load reduction or outage with
consequential loss of capacity and / or generation although they would not individually affect the long range financial viability of the unit.
Addressing these assets in a systematic fashion will result in minimizing forced outages and eliminating major maintenance expenses associated
with component failure. Performing work as scheduled will also levelize maintenance expenditures. Delaying this project could result in the failure
of critical unit equipment and subsequent loss of generation and/ or capacity.
Expenditures FY 17 FY 18 FY 19 FY 20 FY 21 Total
Construction/Maintenance 128,000 261,000 277,000 213,000 65,000 944,000
Total 128,000 261,000 277,000 213,000 65,000 944,000
Funding Sources FY 17 FY 18 FY 19 FY 20 FY 21 Total
Electric Revenue 128,000 261,000 277,000 213,000 65,000 944,000
Total 128,000 261,000 277,000 213,000 65,000 944,000
Budget Impact/Other
Thursday, May 12, 2016
171
Página 178
FY 2017 Capital Investment Plan FY 17 thru FY 21 Department Power Plant
City of Dover, Delaware Contact Power Plant Manager
Type Maintenance
Project # EG1609
Useful Life Unknown
Project Name Van Sant Unit 11 Component Replacements Category Electric
New Project: No Account Number: 487-8101-591.40-31 Priority 4
Time-Line: Multi-year Status Active
Total Project Cost: $484,000
Description
This fund was developed to perform inspections and repairs to the VanSant Unit 11 auxiliary equipment on a predetermined frequency based on
unit operating hours, required regulatory inspection intervals, and known equipment condition. Work to be performed would include the following
equipment:
2017 - Fuel flow divider refurbishment, fuel nozzle refurbishment and an upgrade to the site gas supply skid to keep pace with Eastern Shore
expected improvements and modifications.
Note: Project costs in years beyond 2016 are shown for expense planning purposes and represent future projects related to this equipment that are
anticipated based on expected operation.
Justification
This project is required to fund the replacement of capital items that are expected to reach their useful life and will need to be replaced or
refurbished to maintain plant system and unit reliability. Extended equipment and /or unit outage time will result from lack of funding this project.
This will have a direct effect on the cost of energy during the extended outage time as well as increase future energy capacity charges.
Expenditures FY 17 FY 18 FY 19 FY 20 FY 21 Total
Construction/Maintenance 89,000 305,000 90,000 484,000
Total 89,000 305,000 90,000 484,000
Funding Sources FY 17 FY 18 FY 19 FY 20 FY 21 Total
Electric Revenue 89,000 305,000 90,000 484,000
Total 89,000 305,000 90,000 484,000
Budget Impact/Other
Thursday, May 12, 2016
172
Página 179
FY 2017 Capital Investment Plan FY 17 thru FY 21 Department Power Plant
City of Dover, Delaware Contact Power Plant Manager
Type Maintenance
Project # EG1610
Useful Life
Project Name Plant Systems Safety & Compliance Improvements Category Electric
New Project: No Account Number: 487-8101-591.40-31 Priority 6 --
Time-Line: Multi-year Status Active
Total Project Cost: $149,000
Description
This project will install video cameras to replace outdated cameras and upgrade installed security cameras at McKee Run. The project will also
install cameras at VanSant Generating Station where there are no current cameras installed. Additionally, the project will include replacement of
outdated radios and replace deteriorating boundary fencing at the McKee Run and VanSant Generating Stations. The installation of this equipment
will aid in improving plant security at both sites and improve personnel safety at both sites.
Justification
This project is required to improve overall surveillance coverage and security at both McKee Run and VanSant generating plant sites. Currently,
VanSant Generating Station does not have any video surveillance and the installed cameras at McKee Run are old and antiquated. Boundary line
fencing is original and deteriorated.
Expenditures FY 17 FY 18 FY 19 FY 20 FY 21 Total
Construction/Maintenance 112,000 37,000 149,000
Total 112,000 37,000 149,000
Funding Sources FY 17 FY 18 FY 19 FY 20 FY 21 Total
Electric Revenue 112,000 37,000 149,000
Total 112,000 37,000 149,000
Budget Impact/Other
Thursday, May 12, 2016
173
Página 180
FY 2017 Capital Investment Plan FY 17 thru FY 21 Department Power Plant
City of Dover, Delaware Contact Power Plant Manager
Type Maintenance
Project # EG1611
Useful Life Unknown
Project Name McKee Run & VanSant - Preservation of Structures Category Electric
New Project: No Account Number: 487-8101-591.40-31 Priority 5
Time-Line: Multi-year Status Active
Total Project Cost: $586,000
Description
This project involves the preservation of plant structures in order to prevent deterioration of building structural steel and equipment subject to
corrosion due to the past operations and environment. Refurbishment costs include be the sandblasting and painting of identified structures and
equipment, along with the removal or demolition of equipment that has been retired in place. This work is an ongoing effort spanning multiple
years. Work identified includes the following:
2017 - Unit #3 boiler support beams, sandblast, prime and paint.
2017 - Unit #3 condenser inlet piping inspection and refurbishment or repairs based on inspection findings.
Note: Project costs in years beyond 2017 are shown for expense planning purposes and represent future projects related to this equipment that are
anticipated based on expected operation.
Justification
Structural steel painting is needed in various areas throughout the plant proper as well as various outbuildings on the plant property to maintain the
physical building structures and equipment in an acceptable condition and prevent further deterioration. This project represents a minimum
preservation and maintenance of structures consistent with the expected life of the stations. Consequences of delaying or eliminating this project
will result in the accelerated deterioration of plant structures and larger future costs associated with structural repairs.
Expenditures FY 17 FY 18 FY 19 FY 20 FY 21 Total
Construction/Maintenance 131,000 130,000 100,000 100,000 125,000 586,000
Total 131,000 130,000 100,000 100,000 125,000 586,000
Funding Sources FY 17 FY 18 FY 19 FY 20 FY 21 Total
Electric Revenue 131,000 130,000 100,000 100,000 125,000 586,000
Total 131,000 130,000 100,000 100,000 125,000 586,000
Budget Impact/Other
Thursday, May 12, 2016
174
Página 181
FY 2017 Capital Investment Plan FY 17 thru FY 21 Department Power Plant
City of Dover, Delaware Contact Power Plant Manager
Type Improvement
Project # EG1701
Useful Life 20 years
Project Name Van Sant Unit 11 Major Inspection Category Electric
New Project: No Account Number: 487-8101-591.40-31 Priority 2
Time-Line: Status Active
Total Project Cost: $2,098,000
Description
This project will perform a major overhaul on the turbine generator based on Original Equipment Manufacturer (OEM) recommended repair
frequency which is based on factored starts of the Unit from first commissioning and from last inspection/repair interval. This project will be
implemented in 2017 with long lead material purchases in 2017 and installation in 2018. The project was revised to include the replacement of the
exhaust plenum.
Justification
This project is required to fund the purchase of all parts needed to perform a major overhaul on the unit based on estimated factored starts since
unit was first commissioned and since last the Hot Gas Path inspection. This project will span the course of two years. In Year 1, the majority of
the long lead parts will be purchased. Services will be identified in year 2 and the actual installation will be performed in Year 2. Extended
equipment and /or unit outage time will result from lack of funding this project. This will have a direct effect on the cost of energy during the
extended outage time as well as increase future energy capacity charges. In addition, gradual degradation of the unit’s output could occur which
would have a negative effect on the capacity rating of the unit and reliability of the unit.
Expenditures FY 17 FY 18 FY 19 FY 20 FY 21 Total
Construction/Maintenance 400,000 1,548,000 150,000 2,098,000
Total 400,000 1,548,000 150,000 2,098,000
Funding Sources FY 17 FY 18 FY 19 FY 20 FY 21 Total
Electric Revenue 400,000 1,548,000 150,000 2,098,000
Total 400,000 1,548,000 150,000 2,098,000
Budget Impact/Other
Thursday, May 12, 2016
175
Página 182
FY 2017 Capital Investment Plan FY 17 thru FY 21 Department Power Plant
City of Dover, Delaware Contact Power Plant Manager
Type Maintenance
Project # EG1704
Useful Life
Project Name McKee Run Unit 3 Hydrogen Purity Analyzer Category Electric
New Project: Yes Account Number: 487-8101-591.40-31 Priority 1
Time-Line: FY17 Status Active
Total Project Cost: $96,000
Description
This project will replace the current Hydrogen Purity Analyzer on Unit 3 with newer equipment. Hydrogen Analyzers monitor hydrogen purity in
power generators which use hydrogen gas for cooling. It also monitors CO2 in hydrogen and CO2 in air during shutdown and startup purge
procedure. Hydrogen is the media by which cooling of the generator(s) is achieved. Great importance is placed on the assurance that system is
100% pure hydrogen and not contaminated. In addition, the analyzers also monitor the CO2 content when the generator is taken out of service for
equipment and personnel safety reasons.
Justification
Critical system components that, if they fail, will result in loss of generation and/or capacity. Parts and repair facilities are becoming rare. Newer
equipment enables the facility to secure improved equipment reliability and vendor support in the repair, acquisition of replacement parts and in
the overall maintenance of the analyzers.
CONSEQUENCES OF DELAYING OR ELIMINATING THIS PROJECT: Delaying this project could result in the failure of critical unit
equipment and subsequent lose of generation and or capacity
Expenditures FY 17 FY 18 FY 19 FY 20 FY 21 Total
Construction/Maintenance 96,000 96,000
Total 96,000 96,000
Funding Sources FY 17 FY 18 FY 19 FY 20 FY 21 Total
Electric Revenue 96,000 96,000
Total 96,000 96,000
Budget Impact/Other
We would expect this project to be funded outside the normal operating budget.
Thursday, May 12, 2016
176
Página 183
FY 2017 Capital Investment Plan FY 17 thru FY 21 Department Power Plant
City of Dover, Delaware Contact Power Plant Manager
Type Maintenance
Project # EG1706
Useful Life
Project Name Unit #3 Fast Start Upgrade Category Electric
New Project: Yes Account Number: 487-8101-591-40-31 Priority 2
Time-Line: FY18 Status Active
Total Project Cost: $200,000
Description
An alternative engineered method for starting up the unit 3 steam turbine generator in a reduced start time will reduce start up time and costs. The
benefits are reduced start up time, increased revenue through faster online times, potential increased unit dispatch, reduced startup costs, increased
equipment life, reduced maintenance (both O&M and Capital) and reduced environmental impact.
Justification
Major objective is to increase the number of starts on the unit while minimizing start-up costs, reduce the time to dispatch the unit, reduce boiler
degradation due to differential temperature induced stress on thick walled system and equipment components.
Expenditures FY 17 FY 18 FY 19 FY 20 FY 21 Total
Construction/Maintenance 200,000 200,000
Total 200,000 200,000
Funding Sources FY 17 FY 18 FY 19 FY 20 FY 21 Total
Electric Revenue 200,000 200,000
Total 200,000 200,000
Budget Impact/Other
Thursday, May 12, 2016
177
Página 184
FY 2017 Capital Investment Plan FY 17 thru FY 21 Department Power Plant
City of Dover, Delaware Contact Power Plant Manager
Type Maintenance
Project # EG1709
Useful Life Unknown
Project Name Unit 3 Cooling Water Line Repairs Category Electric
New Project: Yes Account Number: 487-8101-591.40-31 Priority 3
Time-Line: FY17 Status Active
Total Project Cost: $469,000
Description
This project will inspect and repair the underground cooling water line from the Unit 3 condenser to the cooling tower. A condition assessment and
life evaluation was performed on this pipe in 2012 to develop a repair/replace action plan to address the suitability for continued operation as well
as extending the life of the piping beyond 2016. The actual repairs will be completed in 2016.
Justification
The condition of the underground cooling water line has required numerous repairs over the life of the plant and is expected to reach its useful life
in the 2012-2016 time period. It is expected that the repair frequency will accelerate over the next several years as the internal pipe coating
continues to degrade unless a repair process can extend the life of the piping and reduce the need for frequent inspections. Delaying this project
beyond 2016 will increase the risk of a failure causing an extended unit outage to repair or replace the failed pipe as well incur water spillage to the
ground. Additional budget dollars will need to be allocated to repair/ replace sections of piping.
Expenditures FY 17 FY 18 FY 19 FY 20 FY 21 Total
Planning/Design 8,000 8,000
Equip/Vehicle/Furnishings 429,000 429,000
Other 32,000 32,000
Total 469,000 469,000
Funding Sources FY 17 FY 18 FY 19 FY 20 FY 21 Total
Electric Revenue 469,000 469,000
Total 469,000 469,000
Budget Impact/Other
Thursday, May 12, 2016
178
Página 185
FY 2017 Capital Investment Plan FY 17 thru FY 21 Department Power Plant
City of Dover, Delaware Contact Power Plant Manager
Type Maintenance
Project # EG1711
Useful Life Unknown
Project Name VanSant Fire Suppression System Upgrade Category Electric
New Project: Yes Account Number: 487-8101-591.40-31 Priority 4
Time-Line: FY17 Status Active
Total Project Cost: $285,000
Description
This project is to replace the installed CARDOX® fire suppression system for the Van Sant combustion turbine generator. The current system has
been installed since original commercial operation began in 1991.This system has been inadvertently activated three times since installation and
there have been many improvements including more reliable fire suppression systems. The system selected is a water misting system and is the one
of the newer preferred suppression systems using a water mist/injection as the extinguishing agent instead of CO2.
Justification
This critical system can directly impact the Unit operation. Its failure to operate would result in a loss of generation and capacity due to the damage
incurred from a fire. Upgrading this system will result in reduced system maintenance costs, and eliminating major maintenance expenses
associated with the system or component failure.
Expenditures FY 17 FY 18 FY 19 FY 20 FY 21 Total
Construction/Maintenance 285,000 285,000
Total 285,000 285,000
Funding Sources FY 17 FY 18 FY 19 FY 20 FY 21 Total
Electric Revenue 285,000 285,000
Total 285,000 285,000
Budget Impact/Other
Thursday, May 12, 2016
179
Página 186
FY 2017 Capital Investment Plan FY 17 thru FY 21 Department Power Plant
City of Dover, Delaware Contact
Type Maintenance
Project # EG1807
Useful Life
Project Name Hydrogen Generator Category Electric
New Project: Yes Account Number: 487-5101-591.40-31 Priority 1
Time-Line: FY18 Status Active
Total Project Cost: $50,000
Description
Purchase and installation of a Hydrogen generator to supply hydrogen gas cooling medium for the Unit #3 Steam Turbine Generator. .
Justification
During periods of maintenance and operations it is required to purge the hydrogen seals in order to perform work on the turbine unit. After
maintenance is completed it is necessary to restore the hydrogen seals for cooling purpose s prior to operations. The hydrogen generator would
offer significant savings in the gas expenses for the generating station at McKee Run. It would also eliminate bottle rental from the gas provider
and reduce those monthly savings as well. This equipment would pay for itself in 3-4 years reducing the need to purchase hydrogen gas and the
bottle rental costs. This makes for a safer work environment when employees no longer are required to manually move or manage the bottles the
gas is stored in.
Expenditures FY 17 FY 18 FY 19 FY 20 FY 21 Total
Construction/Maintenance 50,000 50,000
Total 50,000 50,000
Funding Sources FY 17 FY 18 FY 19 FY 20 FY 21 Total
Electric Revenue 50,000 50,000
Total 50,000 50,000
Budget Impact/Other
Thursday, May 12, 2016
180
Página 187
FY 2017 Capital Investment Plan FY 17 thru FY 21 Department Power Plant
City of Dover, Delaware Contact Power Plant Manager
Type Maintenance
Project # EG1901
Useful Life Unknown
Project Name McKee Run Unit #3 Turbine Repairs - Generator Category Electric
New Project: Yes Account Number: 487-8101-591.40-31 Priority 1
Time-Line: Multi-year Status Active
Total Project Cost: $488,000
Description
This project will inspect the Unit 3 turbine control and stop valves and auxiliary equipment. This inspection is scheduled on a predetermined
frequency based on Unit operating hours, time since last valve inspection, required regulatory intervals, original equipment manufacturer and
insurance company recommendations. In 2018 all turbine control, stop, and intercept valves will be fully disassembled, and inspected. If the
condition found requires repairs the necessary repairs will be performed as needed and the unit reassembled.
Note: Project costs in years beyond 2018 are shown for expense planning purposes and represent future projects related to this equipment that are
anticipated based on expected operation and insurance company recommendations.
Justification
The valve inspections included in the scope are all related to the normal and emergency turbine generator control and shutdown systems. Industry
standard inspection guidelines are followed in order to minimize the risk of mechanical failure which could result in extended forced outage of the
unit, or the potential indefinite loss of unit availability from damage resulting from the failure of the scope components.
Expenditures FY 17 FY 18 FY 19 FY 20 FY 21 Total
Construction/Maintenance 438,000 25,000 25,000 488,000
Total 438,000 25,000 25,000 488,000
Funding Sources FY 17 FY 18 FY 19 FY 20 FY 21 Total
Electric Revenue 438,000 25,000 25,000 488,000
Total 438,000 25,000 25,000 488,000
Budget Impact/Other
Thursday, May 12, 2016
181
Página 188
FY 2017 Capital Investment Plan FY 17 thru FY 21 Department Power Plant
City of Dover, Delaware Contact Power Plant Manager
Type Maintenance
Project # EG1902
Useful Life Unknown
Project Name McKee Run Unit 3 Turbine Repairs Intercept Valves Category Electric
New Project: No Account Number: 487-8101-591.40-31 Priority 2
Time-Line: FY19-FY20 Status Active
Total Project Cost: $463,000
Description
This project will inspect the Unit 3 turbine control and stop valves and auxiliary equipment. This inspection is scheduled on a predetermined
frequency based on Unit operating hours, required regulatory intervals, original equipment manufacturer and insurance company
recommendations. In 2018 all turbine control, stop, and intercept valves will be fully disassembled, inspected and repaired if needed.
Note: Project costs in years beyond 2018 are shown for expense planning purposes and represent future projects related to this equipment that are
anticipated based on expected operation and insurance company recommendations.
Justification
The valve inspections included in the scope are all related to the normal and emergency turbine generator control and shutdown systems. Industry
standard inspection guidelines are followed in order to minimize the risk of mechanical failure which could result in extended forced outage of the
unit, or the potential indefinite loss of unit availability.
Expenditures FY 17 FY 18 FY 19 FY 20 FY 21 Total
Construction/Maintenance 438,000 25,000 463,000
Total 438,000 25,000 463,000
Funding Sources FY 17 FY 18 FY 19 FY 20 FY 21 Total
Electric Revenue 438,000 25,000 463,000
Total 438,000 25,000 463,000
Budget Impact/Other
Thursday, May 12, 2016
182
Página 190
City of Dover, Delaware
FY 2017 Capital Investment Plan
FY 17 thru FY 21
FUNDING SOURCE SUMMARY
Source FY 17 FY 18 FY 19 FY 20 FY 21 Total
General Fund 840,900 1,752,400 1,553,400 1,366,600 2,121,700 7,635,000
GRAND TOTAL 840,900 1,752,400 1,553,400 1,366,600 2,121,700 7,635,000
Thursday, May 12, 2016
184
Página 191
City of Dover, Delaware
FY 2017 Capital Investment Plan
FY 17 thru FY 21
PROJECTS BY DEPARTMENT
Department Project# Priority FY 17 FY 18 FY 19 FY 20 FY 21 Total
Code Enforcement
2007 Dodge Pick Up 16Veh# 17 n/a 17,000 17,000
1998 Ford Crown Victoria 18Veh# 11 n/a 23,800 23,800
Code Enforcement Total 23,800 17,000 40,800
Facilities Management
1996 Ford Van #436 17Veh #436 n/a 27,700 27,700
2003 Dodge Van (438) 18Veh# 438 n/a 28,200 28,200
2004 Ford Van #439 19Veh# 439 3 28,800 28,800
2005 Ford F150 #433 20Veh#433 n/a 32,200 32,200
Facilities Management Total 27,700 28,200 28,800 32,200 116,900
Fire/Robbins Hose
Engine 7 - 1997 Pierce Dash Pumper FR1700 1 73,400 73,400 73,400 73,400 293,600
Ladder 1 - 2011 Pierce Quantum PUC FR1800 1 145,700 145,700 145,700 0 0 437,100
Engine 3 - 2003 Pierce Lance Pumper FR1900 1 76,100 76,100 76,100 76,100 304,400
Engine 6 - 2003 Pierce Lance Pumper FR2000 1 76,800 76,800 153,600
Fire/Robbins Hose Total 145,700 295,200 295,200 226,300 226,300 1,188,700
Fleet Maintenance
1998 Ford F150 #129 17Veh #129 n/a 31,000 31,000
2001 Dodge Ram 150 #130 18Veh #130 n/a 38,000 38,000
2003 Chevrolet 1500 HD Flat Bed #119 19Veh# 119 n/a 60,000 60,000
Fleet Maintenance Total 31,000 38,000 60,000 129,000
Life Safety (Fire Marshal)
2008 Dodge Durango 17Veh# 12 n/a 29,500 29,500
Life Safety (Fire Marshal) Total 29,500 29,500
Permtting and Inspections
2001 Dodge Pick Up 16Veh# 19 n/a 17,000 17,000
2001 Dodge Pick Up 16Veh# 22 n/a 17,000 17,000
2005 Ford F150 17Veh# 13 n/a 16,000 16,000
Permtting and Inspections Total 16,000 34,000 50,000
Planning
2004 Ford Station Wagon 17Veh# 3 n/a 16,000 16,000
Planning Total 16,000 16,000
Police
Thursday, May 12, 2016
185
Página 192
Department Project# Priority FY 17 FY 18 FY 19 FY 20 FY 21 Total
2017 Dodge Charger PPV (203) 17Veh# 203 n/a 26,500 26,500
2017 Dodge Charger Admin (206) 17Veh# 206 n/a 24,400 24,400
2017 Dodge Charger Admin (212) 17Veh# 212 n/a 24,400 24,400
2017 Dodge Charger PPV (227) 17Veh# 227 n/a 26,500 26,500
2017 Dodge Charger PPV (238) 17Veh# 238 n/a 26,500 26,500
2017 Dodge Charger PPV (252) 17Veh# 252 n/a 26,500 26,500
2017 Dodge Charge PPV (253) 17Veh# 253 n/a 26,500 26,500
2017 Dodge Charger (254) 17Veh# 254 n/a 26,500 26,500
2017 Harley FLHTP (256) 17Veh# 256 n/a 24,400 24,400
2017 Dodge Charger PPV (259) 17Veh# 259 n/a 26,500 26,500
2017 Dodge Charger PPV (271) 17Veh# 271 n/a 26,500 26,500
2017 Dodge Charger PPV (275) 17Veh# 275 n/a 26,500 26,500
2018 Dodge Charger PPV (208) 18Veh# 208 n/a 26,500 26,500
2018 Dodge Charger PPV (209) 18Veh# 209 n/a 26,500 26,500
2000 Ford Taurus (210) 18Veh# 210 n/a 24,400 24,400
2018 Chev Tahoe PPV (222) 18Veh# 222 n/a 33,600 33,600
2018 Chev Tahoe PPV (223) 18Veh# 223 n/a 33,600 33,600
2018 Chev Tahoe PPV (226) 18Veh# 226 n/a 33,600 33,600
2018 Dodge Charger PPV (234) 18Veh# 234 n/a 26,500 26,500
2018 Dodge Charger PPV (255) 18Veh# 255 n/a 26,500 26,500
2018 Dodge Charger Admin (260) 18Veh# 260 n/a 24,400 24,400
2018 Dodge Charger Admin (261) 18Veh# 261 n/a 24,400 24,400
2018 HD Motorcycle FLHTP (266) 18Veh# 266 n/a 24,400 24,400
2018 Dodge Charger PPV (272) 18Veh# 272 n/a 26,500 26,500
2018 Dodge Charger PPV (273) 18Veh# 273 n/a 26,500 26,500
2018 Dodge Charger PPV (276) 18Veh# 276 n/a 26,500 26,500
2019 Dodge Charger PPV (205) 19Veh# 205 n/a 26,500 26,500
2019 Chevy Express (207) 19Veh# 207 n/a 20,400 20,400
2019 Dodge Charger PPV (216) 19Veh# 216 n/a 26,500 26,500
2019 Dodge Charger Admin (221) 19Veh# 221 n/a 24,400 24,400
2019 Dodge Charger Admin (230) 19Veh# 230 n/a 24,400 24,400
2019 Dodge Charger PPV (232) 19Veh# 232 n/a 26,500 26,500
2019 Dodge Charger PPV (239) 19Veh# 239 n/a 26,500 26,500
2019 Dodge Charger Admin (240) 19Veh# 240 n/a 24,400 24,400
2019 Harley Davidson FLHTP (244) 19Veh# 244 n/a 24,400 24,400
2019 Dodge Charger PPV (250) 19Veh# 250 n/a 26,500 26,500
2019 Harley FLHTP (267) 19Veh# 267 n/a 24,400 24,400
2019 Dodge Charger PPV (269) 19Veh# 269 n/a 26,500 26,500
2019 Dodge Ram 1500 Crew 4X4 (296) 19Veh# 296 n/a 28,000 28,000
2019 Dodge Charger PPV (297) 19Veh# 297 n/a 26,500 26,500
2020 Harley FLHTP (211) 20Veh# 211 n/a 24,400 24,400
2020 Dodge Charger PPV (219) 20Veh# 219 n/a 26,500 26,500
2020 Dodge Charger PPV (220) 20Veh# 220 n/a 26,500 26,500
2020 Dodge Charger Admin (237) 20Veh# 237 n/a 24,400 24,400
2020 Dodge Charger PPV (258) 20Veh# 258 n/a 26,500 26,500
2020 Dodge Charger PPV (262) 20Veh# 262 n/a 26,500 26,500
2020 Dodge Charger PPV (263) 20Veh# 263 n/a 26,500 26,500
2020 Dodge Charger PPV (264) 20Veh# 264 n/a 26,500 26,500
2020 Dodge Charger PPV (265) 20Veh# 265 n/a 26,500 26,500
2020 Harley FLHTP (268) 20Veh# 268 n/a 24,400 24,400
2020 Dodge Charger PPV (278) 20Veh# 278 n/a 26,500 26,500
2020 Dodge Charger PPV (282) 20Veh# 282 n/a 26,500 26,500
2020 Dodge Charger PPV (283) 20Veh# 283 n/a 26,500 26,500
2020 Dodge Charger PPV (284) 20Veh# 284 n/a 26,500 26,500
2021 Dodge Charger Admin (201) 21Veh# 201 n/a 24,400 24,400
2021 Dodge Charger Admin (204) 21Veh# 204 n/a 24,400 24,400
2021 Chev Ram 1500 Crew 4X4 (215) 21Veh# 215 n/a 28,000 28,000
Thursday, May 12, 2016
186
Página 193
Department Project# Priority FY 17 FY 18 FY 19 FY 20 FY 21 Total
2021 Chevy Tahoe PPV (229) 21Veh# 229 n/a 33,600 33,600
2021 Dodge Charger Admin (231) 21Veh# 231 n/a 24,400 24,400
2021 Dodge Charger Admin (235) 21Veh# 235 n/a 24,400 24,400
2021 Dodge Charger PPV (241) 21Veh# 241 n/a 26,500 26,500
2021 Dodge Charger PPV (242) 21Veh# 242 n/a 26,500 26,500
2021 Dodge Charger Admin (243) 21Veh# 243 n/a 24,400 24,400
2021 Dodge Ram 1500 Crew 4X4 (245) 21Veh# 245 n/a 28,000 28,000
2021 Dodge Charger Admin (249) 21Veh# 249 n/a 24,400 24,400
2021 Dodge Charger Admin (290) 21Veh# 290 n/a 24,400 24,400
2021 Chevy Tahoe PPV (293) 21Veh# 293 n/a 33,600 33,600
2021 Chevy Express (295) 21Veh# 295 n/a 20,400 20,400
Police Total 287,300 408,300 355,900 364,700 367,400 1,783,600
Public Works - Grounds
2001 Kubota 80" Utility Tractor (569) 17Veh# 569 3 27,000 27,000
1999 Dodge Ram 2500 Truck #558 17Veh#558 n/a 31,200 31,200
2003 Ex-Mark 52" Zero Turn Mower (568) 18Veh# 568 3 15,000 15,000
2004 Kubota Tractor w/Front Loader/Backhoe #572 18Veh# 572 3 44,800 44,800
1995 International Bucket Truck #589 19Veh#589 2 188,000 188,000
2001 Dodge Ram 2500 Truck #580 20 VEH#580 n/a 33,000 33,000
2006 Kubota Mower #581 20Veh #581 n/a 60,000 60,000
2009 Toro Mower #561 20Veh#561 n/a 60,000 60,000
1994 Vermeer Chipper #588 21Veh #588 n/a 89,000 89,000
2012 Toro Mower #562 21Veh#562 n/a 62,000 62,000
Public Works - Grounds Total 58,200 59,800 188,000 153,000 151,000 610,000
Public Works - Sanitation
2008 Peterbilt Automated Trash Truck (441) 17Veh# 441 3 261,500 261,500
2008 Intn't Rear Loader (445) 18Veh# 445 4 165,000 165,000
2010 Peterbilt Automated Trash Truck #455 18Veh# 455 3 266,700 266,700
2009 International Bulk Trash Truck #446 19Veh# 446 3 155,100 155,100
2003 Peterbilt Automated Trash Truck #444 19Veh#444 n/a 272,000 272,000
2002 Hurst Trailer #453 19Veh#453 n/a 2,000 2,000
2008 Ford F150 #440 20Veh#440 n/a 32,200 32,200
2008 International Rear Loader #452 20Veh#452 n/a 172,700 172,700
2011 Peterbilt Automated Trash Truck #450 21Veh#450 n/a 332,000 332,000
2008 International Rear Loader Trash Truck #452 21Veh#452 n/a 295,000 295,000
Public Works - Sanitation Total 261,500 431,700 429,100 204,900 627,000 1,954,200
Public Works - Streets
2001 Int'l Dump Truck (321) 17Veh# 321 3 132,200 132,200
2001 Case Front-End Loader #316 18Veh #316 2 168,300 168,300
1992 International Dump Truck (326) 18Veh# 326 1 134,900 134,900
2001 Int'l Dump Truck (322) 19Veh# 322 2 137,600 137,600
2002 Airman Air Compressor (382) 19Veh# 382 2 26,600 26,600
2003 Chevrolet Silverado 1500 #330 19Veh#330 n/a 32,200 32,200
2001 Case Front-End Loader #312 20Veh #312 2 175,100 175,100
2001 Int'l Dump Truck (324) 20Veh# 324 2 140,400 140,400
2002 Old Dominion Leaf Vac #361 20Veh#361 n/a 70,000 70,000
1969 Caterpillar Grader #301 21Veh#301 n/a 477,000 477,000
2006 International Sweeper #356 21Veh#356 n/a 180,000 180,000
Public Works - Streets Total 435,400 196,400 385,500 657,000 1,674,300
Thursday, May 12, 2016
187
Página 194
Department Project# Priority FY 17 FY 18 FY 19 FY 20 FY 21 Total
Public Works Admin
2008 Toyota Camry Hybrid #6 21Veh# 6 n/a 42,000 42,000
Public Works Admin Total 42,000 42,000
GRAND TOTAL 840,900 1,752,400 1,553,400 1,366,600 2,121,700 7,635,000
Thursday, May 12, 2016
188
Página 195
City of Dover, Delaware
FY 2017 Capital Investment Plan
FY 17 thru FY 21
FUNDING SOURCE SUMMARY
Source FY 17 FY 18 FY 19 FY 20 FY 21 Total
Water/Wastewater Fund 222,600 489,700 684,700 347,100 135,000 1,879,100
GRAND TOTAL 222,600 489,700 684,700 347,100 135,000 1,879,100
Thursday, May 12, 2016
189
Página 196
City of Dover, Delaware
FY 2017 Capital Investment Plan
FY 17 thru FY 21
PROJECTS BY DEPARTMENT
Department Project# Priority FY 17 FY 18 FY 19 FY 20 FY 21 Total
W/WW Engineering
2008 Chevrolet Pickup (421) 17Veh# 421-2 n/a 30,400 30,400
2008 Ford F150 Pick-Up (420) 18Veh# 420-2 1 31,000 31,000
2008 Dodge Avenger (427) 19Veh# 427-2 n/a 23,000 23,000
2008 Dodge Avenger SE #5 20Veh#5-2 n/a 28,000 28,000
W/WW Engineering Total 30,400 31,000 23,000 28,000 112,400
Wastewater Management
1987 Empire Generator (603) 17Veh# 603 n/a 34,400 34,400
2000 Airman Air Compressor #683 (split) 17Veh#683 n/a 12,800 12,800
2008 Chevy 3/4-Ton Utility Truck #667 (Split) 18Veh #667 n/a 16,500 16,500
2006 Sidekick Easement Machine (690) 18Veh# 690 n/a 36,000 36,000
2008 Ford 1-Ton Utility Truck with crane #665 18Veh#665 n/a 50,000 50,000
2008 Ford 1/2 Ton Utility Truck #698 (split) 18Veh#698 n/a 16,500 16,500
2008 Case 590 Backhoe #672 (Split) 19Veh #672 n/a 59,400 59,400
2008 International Dump Truck 14' #681 (Split) 19Veh #681 n/a 78,000 78,000
2009 Chevrolet CUES Camera Truck #684 19Veh #684 5 300,000 300,000
2005 Case Backhoe #682 (split) 20Veh#682 n/a 61,900 61,900
2012 Chevrolet Silverado 1500 WT #695(split) 20Veh#695 n/a 16,500 16,500
2013 Ford 1-Ton Utilty Truck with Crane #655 21Veh#655 n/a 55,000 55,000
2013 Ford 1-Ton Utility Truck with crane 21Veh#664 n/a 55,000 55,000
Wastewater Management Total 47,200 119,000 437,400 78,400 110,000 792,000
Water Management
2002 Sterling STE #424 17Veh#424 n/a 132,200 132,200
2000 Airman air compressor #683 (split) 17Veh#683-2 n/a 12,800 12,800
2008 Chevy 3/4-Ton Utility Truck #667 (Split) 18Veh #667-2 n/a 16,500 16,500
1995 Caterpillar Excavator #400 18Veh#400 n/a 62,700 62,700
1995 Caterpillar Loader #402 18Veh#402 n/a 189,000 189,000
2008 Ingersoll Air Compressor #407 18Veh#407 n/a 29,000 29,000
2008 Ford 1/2 Ton Utility Truck #698 (split) 18Veh#698-2 n/a 16,500 16,500
2008 Case 590 Backhoe #672 (Split) 19Veh #672-1 n/a 59,400 59,400
2008 International Dump Truck 14' #681 (Split) 19Veh #681-1 n/a 78,000 78,000
2009 Wacker RT820 Vibratory Trench Roller #401 19Veh#401 n/a 36,900 36,900
2005 Case Backhoe #682 (Split) 20Veh# 682 n/a 61,900 61,900
2012 Ford F250 Super Duty XL #403 20Veh#403 n/a 40,000 40,000
2012 Ford F250 Super Duty XL #426 20Veh#426 n/a 40,000 40,000
2012 Chevrolet Silverado 1500 WT #695 (split) 20Veh#695-2 n/a 16,500 16,500
1997 Kruger Trailer #415 21Veh#415 n/a 25,000 25,000
Water Management Total 145,000 313,700 174,300 158,400 25,000 816,400
Water Treatment Plant
2008 GMC Cargo Van (662) 18Veh# 662 n/a 26,000 26,000
2007 Kohler Generator Trailer Mounted (604) 19Veh# 604 n/a 50,000 50,000
Thursday, May 12, 2016
190
Página 197
Department Project# Priority FY 17 FY 18 FY 19 FY 20 FY 21 Total
2010 Ford 1-Ton Utility Truck w/ Gate 3620 20Veh# 620 n/a 56,300 56,300
2011 Ford Ranger #621 20Veh#621 n/a 26,000 26,000
Water Treatment Plant Total 26,000 50,000 82,300 158,300
GRAND TOTAL 222,600 489,700 684,700 347,100 135,000 1,879,100
Thursday, May 12, 2016
191
Página 198
City of Dover, Delaware
FY 2017 Capital Investment Plan
FY 17 thru FY 21
FUNDING SOURCE SUMMARY
Source FY 17 FY 18 FY 19 FY 20 FY 21 Total
Electric Revenue 165,800 666,200 325,500 400,000 310,000 1,867,500
GRAND TOTAL 165,800 666,200 325,500 400,000 310,000 1,867,500
Thursday, May 12, 2016
192
Página 199
City of Dover, Delaware
FY 2017 Capital Investment Plan
FY 17 thru FY 21
PROJECTS BY DEPARTMENT
Department Project# Priority FY 17 FY 18 FY 19 FY 20 FY 21 Total
Electric Admin
2008 Ford Escape (#701) Veh #701 1 30,000 30,000
Electric Admin Total 30,000 30,000
Electric Engineering
2008 Dodge Avenger (7) Veh# 007 n/a 28,200 28,200
2005 Dodge Stratus (8) Veh# 008 n/a 25,500 25,500
2007 Dodge Pickup (9) Veh# 009 n/a 29,500 29,500
2006 Ford Pickup (790) Veh# 790 1 33,200 33,200
Electric Engineering Total 33,200 83,200 116,400
Electric Meter Reading
2017 Ford F250XL 4X2 Reg Cab (125) 17Veh# 125 1 20,900 20,900
2017 Ford F250XL 4X2 Reg Cab (158) 17Veh# 158 1 20,900 20,900
Electric Meter Reading Total 41,800 41,800
Electric T & D
1995 Case Backhoe (733) Veh #733 1 125,000 125,000
2004 International Altec Aerial Device Veh #751 1 150,000 150,000
2002 Chevrolet Dump Truck Veh #753 1 150,000 150,000
2006 International Bucket Truck Veh #759 1 160,000 160,000
2007 Dodge Pick Up Veh #771 1 33,000 33,000
2008 International Dueco Line Truck Veh #772 1 250,000 250,000
2001 Freightliner Knuckleboom Veh #776 1 350,000 350,000
2008 Ford Dump F350 (796) Veh #796 1 45,000 45,000
1989 Smith SM160 (716) Veh# 716 1 25,000 25,000
2001 Freightliner (750) Veh# 750 1 300,000 300,000
2005 Ford Pick Up Truck Veh# 770 1 25,500 25,500
Electric T & D Total 25,000 553,000 325,500 400,000 310,000 1,613,500
Power Plant
2017 Ford F250XL 4X4 Reg Cab (727) 17PPVeh# 727 1 32,900 32,900
2017 Ford F250XL 4X4 Reg Cab (729) 17PPVeh# 729 1 32,900 32,900
Power Plant Total 65,800 65,800
GRAND TOTAL 165,800 666,200 325,500 400,000 310,000 1,867,500
Thursday, May 12, 2016
193
Página 200
DEBT LIMIT
DEBT SERVICE
SCHEDULES
Página 201
FY 2017 ANNUAL OPERATING BUDGET - DOVER, DELAWARE
City of Dover, Delaware
Computation of Legal Debt Margin
General Obligation Bonds
(amounts expressed in thousands)
Estimated Estimated
2017 2016 2015 2014 2013 2012 2011 2010
Debt Limit $ 152,960 $ 152,516 $ 158,485 $ 157,995 $ 159,075 $ 158,465 $ 156,832 $ 145,351
Net (Taxable) Assessed Value on Books 3,059,204 3,050,322 3,169,707 3,159,894 3,181,496 3,169,308 3,136,639 2,907,011
Total net debt applicable to limit 7,926 8,587 7,337 4,050 4,479 1,550 1,820 2,080
Legal Debt Margin $ 143,929 $ 151,148 $ 153,945 $ 154,596 $ 156,915 $ 155,012 $ 143,271
Total Net Debt applicable to limit
as a percentage of debt limit 5.18% 5.63% 4.63% 2.56% 2.82% 0.98% 1.00% 1.44%
Legal Debt Margin Calculation for Fiscal Year 2017
Net (Taxable) Assessed Value on Books $ 3,059,204 $ 3,050,322 $ 3,169,707 $ 3,159,894 $ 3,181,496 $ 3,169,308
Debt Limit - 5 Percent of Total Assessed Value $ 152,960 $ 152,516 $ 158,485 $ 157,995 $ 159,075 $ 158,465
DEBT
(For which the City's full faith and credit has been pledged)
Gross Bonded Debt 7,926 8,587 7,337 4,050 4,479 1,550
LEGAL DEBT MARGIN $ 145,034 $ 143,929 $ 151,148 $ 153,945 $ 154,596 $ 156,915
IMPORTANT NOTE: The Total Net Debt applicable to the debt limit includes the remaining Series 2014 A & B Bonds (PNC) and the 2012 Bonds (PNC)
Source: City of Dover Financial Reports, City of Dover Charter, Section 50(b), and Tax Assessor's Office
New Bonds without referendum cannot exceed 1/4 of 1% of taxable assessed value and shall not cause the total aggregate principal outstanding at any one time to exceed 1% of
total taxable assessment for a general tax at the time of issue or $7,648,000 based on the 2017 Estimate.
195
Página 202
FY 2017 ANNUAL OPERATING BUDGET - DOVER, DELAWARE
City of Dover
General Fund
Projected Debt Service
2012 2014 SeriesB Green Energy
Fiscal Year $3,660,000 2014 Total Debt Net Debt
Tax- Exempt Refunding Debt Service
Ending Series A Bonds Service Service
Loan * Bond Contribution
6/30/2017 $ 224,700 $ 204,000 $ 249,400 $ 678,100 $ (98,500) $ 579,600
6/30/2018 224,700 204,000 - 428,700 (98,500) 330,200
6/30/2019 224,700 204,000 - 428,700 (98,500) 330,200
6/30/2020 224,700 204,000 - 428,700 (98,500) 330,200
6/30/2021 224,700 204,000 - 428,700 (98,500) 330,200
6/30/2022 224,700 204,000 - 428,700 (98,500) 330,200
6/30/2023 224,700 204,000 - 428,700 (98,500) 330,200
6/30/2024 224,700 204,000 - 428,700 (98,500) 330,200
6/30/2025 224,700 204,000 - 428,700 (98,500) 330,200
6/30/2026 224,700 204,000 - 428,700 (98,500) 330,200
6/30/2027 224,700 204,000 - 428,700 (98,500) 330,200
6/30/2028 224,700 204,000 - 428,700 (98,500) 330,200
6/30/2029 224,700 204,000 - 428,700 (98,500) 330,200
6/30/2030 224,700 204,000 - 428,700 (98,500) 330,200
6/30/2031 224,700 204,000 - 428,700 (98,500) 330,200
6/30/2032 224,700 204,000 - 428,700 (98,500) 330,200
6/30/2033 205,800 204,000 - 409,800 (98,500) 311,300
6/30/2034 - 204,000 - 204,000 - 204,000
6/30/2035 - 204,000 - 204,000 - 204,000
Totals $ 3,801,000 $ 3,876,000 $ 249,400 $ 7,926,400 $ (1,674,500) $ 6,251,900
Library & Garrison Farm 2003 Bond Library
Streets & Equipment Refinanced
* Annual Debt Service for the 2012 Loan does not reflect any reduction for the sale of the current Library
196
Página 203
FY 2017 ANNUAL OPERATING BUDGET - DOVER, DELAWARE
City of Dover
Water/Wastewater Revenue Bonds
Current Debt Service - Table 1
Total
Fiscal Year Series 2000 Series 2009 Series 2010 Series 2011 Total Water Wastewater Total Debt
Ending Wastewater Wastewater Water Wastewater Debt Service Debt Service Service
6/30/2017 $ 53,000 $ 347,100 $ 161,300 $ 58,200 $ 517,200 $ 610,100 $ 1,127,300
6/30/2018 53,000 347,100 161,300 58,200 517,100 610,100 1,127,200
6/30/2019 53,000 347,100 161,300 58,200 520,400 611,400 1,131,800
6/30/2020 53,000 347,100 161,300 58,200 516,400 609,700 1,126,100
6/30/2021 - 347,100 161,300 58,200 519,200 557,900 1,077,100
6/30/2022 - 347,100 161,300 58,200 518,200 557,500 1,075,700
6/30/2023 - 347,100 161,300 58,200 517,000 557,000 1,074,000
6/30/2024 - 347,100 161,300 58,200 519,000 557,900 1,076,900
6/30/2025 - 347,100 161,300 58,200 375,700 496,800 872,500
6/30/2026 - 347,100 161,300 58,200 374,600 496,300 870,900
6/30/2027 - 347,100 161,300 58,200 373,100 495,600 868,700
6/30/2028 - 347,100 161,300 58,200 374,600 496,300 870,900
6/30/2029 - 347,100 161,300 58,200 375,300 496,600 871,900
6/30/2030 - 347,100 161,300 58,200 375,300 496,600 871,900
6/30/2031 - 347,100 80,700 58,200 295,100 496,800 791,900
6/30/2032 - 173,600 - 29,100 213,200 293,600 506,800
6/30/2033 - - - - 212,300 90,600 302,900
6/30/2034 - - - - 211,100 90,000 301,100
Total $ 212,000 $ 5,380,100 $ 2,338,900 $ 902,100 $ 7,324,800 $ 8,620,800 $ 15,945,600
197
Página 204
FY 2017 ANNUAL OPERATING BUDGET - DOVER, DELAWARE
City of Dover
Water/Wastewater Revenue Bonds
Projected Debt Service - Table 2
New State of Delaware Revolving Fund Loans
Total Tables 1 & 2
Fiscal Year Series 2017 Series 2017 Series 2018 Series 2019 Total Water Wastewater Total Debt
Ending Water Wastewater Wastewater Wastewater Debt Service Debt Service Service
6/30/2017 $ 73,100 $ 27,000 $ - $ - $ 73,100 $ 27,000 $ 1,227,400
6/30/2018 146,200 53,900 12,100 - 146,200 66,000 1,339,400
6/30/2019 146,200 53,900 24,200 12,500 146,200 90,600 1,368,600
6/30/2020 146,200 53,900 24,200 24,900 146,200 103,000 1,375,300
6/30/2021 146,200 53,900 24,200 24,900 146,200 103,000 1,326,300
6/30/2022 146,200 53,900 24,200 24,900 146,200 103,000 1,324,900
6/30/2023 146,200 53,900 24,200 24,900 146,200 103,000 1,323,200
6/30/2024 146,200 53,900 24,200 24,900 146,200 103,000 1,326,100
6/30/2025 146,200 53,900 24,200 24,900 146,200 103,000 1,121,700
6/30/2026 146,200 53,900 24,200 24,900 146,200 103,000 1,120,100
6/30/2027 146,200 53,900 24,200 24,900 146,200 103,000 1,117,900
6/30/2028 146,200 53,900 24,200 24,900 146,200 103,000 1,120,100
6/30/2029 146,200 53,900 24,200 24,900 146,200 103,000 1,121,100
6/30/2030 146,200 53,900 24,200 24,900 146,200 103,000 1,121,100
6/30/2031 146,200 53,900 24,200 24,900 146,200 103,000 1,041,100
6/30/2032 146,200 53,900 24,200 24,900 146,200 103,000 756,000
6/30/2033 146,200 53,900 24,200 24,900 146,200 103,000 552,100
6/30/2034 146,200 53,900 24,200 24,900 146,200 103,000 550,300
6/30/2035 146,200 53,900 24,200 24,900 146,200 103,000 249,200
6/30/2036 146,200 53,900 24,200 24,900 146,200 103,000 249,200
6/30/2037 73,100 26,900 24,200 24,900 73,100 76,000 149,100
6/30/2038 - - 12,100 24,900 - 37,000 37,000
6/30/2039 - - - 12,400 - 12,400 12,400
Total $ 2,924,000 $ 1,078,000 $ 484,000 $ 498,000 $ 2,924,000 $ 2,060,000 $ 20,929,600
198
Página 205
FY 2017 ANNUAL OPERATING BUDGET - DOVER, DELAWARE
City of Dover
Electric Revenue Fund
Projected Debt Service
Electric Revenue Fund
Fiscal Year 2008 Revenue Bonds Total Debt
6/30/2017 $ 695,000 $ 918,704 $ 1,613,704
6/30/2018 730,000 883,954 1,613,954
6/30/2019 765,000 847,454 1,612,454
6/30/2020 800,000 815,706 1,615,706
6/30/2021 840,000 781,706 1,621,706
6/30/2022 880,000 746,006 1,626,006
6/30/2023 925,000 707,506 1,632,506
6/30/2024 970,000 665,881 1,635,881
6/30/2025 1,015,000 622,231 1,637,231
6/30/2026 1,065,000 576,555 1,641,555
6/30/2027 1,120,000 527,300 1,647,300
6/30/2028 1,175,000 475,500 1,650,500
6/30/2029 1,230,000 416,750 1,646,750
6/30/2030 1,290,000 355,250 1,645,250
6/30/2031 1,355,000 290,750 1,645,750
6/30/2032 1,420,000 223,000 1,643,000
6/30/2033 1,485,000 152,000 1,637,000
6/30/2034 1,555,000 77,750 1,632,750
Total $ 19,315,000 $ 10,084,003 $ 32,800,957
199
Página 207
MAYOR
CITY COUNCIL
CITY MANAGER
CITY CLERK
CUSTOMER SERVICES
FINANCE, PROCUREMENT & INVENTORY
FIRE
HUMAN RESOURCES
INFORMATION TECHNOLOGY
PARKS, RECREATION & LIBRARY
POLICE
TAX ASSESSOR
PLANNING & INSPECTIONS
PUBLIC WORKS
Página 208
BUDGET REVIEW
Fiscal Year 2016-2017
May 2016 – Budget Review Hearing
202
Página 209
What You Need to Know
• Percentage changes are calculated on FY16 Original Budgets
• All Department budgets reflect the following in personnel expenses:
– Vacation sell-back, retirement payouts and education assistance are budgeted in a separate
fund expense account in order to reduce the overall amount budgeted for personnel
expenses.
– Health Insurance rates increased.
– OPEB rates decreased across all funds and divisions.
– Pension rates increased for the General Fund and Water/Wastewater Fund, and decreased
for the Electric Fund.
– Actuarial determined contribution for the OPEB and pension liabilities are included in the
pension contribution percentage.
– Worker’s Compensation Rates increased.
203
Página 210
GENERAL FUND
BUDGET REVIEW
Fiscal Year 2016-2017
MAY 2016 – BUDGET REVIEW HEARING
204
Página 211
Mayor
Personnel Costs 57,300 1%
Materials & Supplies 300 0%
Administrative Expenditures 16,400 14%
Overall Operating Expenses 74,000 3%
Highlights:
Personnel costs increase due to increased rates for health insurance.
Materials and Supplies remained constant.
Administrative Expenses decreased over all by $2,700 with the decrease in
community relations expenses.
205
Página 212
City Council
Personnel Costs 91,000 0%
Materials & Supplies 300 0%
Administrative Expenditures 52,800 97%
Overall Operating Expenses 144,100 22%
Highlights:
Personnel Costs remained constant.
Materials and Supplies remained constant.
Administrative Expenditures increased $26,000. The budget was increased
$25,000 for discretionary funds for Council Members with $5,000 per District
and $5,000 for the At-Large position. An increase $1,000 for HRC office
expenses.
206
Página 213
City Manager
Personnel Costs 503,300 1%
Materials & Supplies 8,400 40%
Administrative Expenditures 171,800 31%
Overall Operating Expenses 683,500 9%
Capital Outlay 0 100%
Total Expenditures 683,500 12%
Highlights:
Personnel Costs have increased $6,800 overall due to higher wages and insurance
benefits, net of decreased OPEB expense.
Materials and supplies increased by $2,600 in computer hardware and a small
decrease in printing.
Administrative Expenditures budget increased by $19,000 for legal expenses
offset by a decrease in contractual services of $95,000. Budget for contractual
services in prior year was $100,000 related to an ICMA study.
Capital Outlay has no budget this year. Prior year was $24,700 for a Ford
Explorer for the Public Affairs/Emergency Management Coordinator.
207
Página 214
City Clerk
Personnel Costs 372,800 5%
Materials & Supplies 9,200 104%
Administrative Expenditures 30,300 25%
Overall Operating Expenses 412,300 8%
Highlights:
Personnel Costs increased for wage and benefit cost increases.
Materials and supplies expense had a net increase of $4,700 mainly due to increase in
computer hardware.
Administrative expenditures has a net increase of $6,100 due to an increase of $9,000
in election related expenses offset by decreases of $2,900 in training/travel,
contractual services and subscriptions and dues.
208
Página 215
Customer Services
Personnel Costs 1,077,200 2%
Materials & Supplies 32,600 21%
Administrative Expenditures 34,000 29%
Overall Operating Expenses 1,143,800 2%
Highlights:
Personnel costs had a net increase of $24,800 due to pension cost, net of reduction in
OPEB.
Materials and supplies had a net decrease of $8,800 due to a decrease of $9,400 in
computer hardware offset by a small increase in office supplies.
Administrative expenses had a net increase of $7,700 due to an increase in contractual
services of $8,000 and a small increase in telephone offset by a small decrease in office
equipment repairs and maintenance.
209
Página 216
Finance
Personnel Costs 811,600 2%
Materials & Supplies 2,700 48%
Administrative Expenditures 194,300 11%
Overall Operating Expenses 1,008,600 3%
Highlights:
Personnel costs increased by $13,600 mainly attributed to increases health insurance
and pension cost.
Materials and supplies decreased $2,500 due to decreases in printing and duplicating
of $1,300 and computer hardware of $1,200.
Administrative expenses have increased by $19,000 due to increase in contractual
services of $19,800 mainly due to audit fees and actuarial valuations for pension and
OPEB.
210
Página 217
Procurement & Inventory
Personnel Costs 314,000 11%
Materials & Supplies 13,900 7%
Administrative Expenditures 257,200 2%
Overall Operating Expenses 585,100 4%
Highlights:
Personnel costs increased $30,100 due to wages, health insurance, and pension cost.
Materials and Supplies decreased $1,100 in computer hardware, office supplies and
program expenses and supplies.
Administrative expenditures have increased by $7,800 for contractual services and
training/travel offset by decreases totaling $11,900 in other and office equipment
repairs and maintenance, electricity, heating oil/gas and gasoline expense.
211
Página 218
Fire
Personnel Costs 437,700 7%
Materials & Supplies 0 100%
Administrative Expenditures 284,000 15%
Overall Operating Expenses 721,700 3%
Capital Outlay 145,700 0%
Total Expenditures 867,400 3%
Highlights:
Personnel Costs increased temporary help (relief dispatchers) and pension cost, net of
reduced OPEB cost.
Material & Supplies no budgeted expense this fiscal year. Prior year expense was $600.
Administrative Expenditures decreased $49,700 in contractual services, net of $1,300 in
training/travel expense. (The additional $50,000 appropriation requested in the prior
year was removed this fiscal year)
Capital Expenses remained constant. Engine 7 replacement has been requested but is not
included in the Draft Budget.
212
Página 219
Human Resources
Personnel Costs 345,100 8%
Materials & Supplies 29,400 24%
Administrative Expenditures 18,000 33%
Overall Operating Expenses 392,500 2%
Highlights:
Personnel Costs have increased overall by $26,900 due to benefit cost increases.
Materials and Supplies have decreased $9,700 in personnel related supplies, computer
hardware, medical supplies & physicals, and program expenses offset by a small increase
in computer software.
Administrative Expenditures decreased $10,900 in unemployment compensation
expense and training/travel offset by small increases in advertisement and in-house
training.
213
Página 220
Information Technology
Personnel Costs 441,400 0%
Materials & Supplies 98,700 2%
Administrative Expenditures 176,200 5%
Overall Operating Expenses 716,300 2%
Highlights:
Personnel Costs remained constant.
Materials and supplies are increased by $2,100 in computer software offset by a
small decrease in computer hardware.
Administrative Expenditures increased $8,400 due to increases in telephone,
contractual services and office equip/repairs & maintenance.
214
Página 221
Library
Personnel Costs 1,369,000 7%
Materials & Supplies 58,900 18%
Administrative Expenditures 207,100 34%
Overall Operating Expenses 1,635,000 8%
Highlights:
Personnel Costs increased by $85,500 mainly due to wage and benefit increases,
particularly health insurance and pension cost. One full-time position was not budgeted for
all year in FY16.
Materials & Supplies decreased overall by $12,500 mainly to a decrease in books offset by
an increase of $7,000 in city building maintenance supplies.
Administrative expenditures increased $52,000 mainly due to a new custodial contractor.
215
Página 222
Parks & Recreation
Personnel Costs 499,500 7%
Materials & Supplies 57,000 6%
Administrative Expenditures 191,400 5%
Overall Operating Expenses 747,900 3%
Capital Outlay 165,000 0%
Total Expenditures 912,900 25%
Highlights:
Personnel Costs increased by $32,800 mainly due to wage increases in full-time and temporary
help positions, health insurance and pension cost.
Materials & Supplies expenditures have decreased overall by $3,500 due to decreases in printing
and duplicating, computer hardware and water/sewer offset by an increase of $1,000 in program
expenses.
Administrative Expenditures decreased overall by $10,900 due to a reduction in electricity,
heating oil/gas, gasoline and subscription and dues offset by an increase of $11,500 mainly due
to contractual services for janitorial services. African American Festival contribution was
decreased $3,000 (previously $15K).
Capital Outlay increased $165,000 due to Schutte Park land improvements and plans for Dover
Park.
216
Página 223
Police
Personnel Costs 15,630,200 7%
Materials & Supplies 370,600 14%
Administrative Expenditures 874,400 25%
Overall Operating Expenses 16,875,200 7%
Capital Outlay 299,800 14%
Total Expenditures 17,175,000 7%
Highlights:
Personnel Costs increased by $1,002,800 due to an increase in wages and benefits as follows –
Civilian Division $189,000; Law Enforcement $632,600; Extra Duty $181,200; In the prior fiscal
year four cadets were budgeted for 10 months.
Materials and Supplies has a net decrease of $62,200 for reductions in program expenses/supplies,
uniforms/uniform allowances, computer hardware and CI petty cash disbursements offset by
increases mainly in medical supplies and physicals, computer software, books, and security and
safety materials.
Administrative Expenses has a net increase of $173,200 due to increases in insurance, training &
conference, auto repairs/maintenance and contractual services for custodial services and animal
control offset by decreases in radio equipment/lease, gasoline and advertisement expenses.
Capital Outlay of $299,800 is up from prior year by $37,700 and includes the purchase of 11 vehicles
and 1 motorcycle. Prior year included budget for a camera monitoring system.
217
Página 224
Tax Assessor
Personnel Costs 217,900 5%
Materials & Supplies 2,500 17%
Administrative Expenditures 23,600 4%
Overall Operating Expenses 244,000 4%
Highlights:
Personnel increased due to wage and benefit cost increases.
Materials and Supplies had small decreases for office supplies and computer software.
Administrative Expenses had a net decrease of $1,000 with reductions in contractual
services, gasoline and subscription and dues offset by increases in training/travel and
telephone.
218
Página 225
Planning/Inspections &
Community Development
219
Página 226
Planning
Personnel Costs 513,100 2%
Materials & Supplies 13,300 24%
Administrative Expenditures 20,400 3%
Overall Operating Expenses 546,800 2%
Capital Outlay 0 0%
Total Expenditures 546,800 2%
Highlights:
Personnel Costs increased by $9,700 due to wage and benefit increases.
Materials & Supplies expenditures increased $2,600 in computer hardware for 2 flat
panel monitors.
Administrative expenditures increased slightly by $500 for telephone and
subscription and dues.
220
Página 227
Inspections & Permitting
Personnel Costs 503,600 9%
Materials & Supplies 2,200 70%
Administrative Expenditures 192,100 1%
Overall Operating Expenses 697,900 5%
Highlights:
Personnel Costs increased $41,100 due to wage increases and higher benefit cost
particularly pension cost.
Materials & Supplies have decreased $6,400 in computer hardware and small
decreases in uniforms and security and safety materials offset by an increase of
$2,000 in code books.
Administrative Expenses have decreased $3,000 in contractual services and gasoline
offset by a small increase in training/travel expense.
221
Página 228
Code Enforcement
Personnel Costs 396,300 3%
Materials & Supplies 18,300 18%
Administrative Expenditures 6,500 44%
Overall Operating Expenses 421,100 0%
Highlights:
Personnel Costs increased overall due to wage and benefit cost increases.
Materials & Supplies decreased $4,000 due to a reduction in computer hardware,
uniforms and security and safety materials.
Administrative Expenditures decreased $5,100 due to reductions in telephone,
contractual services and gasoline.
222
Página 229
Life Safety
Personnel Costs 231,600 5%
Materials & Supplies 300 96%
Administrative Expenditures 253,300 0%
Overall Operating Expenses 485,200 1%
Capital Outlay 29,500 47%
Total Expenditures 514,700 4%
Highlights:
Personnel Costs increased $11,500 due to wage and benefit increases.
Materials & Supplies have decreased $6,600 due to a reduction uniforms, program
expense, computer hardware, security and safety materials, and small tools.
Administrative Expenses remain constant with small decreases in telephone and
gasoline and small increase in radio repairs and maintenance.
Capital Outlay includes $29,500 for 1 vehicle.
223
Página 230
Economic Development
Personnel Costs 214,400 2%
Materials & Supplies 900 40%
Administrative Expenditures 22,400 13%
Overall Operating Expenses 237,700 0%
Highlights:
Personnel Costs increased overall by $3,600 due to wage and benefit cost increases.
Materials and Supplies had small decreases in printing and duplicating, photographic
and office supplies.
Administrative Expenses had a net decrease of $3,300 with reductions in economic
development, telephone and gasoline offset by small increase in subscriptions and
dues.
224
Página 231
Public Works
225
Página 232
Public Works Admin
Personnel Costs 661,600 11%
Materials & Supplies 6,900 38%
Administrative Expenditures 11,500 47%
Overall Operating Expenses 680,000 8%
Highlights:
Personnel Costs increased by $67,600 due to wage and benefit increases,
particularly health insurance and pension cost. The PW Operations Manager was
budgeted for 10 months in the prior year. This position is currently being recruited.
Materials & Supplies decreased $4,300 in computer hardware offset by a small
increase in computer software.
Administrative Expenditures decreased by $10,200. Areas significantly decreased
are contractual services for $7,000 and subscription and dues for $2,600. Other
small decreases in training/travel and gasoline.
226
Página 233
Facilities Management
Personnel Costs 459,500 13%
Materials & Supplies 24,400 11%
Administrative Expenditures 123,200 14%
Overall Operating Expenses 607,100 14%
Capital Outlay 27,700 0%
Total Expenditures 634,800 10%
Highlights:
Personnel Costs decreased $71,700 due to wage and benefit cost decreases as a result of
outsourcing janitors, net of full-time staff increases.
Materials and Supplies decreased $3,100 due to small tools, computer hardware, uniforms and
city building maintenance supplies.
Administrative Expenditures decreased $20,600 due to contractual services, gasoline and radio
repairs and maintenance. Janitors are charged to the Fund in which they work now. i.e. Electric
Fund is charged for the Electric Administrative offices.
Capital Outlay includes $27,700 for 1 vehicle.
227
Página 234
Fleet Maintenance
Personnel Costs 466,200 3%
Materials & Supplies 304,100 1%
Administrative Expenditures 6,000 9%
Overall Operating Expenses 776,300 1%
Capital Outlay 31,000 63%
Total Expenditures 807,300 5%
Highlights:
Personnel Costs increased due to wages and benefits.
Materials and Supplies decreased $3,000 due to a reduction in small tools and city
building maintenance supplies.
Administrative Expenses decreased $600 in training/travel and radio repairs and
maintenance.
Capital Outlay includes $31,000 for 1 vehicle.
228
Página 235
Grounds
Personnel Costs 953,400 3%
Materials & Supplies 53,200 2%
Administrative Expenditures 194,700 16%
Overall Operating Expenses 1,201,300 1%
Capital Outlay 58,200 71%
Total Expenditures 1,259,500 11%
Highlights:
Personnel Costs increased $29,900 as a result of wages and benefits, particularly health
insurance and pension cost.
Materials & Supplies had various small decreases for $1,300 offset by a small increase of
$200 in uniforms.
Administrative Expenditures decreased by $37,800 due to reductions in contractual
services, gasoline, electricity, heating oil/gas and radio repairs and maintenance.
Capital expenses includes 1 new vehicle and a utility tractor.
229
Página 236
Sanitation
Personnel Costs 732,900 7%
Materials & Supplies 24,700 1%
Administrative Expenditures 1,275,200 12%
Overall Operating Expenses 2,032,800 6%
Capital Outlay 261,500 42%
Total Expenditures 2,294,300 12%
Highlights:
Personnel Costs increased $49,200 due to wages and benefit increases, mainly health
insurance and pension cost.
Materials & Supplies had a small increase in uniforms offset by small decreases in small
tools and computer hardware.
Administrative Expenses decreased $174,000 mainly due to a reduction in DSWA cost per
ton in contractual services of $148,800, decrease in gasoline of $25,000 and small
decrease in radio repairs and maintenance.
Capital outlay is related to the replacement of an automated trash truck for $261,500.
230
Página 237
Streets
Personnel Costs 589,000 16%
Materials & Supplies 247,000 171%
Administrative Expenditures 327,500 343%
Overall Operating Expenses 1,163,500 72%
Capital Outlay 1,026,000 28%
Total Expenditures 2,189,500 4%
Highlights:
Personnel costs increased $79,700 due to wages and benefits, mainly health insurance and
pension cost.
Materials and supplies have increased by $155,800 mostly in program expenses related to MS4
program of $151,900. Other small increases in sand and salt and computer hardware offset by a
reduction in uniforms and security and safety materials.
Administrative expenses increased $263,700 in contractual services related to the outsourcing of
ditch and garrison tract maintenance offset by decreases in gasoline of $8,000, maintenance
equipment and repairs of $2,000 and small reduction in radio repairs and maintenance.
Capital Outlay includes $900,000 for street and alley program and $126,000 for Silver Lake
dam improvements.
231
Página 238
Public Works - Engineering
Personnel Costs 203,600 16%
Materials & Supplies 900 55%
Administrative Expenditures 2,500 38%
Overall Operating Expenses 207,000 14%
Highlights:
Personnel costs increased $28,200 due to having a full year budget for all three
positions versus 10 months in the prior year.
Materials and supplies have decreased due to reduction of computer hardware of
$1,300 offset by a small increase in computer software.
Administrative expenditures decreased $1,500 in contractual services.
232
Página 239
FY 2017 Annual Operating Budget —Dover, Delaware
Mayor
Fiscal Year 2017 Organizational Chart
Citiz ens of Do ver
Mayor
Police Economic
Department Development
233
Página 240
FY 2017 DRAFT ANNUAL OPERATING BUDGET - DOVER, DELAWARE
MAYOR
110-3200-519
2012-2013 2013-2014 2014-2015 2015-2016 2015-2016 2016-2017 %
ACCT DESCRIPTION ACTUAL ACTUAL ACTUAL BUDGET REVISED PROPOSED CHANGE
10-11 SALARIES $ 45,000 $ 39,621 $ 44,965 $ 45,000 $ 45,000 $ 45,000 0%
10-14 FICA TAXES 3,437 2,998 3,260 3,400 3,400 3,400 0%
10-15 HEALTH INSURANCE 6,768 5,634 6,220 7,900 7,900 8,500 8%
10-16 L I D INSURANCE 340 283 340 300 300 300 0%
10-17 WORKERS COMPENSATION 236 82 94 100 100 100 0%
PERSONNEL COSTS 55,780 48,618 54,879 56,700 56,700 57,300 1%
20-21 FURNITURE/FIXTURES - 1,108 - - - - 0%
20-22 OFFICE SUPPLIES 73 170 - 100 100 100 0%
20-23 PRINTING AND DUPLICATING 86 334 157 200 200 200 0%
MATERIALS & SUPPLIES 158 1,612 157 300 300 300 0%
30-21 TELEPHONE/FAX 1,261 1,110 387 500 500 500 0%
30-25 ADVERTISEMENT 994 672 806 1,500 1,500 1,500 0%
30-27 SUBSCRIPTIONS AND DUES 5,449 5,293 657 3,500 3,500 3,500 0%
30-28 TRAINING/CONF/FOOD/TRAVEL 5,900 5,091 - - - - 0%
30-35 COMMUNITY RELATIONS EXP 5,737 7,244 14,796 8,200 8,200 5,500 -33%
30-37 OTHER EXPENSES 3,938 4,567 6,179 5,000 5,000 5,000 0%
30-62 GASOLINE 1,606 1,055 - 300 300 300 0%
30-63 AUTO REPAIRS/MAINTENANCE 170 120 - 100 100 100 0%
30-67 RADIO REPAIRS/MAINTENANCE 80 - - - - - 0%
ADMINISTRATIVE EXPENDITURES 25,135 25,150 22,825 19,100 19,100 16,400 -14%
OPERATING EXPENDITURES 81,073 75,380 77,861 76,100 76,100 74,000 -3%
40-25 OTHER EQUIP - PURCHASE 33,000 - - - - - 0%
CAPITAL OUTLAY 33,000 - - - - - 0%
TOTAL EXPENDITURES $ 114,073 $ 75,380 $ 77,861 $ 76,100 $ 76,100 $ 74,000 -3%
OPERATING BUDGET STATS $ 81,073 $ 75,380 $ 77,861 $ 76,100 $ 76,100 $ 74,000
ACTUAL % OF OPER BUDGET 102% 93% 103% 98% 100% 97%
BUDGET % CHANGE 2% -7% 3% -2% 0% -3%
REVENUES
GENERAL FUND $ 81,073 $ 75,380 $ 77,861 $ 76,100 $ 76,100 $ 74,000
GOV. CAPITAL PROJECT FUND 33,000 - - - - -
PERSONNEL
BUDGETED FULL-TIME POSITIONS 1.0 1.0 1.0 1.0 1.0 1.0
234
Página 241
FY 2017 DRAFT ANNUAL OPERATING BUDGET - DOVER, DELAWARE
ECONOMIC DEVELOPMENT
110-1600-535
2012-2013 2013-2014 2014-2015 2015-2016 2015-2016 2016-2017 %
ACCT DESCRIPTION ACTUAL ACTUAL ACTUAL BUDGET REVISED PROPOSED CHANGE
10-11 SALARIES $ 135,056 $ 137,417 $ 145,872 $ 147,500 $ 149,500 $ 151,700 3%
10-14 FICA TAXES 9,916 10,013 10,702 11,300 11,300 11,600 3%
10-15 HEALTH INSURANCE 20,353 20,332 20,381 24,000 24,000 25,800 8%
10-16 L I D INSURANCE 1,020 1,029 937 1,000 1,000 1,000 0%
10-17 WORKERS COMPENSATION 900 472 523 500 500 500 0%
10-19 PENSION 8,103 8,176 8,656 8,900 8,900 9,100 2%
10-20 OPEB 11,747 14,742 16,910 17,600 17,600 14,700 -16%
PERSONNEL COSTS 187,096 192,180 203,981 210,800 212,800 214,400 2%
20-22 OFFICE SUPPLIES 386 103 108 300 300 200 -33%
20-23 PRINTING AND DUPLICATING 520 256 689 1,000 1,000 700 -30%
20-24 PHOTOGRAPHIC - - - 200 200 - -100%
20-33 SMALL TOOLS - - 51 - - - 0%
20-38 COMPUTER HARDWARE 1,290 2,646 495 - - - 0%
MATERIALS & SUPPLIES 2,195 3,005 1,343 1,500 1,500 900 -40%
30-21 TELEPHONE/FAX 3,338 1,640 1,114 2,400 1,400 1,500 -38%
30-25 ADVERTISEMENT 1,250 1,250 1,250 1,300 1,300 1,300 0%
30-27 SUBSCRIPTIONS AND DUES - - - 100 100 300 200%
30-28 TRAINING/CONF/FOOD/TRAVEL 260 814 120 800 800 800 0%
30-31 CONTRACTUAL SERVICES 10,368 - - - 6,000 - 0%
30-62 GASOLINE 61 - 0.10 100 100 - -100%
30-91 ECONOMIC DEVELOPMENT 15,379 15,000 18,500 21,000 21,000 18,500 -12%
ADMINISTRATIVE EXPENDITURES 30,656 18,704 20,984 25,700 30,700 22,400 -13%
OPERATING EXPENDITURES 219,947 213,889 226,308 238,000 245,000 237,700 0%
TOTAL EXPENDITURES $ 219,947 $ 213,889 $ 226,308 $ 238,000 $ 245,000 $ 237,700 0%
OPERATING BUDGET STATS $ 219,947 $ 213,889 $ 226,308 $ 238,000 $ 245,000 $ 237,700
ACTUAL % OF OPER BUDGET 100% 100% 100% 100% 100% 100%
BUDGET % CHANGE 1% -3% 6% 5% 3% -3%
REVENUES
GENERAL FUND $ 219,947 $ 213,889 $ 226,308 $ 238,000 $ 245,000 $ 237,700
PERSONNEL
BUDGETED FULL-TIME POSITIONS 3.0 3.0 3.0 3.0 3.0 3.0
235
Página 242
FY 2017 Annual Operating Budget—Dover, Delaware
City Council
Fiscal Year 2017 Organizational Chart
CITIZENS OF DOVER
MAYOR AND COUNCIL
At-Large
Timothy A. Slavin
1st District 2nd District
Councilman Councilman
James E. Hosfelt, Jr. William F. Hare
Councilman Councilman
James L. Hutchison, Sr. Brian E. Lewis
3rd District 4th District
Councilman Councilman
Scott W. Cole David L. Anderson
Councilman Councilman
Fred A. Neil Roy Sudler, Jr.
236
Página 243
FY 2017 DRAFT ANNUAL OPERATING BUDGET - DOVER, DELAWARE
CITY COUNCIL
110-1200-512
2012-2013 2013-2014 2014-2015 2015-2016 2015-2016 2016-2017 %
ACCT DESCRIPTION ACTUAL ACTUAL ACTUAL BUDGET REVISED PROPOSED CHANGE
10-13 TEMPORARY HELP $ 73,774 $ 76,566 $ 71,315 $ 84,300 $ 79,300 $ 84,300 0%
10-14 FICA TAXES 5,628 5,857 5,456 6,400 6,400 6,400 0%
10-17 WORKERS COMPENSATION 382 157 151 300 300 300 0%
PERSONNEL COSTS 79,785 82,581 76,922 91,000 86,000 91,000 0%
20-22 OFFICE SUPPLIES 339 21 38 - - - 0%
20-23 PRINTING AND DUPLICATING 260 - 269 300 300 300 0%
MATERIALS & SUPPLIES 599 21 307 300 300 300 0%
30-21 TELEPHONE/FAX 169 173 178 200 200 200 0%
30-27 SUBSCRIPTIONS AND DUES 11,098 11,153 11,203 11,500 11,500 11,500 0%
30-28 TRAINING/CONF/FOOD/TRAVEL 5,037 3,027 - 9,600 9,600 9,600 0%
30-35 COMMUNITY RELATIONS EXP 4,393 2,118 4,261 3,500 4,000 3,500 0%
30-37 OTHER EXPENSES - - - - - 25,000 0%
30-92 HRC-OFFICE SUPPLIES 625 757 - 2,000 2,000 3,000 50%
ADMINISTRATIVE EXPENDITURES 21,323 17,228 15,642 26,800 27,300 52,800 97%
OPERATING EXPENDITURES 101,707 99,829 92,870 118,100 113,600 144,100 22%
TOTAL EXPENDITURES $ 101,707 $ 99,829 $ 92,870 $ 118,100 $ 113,600 $ 144,100 22%
OPERATING BUDGET STATS $ 101,707 $ 99,829 $ 92,870 $ 118,100 $ 113,600 $ 144,100
ACTUAL % OF OPER BUDGET 100% 100% 100% 100% 100% 100%
BUDGET % CHANGE -4% -2% -7% 27% -4% 27%
REVENUES
GENERAL FUND $ 101,707 $ 99,829 $ 92,870 $ 118,100 $ 113,600 $ 144,100
PERSONNEL
PP/COUNCIL 9.0 9.0 9.0 9.0 9.0 9.0
PP/TEMP COMMITTEES 8.0 8.0 8.0 8.0 8.0 8.0
237
Página 244
FY 2017 ANNUAL OPERATING BUDGET – DOVER, DELAWARE
City Manager
Fiscal Year 2017 Organization Chart
CITY COUNCIL
CITY MANAGER*
1
Assistant City Manager
1 HUMAN RESOURCES
INFORMATION
CUSTOMER SERVICE
TECHNOLOGY LIBRARY
Public Affairs & Emergency
Management Coordinator PUBLIC WORKS
1
Administrative Assistant
ELECTRIC
1
*Appointed by Council
238
Página 245
FY 2017 DRAFT ANNUAL OPERATING BUDGET - DOVER, DELAWARE
CITY MANAGER
110-2100-515
2012-2013 2013-2014 2014-2015 2015-2016 2015-2016 2016-2017 %
ACCT DESCRIPTION ACTUAL ACTUAL ACTUAL BUDGET REVISED PROPOSED CHANGE
10-11 SALARIES $ 214,206 $ 217,374 $ 278,681 $ 345,100 $ 356,100 $ 351,500 2%
10-12 OVERTIME 1,737 2,513 517 2,000 2,000 2,000 0%
10-13 TEMPORARY - - 3,606 11,500 11,500 11,500 0%
10-14 FICA TAXES 15,291 15,545 20,483 27,400 27,900 27,900 2%
10-15 HEALTH INSURANCE 28,853 30,983 34,572 46,700 49,200 52,500 12%
10-16 L I D INSURANCE 1,331 1,362 1,584 1,900 1,900 2,000 5%
10-17 WORKERS COMPENSATION 1,131 453 594 1,600 1,600 1,700 6%
10-19 PENSION 12,067 12,481 16,103 20,200 20,200 20,700 2%
10-20 OPEB 17,509 22,310 31,719 40,100 40,100 33,500 -16%
PERSONNEL COSTS 292,123 303,022 387,858 496,500 510,500 503,300 1%
20-21 FURNITURE/FIXTURES - - 668 - - - 0%
20-22 OFFICE SUPPLIES 716 628 623 700 700 700 0%
20-23 PRINTING AND DUPLICATING 2,664 3,231 3,168 3,500 3,500 3,300 -6%
20-26 PROGRAM EXPENSES/SUPPLIES 2,236 1,800 1,800 1,800 1,800 1,800 0%
20-38 COMPUTER HARDWARE 1,893 1,402 - - - 2,600 0%
MATERIALS & SUPPLIES 7,509 7,062 6,259 6,000 6,000 8,400 40%
30-21 TELEPHONE/FAX 597 610 628 1,000 1,000 800 -20%
30-27 SUBSCRIPTIONS AND DUES 1,571 3,174 4,056 4,500 4,500 4,500 0%
30-28 TRAINING/CONF/FOOD/TRAVEL 622 2,444 3,316 2,000 3,000 2,200 10%
30-31 CONTRACTUAL SERVICES - - - 100,000.0 95,000 5,000 -95%
30-32 LEGAL EXPENSES 190,619 216,264 151,419 140,000 287,600 159,000 14%
30-35 COMMUNITY RELATIONS EXP 4,218 680 24 200 1,600 200 0%
30-61 OFF EQUIP/REPAIRS & MAINT - 80 - - - - 0%
30-62 GASOLINE 22 - - 100 100 100 0%
ADMINISTRATIVE EXPENDITURES 197,649 223,252 159,442 247,800 392,800 171,800 -31%
OPERATING EXPENDITURES 497,281 533,336 553,558 750,300 909,300 683,500 -9%
40-22 AUTOMOBILES - PURCHASE - - - 24,700 24,700 - -100%
CAPITAL OUTLAY - - - 24,700 24,700 - -100%
TOTAL EXPENDITURES $ 497,281 $ 533,336 $ 553,558 $ 775,000 $ 934,000 $ 683,500 -12%
OPERATING BUDGET STATS $ 497,281 $ 533,336 $ 553,558 $ 750,300 $ 909,300 $ 683,500
ACTUAL % OF OPER BUDGET 100% 100% 100% 100% 100% 100%
BUDGET % OF CHANGE -22% 7% 4% 36% 21% -25%
REVENUES
GENERAL FUND $ 497,281 $ 533,336 $ 553,558 $ 750,300 $ 909,300 $ 683,500
GOV. CAPITAL PROJECT FUND - - - 24,700 24,700 -
PERSONNEL
BUDGETED FULL-TIME POSITIONS 3.0 3.0 4.0 4.0 4.0 4.0
BUDGETED PART-TIME POSITIONS 4.0 4.0 4.0
239
Página 246
FY 2017 DRAFT ANNUAL OPERATING BUDGET –
DOVER, DELAWARE
City Clerk
Fiscal Year 2017 Organizational Chart
CITY
COUNCIL
CITY CLERK
CITY CLERK, DIRECTOR OF COUNCIL AFFAIRS AND
CONSTITUENT SERVICES/ASSISTANT TREASURER*
1
ASSISTANT CITY CLERK, DEPUTY
DIRECTOR OF COUNCIL AFFAIRS &
CONSTITUENT SERVICES/ASSISTANT
TREASURER*
1
ASSISTANT TO THE DIRECTOR OF
COUNCIL AFFAIRS & CONSTITUENT
SERVICES
1
ADMINISTRATIVE ASSISTANT
1
*Appointed by Council
240
Página 247
FY 2017 DRAFT ANNUAL OPERATING BUDGET - DOVER, DELAWARE
CITY CLERK
110-1100-511
2012-2013 2013-2014 2014-2015 2015-2016 2015-2016 2016-2017 %
ACCT DESCRIPTION ACTUAL ACTUAL ACTUAL BUDGET REVISED PROPOSED CHANGE
10-11 SALARIES $ 204,935 $ 218,533 $ 225,061 $ 226,400 $ 225,500 $ 228,300 1%
10-14 FICA TAXES 15,125 16,189 16,711 17,300 17,600 17,500 1%
10-15 HEALTH INSURANCE 37,907 34,888 32,897 38,700 38,700 42,800 11%
10-16 L I D INSURANCE 1,423 1,523 1,554 1,600 1,600 1,600 0%
10-17 WORKERS COMPENSATION 1,078 451 472 700 700 700 0%
10-19 PENSION 7,866 45,634 43,297 43,300 43,300 59,800 38%
10-20 OPEB 17,624 23,094 26,378 26,700 26,700 22,100 -17%
PERSONNEL COSTS 285,958 340,312 346,369 354,700 354,100 372,800 5%
20-22 OFFICE SUPPLIES 1,374 141 1,338 1,400 1,400 1,400 0%
20-23 PRINTING AND DUPLICATING 2,675 2,514 2,214 3,000 3,000 2,700 -10%
20-37 COMPUTER SOFTWARE 445 727 50 100 500 500 400%
20-38 COMPUTER HARDWARE - 3,246 - - - 4,600 0%
MATERIALS & SUPPLIES 4,494 6,629 3,603 4,500 4,900 9,200 104%
30-21 TELEPHONE/FAX 423 486 478 500 500 500 0%
30-25 ADVERTISEMENT 1,036 826 641 1,000 1,000 1,000 0%
30-27 SUBSCRIPTIONS AND DUES 676 694 805 900 900 700 -22%
30-28 TRAINING/CONF/FOOD/TRAVEL 6,245 383 6,873 5,100 5,100 2,900 -43%
30-31 CONTRACTUAL SERVICES 13,024 12,989 11,659 15,500 15,500 15,000 -3%
30-34 ELECTION RELATED EXPENSES 3,611 5,626 7,137 200 200 9,200 4500%
30-61 OFF EQUIP/REPAIRS & MAINT 45 - - 1,000 600 1,000 0%
ADMINISTRATIVE EXPENDITURES 25,059 21,004 27,593 24,200 23,800 30,300 25%
OPERATING EXPENDITURES 315,512 367,944 377,564 383,400 382,800 412,300 8%
TOTAL EXPENDITURES $ 315,512 $ 367,944 $ 377,564 $ 383,400 $ 382,800 $ 412,300 8%
OPERATING BUDGET STATS $ 315,512 $ 367,944 $ 377,564 $ 383,400 $ 382,800 $ 412,300
ACTUAL % OF OPER BUDGET 100% 100% 100% 100% 100% 100%
BUDGET % CHANGE 6% 17% 3% 2% 0% 8%
REVENUES
GENERAL FUND $ 315,512 $ 367,944 $ 377,564 $ 383,400 $ 382,800 $ 412,300
PERSONNEL
BUDGETED FULL-TIME POSITIONS 4.0 4.0 4.0 4.0 4.0 4.0
241
Página 248
FY 2017 ANNUAL OPERATING BUDGET – DOVER, DELAWARE
Customer Service
Fiscal Year 2017 Organization Chart
CITY MANAGER
ASSISTANT CITY
MANAGER
CUSTOMER SERVICE
Customer Service Manager
1
Office Assistant
1
BILLING / COLLECTIONS CUSTOMER SERVICES
Account Clerk III Customer Services Supervisor
1 1
Account Clerk II Account Clerk II
2 4
Account Clerk II – Part-time Account Clerk II – Part-time
1 3
CASHIERS METER READING
Account Clerk III Field Service Representative III
1 1
Account Clerk II Field Service Representative II
2 3
242
Página 249
FY 2017 DRAFT ANNUAL OPERATING BUDGET - DOVER, DELAWARE
CUSTOMER SERVICES
110-2900-529
2012-2013 2013-2014 2014-2015 2015-2016 2015-2016 2016-2017 %
ACCT DESCRIPTION ACTUAL ACTUAL ACTUAL BUDGET REVISED PROPOSED CHANGE
10-11 SALARIES $ 523,885 $ 556,289 $ 549,628 $ 556,600 $ 551,000 $ 556,100 0%
10-12 OVERTIME - - - - 200 - 0%
10-13 TEMPORARY HELP - 11,458 28,982 85,500 65,500 82,700 -3%
10-14 FICA TAXES 39,189 41,914 42,912 49,100 49,500 48,800 -1%
10-15 HEALTH INSURANCE 109,714 108,452 102,609 144,700 129,700 133,700 -8%
10-16 L I D INSURANCE 3,166 3,411 3,230 3,200 3,200 3,200 0%
10-17 WORKERS COMPENSATION 2,744 1,162 1,211 2,100 2,100 2,100 0%
10-18 EDUCATIONAL ASSISTANCE - 1,500 1,640 - - - 0%
10-19 PENSION 25,434 152,791 133,010 145,000 140,000 196,700 36%
10-20 OPEB 44,565 58,476 63,280 66,200 66,200 53,900 -19%
PERSONNEL COSTS 748,697 935,454 926,502 1,052,400 1,007,400 1,077,200 2%
20-21 FURNITURE/FIXTURES - - 365 400 400 400 0%
20-22 OFFICE SUPPLIES 13,357 12,211 12,690 13,000 13,000 13,600 5%
20-23 PRINTING AND DUPLICATING 16,607 14,497 14,152 15,000 15,000 15,000 0%
20-37 COMPUTER SOFTWARE - - 199 300 300 300 0%
20-38 COMPUTER HARDWARE 3,349 2,389 3,020 12,700 12,700 3,300 -74%
MATERIALS & SUPPLIES 33,312 29,096 30,426 41,400 41,400 32,600 -21%
30-21 TELEPHONE/FAX 3,998 4,289 4,444 4,700 4,700 5,100 9%
30-28 TRAINING/CONF/FOOD/TRAVEL - - - 1,000 1,000 1,000 0%
30-31 CONTRACTUAL SERVICES 63,060 217,564 72,537 4,500 16,400 12,500 178%
30-61 OFF EQUIP/REPAIRS & MAINT 11,589 15,573 11,680 16,100 11,100 15,400 -4%
ADMINISTRATIVE EXPENDITURES 78,647 237,426 88,660 26,300 33,200 34,000 29%
OPERATING EXPENDITURES 860,657 1,201,976 1,045,588 1,120,100 1,082,000 1,143,800 2%
TOTAL EXPENDITURES $ 860,657 $ 1,201,976 $ 1,045,588 $ 1,120,100 $ 1,082,000 $ 1,143,800 2%
OPERATING BUDGET STATS $ 860,657 $ 1,201,976 $ 1,045,588 $ 1,120,100 $ 1,082,000 $ 1,143,800
ACTUAL % OF OPER BUDGET 100% 100% 100% 100% 100% 100%
BUDGET % CHANGE -4% 40% -13% 7% -3% 6%
REVENUES
GENERAL FUND $ 860,657 $ 1,201,976 $ 1,045,588 $ 1,120,100 $ 1,082,000 $ 1,143,800
PERSONNEL
BUDGETED FULL-TIME POSITIONS 14.0 14.0 14.0 14.0 14.0 13.0
BUDGETED PART-TIME POSITIONS - - 1.0 4.0 4.0 4.0
243
Página 250
FY 2017 Annual Operating Budget—Dover, Delaware
Finance
Fiscal Year 2017 Organizational Chart
CITY COUNCIL
Controller/Treasurer*
1
PROCUREMENT/
FINANCE
INVENTORY
Assistant Controller/Treasurer Contract & Procurement Manager
1 1
Payroll Specialist Storekeeper/Buyer II
1 2
Account Clerk II
1 Mail Clerk
1
Financial Reporting & Accounting
Manager
1
Accountant II
2
Administrative Assistant
1
* Appointed by Council
244
Página 251
FY 2017 DRAFT ANNUAL OPERATING BUDGET - DOVER, DELAWARE
FINANCE
110-2300-517
2012-2013 2013-2014 2014-2015 2015-2016 2015-2016 2016-2017 %
ACCT DESCRIPTION ACTUAL ACTUAL ACTUAL BUDGET REVISED PROPOSED CHANGE
10-11 SALARIES $ 481,755 $ 453,720 $ 496,728 $ 507,200 $ 520,400 $ 515,800 2%
10-12 OVERTIME - 104 37 - - - 0%
10-13 TEMPORARY HELP - - - 17,700 - - -100%
10-14 FICA TAXES 34,623 32,288 35,548 38,800 39,400 39,400 2%
10-15 HEALTH INSURANCE 80,092 80,052 85,752 98,200 98,200 104,000 6%
10-16 L I D INSURANCE 2,904 2,627 2,675 2,800 2,800 2,900 4%
10-17 WORKERS COMPENSATION 2,523 924 1,002 1,600 1,700 1,700 6%
10-18 EDUCATIONAL ASSISTANCE - - 3,203 - 3,500 - 0%
10-19 PENSION 23,832 91,970 70,893 72,000 74,500 97,800 36%
10-20 OPEB 41,576 46,797 57,886 59,700 60,700 50,000 -16%
PERSONNEL COSTS 667,304 708,481 753,725 798,000 801,200 811,600 2%
20-21 FURNITURE/FIXTURES - 480 - - - - 0%
20-22 OFFICE SUPPLIES 720 751 669 800 800 800 0%
20-23 PRINTING AND DUPLICATING 3,342 1,544 1,902 3,200 3,200 1,900 -41%
20-38 COMPUTER HARDWARE 4,591 7,138 - 1,200 1,200 - -100%
MATERIALS & SUPPLIES 8,653 9,913 2,571 5,200 5,200 2,700 -48%
30-21 TELEPHONE/FAX 1,261 1,340 1,448 1,400 1,400 1,400 0%
30-25 ADVERTISEMENT 203 214 186 200 200 200 0%
30-27 SUBSCRIPTIONS AND DUES 1,407 1,311 1,291 1,200 1,200 1,200 0%
30-28 TRAINING/CONF/FOOD/TRAVEL 7,820 3,645 5,842 3,000 3,000 2,200 -27%
30-31 CONTRACTUAL SERVICES 163,134 182,212 179,155 168,300 176,800 188,100 12%
30-37 OTHER EXPENSES 222 - - - - - 0%
30-61 OFF EQUIP/REPAIRS & MAINT 4,305 3,608 2,400 1,200 1,200 1,200 0%
ADMINISTRATIVE EXPENDITURES 178,353 192,330 190,322 175,300 183,800 194,300 11%
OPERATING EXPENDITURES 854,310 910,724 946,618 978,500 990,200 1,008,600 3%
TOTAL EXPENDITURES $ 854,310 $ 910,724 $ 946,618 $ 978,500 $ 990,200 $ 1,008,600 3%
OPERATING BUDGET STATS $ 854,310 $ 910,724 $ 946,618 $ 978,500 $ 990,200 $ 1,008,600
ACTUAL % OF OPER BUDGET 100% 100% 100% 100% 100% 100%
BUDGET % CHANGE 8% 7% 4% 3% 1% 2%
REVENUES
GENERAL FUND $ 854,310 $ 910,724 $ 946,618 $ 978,500 $ 990,200 $ 1,008,600
BOND PROCEEDS - - - - - 1,000,000
PERSONNEL
BUDGETED FULL-TIME POSITIONS 8.0 8.0 8.0 8.0 8.0 8.0
BUDGETED PART-TIME POSITIONS - - - 1.0 1.0 -
245
Página 252
FY 2017 DRAFT ANNUAL OPERATING BUDGET - DOVER, DELAWARE
PROCUREMENT & INVENTORY
110-2700-571
2012-2013 2013-2014 2014-2015 2015-2016 2015-2016 2016-2017 %
ACCT DESCRIPTION ACTUAL ACTUAL ACTUAL BUDGET REVISED PROPOSED CHANGE
10-11 SALARIES $ 185,353 $ 158,271 $ 156,237 $ 159,200 $ 163,300 $ 165,800 4%
10-12 OVERTIME 1,749 2,132 756 1,000 1,000 1,000 0%
10-13 TEMPORARY HELP - - 11,134 20,300 11,800 21,400 5%
10-14 FICA TAXES 14,616 12,234 12,670 13,800 13,800 14,400 4%
10-15 HEALTH INSURANCE 20,464 13,552 12,471 14,600 14,600 15,700 8%
10-16 L I D INSURANCE 1,054 916 900 1,000 1,000 1,000 0%
10-17 WORKERS COMPENSATION 5,281 3,186 3,082 4,700 4,700 6,100 30%
10-18 EDUCATIONAL ASSISTANCE - 5,016 8,209 - 4,800 - 0%
10-19 PENSION 9,439 52,702 49,346 50,400 51,500 72,500 44%
10-20 OPEB 15,253 16,697 18,570 18,900 19,300 16,100 -15%
PERSONNEL COSTS 253,208 264,706 273,375 283,900 285,800 314,000 11%
20-21 FURNITURE/FIXTURES - - - - - 300 0%
20-22 OFFICE SUPPLIES 1,634 379 236 600 600 400 -33%
20-23 PRINTING AND DUPLICATING 4,116 3,799 3,612 3,600 3,600 3,600 0%
20-25 CUSTODIAL 951 992 519 - - - 0%
20-26 PROGRAM EXPENSES/SUPPLIES 584 864 581 1,500 1,500 1,000 -33%
20-29 UNIFORMS/UNIFORM ALLOW 828 663 725 900 900 900 0%
20-32 SECURITY/SAFETY MATERIALS 384 263 36 500 500 500 0%
20-37 COMPUTER SOFTWARE - - 50 200 200 200 0%
20-38 COMPUTER HARDWARE 2,370 - 94 2,200 2,200 1,800 -18%
20-46 CITY BLDG MAINT SUPPLIES 3,482 2,790 2,348 2,500 2,500 2,200 -12%
20-58 WATER/SEWER 4,753 3,284 2,574 3,000 3,000 3,000 0%
MATERIALS & SUPPLIES 19,102 13,033 10,775 15,000 15,000 13,900 -7%
30-21 TELEPHONE/FAX 1,439 1,418 1,366 1,400 1,400 1,400 0%
30-22 POSTAGE 143,685 127,822 129,272 150,000 150,000 150,000 0%
30-23 ELECTRICITY 71,795 70,802 70,249 68,000 64,000 65,000 -4%
30-24 HEATING OIL/GAS 216 - - 300 300 100 -67%
30-25 ADVERTISEMENT 1,379 2,228 1,951 2,500 2,500 2,500 0%
30-27 SUBSCRIPTIONS AND DUES 520 545 440 600 600 600 0%
30-28 TRAINING/CONF/FOOD/TRAVEL 1,248 60 - - - 2,700 0%
30-31 CONTRACTUAL SERVICES 16,288 17,831 18,801 19,400 19,400 24,500 26%
30-43 ENVIRONMENTAL EXPENSES 3,574 4,508 4,128 3,500 3,500 3,500 0%
30-61 OFF EQUIP/REPAIRS & MAINT 8,573 9,904 9,882 11,000 11,000 5,000 -55%
30-62 GASOLINE 2,249 1,732 1,399 1,800 1,800 1,500 -17%
30-66 OTHER EQUIP REPAIRS/MAINT 1,452 3,057 6,583 2,600 13,800 200 -92%
30-67 RADIO REPAIRS/MAINTENANCE 1,508 165 91 200 200 200 0%
ADMINISTRATIVE EXPENDITURES 253,925 240,070 244,161 261,300 268,500 257,200 -2%
OPERATING EXPENDITURES 526,235 517,809 528,311 560,200 569,300 585,100 4%
40-25 OTHER EQUIP - PURCHASE - - 49,672 - - - 0%
CAPITAL OUTLAY - - 49,672 - - - 0%
TOTAL EXPENDITURES $ 526,235 $ 517,809 $ 577,983 $ 560,200 $ 569,300 $ 585,100 4%
OPERATING BUDGET STATS $ 526,235 $ 517,809 $ 528,311 $ 560,200 $ 569,300 $ 585,100
ACTUAL % OF OPER BUDGET 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%
BUDGET % CHANGE -14% -2% 2% 6% 2% 3%
REVENUES
GENERAL FUND $ 526,235 $ 517,809 $ 528,311 $ 560,200 $ 569,300 $ 585,100
GOV. CAPITAL PROJECT FUND - - 49,672 - - -
PERSONNEL
BUDGETED FULL-TIME POSITIONS 4.0 4.0 3.0 3.0 3.0 3.0
BUDGETED PART-TIME POSITIONS - - 1.0 1.0 1.0 1.0
246
Página 253
FY 2017 Annual Operatin g Budget —Dover, Delaware
Dover Fire Department
Fiscal Year 2017 Organizational Chart
CITY COUNCIL
DOVER FIRE DEPARTMENT
Fire Chief
Deputy Fire Chief Fire Chief’s Assistant
1 (Volunteer) 1 P/T
Assistant Fire Chief Fire Dispatcher
4 (Volunteer) 5 F/T
Fire Line Captain
2 (Volunteer)
247
Página 254
FY 2017 DRAFT ANNUAL OPERATING BUDGET - DOVER, DELAWARE
FIRE DEPARTMENT
110-1400-514
2012-2013 2013-2014 2014-2015 2015-2016 2015-2016 2016-2017 %
ACCT DESCRIPTION ACTUAL ACTUAL ACTUAL BUDGET REVISED PROPOSED CHANGE
10-11 SALARIES $ 215,682 $ 196,608 $ 215,877 $ 229,900 $ 184,900 $ 208,100 -9%
10-12 OVERTIME 59,659 45,836 43,706 43,000 43,000 43,000 0%
10-13 TEMPORARY HELP 2,427 8,278 7,697 10,000 45,000 37,100 271%
10-14 FICA TAXES 20,868 18,603 19,890 21,600 21,600 22,000 2%
10-15 HEALTH INSURANCE 41,370 36,155 36,451 36,200 36,200 39,000 8%
10-16 L I D INSURANCE 1,229 1,089 1,199 1,100 1,100 1,100 0%
10-17 WORKERS COMPENSATION 1,461 518 557 900 900 900 0%
10-19 PENSION 11,802 61,862 47,308 43,400 43,400 66,400 53%
10-20 OPEB 18,217 20,444 25,234 23,700 23,700 20,100 -15%
PERSONNEL COSTS 372,717 389,394 397,918 409,800 399,800 437,700 7%
20-32 SECURITY/SAFETY MATERIALS 625 500 - 600 600 - -100%
MATERIALS & SUPPLIES 625 500 - 600 600 - -100%
30-28 TRAINING/CONF/FOOD/TRAVEL - - - 2,300 2,300 1,000 -57%
30-31 CONTRACTUAL SERVICES 281,300 281,300 282,740 332,700 332,700 283,000 -15%
ADMINISTRATIVE EXPENDITURES 281,300 281,300 282,740 335,000 335,000 284,000 -15%
OPERATING EXPENDITURES 654,642 671,194 680,658 745,400 735,400 721,700 -3%
40-25 OTHER EQUIP - PURCHASE - - 288,651 - 300,200 - 0%
40-31 CONSTRUCTION - PURCHASE 238,515 238,515 237,965 145,600 145,600 145,700 0%
CAPITAL OUTLAY 238,515 238,515 526,617 145,600 445,800 145,700 0%
TOTAL EXPENDITURES $ 893,156 $ 909,708 $ 1,207,275 $ 891,000 $ 1,181,200 $ 867,400 -3%
OPERATING BUDGET STATS $ 654,642 $ 671,194 $ 680,658 $ 745,400 $ 735,400 $ 721,700
ACTUAL % OF OPER BUDGET 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%
BUDGET % CHANGE -1% 3% 1% 10% -1% -2%
REVENUES
GENERAL FUND $ 654,642 $ 671,194 $ 680,658 $ 745,400 $ 735,400 $ 721,700
GOV. CAPITAL PROJECT FUND 238,515 238,515 526,617 145,600 445,800 145,700
PERSONNEL
BUDGETED FULL-TIME POSITIONS 6.0 6.0 6.0 5.0 5.0 5.0
BUDGETED PART-TIME POSITIONS 1.0 1.0 2.0 3.0 3.0 3.0
248
Página 255
FY 2017 ANNUAL OPERATING BUDGET— DOVER, DELAWARE
Human Resources
Fiscal Year 2017 Organizational Chart
CITY
MANAGER
HUMAN RESOURCES DIRECTOR
1
HUMAN RESOURCES COORDINATOR ADMINISTRATIVE ASSISTANT
1 1
249
Página 256
FY 2017 DRAFT ANNUAL OPERATING BUDGET - DOVER, DELAWARE
HUMAN RESOURCES
110-3100-518
2012-2013 2013-2014 2014-2015 2015-2016 2015-2016 2016-2017 %
ACCT DESCRIPTION ACTUAL ACTUAL ACTUAL BUDGET REVISED PROPOSED CHANGE
10-11 SALARIES $ 160,713 $ 180,183 $ 181,435 $ 184,300 $ 191,600 $ 187,100 2%
10-12 OVERTIME - - - - 200 - 0%
10-14 FICA TAXES 11,663 13,282 13,309 14,100 14,500 14,300 1%
10-15 HEALTH INSURANCE 29,829 30,157 25,166 36,800 34,500 39,600 8%
10-16 L I D INSURANCE 1,070 1,207 1,205 1,300 1,300 1,300 0%
10-17 WORKERS COMPENSATION 841 371 379 600 600 600 0%
10-18 EDUCATIONAL ASSISTANCE 2,045 4,624 3,297 - 1,200 - 0%
10-19 PENSION 6,660 61,954 57,914 59,400 59,400 84,100 42%
10-20 OPEB 13,801 18,807 21,124 21,700 21,700 18,100 -17%
PERSONNEL COSTS 226,622 310,585 303,828 318,200 325,000 345,100 8%
20-22 OFFICE SUPPLIES 645 685 795 800 800 800 0%
20-23 PRINTING AND DUPLICATING 3,098 2,865 3,892 3,000 3,000 3,000 0%
20-26 PROGRAM EXPENSES/SUPPLIES 548 205 145 800 800 400 -50%
20-28 MEDICAL SUP & PHYSICALS 12,723 16,201 10,731 17,000 17,000 14,000 -18%
20-31 BOOKS - - - 500 500 500 0%
20-32 SECURITY/SAFETY MATERIALS 504 544 505 500 500 300 -40%
20-37 COMPUTER SOFTWARE - - - - - 400 0%
20-38 COMPUTER HARDWARE 1,601 1,233 2,474 3,600 2,800 - -100%
20-48 PERSONNEL RELATED SUP 8,626 9,144 10,180 12,500 10,000 10,000 -20%
MATERIALS & SUPPLIES 27,745 30,877 28,721 38,700 35,400 29,400 -24%
30-21 TELEPHONE/FAX 388 432 445 500 500 500 0%
30-25 ADVERTISEMENT 4,746 10,073 14,457 4,500 4,500 5,600 24%
30-27 SUBSCRIPTIONS AND DUES 415 375 110 900 900 900 0%
30-28 TRAINING/CONF/FOOD/TRAVEL 1,450 2,701 3,550 2,900 3,700 2,500 -14%
30-29 CONSULTING FEES 3,478 60 - - - - 0%
30-31 CONTRACTUAL SERVICES 1,100 1,000 2,000 1,000 1,000 1,000 0%
30-39 IN-HOUSE TRAINING 373 295 660 700 700 1,500 114%
30-41 UNEMPLOYMENT COMP EXPENSE 27,804 6,666 6,437 16,500 5,000 6,000 -64%
30-61 OFF EQUIP/REPAIRS & MAINT 1,024 - 1,175 - - - 0%
ADMINISTRATIVE EXPENDITURES 40,778 21,602 28,834 27,000 16,300 18,000 -33%
OPERATING EXPENDITURES 295,146 363,064 361,384 383,900 376,700 392,500 2%
TOTAL EXPENDITURES $ 295,146 $ 363,064 $ 361,384 $ 383,900 $ 376,700 $ 392,500 2%
OPERATING BUDGET STATS $ 295,146 $ 363,064 $ 361,384 $ 383,900 $ 376,700 $ 392,500
ACTUAL % OF OPER BUDGET 100% 100% 100% 100% 100% 100%
BUDGET % CHANGE 12% 23% 0% 6% -2% 4%
REVENUES
GENERAL FUND $ 295,146 $ 363,064 $ 361,384 $ 383,900 $ 376,700 $ 392,500
PERSONNEL
BUDGETED FULL-TIME POSITIONS 3.0 3.0 3.0 3.0 3.0 3.0
250
Página 257
FY 2017 Annual Operating Budget—Dover, Delaware
Information Technology
Fiscal Year 2017 Organization Chart
City Manager
Assistant City Manager
Information Technology
Information Technology Director
1
AS400 System Administrator
1 (Vacant)
LAN Analyst
1
Senior Programmer Analyst
1
Administrative Assistant
1 (Vacant)
251
Página 258
FY 2017 DRAFT ANNUAL OPERATING BUDGET - DOVER, DELAWARE
INFORMATION TECHNOLOGY
110-2200-516
2012-2013 2013-2014 2014-2015 2015-2016 2015-2016 2016-2017 %
ACCT DESCRIPTION ACTUAL ACTUAL ACTUAL BUDGET REVISED PROPOSED CHANGE
10-11 SALARIES $ 252,748 $ 283,375 $ 306,042 $ 249,600 $ 216,300 $ 250,200 0%
10-13 TEMPORARY - - - 12,700 - 13,800 9%
10-14 FICA TAXES 18,829 20,913 22,969 20,100 16,700 20,200 0%
10-15 HEALTH INSURANCE 36,043 39,584 36,705 39,000 24,000 33,500 -14%
10-16 L I D INSURANCE 1,722 1,949 1,617 1,300 1,300 1,300 0%
10-17 WORKERS COMPENSATION 1,322 584 656 800 800 900 13%
10-18 EDUCATIONAL ASSISTANCE - - 4,118 - 5,300 - 0%
10-19 PENSION 12,231 107,175 99,893 86,800 67,800 97,200 12%
10-20 OPEB 21,602 29,869 32,456 29,500 24,500 24,300 -18%
PERSONNEL COSTS 344,497 483,450 504,455 439,800 356,700 441,400 0%
20-22 OFFICE SUPPLIES 1,075 1,144 824 1,100 1,100 1,100 0%
20-34 DATA PROCESSING SUPPLIES 1,141 767 986 1,000 1,000 1,000 0%
20-37 COMPUTER SOFTWARE 66,654 66,571 66,718 80,900 80,900 83,000 3%
20-38 COMPUTER HARDWARE 25,936 15,265 8,183 14,200 14,200 13,600 -4%
MATERIALS & SUPPLIES 94,806 83,748 76,711 97,200 97,200 98,700 2%
30-21 TELEPHONE/FAX 3,252 2,077 2,165 2,100 2,100 2,300 10%
30-27 SUBSCRIPTIONS AND DUES 195 653 195 200 200 200 0%
30-28 TRAINING/CONF/FOOD/TRAVEL 847 126 1,655 1,500 1,500 1,500 0%
30-31 CONTRACTUAL SERVICES 35,261 22,127 24,427 29,300 33,100 34,800 19%
30-39 IN-HOUSE TRAINING 6,050 6,000 5,000 6,400 6,400 6,400 0%
30-61 OFF EQUIP/REPAIRS & MAINT 126,340 117,975 115,416 128,200 128,200 130,900 2%
30-62 GASOLINE 53 61 22 100 100 100 0%
ADMINISTRATIVE EXPENDITURES 171,998 149,019 148,880 167,800 171,600 176,200 5%
OPERATING EXPENSES 611,301 716,217 730,046 704,800 625,500 716,300 2%
40-28 COMPUTER HARDWARE/CAPITAL 102,589 - - - - - 0%
CAPITAL OUTLAY 102,589 - - - - - 0%
TOTAL EXPENDITURES $ 713,890 $ 716,217 $ 730,046 $ 704,800 $ 625,500 $ 716,300 2%
OPERATING BUDGET STATS $ 611,301 $ 716,217 $ 730,046 $ 704,800 $ 625,500 $ 716,300
ACTUAL % OF OPER BUDGET 100% 100% 100% 100% 100% 100%
BUDGET % CHANGE -15% 17% 2% -3% -11% 15%
REVENUES
GENERAL FUND $ 611,301 $ 716,217 $ 730,046 $ 704,800 $ 625,500 $ 716,300
GOV. CAPITAL PROJECT FUND 87,589 - - - - -
DEMA GRANT 15,000 - - - - -
PERSONNEL
BUDGETED FULL-TIME POSITIONS 5.0 5.0 5.0 4.0 4.0 4.0
BUDGETED PART-TIME POSITIONS - - - 1.0 1.0 1.0
252
Página 259
FY 2017 Annual Operating Budget—Dover, Delaware
Parks & Recreation
Fiscal Year 2017 Organization Chart
Parks & Recreation
Planning & Community Development Director
1
Administrative Assistant
1
Recreation Specialist
1
Playground Leader I
T/P 20
Playground Leader II
T/P 2
Sports Coordinator
1
Recreation Center Coordinator
1
Office Assistant
1
Building Supervisor
2 P/P (1 Vacant)
Service Center Clerk
2 P/P
253
Página 260
FY 2017 DRAFT ANNUAL OPERATING BUDGET - DOVER, DELAWARE
RECREATION
110-1500-525
2016-2017
2012-2013 2013-2014 2014-2015 2015-2016 2015-2016 2016-2017 % Subs Abuse
ACCT DESCRIPTION ACTUAL ACTUAL ACTUAL BUDGET REVISED PROPOSED CHANGE BUDGET
10-11 SALARIES $ 208,858 $ 217,283 $ 229,135 $ 226,700 $ 236,000 $ 234,400 3% $ -
10-12 OVERTIME 342 102 398 1,500 1,500 1,600 7% -
10-13 TEMPORARY HELP 80,103 101,497 85,587 107,000 107,000 122,100 14% 59,600
10-14 FICA TAXES 21,390 23,734 23,484 25,600 26,000 27,400 7% 4,500
10-15 HEALTH INSURANCE 49,912 40,478 40,628 47,700 47,700 51,400 8% -
10-16 L I D INSURANCE 1,592 1,702 1,567 1,200 1,200 1,200 0% -
10-17 WORKERS COMPENSATION 1,971 694 656 1,100 1,100 1,100 0% 200
10-19 PENSION 12,008 28,377 28,365 28,900 28,900 37,600 30% -
10-20 OPEB 18,175 22,655 25,962 27,000 27,000 22,700 -16% -
PERSONNEL COSTS 394,350 436,522 435,783 466,700 476,400 499,500 7% 64,300
20-22 OFFICE SUPPLIES 2,430 2,428 1,950 2,000 2,000 2,000 0% -
20-23 PRINTING AND DUPLICATING 2,033 2,193 2,226 3,800 3,800 3,000 -21% -
20-26 PROGRAM EXPENSES/SUPPLIES 40,539 42,776 42,050 42,000 42,000 43,000 2% 55,700
20-28 MEDICAL SUP & PHYSICALS 15 221 - - - - 0% -
20-32 SECURITY/SAFETY MATERIALS 1,427 993 432 500 500 500 0% -
20-37 COMPUTER SOFTWARE 2,175 5,525 2,492 2,700 2,700 2,700 0% -
20-38 COMPUTER HARDWARE 3,176 1,009 3,176 3,500 3,500 - -100% -
20-46 CITY BLDG MAINT SUPPLIES 5,326 4,132 4,822 5,000 5,000 5,000 0% -
20-58 WATER/SEWER 819 873 775 1,000 1,000 800 -20% -
MATERIALS & SUPPLIES 57,941 60,151 57,922 60,500 60,500 57,000 -6% 55,700
30-21 TELEPHONE/FAX 2,040 1,927 2,147 2,100 2,100 2,100 0% -
30-23 ELECTRICITY 66,921 57,775 51,864 78,000 62,000 62,000 -21% -
30-24 HEATING OIL/GAS 5,827 12,197 11,046 12,000 12,000 6,000 -50% -
30-27 SUBSCRIPTIONS AND DUES 165 165 2,080 2,200 2,200 2,100 -5% -
30-28 TRAINING/CONF/FOOD/TRAVEL 1,314 2,560 492 500 500 500 0% -
30-31 CONTRACTUAL SERVICES 110,483 103,781 95,302 105,000 105,000 116,500 11% -
30-61 OFF EQUIP/REPAIRS & MAINT 1,420 925 1,035 1,000 1,000 1,000 0% -
30-62 GASOLINE 1,465 1,531 945 1,500 1,500 1,200 -20% -
30-67 RADIO REPAIRS/MAINTENANCE 2,422 - - - - - 0% -
ADMINISTRATIVE EXPENDITURES 192,056 180,861 164,910 202,300 186,300 191,400 -5% -
OPERATING EXPENDITURES 644,346 677,534 658,615 729,500 723,200 747,900 3% 120,000
40-25 OTHER EQUIP - PURCHASE - - 104,000 - 7,900 - 0% -
40-31 CONSTRUCTION - PURCHASE 6,995 5,829 103,323 - 66,000 165,000 0% -
CAPITAL OUTLAY 6,995 5,829 207,323 - 73,900 165,000 0% -
TOTAL EXPENDITURES $ 651,341 $ 683,363 $ 865,938 $ 729,500 $ 797,100 $ 912,900 25% $ 120,000
OPERATING BUDGET STATS $ 644,346 $ 677,534 $ 658,615 $ 729,500 $ 723,200 $ 747,900
ACTUAL % OF OPER BUDGET 100% 100% 100% 100% 100% 100%
BUDGET % CHANGE -22% 5% -3% 11% -1% 3%
REVENUES
GENERAL FUND $ 644,346 $ 677,534 $ 658,615 $ 729,500 $ 723,200 $ 747,900 $ -
GOV. CAPITAL PROJECT FUND 6,995 5,829 207,323 - 73,900 165,000 -
GRANT FUNDS - - - - - - 120,000
PERSONNEL
BUDGETED FULL-TIME POSITIONS 5.0 5.0 5.0 5.0 5.0 5.0 -
PP/TEMP 10.0 10.0 14.0 14.0 14.0 14.0 10.0
254
Página 261
FY 2017 Annual Operating Budget—Dover, Delaware
Dover Public Library
Fiscal Year 2017 Organization Chart
City Manager
Library Administrative Asst BTOP/Inspiration Space
Library Director Coordinator
1 1 1
Assistant Library Director
1
Youth Services Adult Services
Librarian II Librarian I
1 2 FT (1 Vacant)
Librarian I Librarian I
1 P/P 2 PT
Library Assistant Librarian Assistant
1 1
Library Assistant Library Assistant
1 P/P 2 P/P
Circulation Services Technical Services
Head of Circulation Svcs Lib II Head of Technical Svcs Lib I
1 1
Library Clerk I Library Assistant
2 1
Library Clerk I (6) P/P
(1 Vacant)
Dover Police Cadets
3
Library Pages
4 P/P
255
Página 262
FY 2017 DRAFT ANNUAL OPERATING BUDGET - DOVER, DELAWARE
LIBRARY
110-1500-523
2016-2017
2012-2013 2013-2014 2014-2015 2015-2016 2015-2016 2016-2017 % GRANTS
ACCT DESCRIPTION ACTUAL ACTUAL ACTUAL BUDGET REVISED PROPOSED CHANGE BUDGET
10-11 SALARIES $ 541,590 $ 571,704 $ 567,471 $ 590,700 $ 571,300 $ 616,300 4% $ -
10-12 OVERTIME 4,868 5,496 3,714 5,600 5,600 3,700 -34% -
10-13 TEMPORARY HELP 158,352 135,502 171,424 263,100 233,100 271,200 3% -
10-14 FICA TAXES 51,780 51,668 54,098 65,700 66,100 68,100 4% -
10-15 HEALTH INSURANCE 108,315 145,383 137,453 168,200 163,200 182,700 9% -
10-16 L I D INSURANCE 3,649 3,539 3,181 3,200 3,200 2,500 -22% -
10-17 WORKERS COMPENSATION 3,729 3,457 3,751 7,700 7,700 9,200 19% -
10-19 PENSION 27,074 112,239 106,208 109,200 109,200 155,500 42% -
10-20 OPEB 45,958 60,488 64,611 70,100 70,100 59,800 -15% -
PERSONNEL COSTS 945,314 1,089,476 1,111,912 1,283,500 1,229,500 1,369,000 7% -
20-21 FURNITURE/FIXTURES - - - - - - 0% 3,100
20-22 OFFICE SUPPLIES 1,497 1,497 1,495 1,500 1,500 1,500 0% 24,000
20-23 PRINTING AND DUPLICATING 2,088 2,194 - - - - 0% 13,200
20-26 PROGRAM EXPENSES/SUPPLIES 3,193 3,199 600 600 600 - -100% 24,100
20-31 BOOKS 53,998 53,999 53,997 54,000 54,000 35,200 -35% 129,200
20-32 SECURITY/SAFETY MATERIALS 288 1,200 1,800 3,300 3,300 3,300 0% -
20-37 COMPUTER SOFTWARE 42 1,000 500 500 500 500 0% -
20-38 COMPUTER HARDWARE 7,910 6,999 5,699 1,100 1,100 1,000 -9% -
20-46 CITY BLDG MAINT SUPPLIES 8,578 9,213 17,508 8,000 8,000 15,000 88% -
20-47 AUDIO VISUAL SUPPLIES 1,100 1,099 - - - - 0% 75,100
20-58 WATER/SEWER 2,929 3,125 2,426 2,400 2,400 2,400 0% -
MATERIALS & SUPPLIES 81,623 83,524 84,026 71,400 71,400 58,900 -18% 268,700
30-21 TELEPHONE/FAX 3,801 3,902 4,034 3,800 3,800 4,000 5% -
30-22 POSTAGE - - - - - - 0% 100
30-23 ELECTRICITY 81,200 84,115 94,173 93,000 93,000 93,000 0% -
30-24 HEATING OIL/GAS 19,288 16,007 5,676 6,000 6,000 6,000 0% -
30-27 SUBSCRIPTIONS AND DUES 10,989 10,998 11,000 11,000 11,000 11,000 0% -
30-28 TRAINING/CONF/FOOD/TRAVEL 200 200 - - - - 0% 2,000
30-31 CONTRACTUAL SERVICES 24,691 31,026 65,818 37,500 37,500 89,300 138% 900.00
30-61 OFF EQUIP/REPAIRS & MAINT 2,500 2,500 3,800 3,800 3,800 3,800 0% 6,000
30-69 OFFICE EQUIPMENT/LEASE - - - - - - 0% 1,200
ADMINISTRATIVE EXPENDITURES 142,668 148,748 184,499 155,100 155,100 207,100 34% 10,200
OPERATING EXPENDITURES 1,169,605 1,321,748 1,380,437 1,510,000 1,456,000 1,635,000 8% 278,900
40-25 OTHER EQUIP - PURCHASE - 32,302 - - - - 0% -
40-31 CONSTRUCTION - PURCHASE 4,070,899 80,566 - - - - 0% -
CAPITAL OUTLAY 4,070,899 112,868 - - - - 0% -
TOTAL EXPENDITURES $ 5,240,504 $ 1,434,616 $ 1,380,437 $ 1,510,000 $ 1,456,000 $ 1,635,000 8% $ 281,400
OPERATING BUDGET STATS $ 1,169,605 $ 1,321,748 $ 1,380,437 $ 1,510,000 $ 1,456,000 $ 1,635,000
ACTUAL $ OF OPER BUDGET 100% 100% 100% 100% 100% 100%
BUDGET % CHANGE 6% 13% 4% 9% -4% 12%
REVENUES
GENERAL FUND $ 1,169,605 $ 1,321,748 $ 1,380,437 $ 1,510,000 $ 1,456,000 $ 1,635,000 $ -
GOV. CAPITAL PROJECT FUND 4,070,899 112,868 - - - - -
GRANT FUNDS - - - - - - 281,400
PERSONNEL
BUDGETED FULL-TIME POSITIONS 13.0 13.0 13.0 13.0 13.0 13.0
BUDGETED PART-TIME POSITIONS 13.0 13.0 13.0 19.0 19.0 19.0
256
Página 263
FY 2017 ANNUAL OPERATING Budget - DOVER, DELAWARE
DOVER POLICE DEPARTMENT ORGANIZATIONAL CHART
April 2016
MAYOR
City of Dover
CHIEF OF POLICE
1 Sworn
Administrative Assistant Chaplain
1 Civilian 3 (Appointed Volunteer Civilians)
SORT Commander Deputy Chief Internal Affairs
(not an additional position) 1 Sworn 1 Sworn
CNT Commander
(not an additional position)
Operations Division Cmdr Administrative Division Cmdr
1 Sworn 1 Sworn
Criminal Investigations Cmdr Patrol Unit Cmdr Special Enforcement Police Resource Manager
1 Sworn 1 Sworn Unit Commander 1 Civilian
1 Sworn
Criminal Investigations “A” Platoon Special Enforcement Central Services Coordinator
11 Sworn Supervisor MC and ERLS 1 Civilian
Supervisor
1 Sworn Program (1 Sworn)
Building Craftsperson
“B” Platoon 1 Civilian (vacant)
Detectives Section Motorcycle Section
11 Sworn
8 Sworn 5 Sworn
“C” Platoon Evidence Technician and
Crime Scene Investigations Parking Enforcement Photographer
11 Sworn
1 Sworn Section 1 Civilian
2 Civilians
“D” Platoon
Sex Offender Section Records Administrator
11 Sworn Animal Control Section
2 Civilians 1 Civilian
1 Civilian
Public Affairs
Police Cadets Records Unit
1 Sworn
DVOC Supervisor 7 Civilians, 2 vacant 5 Civilians
1 Sworn
911 Manager
Special Enforcement Planning and Training
1 Civilian
DVOC Section Supervisor Community 1 Sworn
4 Sworn Policing
1 Sworn Police Academy/ Field Training
Communications Section 9 Recruit Officers
TAC Section 12 Civilians
1 Sworn Community Policing
Actual On Staff Section (3 Sworn) Crime Analysis/ Accreditation Section
1 Civilian
Gang Intelligence 99 Sworn
1 Sworn 31 Civilians (full time) Police Athletic League (PAL)
130 Employees 1 Sworn
Victim Services
8 Part‐time Civilians 1 Civilian
Street Crimes Initiative
4 Sworn Juvenile Section and
Vacancies
School Resource Officers LAN Analyst
2 Sworn, 4 Sworn 1 Fulltime and 1 Part time Civilian
Revised: April 2016 1 Civilian
2 Part‐time Civilians
257
Página 264
FY 2017 DRAFT ANNUAL OPERATING BUDGET - DOVER, DELAWARE
POLICE - CIVILIAN
110-1700-542
2012-2013 2013-2014 2014-2015 2015-2016 2015-2016 2016-2017 %
ACCT DESCRIPTION ACTUAL ACTUAL ACTUAL BUDGET REVISED PROPOSED CHANGE
10-11 SALARIES $ 1,244,096 $ 1,298,961 $ 1,337,882 $ 1,428,500 $ 1,469,400 $ 1,493,700 5%
10-12 OVERTIME 77,476 83,514 82,711 66,400 86,400 70,900 7%
10-13 TEMPORARY HELP 17,150 - - - - - 0%
10-14 FICA TAXES 100,041 102,029 104,231 114,300 115,900 119,600 5%
10-15 HEALTH INSURANCE 219,050 226,146 242,274 289,700 302,700 325,900 12%
10-16 L I D INSURANCE 6,610 7,156 7,076 7,100 7,100 7,200 1%
10-17 WORKERS COMPENSATION 9,366 5,244 7,307 4,800 12,600 7,200 50%
10-18 EDUCATIONAL ASSISTANCE 1,689 - 3,797 - - - 0%
10-19 PENSION 54,768 332,636 319,306 326,500 335,000 426,800 31%
10-20 OPEB 100,254 130,280 153,024 167,400 167,400 142,400 -15%
PERSONNEL COSTS 1,830,502 2,185,966 2,257,607 2,404,700 2,496,500 2,593,700 8%
POLICE - LAW ENFORCEMENT
110-1700-543
2012-2013 2013-2014 2014-2015 2015-2016 2015-2016 2016-2017 %
ACCT DESCRIPTION ACTUAL ACTUAL ACTUAL BUDGET REVISED PROPOSED CHANGE
10-11 SALARIES 6,800,947 6,917,618 7,332,327 7,094,300 7,678,900 7,503,800 6%
10-12 OVERTIME 446,587 355,468 433,344 445,000 410,000 450,600 1%
10-14 FICA TAXES 535,448 539,893 573,899 536,100 586,900 608,300 14%
10-15 HEALTH INSURANCE 961,516 1,023,394 1,058,741 1,387,200 1,317,200 1,480,100 7%
10-16 L I D INSURANCE 26,326 26,247 26,520 28,500 28,500 28,400 0%
10-17 WORKERS COMPENSATION 349,846 284,518 308,197 340,200 394,900 473,000 39%
10-18 EDUCATIONAL ASSISTANCE 7,143 7,922 13,260 - 14,800 - 0%
10-19 PENSION 937,822 992,648 936,612 962,200 1,006,000 1,004,100 4%
10-20 OPEB 551,936 687,480 787,743 826,800 831,700 704,600 -14%
PERSONNEL COSTS 10,617,571 10,835,188 11,470,644 11,620,300 12,268,900 12,252,900 5%
POLICE - EXTRA DUTY
110-1700-544
2012-2013 2013-2014 2014-2015 2015-2016 2015-2016 2016-2017 %
ACCT DESCRIPTION ACTUAL ACTUAL ACTUAL BUDGET REVISED PROPOSED CHANGE
10-11 SALARIES 738,537 588,971 501,907 529,200 558,300 689,800 30%
10-14 FICA TAXES 56,808 45,050 36,631 40,500 42,700 52,800 30%
10-17 WORKERS COMPENSATION 36,164 25,736 18,895 32,700 33,200 41,000 25%
PERSONNEL COSTS 831,510 659,757 557,432 602,400 634,200 783,600 30%
TOTAL PERSONNEL COSTS $ 13,279,582 $ 13,680,911 $ 14,285,683 $ 14,627,400 $ 15,399,600 $ 15,630,200 7%
POLICE - CADET PROGRAM IN POLICE GRANT FUND
710-1700-545
2012-2013 2013-2014 2014-2015 2015-2016 2015-2016 2016-2017 %
ACCT DESCRIPTION ACTUAL ACTUAL ACTUAL BUDGET REVISED PROPOSED CHANGE
10-13 TEMPORARY HELP - - - 71,400 71,400 71,400 0%
10-14 FICA TAXES - - 986 5,400 5,400 5,500 2%
10-17 WORKERS COMPENSATION - - 516 3,500 3,500 4,200 20%
PERSONNEL COSTS - - 1,503 80,300 80,300 81,100 1%
PERSONNEL
BUDGETED FULL-TIME POSITIONS 122.0 122.0 124.0 134.0 134.0 134.0
BUDGETED PART-TIME POSITIONS - GRANT FUNDED
- - - 6.0 6.0 6.0
258
Página 265
FY 2017 DRAFT ANNUAL OPERATING BUDGET - DOVER, DELAWARE
POLICE - ADMINISTRATION
110-1700-541
2015-2016
2012-2013 2013-2014 2014-2015 2015-2016 2015-2016 2016-2017 % GRANTS
ACCT DESCRIPTION ACTUAL ACTUAL ACTUAL BUDGET REVISED PROPOSED CHANGE BUDGET
20-14 CI PETTY CASH DISBURSEMTS $ 2,249 $ 3,243 $ 6,933 $ 20,200 $ 42,200 $ 8,000 -60% $ -
20-22 OFFICE SUPPLIES 7,310 10,016 5,683 7,000 7,000 7,000 0% -
20-23 PRINTING AND DUPLICATING 16,758 11,810 18,756 14,000 19,000 14,000 0% -
20-24 PHOTOGRAPHIC 1,514 696 942 1,000 1,000 1,500 50% -
20-25 CUSTODIAL 4,528 4,489 4,583 4,200 4,200 4,500 7% -
20-26 PROGRAM EXPENSES/SUPPLIES 51,960 48,747 81,040 93,600 93,600 67,000 -28% 156,000
20-28 MEDICAL SUP & PHYSICALS 24,008 25,143 29,534 26,000 26,000 32,000 23% -
20-29 UNIFORMS/UNIFORM ALLOW 83,467 81,653 82,894 99,800 99,800 82,000 -18% -
20-31 BOOKS 1,935 - 2,240 700 700 3,000 329% -
20-32 SECURITY/SAFETY MATERIALS 18,905 18,807 1,080 - - 1,500 0% -
20-36 ANIMAL CARE EXPENSES 4,711 3,692 20,293 17,000 15,000 17,000 0% -
20-37 COMPUTER SOFTWARE 11,591 12,267 13,390 13,000 13,000 16,700 28% -
20-38 COMPUTER HARDWARE 54,393 59,158 50,001 102,200 102,200 82,300 -19% 50,000
20-46 CITY BLDG MAINT SUPPLIES 35,435 31,608 31,506 31,400 50,900 31,400 0% -
20-58 WATER/SEWER 3,181 1,593 2,197 2,700 2,700 2,700 0% -
MATERIALS & SUPPLIES 321,945 312,923 351,073 432,800 477,300 370,600 -14% 206,000
30-21 TELEPHONE/FAX 49,452 50,816 53,750 52,900 47,900 52,900 0% 15,000
30-22 POSTAGE 82 74 364 100 100 100 0% -
30-23 ELECTRICITY 87,044 74,064 76,321 85,000 82,500 85,000 0% -
30-24 HEATING OIL/GAS 12,743 13,294 15,424 12,800 9,800 12,800 0% -
30-25 ADVERTISEMENT 3,000 1,039 - 2,000 1,000 1,000 -50% -
30-26 INSURANCE 10,733 12,115 43,052 20,000 33,500 30,000 50% -
30-27 SUBSCRIPTIONS AND DUES 2,992 4,666 5,423 5,100 5,100 5,000 -2% -
30-28 TRAINING/CONF/FOOD/TRAVEL 19,492 30,404 38,903 44,900 44,900 71,000 58% 32,000
30-29 CONSULTING FEES/AUDIT FEES 9,393 9,933 11,609 9,000 9,000 10,400 16% 1,000
30-31 CONTRACTUAL SERVICES 52,126 55,635 44,262 68,600 68,600 192,600 181% 6,000
30-61 OFF EQUIP/REPAIRS & MAINT 38,692 26,291 28,374 38,700 38,700 38,200 -1% -
30-62 GASOLINE 223,301 208,529 175,604 200,000 132,000 135,000 -33% -
30-63 AUTO REPAIRS/MAINTENANCE 128,788 159,401 147,690 127,600 177,100 217,400 70% -
30-67 RADIO REPAIRS/MAINTENANCE 17,909 17,068 18,782 20,000 20,000 22,500 13% -
30-68 RADIO EQUIPMENT/LEASE 980 520 800 14,500 8,500 500 -97% -
ADMINISTRATIVE EXPENDITURES 656,727 663,849 660,359 701,200 678,700 874,400 25% 54,000
OPERATING EXPENDITURES 14,258,254 14,657,683 15,297,116 15,761,400 16,555,600 16,875,200 7% 260,000
40-21 OFFICE EQUIPMENT PURCHASE - 8,865 - - - - 0% -
40-22 AUTOMOBILES - PURCHASE 137,504 227,300 148,978 242,200 282,800 287,300 19% -
40-25 OTHER EQUIP - PURCHASE 33,800 54,160 432,035 - - 12,500 0% -
40-31 CONSTRUCTION - PURCHASE 19,715 51,800 - 19,900 19,900 - -100% -
CAPITAL OUTLAY 191,019 342,125 581,012 262,100 302,700 299,800 14% 74,400
TOTAL EXPENDITURES $ 14,449,273 $ 14,999,808 $ 15,878,128 $ 16,023,500 $ 16,858,300 $ 17,175,000 7% $ 334,400
OPERATING BUDGET STATS $ 14,258,254 $ 14,657,683 $ 15,297,116 $ 15,761,400 $ 16,555,600 $ 16,875,200
ACTUAL % OF OPER BUDGET 101% 102% 104% 102% 102% 102%
BUDGET % CHANGE 5% 3% 4% 3% 5% 2%
REVENUES
GENERAL FUND $ 14,258,254 $ 14,657,683 $ 15,297,116 $ 15,761,400 $ 16,555,600 $ 16,875,200
GOV. CAPITAL PROJECT FUND 191,019 342,125 581,012 262,100 302,700 299,800
PERSONNEL
BUDGETED FULL-TIME POSITIONS 122.0 122.0 124.0 134.0 134.0 134.0 -
BUDGETED PART-TIME POSITIONS - GRANT FUNDED
- - - 6.0 6.0 6.0 6
259
Página 266
FY 2017 ANNUAL OPERATING BUDGET— DOVER, DELAWARE
Fiscal Year 2017 Organization Chart
CITY
COUNCIL
TAX
ASSESSOR
City Assessor*
1
Administrative Assistant
1
Residential Assessment Tech.
1
* Appointed by Council
260
Página 267
FY 2017 DRAFT ANNUAL OPERATING BUDGET - DOVER, DELAWARE
TAX ASSESSOR
110-1300-513
2012-2013 2013-2014 2014-2015 2015-2016 2015-2016 2016-2017 %
ACCT DESCRIPTION ACTUAL ACTUAL ACTUAL BUDGET REVISED PROPOSED CHANGE
10-11 SALARIES $ 124,167 $ 125,250 $ 119,460 $ 129,000 $ 131,400 $ 132,200 2%
10-14 FICA TAXES 9,299 9,341 8,774 9,900 10,100 10,100 2%
10-15 HEALTH INSURANCE 16,571 17,182 19,826 31,600 31,600 34,100 8%
10-16 L I D INSURANCE 963 972 808 800 800 800 0%
10-17 WORKERS COMPENSATION 795 422 411 400 400 700 75%
10-18 EDUCATIONAL ASSISTANCE - - - - 2,400 - 0%
10-19 PENSION 6,925 21,126 19,593 20,200 20,200 27,200 35%
10-20 OPEB 10,706 13,441 13,864 15,300 15,300 12,800 -16%
PERSONNEL COSTS 169,427 187,735 182,735 207,200 212,200 217,900 5%
20-21 FURNITURE/FIXTURES 32 - 111 - - - 0%
20-22 OFFICE SUPPLIES 1,842 3,473 2,263 2,700 2,700 2,300 -15%
20-23 PRINTING AND DUPLICATING 78 76 9,828 200 200 200 0%
20-37 COMPUTER SOFTWARE - - 50 100 100 - -100%
MATERIALS & SUPPLIES 3,087 6,014 12,252 3,000 3,000 2,500 -17%
30-21 TELEPHONE/FAX 1,218 1,098 1,132 1,100 1,100 1,300 18%
30-25 ADVERTISEMENT 775 615 985 1,000 1,000 1,000 0%
30-27 SUBSCRIPTIONS AND DUES 850 875 905 900 900 800 -11%
30-28 TRAINING/CONF/FOOD/TRAVEL 1,788 2,242 1,896 5,000 5,000 7,500 50%
30-31 CONTRACTUAL SERVICES 8,860 9,210 102,760 15,600 15,600 12,400 -21%
30-62 GASOLINE 1,432 1,607 775 1,000 1,000 600 -40%
ADMINISTRATIVE EXPENDITURES 14,924 15,646 108,453 24,600 24,600 23,600 -4%
OPERATING EXPENDITURES 187,438 209,395 303,439 234,800 239,800 244,000 4%
TOTAL EXPENDITURES $ 187,438 $ 209,395 $ 303,439 $ 234,800 $ 239,800 $ 244,000 4%
OPERATING BUDGET STATS $ 187,438 $ 209,395 $ 303,439 $ 234,800 $ 239,800 $ 244,000
ACTUAL % OF OPER BUDGET 100% 100% 100% 100% 100% 100%
BUDGET % CHANGE 1% 12% 45% -23% 2% 2%
REVENUES
GENERAL FUND $ 187,438 $ 209,395 $ 303,439 $ 234,800 $ 239,800 $ 244,000
PERSONNEL
BUDGETED FULL-TIME POSITIONS 3.0 3.0 3.0 3.0 3.0 3.0
BUDGETED PART-TIME POSITIONS - - - - - -
261
Página 268
FY 2017 Annual Operating Budget—Dover, Delaware
Planning & Inspections
Fiscal Year 2017 Organization Chart
City Council
Planning & Inspections
Director of Planning & Community
Development Director
1
Planning Life Safety Code Enforcement Inspections & Permitting
Secretary II Fire Marshal Inspector III Chief Building Inspector
1 1 (Vacant) 1 1
Principal Planner Deputy Fire Marshal/ Inspector II Inspector II
1 Inspector II 1 2
1
Planner I Deputy Fire Marshal/ Inspector I Inspections/Licensing
2 Inspector I 3
1
Licensing & Permitting
Planner I/Community Dev. Supervisor
1 1
Office Assistant II
2 (1 Vacant)
262
Página 269
FY 2017 DRAFT ANNUAL OPERATING BUDGET - DOVER, DELAWARE
PLANNING/CDBG
110-1600-533/715-2016-596
2012-2013 2013-2014 2014-2015 2015-2016 2015-2016 2016-2017 %
ACCT DESCRIPTION ACTUAL ACTUAL ACTUAL BUDGET REVISED PROPOSED CHANGE
10-11 SALARIES $ 306,920 $ 299,850 $ 330,438 $ 364,200 $ 366,100 $ 380,300 4%
10-12 OVERTIME 770 377 282 700 700 1,000 43%
10-13 TEMPORARY HELP 11,950 13,600 11,475 17,100 17,100 15,000 -12%
10-14 FICA TAXES 23,591 23,083 25,085 29,400 29,800 30,300 3%
10-15 HEALTH INSURANCE 38,269 37,741 41,281 58,600 55,100 60,200 3%
10-16 L I D INSURANCE 2,011 1,846 1,900 2,200 2,200 2,200 0%
10-17 WORKERS COMPENSATION 1,978 664 715 1,100 1,100 1,200 9%
10-19 PENSION 17,610 17,039 18,529 20,500 20,500 22,000 7%
10-20 OPEB 25,919 31,408 38,150 43,300 43,300 36,900 -15%
10-21 COSTS ALLOCATED TO CDBG (51,853) (40,364) (45,973) (33,700) (33,700) (36,000) 7%
PERSONNEL COSTS 377,165 385,245 421,882 503,400 502,200 513,100 2%
20-21 FURNITURE/FIXTURES 77 - - - - - 0%
20-22 OFFICE SUPPLIES 2,971 4,133 3,815 4,000 4,000 4,000 0%
20-23 PRINTING AND DUPLICATING 8,272 9,855 8,654 6,000 6,000 6,000 0%
20-31 BOOKS 570 717 616 700 700 700 0%
20-38 COMPUTER HARDWARE - 5,591 - - - 2,600 0%
MATERIALS & SUPPLIES 11,890 20,297 13,086 10,700 10,700 13,300 24%
30-21 TELEPHONE/FAX 989 943 998 1,200 1,200 1,300 8%
30-25 ADVERTISEMENT 2,122 1,759 2,220 2,000 2,000 2,000 0%
30-27 SUBSCRIPTIONS AND DUES 1,529 2,055 2,065 2,500 2,500 2,900 16%
30-28 TRAINING/CONF/FOOD/TRAVEL 2,239 1,482 6,280 4,200 4,200 4,200 0%
30-31 CONTRACTUAL SERVICES 1,267 10,305 3,870 10,000 10,000 10,000 0%
30-67 RADIO REPAIRS/MAINTENANCE 2,262 - - - - - 0%
ADMINISTRATIVE EXPENDITURES 10,406 16,544 15,432 19,900 19,900 20,400 3%
OPERATING EXPENDITURES 399,461 422,085 450,400 534,000 532,800 546,800 2%
40-31 CONSTRUCTION - PURCHASE - - - - 36,000 0%
70-42 CLOSING COST/DWNPYMT PROG - - - - - 60,000 0%
70-43 CONNECTIONS COMM SUPPORT - - - - - 7,400 0%
70-44 DOVER INTERFAITH MINISTRY - - - - - 27,000 0%
70-59 MHDC EMERGENCY HOME REPAIR - - - - - 35,300 0%
70-63 HABITAT FOR HUMANITY - - - - - 40,000 0%
70-66 MILFORD HOUSING H/O REHAB - - - - - 52,900 0%
70-67 PEOPLE'S PLACE - - - - - 6,800 0%
CAPITAL OUTLAY - - - - - 265,400 0%
TOTAL EXPENDITURES $ 399,461 $ 422,085 $ 450,400 $ 534,000 $ 532,800 $ 546,800 2%
OPERATING BUDGET STATS $ 399,461 $ 422,085 $ 450,400 $ 534,000 $ 532,800 $ 546,800
ACTUAL %OF OPER BUDGET 87% 90% 90% 94% 94% 93%
BUDGET % CHANGE 6% 6% 7% 19% 0% 3%
REVENUES
GENERAL FUND $ 347,608 $ 381,722 $ 404,427 $ 500,300 $ 499,100 $ 510,800
CDBG GRANT 51,853 40,364 45,973 33,700 33,700 36,000
GOV. CAPITAL PROJECT FUND - - - - - -
PERSONNEL
BUDGETED FULL-TIME POSITIONS 4.5 4.5 5.0 6.0 6.0 6.0
PP/TEMP/COMMITTEES 14.0 14.0 14.0 14.0 14.0 14.0
263
Página 270
FY 2017 DRAFT ANNUAL OPERATING BUDGET - DOVER, DELAWARE
LIFE SAFETY
110-1600-531
2012-2013 2013-2014 2014-2015 2015-2016 2015-2016 2016-2017 %
ACCT DESCRIPTION ACTUAL ACTUAL ACTUAL BUDGET REVISED PROPOSED CHANGE
10-11 SALARIES $ 132,521 $ 159,634 $ 168,537 $ 148,400 $ 150,600 $ 158,800 7%
10-12 OVERTIME 7,608 9,523 8,683 8,600 5,600 8,000 -7%
10-14 FICA TAXES 10,566 12,590 13,265 12,000 12,200 12,800 7%
10-15 HEALTH INSURANCE 17,776 20,314 18,636 23,900 23,900 25,700 8%
10-16 L I D INSURANCE 725 851 767 800 800 800 0%
10-17 WORKERS COMPENSATION 1,385 685 719 800 800 1,000 25%
10-19 PENSION 7,806 31,856 8,429 8,600 8,600 9,900 15%
10-20 OPEB 10,458 15,730 15,422 17,000 17,000 14,600 -14%
PERSONNEL COSTS 188,846 251,183 234,458 220,100 219,500 231,600 5%
20-26 PROGRAM EXPENSES/SUPPLIES 445 - 14,053 3,200 1,400 - -100%
20-29 UNIFORMS/UNIFORM ALLOW 577 912 450 600 600 300 -50%
20-31 BOOKS 259 - - - - - 0%
20-32 SECURITY/SAFETY MATERIALS 1,729 685 1,358 400 400 - -100%
20-33 SMALL TOOLS 37 51 - 100 100 - -100%
20-38 COMPUTER HARDWARE 2,980 - 2,033 2,600 2,500 - -100%
MATERIALS & SUPPLIES 6,027 1,648 17,895 6,900 5,000 300 -96%
30-21 TELEPHONE/FAX 3,830 2,546 1,871 2,100 2,100 1,900 -10%
30-27 SUBSCRIPTIONS AND DUES 985 1,296 1,166 1,300 1,400 1,300 0%
30-28 TRAINING/CONF/FOOD/TRAVEL 420 3,648 391 1,500 3,000 1,500 0%
30-31 CONTRACTUAL SERVICES 239,569 253,900 244,463 245,000 245,000 245,000 0%
30-62 GASOLINE 6,137 5,655 3,959 3,500 3,500 3,000 -14%
30-67 RADIO REPAIRS/MAINTENANCE 1,722 - 639 300 300 600 100%
ADMINISTRATIVE EXPENDITURES 252,664 267,044 252,488 253,700 255,300 253,300 0%
OPERATING EXPENDITURES 447,537 519,875 504,840 480,700 479,800 485,200 1%
40-22 AUTOMOBILE/PURCHASE - - - 55,700 55,700 29,500 -47%
CAPITAL OUTLAY - - - 55,700 55,700 29,500 -47%
TOTAL EXPENDITURES $ 447,537 $ 519,875 $ 504,840 $ 536,400 $ 535,500 $ 514,700 -4%
OPERATING BUDGET STATS $ 447,537 $ 519,875 $ 504,840 $ 480,700 $ 479,800 $ 485,200
ACTUAL % OF OPER BUDGET 100% 100% 100% 100% 100% 100%
BUDGET % CHANGE -10% 16% -3% -5% 0% 1%
REVENUES
GENERAL FUND $ 447,537 $ 519,875 $ 504,840 $ 480,700 $ 479,800 $ 485,200
GOV. CAPITAL PROJECT FUND - - - 55,700 55,700 29,500
PERSONNEL
BUDGETED FULL-TIME POSITIONS 3.0 3.0 3.0 3.0 3.0 3.0
264
Página 271
FY 2017 DRAFT ANNUAL OPERATING BUDGET - DOVER, DELAWARE
CODE ENFORCEMENT
110-1600-532
2012-2013 2013-2014 2014-2015 2015-2016 2015-2016 2016-2017 %
ACCT DESCRIPTION ACTUAL ACTUAL ACTUAL BUDGET REVISED PROPOSED CHANGE
10-11 SALARIES $ 203,806 $ 230,998 $ 199,755 $ 215,200 $ 207,800 $ 222,700 3%
10-12 OVERTIME 2,918 1,179 1,891 5,000 5,000 2,500 -50%
10-13 TEMPORARY HELP - 1,375 9,557 - 8,500 - 0%
10-14 FICA TAXES 15,425 17,257 15,385 16,800 16,900 17,200 2%
10-15 HEALTH INSURANCE 40,899 38,525 43,731 56,000 52,000 55,700 -1%
10-16 L I D INSURANCE 1,137 1,207 1,158 1,200 1,200 1,200 0%
10-17 WORKERS COMPENSATION 2,034 944 839 1,100 1,100 1,300 18%
10-18 EDUCATIONAL ASSISTANCE - - - - 3,600 - 0%
10-19 PENSION 9,683 68,495 62,830 64,600 59,600 74,100 15%
10-20 OPEB 17,581 22,545 23,581 25,600 25,600 21,600 -16%
PERSONNEL COSTS 293,483 382,526 358,727 385,500 381,300 396,300 3%
20-22 OFFICE SUPPLIES 32 - - - - - 0%
20-26 PROGRAM EXPENSES/SUPPLIES 18,210 16,755 17,985 18,000 18,000 18,000 0%
20-29 UNIFORMS/UNIFORM ALLOW 3,628 1,380 1,216 1,100 1,100 300 -73%
20-31 BOOKS - 379 177 - - - 0%
20-32 SECURITY/SAFETY MATERIALS 562 789 1,879 600 600 - -100%
20-33 SMALL TOOLS 43 - - - - - 0%
20-38 COMPUTER HARDWARE - 3,055 5,236 2,600 2,600 - -100%
MATERIALS & SUPPLIES 22,475 22,358 26,493 22,300 22,300 18,300 -18%
30-21 TELEPHONE/FAX 2,576 1,953 1,829 1,400 1,400 700 -50%
30-27 SUBSCRIPTIONS AND DUES 295 165 165 200 200 200 0%
30-28 TRAINING/CONF/FOOD/TRAVEL 340 610 1,020 1,000 1,000 1,000 0%
30-31 CONTRACTUAL SERVICES - - 1,174 4,000 4,000 1,600 -60%
30-62 GASOLINE 5,006 5,219 3,453 5,000 2,500 3,000 -40%
30-67 RADIO REPAIRS/MAINTENANCE 2,262 - - - - - 0%
ADMINISTRATIVE EXPENDITURES 10,479 7,947 7,640 11,600 9,100 6,500 -44%
OPERATING EXPENDITURES 326,437 412,830 392,859 419,400 412,700 421,100 0%
40-22 AUTOMOBILES- PURCHASE - 30,840 - - - - 0%
CAPITAL OUTLAY - 30,840 - - - - 0%
TOTAL EXPENDITURES $ 326,437 $ 443,670 $ 392,859 $ 419,400 $ 412,700 $ 421,100 0%
OPERATING BUDGET STATS $ 326,437 $ 412,830 $ 392,859 $ 419,400 $ 412,700 $ 421,100
ACTUAL % OF OPER BUDGET 100% 100% 100% 100% 100% 100%
BUDGET % CHANGE 20% 26% -5% 7% -2% 2%
REVENUES
GENERAL FUND $ 326,437 $ 412,830 $ 392,859 $ 419,400 $ 412,700 $ 421,100
PERSONNEL
BUDGETED FULL-TIME POSITIONS 4.0 4.0 5.0 5.0 5.0 5.0
265
Página 272
FY 2017 DRAFT ANNUAL OPERATING BUDGET - DOVER, DELAWARE
INSPECTIONS
110-1600-534
2012-2013 2013-2014 2014-2015 2015-2016 2015-2016 2016-2017 %
ACCT DESCRIPTION ACTUAL ACTUAL ACTUAL BUDGET REVISED PROPOSED CHANGE
10-11 SALARIES $ 250,047 $ 248,150 $ 264,356 $ 268,500 $ 272,200 $ 277,500 3%
10-12 OVERTIME 853 1,840 2,084 1,800 4,300 2,000 11%
10-13 TEMPORARY HELP 5,583 - - - - - 0%
10-14 FICA TAXES 19,139 18,235 19,344 20,700 21,000 21,400 3%
10-15 HEALTH INSURANCE 52,674 53,663 56,231 66,000 62,500 69,900 6%
10-16 L I D INSURANCE 1,435 1,354 1,351 1,100 1,100 1,200 9%
10-17 WORKERS COMPENSATION 2,174 845 896 1,100 1,100 1,400 27%
10-19 PENSION 12,809 70,321 69,660 71,300 72,300 103,300 45%
10-20 OPEB 21,609 26,219 30,544 32,000 32,000 26,900 -16%
PERSONNEL COSTS 366,324 420,625 444,465 462,500 466,500 503,600 9%
20-22 OFFICE SUPPLIES 99 - - - - - 0%
20-26 PROGRAM EXPENSES/SUPPLIES 101 - - - - - 0%
20-29 UNIFORMS/UNIFORM ALLOW 660 530 512 500 500 200 -60%
20-31 BOOKS - 1,869 494 - 300 2,000 0%
20-32 SECURITY/SAFETY MATERIALS 418 400 - 400 400 - -100%
20-33 SMALL TOOLS - - - - - - 0%
20-38 COMPUTER HARDWARE 2,606 3,443 - 6,400 6,400 - -100%
MATERIALS & SUPPLIES 3,884 6,242 1,006 7,300 7,600 2,200 -70%
30-21 TELEPHONE/FAX 3,528 3,076 2,962 3,000 3,000 3,000 0%
30-27 SUBSCRIPTIONS AND DUES 666 380 668 600 600 600 0%
30-28 TRAINING/CONF/FOOD/TRAVEL 413 903 704 800 800 1,000 25%
30-31 CONTRACTUAL SERVICES 40 3,993 4,528 7,500 7,500 6,000 -20%
30-33 DEMOLITION EXPENSES 103,820 216,980 120,005 175,000 256,500 175,000 0%
30-61 OFF EQUIP/REPAIRS & MAINT 3,029 3,014 2,356 3,000 1,500 3,000 0%
30-62 GASOLINE 6,520 5,366 4,785 5,000 5,000 3,500 -30%
30-67 RADIO REPAIRS/MAINTENANCE 5,678 - - - - - 0%
ADMINISTRATIVE EXPENDITURES 123,694 233,713 136,009 194,900 274,900 192,100 -1%
OPERATING EXPENSES 493,902 660,580 581,480 664,700 749,000 697,900 5%
TOTAL EXPENDITURES $ 493,902 $ 660,580 $ 581,480 $ 664,700 $ 749,000 $ 697,900 5%
OPERATING BUDGET STATS $ 493,902 $ 660,580 $ 581,480 $ 664,700 $ 749,000 $ 697,900
ACTUAL % OF OPER BUDGET 100% 100% 100% 100% 100% 100%
BUDGET % CHANGE -10% 34% -12% 14% 13% -7%
REVENUES
GENERAL FUND $ 493,902 $ 660,580 $ 581,480 $ 664,700 $ 749,000 $ 697,900
PERSONNEL
BUDGETED FULL-TIME POSITIONS 7.0 7.0 6.0 6.0 6.0 6.0
266
Página 273
FY 2017 ANNUAL OPERATING BUDGET - DOVER, DELAWARE
CITY MANAGER
DEPARTMENT OF PUBLIC WORKS - GENERAL FUND
FISCAL YEAR 2017 ORGANIZATION CHART
PUBLIC WORKS DIRECTOR / CITY ENGINEER
1 (accounted for in Public Works Administration)
FLEET FACILITIES SANITATION STREET & STORMWATER GROUNDS & PARKS PUBLIC WORKS GENERAL FUND
MAINTENANCE MANAGEMENT MAINTENANCE MAINTENANCE ADMINISTRATION ENG. & INSPECTIONS
PUBLIC WORKS OPERATIONS MANAGER WATER / WASTEWATER MANAGER
1 (accounted for in Public Works Administration) 1 (accounted for in Water / Wastewater Eng. & Insp.)
FLEET, FACILITIES & SANITATION FIELD SUPERVISOR II STREETS FIELD SUPER. I GROUNDS FIELD SUPER. II ADMINISTRATIVE ASSIST. CIVIL ENGINEER I
1 (accounted for in Fleet Maintenance) 1 1 2 1
MECHANIC II CRAFTSPERSON II CREW LEADER CREW LEADER CREW LEADER GIS MANAGER ENVIRON. SCIENTIST
2 2 1 1 1 1 1
MECHANIC I CRAFTSPERSON I MOTOR EQUIP. OPER. III LEAD LABORER ARBORIST GIS TECHNICIAN CONSTRUCTION MGR.
3 1 3 1 2 1 1 (in W/WW Eng. & Insp.)
6 ELECTRICIAN II MOTOR EQUIP. OPER. II MOTOR EQUIP. OPER. II GARDENER II 6 PUBLIC WORKS INSPECT.
1 2 2 1 1
CUSTODIAN II MOTOR EQUIP. OPER. I MOTOR EQUIP. OPER. I GARDENER I 3
1 4 2 1
5 10 SIGN / STREET PAINTER LEAD LABORER
1 2
8 LABORER II
1
MOTOR EQUIP. OPER. II
3
SMALL ENGINE MECH. I
1
51
13
267
Página 274
FY 2017 DRAFT ANNUAL OPERATING BUDGET - DOVER, DELAWARE
PUBLIC WORKS - ADMINISTRATION
110-2400-551
2012-2013 2013-2014 2014-2015 2015-2016 2015-2016 2016-2017 %
ACCT DESCRIPTION ACTUAL ACTUAL ACTUAL BUDGET REVISED PROPOSED CHANGE
10-11 SALARIES $ 245,607 $ 298,489 $ 303,856 $ 354,200 $ 322,100 $ 371,000 5%
10-12 OVERTIME 541 - - - - - 0%
10-14 FICA TAXES 17,941 22,057 22,384 27,100 24,800 28,400 5%
10-15 HEALTH INSURANCE 40,150 44,652 44,817 62,900 60,700 74,500 18%
10-16 L I D INSURANCE 1,562 1,949 1,817 1,900 1,900 2,000 5%
10-17 WORKERS COMPENSATION 1,554 793 849 1,100 1,200 1,200 9%
10-19 PENSION 10,479 15,565 100,039 104,900 104,900 148,600 42%
10-20 OPEB 19,711 28,805 34,470 41,900 37,900 35,900 -14%
PERSONNEL COSTS 337,544 412,311 508,231 594,000 553,500 661,600 11%
20-22 OFFICE SUPPLIES 2,923 3,492 3,060 3,500 3,500 3,500 0%
20-23 PRINTING AND DUPLICATING 1,549 2,819 1,928 3,000 3,000 3,000 0%
20-31 BOOKS - - 149 - - - 0%
20-32 SECURITY/SAFETY MATERIALS 125 - - - - - 0%
20-37 COMPUTER SOFTWARE - - 150 300 300 400 33%
20-38 COMPUTER HARDWARE 8,215 50 2,845 4,300 4,300 - -100%
MATERIALS & SUPPLIES 12,812 6,361 8,131 11,100 11,100 6,900 -38%
30-21 TELEPHONE/FAX 3,127 2,565 1,976 1,900 1,900 1,900 0%
30-27 SUBSCRIPTIONS AND DUES - 240 955 7,000 1,000 4,400 -37%
30-28 TRAINING/CONF/FOOD/TRAVEL - 3,149 2,217 4,500 4,500 4,000 -11%
30-31 CONTRACTUAL SERVICES - 6,979 - 7,000 7,000 - -100%
30-62 GASOLINE 2,432 412 786 600 600 500 -17%
30-67 RADIO REPAIRS/MAINTENANCE 4,203 408 639 700 700 700 0%
ADMINISTRATIVE EXPENDITURES 9,762 13,754 6,573 21,700 15,700 11,500 -47%
OPERATING EXPENDITURES 360,118 432,425 522,935 626,800 580,300 680,000 8%
TOTAL EXPENDITURES $ 360,118 $ 432,425 $ 522,935 $ 626,800 $ 580,300 $ 680,000 8%
OPERATING BUDGET STATS $ 360,118 $ 432,425 $ 522,935 $ 626,800 $ 580,300 $ 680,000
ACTUAL % OF OPER BUDGET 100% 100% 100% 100% 100% 100%
BUDGET % CHANGE 8% 20% 21% 20% -7% 17%
REVENUES
GENERAL FUND $ 360,118 $ 432,425 $ 522,935 $ 626,800 $ 580,300 $ 680,000
PERSONNEL
BUDGETED FULL-TIME POSITIONS 6.0 6.0 5.0 6.0 6.0 6.0
268
Página 275
FY 2017 DRAFT ANNUAL OPERATING BUDGET - DOVER, DELAWARE
PUBLIC WORKS ENGINEERING
110/147-2600-553
2012-2013 2013-2014 2014-2015 2015-2016 2015-2016 2016-2017 %
ACCT DESCRIPTION ACTUAL ACTUAL ACTUAL BUDGET REVISED PROPOSED CHANGE
10-11 SALARIES $ - $ - $ 16,344 $114,400 $116,400 $132,800 16%
10-12 OVERTIME - - - - - 500 0%
10-14 FICA TAXES - - 1,211 8,700 8,700 10,200 17%
10-15 HEALTH INSURANCE - - 2,216 30,600 20,600 38,900 27%
10-16 L I D INSURANCE - - 121 900 900 900 0%
10-17 WORKERS COMPENSATION - - 67 400 400 400 0%
10-19 PENSION - - 792 6,800 6,800 7,100 4%
10-20 OPEB - - 1,720 13,600 13,600 12,800 -6%
PERSONNEL COSTS - - 22,470 175,400 167,400 203,600 16%
20-29 UNIFORMS/UNIFORM ALLOW - - 192 200 200 200 0%
20-32 SECURITY/SAFETY MATERIALS - - 61 200 200 200 0%
20-33 SMALL TOOLS - - 95 100 100 100 0%
20-37 COMPUTER SOFTWARE - - 846 200 200 400 100%
20-38 COMPUTER HARDWARE - - 2,592 1,300 1,300 - -100%
MATERIALS & SUPPLIES - - 3,785 2,000 2,000 900 -55%
30-21 TELEPHONE/FAX - - 189 500 500 500 0%
30-28 TRAINING/CONF/FOOD/TRAVEL - - 90 500 500 500 0%
30-31 CONTRACTUAL SERVICES - - - 1,500 1,500 - -100%
30-62 GASOLINE - - 462 1,500 1,500 1,500 0%
ADMINISTRATIVE EXPENDITURES - - 741 4,000 4,000 2,500 -38%
OPERATING EXPENDITURES - - 26,996 181,400 173,400 207,000 14%
TOTAL EXPENDITURES $ - $ - $ 26,996 $ 181,400 $ 173,400 $ 207,000 14%
OPERATING BUDGET STATS $ - $ - $ 26,996 $ 181,400 $ 173,400 $ 207,000
ACTUAL % OF OPER BUDGET 0% 0% 100% 100% 100% 100%
BUDGET % CHANGE 0% 0% 0% 0% 0% 0%
REVENUES
GENERAL FUND $ - $ - $ 26,996 $ 181,400 $ 173,400 $ 207,000
PERSONNEL
BUDGETED FULL-TIME POSITIONS - - 3.0 3.0 3.0 3.0
269
Página 276
FY 2017 DRAFT ANNUAL OPERATING BUDGET - DOVER, DELAWARE
FACILITIES MANAGEMENT
110-2500-552
2012-2013 2013-2014 2014-2015 2015-2016 2015-2016 2016-2017 %
ACCT DESCRIPTION ACTUAL ACTUAL ACTUAL BUDGET REVISED PROPOSED CHANGE
10-11 SALARIES $ 333,501 $ 255,857 $ 293,454 $ 295,700 $ 255,500 $ 235,600 -20%
10-12 OVERTIME 8,514 14,238 11,771 10,500 10,500 6,400 -39%
10-13 TEMPORARY HELP - 10,793 - - - - 0%
10-14 FICA TAXES 26,417 20,731 22,140 23,400 24,300 18,500 -21%
10-15 HEALTH INSURANCE 65,290 51,644 61,893 72,800 56,800 47,500 -35%
10-16 L I D INSURANCE 1,566 1,303 1,533 1,500 1,500 1,100 -27%
10-17 WORKERS COMPENSATION 13,880 9,278 10,114 12,300 12,700 12,200 -1%
10-19 PENSION 12,246 69,714 78,741 79,900 79,900 115,400 44%
10-20 OPEB 25,502 26,821 34,357 35,100 31,600 22,800 -35%
PERSONNEL COSTS 486,916 460,378 514,003 531,200 472,800 459,500 -13%
20-25 CUSTODIAL 8,137 7,453 8,893 8,500 8,500 8,500 0%
20-29 UNIFORMS/UNIFORM ALLOW 2,628 2,429 3,371 2,900 2,900 2,300 -21%
20-32 SECURITY/SAFETY MATERIALS 16,790 7,254 109 200 200 200 0%
20-33 SMALL TOOLS 396 427 3,008 2,700 2,700 1,500 -44%
20-38 COMPUTER HARDWARE - - 1,092 300 300 - -100%
20-46 CITY BLDG MAINT SUPPLIES 9,017 10,675 5,756 9,000 6,000 8,000 -11%
20-58 WATER/SEWER 1,645 1,618 1,309 1,700 1,700 1,700 0%
20-61 ELEC MATERIALS/SUPPLIES 1,434 2,607 2,158 2,200 2,200 2,200 0%
MATERIALS & SUPPLIES 40,046 32,462 25,696 27,500 24,500 24,400 -11%
30-21 TELEPHONE/FAX 1,223 1,231 1,235 1,200 1,200 1,200 0%
30-23 ELECTRICITY 76,404 67,537 67,021 65,000 65,000 65,000 0%
30-24 HEATING OIL/GAS 2,250 1,095 8,379 6,400 6,400 6,400 0%
30-27 SUBSCRIPTIONS & DUES - - - 100 100 100 0%
30-28 TRAINING/CONF/FOOD/TRAVEL - 185 130 100 100 100 0%
30-31 CONTRACTUAL SERVICES 22,500 66,471 67,191 66,500 117,600 47,000 -29%
30-62 GASOLINE 4,133 4,386 4,142 4,000 4,000 3,000 -25%
30-67 RADIO REPAIRS/MAINTENANCE 5,277 570 365 500 500 400 -20%
ADMINISTRATIVE EXPENDITURES 111,787 141,475 148,463 143,800 194,900 123,200 -14%
OPERATING EXPENDITURES 638,748 634,315 688,162 702,500 692,200 607,100 -14%
40-23 TRUCKS-PURCHASE - 17,795 - - - 27,700 0%
40-25 OTHER EQUIP - PURCHASE 109,875 - - - - - 0%
CAPITAL OUTLAY 109,875 17,795 - - - 27,700 0%
TOTAL EXPENDITURES $ 748,623 $ 652,110 $ 688,162 $ 702,500 $ 692,200 $ 634,800 -10%
OPERATING BUDGET STATS $ 638,748 $ 634,315 $ 688,162 $ 702,500 $ 692,200 $ 607,100
ACTUAL % OF OPER BUDGET 100% 100% 100% 100% 100% 100%
BUDGET % CHANGE -24% -1% 8% 2% -1% -12%
REVENUES
GENERAL FUND $ 638,748 $ 634,315 $ 688,162 $ 702,500 $ 692,200 $ 607,100
GOV. CAPITAL PROJECT FUND 16,875 (75,205) - - - 27,700
HOMELAND SECURITY GRANT 93,000 93,000 - - - -
PERSONNEL
BUDGETED FULL-TIME POSITIONS 9.0 9.0 7.0 7.0 7.0 5.0
PP/TEMP - - - - - -
270
Página 277
FY 2017 DRAFT ANNUAL OPERATING BUDGET - DOVER, DELAWARE
FLEET MAINTENANCE
110-2800-572
2012-2013 2013-2014 2014-2015 2015-2016 2015-2016 2016-2017 %
ACCT DESCRIPTION ACTUAL ACTUAL ACTUAL BUDGET REVISED PROPOSED CHANGE
10-11 SALARIES $ 232,542 $ 269,081 $ 271,621 $ 267,700 $ 267,700 $ 283,400 6%
10-12 OVERTIME 773 10,451 6,302 1,000 7,000 6,700 570%
10-14 FICA 17,075 20,298 20,430 20,500 20,500 22,200 8%
10-15 HEALTH INSURANCE 57,495 64,275 54,157 73,200 58,700 65,000 -11%
10-16 LID 1,140 1,367 1,339 1,500 1,500 1,500 0%
10-17 WORKERS COMPENSATION 9,455 9,233 9,203 10,800 10,800 14,500 34%
10-19 PENSION 11,792 66,730 51,801 48,300 48,300 45,700 -5%
10-20 OPEB 19,635 27,783 29,247 31,800 31,800 27,200 -14%
PERSONNEL COSTS 349,907 469,219 444,099 454,800 446,300 466,200 3%
20-23 PRINTING AND DUPLICATING - 101 - - - - 0%
20-26 PROGRAM EXPENSES/SUPPLIES 269,763 287,716 322,924 275,000 275,000 275,000 0%
20-29 UNIFORMS/UNIFORM ALLOW 1,036 1,312 1,174 1,400 1,400 1,400 0%
20-31 BOOKS 399 599 489 600 600 600 0%
20-32 SECURITY/SAFETY MATERIALS 730 1,094 227 400 400 400 0%
20-33 SMALL TOOLS 883 1,658 1,491 17,000 17,000 15,000 -12%
20-37 COMPUTER SOFTWARE 1,389 5,781 4,921 6,200 6,200 5,100 -18%
20-38 COMPUTER HARDWARE - - 1,199 - - 1,100 0%
20-46 CITY BLDG MAINT SUPPLIES - 7,986 5,312 6,500 6,500 5,500 -15%
MATERIALS & SUPPLIES 274,200 306,247 337,737 307,100 307,100 304,100 -1%
30-21 TELEPHONE/FAX 494 649 663 1,100 1,100 1,100 0%
30-28 TRAINING/CONF/FOOD/TRAVEL 50 346 913 2,500 2,500 2,000 -20%
30-31 CONTRACTUAL SERVICES - 24 - 500 500 500 0%
30-43 ENVIRONMENTAL EXPENSES 400 200 200 200 200 200 0%
30-62 GASOLINE 1,946 2,909 2,516 1,800 1,800 1,800 0%
30-67 RADIO REPAIRS/MAINTENANCE 3,689 491 371 500 500 400 -20%
ADMINISTRATIVE EXPENDITURES 6,580 4,619 4,663 6,600 6,600 6,000 -9%
OPERATING EXPENDITURES 630,686 780,084 786,500 768,500 760,000 776,300 1%
40-23 TRUCKS - PURCHASE - - - 84,000 84,500 31,000 -63%
CAPITAL OUTLAY - - - 84,000 84,500 31,000 -63%
TOTAL EXPENDITURES $ 630,686 $ 780,084 $ 786,500 $ 852,500 $ 844,500 $ 807,300 -5%
OPERATING BUDGET STATS $ 630,686 $ 780,084 $ 786,500 $ 768,500 $ 760,000 $ 776,300
ACTUAL % OF OPER BUDGET 100% 100% 100% 100% 100% 100%
BUDGET % CHANGE -14% 24% 1% -2% -1% 2%
REVENUES
GENERAL FUND $ 630,686 $ 780,084 $ 786,500 $ 768,500 $ 760,000 $ 776,300
GOV. CAPITAL PROJECT FUND - 84,000 84,500 31,000
PERSONNEL
BUDGETED FULL-TIME POSITIONS 6.0 6.0 6.0 6.0 6.0 6.0
271
Página 278
FY 2017 DRAFT ANNUAL OPERATING BUDGET - DOVER, DELAWARE
GROUNDS
110-1500-522
2012-2013 2013-2014 2014-2015 2015-2016 2015-2016 2016-2017 %
ACCT DESCRIPTION ACTUAL ACTUAL ACTUAL BUDGET REVISED PROPOSED CHANGE
10-11 SALARIES $ 523,548 $ 443,450 $ 389,631 $ 495,300 $ 427,900 $ 495,400 0%
10-12 OVERTIME 10,147 15,057 12,002 8,300 13,300 12,200 47%
10-13 TEMPORARY HELP - - - - - 0%
10-14 FICA TAXES 40,186 34,204 29,366 38,500 34,500 38,800 1%
10-15 HEALTH INSURANCE 109,647 79,607 90,268 148,400 128,400 165,000 11%
10-16 L I D INSURANCE 3,011 2,135 2,006 2,800 2,800 2,800 0%
10-17 WORKERS COMPENSATION 21,398 15,134 13,303 20,000 20,600 25,500 28%
10-18 EDUCATIONAL ASSISTANCE - 0%
10-19 PENSION 24,355 183,267 138,898 152,300 132,300 165,900 9%
10-20 OPEB 45,640 40,196 45,042 57,900 52,900 47,800 -17%
PERSONNEL COSTS 777,930 813,049 720,515 923,500 812,700 953,400 3%
20-21 FURNITURE/FIXTURES - 0%
20-22 OFFICE SUPPLIES - - - - - - 0%
20-23 PRINTING AND DUPLICATING - 0%
20-25 CUSTODIAL 235 285 199 300 300 300 0%
20-26 PROGRAM EXPENSES/SUPPLIES 40,882 32,194 35,906 41,000 41,000 41,000 0%
20-28 MEDICAL SUP & PHYSICALS - - - - - - 0%
20-29 UNIFORMS/UNIFORM ALLOW 3,021 2,245 2,705 3,200 3,200 3,400 6%
20-31 BOOKS - 0%
20-32 SECURITY/SAFETY MATERIALS 2,725 2,634 1,527 1,800 1,800 1,600 -11%
20-33 SMALL TOOLS 2,945 3,135 2,159 3,000 3,000 3,000 0%
20-38 COMPUTER HARDWARE - - - 400 400 - -100%
20-44 SAND AND SALT 315 353 1,080 600 600 400 -33%
20-46 CITY BLDG MAINT SUPPLIES 322 35 498 800 800 500 -38%
20-58 WATER/SEWER 2,718 1,854 2,456 3,200 3,200 3,000 -6%
MATERIALS & SUPPLIES 53,163 42,736 46,530 54,300 54,300 53,200 -2%
30-21 TELEPHONE/FAX 507 471 471 1,100 1,100 1,100 0%
30-23 ELECTRICITY 2,899 2,078 2,229 4,300 4,300 4,000 -7%
30-24 HEATING OIL/GAS 5,446 6,093 6,691 7,500 7,500 6,000 -20%
30-25 ADVERTISEMENT - 0%
30-27 SUBSCRIPTIONS AND DUES 435 260 416 500 500 500 0%
30-28 TRAINING/CONF/FOOD/TRAVEL 1,226 1,121 1,711 1,600 1,600 1,600 0%
30-31 CONTRACTUAL SERVICES 23,282 96,425 104,763 141,500 185,000 112,800 -20%
30-43 ENVIRONMENTAL EXPENSES 13,148 3,335 3,585 3,700 3,700 3,700 0%
30-44 AGENCY BILLING-TEMP HELP 20,507 22,040 26,794 31,000 31,000 31,000 0%
30-62 GASOLINE 32,037 29,384 23,626 25,000 15,000 18,000 -28%
30-65 MAINT EQUIP REPAIRS/MAINT 14,291 12,163 13,641 15,000 15,000 15,000 0%
30-67 RADIO REPAIRS/MAINTENANCE 16,618 1,979 1,186 1,300 1,300 1,000 -23%
ADMINISTRATIVE EXPENDITURES 130,396 175,349 185,113 232,500 266,000 194,700 -16%
OPERATING EXPENSES 961,489 1,031,134 952,159 1,210,300 1,133,000 1,201,300 -1%
40-23 TRUCKS - PURCHASE 39,157 - 65,947 94,900 96,100 31,200 -67%
40-24 MAINT EQUIP - PURCHASE 72,610 30,249 - 106,200 89,100 27,000 -75%
CAPITAL OUTLAY 111,767 30,249 65,947 201,100 185,200 58,200 -71%
TOTAL EXPENDITURES $ 1,073,256 $ 1,061,383 $ 1,018,106 $ 1,411,400 $ 1,318,200 $ 1,259,500 -11%
OPERATING BUDGET STATS $ 961,489 $ 1,031,134 $ 952,159 $ 1,210,300 $ 1,133,000 $ 1,201,300
ACTUAL % OF OPER BUDGET 100% 100% 100% 100% 100% 100%
BUDGET % CHANGE 0% 7% -8% 27% -6% 6%
REVENUES
GENERAL FUND $ 961,489 $ 1,031,134 $ 952,159 $ 1,210,300 $ 1,133,000 $ 1,201,300
GOV. CAPITAL PROJECT FUND 111,767 30,249 65,947 201,100 185,200 58,200
PERSONNEL
BUDGETED FULL-TIME POSITIONS 14.0 13.0 13.0 13.0 13.0 13.0
BUDGETED PART-TIME POSITIONS - - 1.0 - - -
272
Página 279
FY 2017 DRAFT ANNUAL OPERATING BUDGET - DOVER, DELAWARE
SANITATION
110-1800-555
2012-2013 2013-2014 2014-2015 2015-2016 2015-2016 2016-2017 %
ACCT DESCRIPTION ACTUAL ACTUAL ACTUAL BUDGET REVISED PROPOSED CHANGE
10-11 SALARIES $ 365,463 $ 394,767 $ 409,168 $ 372,300 $ 374,000 $ 382,100 3%
10-12 OVERTIME 13,406 26,215 17,988 12,100 16,100 17,500 45%
10-14 FICA TAXES 28,287 31,054 31,619 29,400 30,700 30,500 4%
10-15 HEALTH INSURANCE 82,618 82,708 87,235 104,500 89,500 111,000 6%
10-16 L I D INSURANCE 2,074 2,062 2,206 1,800 1,800 1,700 -6%
10-17 WORKERS COMPENSATION 15,368 13,913 14,156 15,500 16,200 20,100 30%
10-19 PENSION 17,298 121,754 124,738 104,300 101,800 133,100 28%
10-20 OPEB 31,803 41,110 48,295 43,800 43,800 36,900 -16%
PERSONNEL COSTS 556,317 713,584 735,405 683,700 673,900 732,900 7%
20-26 PROGRAM EXPENSES/SUPPLIES 11,476 20,586 29,843 20,000 23,000 20,000 0%
20-29 UNIFORMS/UNIFORM ALLOW 2,190 2,272 2,431 2,700 2,700 2,900 7%
20-32 SECURITY/SAFETY MATERIALS 1,983 2,496 910 1,000 1,000 1,000 0%
20-33 SMALL TOOLS 246 287 181 400 400 300 -25%
20-38 COMPUTER HARDWARE - - - 400 400 - -100%
20-46 CITY BLDG MAINT SUPPLIES 865 1,612 661 500 500 500 0%
MATERIALS & SUPPLIES 16,762 27,253 34,027 25,000 28,000 24,700 -1%
30-21 TELEPHONE/FAX 468 571 508 300 300 300 0%
30-25 ADVERTISEMENT 453 673 673 700 700 700 0%
30-28 TRAINING/CONF/FOOD/TRAVEL 40 610 1,975 100 100 100 0%
30-31 CONTRACTUAL SERVICES 1,215,190 1,252,670 1,278,757 1,306,600 1,306,600 1,157,800 -11%
30-43 ENVIRONMENTAL EXPENSES 5,837 1,951 1,607 5,000 5,000 5,000 0%
30-44 AGENCY BILLING-TEMP HELP 74,418 38,506 40,145 35,000 62,000 35,000 0%
30-62 GASOLINE 120,912 120,599 91,119 100,000 73,000 75,000 -25%
30-64 TRUCK REPAIRS/MAINTENANCE - (1,856) - - - - 0%
30-67 RADIO REPAIRS/MAINTENANCE 13,490 1,666 1,193 1,500 1,500 1,300 -13%
ADMINISTRATIVE EXPENDITURES 1,430,808 1,415,391 1,415,977 1,449,200 1,449,200 1,275,200 -12%
OPERATING EXPENSES 2,003,887 2,156,228 2,185,408 2,157,900 2,151,100 2,032,800 -6%
40-23 TRUCKS - PURCHASE 130,758 387,504 247,858 449,000 449,000 261,500 -42%
CAPITAL OUTLAY 130,758 387,504 247,858 449,000 449,000 261,500 -42%
TOTAL EXPENDITURES $ 2,134,645 $ 2,543,731 $ 2,433,267 $ 2,606,900 $ 2,600,100 $ 2,294,300 -12%
OPERATING BUDGET STATS $ 2,003,887 $ 2,156,228 $ 2,185,408 $ 2,157,900 $ 2,151,100 $ 2,032,800
ACTUAL % OF OPER BUDGET 100% 100% 100% 100% 100% 100%
BUDGET % CHANGE -4% 8% 1% -1% 0% -5%
REVENUES
GENERAL FUND $ 2,003,887 $ 2,156,228 $ 2,185,408 $ 2,157,900 $ 2,151,100 $ 2,032,800
GOV. CAPITAL PROJECT FUND 130,758 387,504 247,858 449,000 449,000 261,500
PERSONNEL
BUDGETED FULL-TIME POSITIONS 11.0 11.0 11.0 10.0 10.0 10.0
273
Página 280
FY 2017 DRAFT ANNUAL OPERATING BUDGET - DOVER, DELAWARE
STREET
110-1800-554
2012-2013 2013-2014 2014-2015 2015-2016 2015-2016 2016-2017 %
ACCT DESCRIPTION ACTUAL ACTUAL ACTUAL BUDGET REVISED PROPOSED CHANGE
10-11 SALARIES $ 363,352 $ 241,483 $ 221,369 $ 287,200 $ 263,000 $ 308,500 7%
10-12 OVERTIME 4,465 10,867 7,574 4,100 8,100 7,900 93%
10-14 FICA TAXES 28,166 18,354 16,404 22,300 22,400 24,200 9%
10-15 HEALTH INSURANCE 74,415 64,580 65,653 101,900 81,900 118,700 16%
10-16 L I D INSURANCE 1,905 1,329 1,267 1,600 1,600 1,800 13%
10-17 WORKERS COMPENSATION 11,630 8,013 7,578 11,700 11,700 15,900 36%
10-18 EDUCATIONAL ASSISTANCE 1,687 570 - - - - 0%
10-19 PENSION 15,679 70,123 52,677 46,400 46,400 82,200 77%
10-20 OPEB 27,945 24,877 25,908 34,100 31,600 29,800 -13%
PERSONNEL COSTS 529,244 440,197 398,432 509,300 466,700 589,000 16%
20-26 PROGRAM EXPENSES/SUPPLIES 31,104 23,701 858 35,000 15,000 186,900 434%
20-29 UNIFORMS/UNIFORM ALLOW 2,148 2,080 1,634 2,100 2,100 2,000 -5%
20-32 SECURITY/SAFETY MATERIALS 2,039 2,252 1,117 2,000 2,000 1,500 -25%
20-33 SMALL TOOLS 2,433 2,810 2,341 2,500 2,500 2,500 0%
20-38 COMPUTER HARDWARE - - - 400 400 1,100 175%
20-41 STREET REPAIRING MATERIAL 7,171 9,385 11,631 10,000 10,000 10,000 0%
20-42 STREET CLEANING SUPPLIES 2,514 1,887 2,357 3,000 3,000 3,000 0%
20-43 STREET SIGNS/MARKING 22,037 15,367 17,323 16,000 16,000 16,000 0%
20-44 SAND AND SALT 6,593 23,484 20,559 10,000 10,000 13,800 38%
20-46 CITY BLDG MAINT SUPPLIES 10,137 279 50 200 200 200 0%
20-62 STORM SEWER SUPPLIES - 2,910 8,373 10,000 10,000 10,000 0%
20-64 DITCH MAINTENANCE 26 11,862 56 - - - 0%
MATERIALS & SUPPLIES 86,202 96,017 66,299 91,200 71,200 247,000 171%
30-21 TELEPHONE/FAX 461 451 518 800 800 800 0%
30-25 ADVERTISEMENT 792 495 670 700 700 700 0%
30-28 TRAINING/CONF/FOOD/TRAVEL 8,790 2,327 680 100 100 100 0%
30-29 CONSULTING FEES 893 - - 1,500 1,500 1,500 0%
30-31 CONTRACTUAL SERVICES 590 31,450 16,585 1,200 1,200 264,900 21975%
30-43 ENVIRONMENTAL EXPENSES - - 1,939 2,000 2,000 2,000 0%
30-44 AGENCY BILLING-TEMP HELP 4,294 13,867 16,951 15,000 25,000 15,000 0%
30-62 GASOLINE 48,443 52,640 39,391 46,000 30,000 38,000 -17%
30-65 MAINT EQUIP REPAIRS/MAINT 8,023 1,740 1,000 5,000 5,000 3,000 -40%
30-67 RADIO REPAIRS/MAINTENANCE 17,340 1,985 1,369 1,700 1,700 1,500 -12%
30-99 SNOW EMERGENCY - - - - 52,600 - 0%
ADMINISTRATIVE EXPENDITURES 89,624 104,953 79,101 74,000 120,600 327,500 343%
OPERATING EXPENDITURES 705,071 641,167 543,832 674,500 658,500 1,163,500 72%
40-23 TRUCKS - PURCHASE 16,704 138,789 170,086 38,500 46,000 - -100%
40-25 OTHER EQUIPMENT PURCHASE - 38,300 130,808 - - - 0%
40-31 CONSTRUCTION - PURCHASE 134,010 1,272,104 3,296,269 1,390,000 3,689,000 1,026,000 -26%
CAPITAL OUTLAY 150,714 1,449,193 3,597,163 1,428,500 3,735,000 1,026,000 -28%
TOTAL EXPENDITURES $ 855,785 $ 2,090,359 $ 4,140,995 $ 2,103,000 $ 4,393,500 $ 2,189,500 4%
OPERATING BUDGET STATS $ 705,071 $ 641,167 $ 543,832 $ 674,500 $ 658,500 $ 1,163,500
ACTUAL % OF OPER BUDGET 100% 100% 100% 100% 100% 100%
BUDGET % OF CHANGE -19% -9% -15% 24% -2% 77%
REVENUES
GENERAL FUND $ 705,071 $ 641,167 $ 543,832 $ 674,500 $ 658,500 $ 1,163,500
GOV. CAPITAL PROJECT FUND 150,714 1,449,193 3,597,163 1,428,500 3,735,000 1,026,000
PERSONNEL
BUDGETED FULL-TIME POSITIONS 10.0 8.0 8.0 8.0 8.0 8.0
274
Página 281
PUBLIC WORKS WATER/
WASTEWATER
ELECTRIC
Página 283
WATER/WASTEWATER FUND
BUDGET REVIEW
Fiscal Year 2016-2017
May 2016 – Budget Review Hearing
277
Página 284
Water/Wastewater Engineering
Personnel Costs 453,600 0%
Materials & Supplies 16,300 17%
Administrative Expenditures 46,600 7%
Overall Operating Expenses 516,500 0%
Capital Outlay 30,400 0%
Total Expenditures 546,900 6%
Highlights:
Materials & Supplies expenditures are increased by $2,400 for computer
hardware and books.
Administrative expenditures are decreased by $2,500 for subscriptions and dues
and $1,200 for gasoline.
278
Página 285
Water Management
Personnel Costs 527,400 1%
Materials & Supplies 71,800 4%
Administrative Expenditures 56,200 23%
Overall Operating Expenses 655,400 3%
Capital Outlay 1,338,800 34%
Total Expenditures 1,994,200 26%
Highlights:
Personnel costs decreased as a result of lower OPEB costs.
Materials & Supplies increased by $2,800 due to increases in medical supplies and computer
hardware.
Administrative Expenditures decreased $16,600 for gasoline, training/conf./food/travel,
contractual services, maintenance equip repairs and radio repairs/maintenance.
Capital Expenses decreased by $790,700 mainly due to the transfer of Water Treatment Plant
Process Improvements to Water Treatment Plant Division. Capital Expenses increased
$88,100 for vehicles and other equipment.
279
Página 286
Wastewater Management
Personnel Costs 654,400 2%
Materials & Supplies 88,200 6%
Administrative Expenditures 219,800 9%
Overall Operating Expenses 962,400 1%
Capital Outlay 2,021,200 11%
Total Expenditures 2,983,600 7%
Highlights:
Personnel costs increased $30,100 due wages and worker’s compensation with an offsetting
decrease of $19,100 in OPEB, pension and overtime.
Materials & Supplies increased $3,500 in medical supplies and small increases for
security/safety materials and computer hardware.
Administrative Expenses decreased $22,200 in gasoline, electricity, and radio repairs and
maintenance.
Capital Expenses have increased by $199,100.
280
Página 287
Water Treatment
Personnel Costs 1,040,100 3%
Materials & Supplies 159,800 10%
Administrative Expenditures 527,500 27%
Overall Operating Expenses 1,727,400 10%
Capital Outlay 1,200,000 0%
Total Expenditures 2,927,400 53%
Highlights:
Personnel costs are increased for wages and benefit costs offset by a decrease in
OPEB cost.
Materials & Supplies decreased by $20,000 for chemicals and additives due to
decreased water demand from Garrison Energy Center and increased $2,700 in
computer hardware.
Administrative Expenditures decreased $160,000 in electricity as a result of
Calpine demand, $28,800 in contractual services and $2,000 in gasoline.
Capital Outlay increased $1,200,000 due to Water Treatment Plant Process
Improvements incorrectly budgeted in Water Management last fiscal year.
281
Página 288
FY 2017 ANNUAL OPERATING BUDGET - DOVER, DELAWARE
CITY MANAGER
DEPARTMENT OF PUBLIC WORKS - WATER / WASTEWATER FUND
FISCAL YEAR 2017 ORGANIZATION CHART
PUBLIC WORKS DIRECTOR / CITY ENGINEER
1 (accounted for in Public Works Administration)
WATER WASTEWATER WATER TREATMENT WATER / WASTEWATER
MANAGEMENT MANAGEMENT & PRODUCTION ENG. & INSPECTIONS
PUBLIC WORKS OPERATIONS MANAGER WATER / WW MANAGER
1 (accounted for in Public Works Administration) 1
WATER / WASTEWATER MAINTENANCE SUPERVISOR WATER PROD. SUPER. CIVIL ENGINEER I
1 (accounted for in Water Management) 1 2
UTIL. CON. CREW LEADER UTILITY MAINT. MECH. II WATER TR. PLANT OP. II CONSTRUCTION MGR.
1 3 4 1
CREW LEADER UTILITY MAINT. MECH. I UTILITY MAINT. MECH. II PUBLIC WORKS INSPECT.
1 3 1 1
HEAVY EQUIP. OPER. I WATER SERVICE PERSON WATER TR. PLANT OP. I 5
1 1 7
MOTOR EQUIP. OPER. III MOTOR EQUIP. OPER. II 13
1 2
MOTOR EQUIP. OPER. II MOTOR EQUIP. OPER. I
1 2
35
6 11
282
Página 289
FY 2017 DRAFT ANNUAL OPERATING BUDGET - DOVER, DELAWARE
WATER/WASTEWATER ENGINEERING
412/417-2600-553
2012-2013 2013-2014 2014-2015 2015-2016 2015-2016 2016-2017 %
ACCT DESCRIPTION ACTUAL ACTUAL ACTUAL BUDGET REVISED PROPOSED CHANGE
10-11 SALARIES $ 319,364 $ 243,209 $ 285,409 $ 303,400 $ 311,100 $ 311,800 3%
10-12 OVERTIME 949 927 943 800 800 1,000 25%
10-13 TEMPORARY HELP - 10,244 - - - - 0%
10-14 FICA TAXES 23,723 18,781 21,158 23,300 23,600 23,900 3%
10-15 HEALTH INSURANCE 48,610 39,707 42,421 52,400 52,400 52,000 -1%
10-16 L I D INSURANCE 1,818 1,341 1,468 1,900 1,900 1,900 0%
10-17 WORKERS COMPENSATION 2,694 896 1,003 1,200 1,200 1,300 8%
10-19 PENSION 14,684 67,034 43,909 45,400 45,400 49,900 10%
10-20 OPEB 18,007 16,159 15,163 25,300 20,300 11,800 -53%
PERSONNEL COSTS 429,849 398,297 411,473 453,700 456,700 453,600 0%
20-22 OFFICE SUPPLIES 861 2,522 3,818 2,700 2,700 2,700 0%
20-29 UNIFORMS/UNIFORM ALLOW 38 - 300 200 200 200 0%
20-31 BOOKS 155 - 420 400 400 800 100%
20-32 SECURITY/SAFETY MATERIALS 947 806 244 300 300 300 0%
20-33 SMALL TOOLS - 40 56 100 100 100 0%
20-37 COMPUTER SOFTWARE 7,920 8,116 11,818 9,800 9,800 9,800 0%
20-38 COMPUTER HARDWARE - - 1,296 400 400 2,400 500%
MATERIALS & SUPPLIES 9,920 11,484 17,952 13,900 13,900 16,300 17%
30-21 TELEPHONE/FAX 766 1,342 1,138 1,400 1,400 1,700 21%
30-27 SUBSCRIPTIONS AND DUES 1,332 1,116 540 6,600 6,600 4,100 -38%
30-28 TRAINING/CONF/FOOD/TRAVEL 50 2,398 1,147 900 900 1,100 22%
30-31 CONTRACTUAL SERVICES 33,678 34,964 30,696 35,000 35,000 35,000 0%
30-39 IN-HOUSE TRAINING 650 2,825 1,575 1,500 1,500 1,500 0%
30-62 GASOLINE 5,946 6,138 3,820 4,000 4,000 2,800 -30%
30-67 RADIO REPAIRS/MAINTENANCE 4,523 408 365 500 500 400 -20%
ADMINISTRATIVE EXPENDITURES 46,945 49,192 39,281 49,900 49,900 46,600 -7%
OPERATING EXPENDITURES 486,714 458,973 468,706 517,500 520,500 516,500 0%
40-23 TRUCKS - PURCHASE 29,208 - - - - 30,400 0%
CAPITAL OUTLAY 29,208 - - - - 30,400 0%
TOTAL EXPENDITURES $ 515,922 $ 458,973 $ 468,706 $ 517,500 $ 520,500 $ 546,900 6%
OPERATING BUDGET STATS $ 486,714 $ 458,973 $ 468,706 $ 517,500 $ 520,500 $ 516,500
ACTUAL % OF OPER BUDGET 100% 100% 100% 100% 100% 100%
BUDGET % CHANGE -4% -6% 2% 10% 1% -1%
REVENUES
WATER/WASTEWATER FUND $ 486,714 $ 458,973 $ 468,706 $ 517,500 $ 520,500 $ 516,500
WATER/WASTEWATER I & E FUND 29,208 - - - - 30,400
PERSONNEL
BUDGETED FULL-TIME POSITIONS 6.0 6.0 5.0 5.0 5.0 5.0
283
Página 290
FY 2017 DRAFT ANNUAL OPERATING BUDGET - DOVER, DELAWARE
WATER MANAGEMENT
412/417-6800-568
2012-2013 2013-2014 2014-2015 2015-2016 2015-2016 2016-2017 %
ACCT DESCRIPTION ACTUAL ACTUAL ACTUAL BUDGET REVISED PROPOSED CHANGE
10-11 SALARIES $ 146,288 $ 187,126 $ 154,580 $ 279,700 $ 284,000 $ 289,200 3%
10-12 OVERTIME 7,354 11,755 8,632 13,400 14,700 12,000 -10%
10-14 FICA TAXES 11,138 14,772 11,981 22,400 22,700 23,000 3%
10-15 HEALTH INSURANCE 76,590 54,365 39,661 81,400 78,900 78,000 -4%
10-16 L I D INSURANCE 1,540 1,077 894 1,600 1,600 1,600 0%
10-17 WORKERS COMPENSATION 6,156 6,568 5,408 11,800 12,000 15,200 29%
10-19 PENSION 6,787 67,879 46,449 98,300 98,300 97,700 -1%
10-20 OPEB 18,163 15,533 12,515 22,900 22,900 10,700 -53%
PERSONNEL COSTS 274,016 359,076 280,120 531,500 535,100 527,400 -1%
20-28 MEDICAL SUP & PHYSICALS 100 100 515 600 600 2,500 317%
20-29 UNIFORMS/UNIFORM ALLOW 609 783 593 1,400 1,400 1,400 0%
20-32 SECURITY/SAFETY MATERIALS 727 970 123 1,300 1,300 1,300 0%
20-33 SMALL TOOLS 7,215 6,125 6,220 5,500 5,500 5,500 0%
20-38 COMPUTER HARDWARE - - - 200 200 1,100 450%
20-46 CITY BLDG MAINT SUPPLIES 4 - - - - - 0%
20-51 WATER/SEWER SYSTEM SUP 49,200 50,297 65,653 50,000 50,000 50,000 0%
20-53 METERS/METER SUPPLIES 11,901 9,928 9,427 10,000 10,000 10,000 0%
20-54 PUMPING STATION SUPPLIES - 130 - - - - 0%
MATERIALS & SUPPLIES 69,755 68,332 82,531 69,000 69,000 71,800 4%
30-21 TELEPHONE/FAX 4,126 3,907 4,067 4,000 4,000 4,000 0%
30-25 ADVERTISEMENT 2,340 2,478 2,562 2,500 2,500 2,500 0%
30-27 SUBSCRIPTIONS AND DUES 2,837 2,800 2,901 2,900 2,900 2,900 0%
30-28 TRAINING/CONF/FOOD/TRAVEL 60 3,356 2,839 2,800 2,800 1,800 -36%
30-29 CONSULTING FEES 941 1,683 1,880 2,000 2,000 2,000 0%
30-31 CONTRACTUAL SERVICES 26,120 47,214 8,259 28,000 28,000 25,000 -11%
30-62 GASOLINE 19,772 19,877 15,466 28,000 16,000 16,000 -43%
30-64 TRUCK REPAIRS/MAINTENANCE - 8 (1,668) - - - 0%
30-65 MAINT EQUIP REPAIRS/MAINT 368 349 300 1,200 1,200 1,000 -17%
30-67 RADIO REPAIRS/MAINTENANCE 15,366 817 274 1,400 1,400 1,000 -29%
ADMINISTRATIVE EXPENDITURES 71,929 82,489 36,880 72,800 60,800 56,200 -23%
OPERATING EXPENDITURES 415,700 509,897 399,530 673,300 664,900 655,400 -3%
40-23 TRUCKS - PURCHASE 153,036 26,780 - 44,100 104,000 132,200 200%
40-25 OTHER EQUIP - PURCHASE 19,128 - - - - 200,000 0%
40-31 CONSTRUCTION - PURCHASE 915,012 1,341,979 3,392,546 1,984,500 5,338,600 993,800 -50%
40-34 WATER LINES 67,675 - - - - - 0%
CAPITAL OUTLAY 1,154,852 1,368,759 3,392,546 2,028,600 5,442,600 1,338,800 -34%
TOTAL EXPENDITURES $ 1,570,552 $ 1,878,655 $ 3,792,076 $ 2,701,900 $ 6,107,500 $ 1,994,200 -26%
OPERATING BUDGET STATS $ 415,700 $ 509,897 $ 399,530 $ 673,300 $ 664,900 $ 655,400
ACTUAL % OF OPER BUDGET 100% 100% 100% 100% 100% 100%
BUDGET % CHANGE 5% 23% -22% 69% -1% -1%
REVENUES
WATER/WASTEWATER FUND $ 415,700 $ 509,897 $ 399,530 $ 673,300 $ 664,900 $ 655,400
WATER/WASTEWATER I & E FUND 1,154,852 1,368,759 3,392,546 2,028,600 5,442,600 1,338,800
PERSONNEL
BUDGETED FULL-TIME POSITIONS 5.0 5.0 4.0 6.0 6.0 6.0
284
Página 291
FY 2017 DRAFT ANNUAL OPERATING BUDGET - DOVER, DELAWARE
WASTE WATER MANAGEMENT
412/417-6900-569
2012-2013 2013-2014 2014-2015 2015-2016 2015-2016 2016-2017 %
ACCT DESCRIPTION ACTUAL ACTUAL ACTUAL BUDGET REVISED PROPOSED CHANGE
10-11 SALARIES $ 304,371 $ 293,585 $ 324,631 $ 374,300 $ 299,300 $ 396,100 6%
10-12 OVERTIME 26,562 24,351 23,559 27,000 14,000 25,000 -7%
10-14 FICA TAXES 25,167 23,281 25,370 30,700 25,700 32,200 5%
10-15 HEALTH INSURANCE 26,303 61,170 72,166 121,300 91,300 123,000 1%
10-16 L I D INSURANCE 756 1,441 1,605 1,900 1,900 2,000 5%
10-17 WORKERS COMPENSATION 13,355 10,501 10,987 16,200 14,200 21,200 31%
10-19 PENSION 14,252 57,039 39,070 42,300 40,300 40,300 -5%
10-20 OPEB 10,078 22,987 25,897 29,700 25,700 14,600 -51%
PERSONNEL COSTS 420,845 494,353 523,286 643,400 512,400 654,400 2%
20-28 MEDICAL SUP & PHYSICALS 88 75 - 700 700 4,200 500%
20-29 UNIFORMS/UNIFORM ALLOW 1,938 1,827 2,395 3,000 3,000 3,000 0%
20-32 SECURITY/SAFETY MATERIALS 2,591 2,725 1,630 3,000 3,000 3,600 20%
20-33 SMALL TOOLS 2,723 5,083 4,072 5,000 5,000 5,000 0%
20-35 CHEMICALS & ADDITIVES 2,117 2,734 - 2,000 2,000 2,000 0%
20-37 COMPUTER SOFTWARE 3,600 3,600 3,600 3,600 3,600 3,600 0%
20-38 COMPUTER HARDWARE - - - 200 200 1,100 450%
20-46 CITY BLDG MAINT SUPPLIES 300 308 46 500 500 500 0%
20-51 WATER/SEWER SYSTEM SUP 9,510 13,768 17,202 16,000 16,000 16,000 0%
20-53 METERS/METER SUPPLIES 11,952 9,676 9,987 10,000 10,000 10,000 0%
20-54 PUMPING STATION SUPPLIES 36,851 37,244 20,553 38,000 38,000 38,000 0%
20-58 WATER/SEWER 997 970 1,741 1,200 1,200 1,200 0%
MATERIALS & SUPPLIES 72,667 78,011 61,225 83,200 83,200 88,200 6%
30-21 TELEPHONE/FAX 4,126 3,970 4,030 4,000 4,000 4,000 0%
30-23 ELECTRICITY 171,042 155,493 134,248 155,000 148,000 145,000 -6%
30-24 HEATING OIL/GAS - - 3,065 - - - 0%
30-28 TRAINING/CONF/FOOD/TRAVEL 61 7,020 498 100 100 100 0%
30-29 CONSULTING FEES - 2,256 322 2,000 2,000 2,000 0%
30-31 CONTRACTUAL SERVICES 90,298 140,589 41,572 52,500 52,500 52,500 0%
30-62 GASOLINE 30,840 28,010 22,130 27,000 15,000 15,000 -44%
30-64 TRUCK REPAIRS/MAINTENANCE 4 54 (1,668) - - - 0%
30-65 MAINT EQUIP REPAIRS/MAINT 5,803 2,080 1,167 600 600 600 0%
30-67 RADIO REPAIRS/MAINTENANCE 6,865 1,551 649 800 800 600 -25%
ADMINISTRATIVE EXPENDITURES 309,039 341,024 206,013 242,000 223,000 219,800 -9%
OPERATING EXPENDITURES 802,551 913,389 790,525 968,600 818,600 962,400 -1%
40-23 TRUCKS - PURCHASE 234,994 26,780 - - 245,900 - 0%
40-24 MAINT EQUIP REPAIRS/MAINT - - - 59,600 59,600 47,200 -21%
40-25 OTHER EQUIPMENT 19,128 9,330 - - - 200,000 0%
40-31 CONSTRUCTION - PURCHASE 1,561,447 698,929 4,277,921 1,762,500 4,993,600 1,774,000 1%
40-35 SEWER LINES - - - - - - 0%
CAPITAL OUTLAY 1,815,569 735,039 4,277,921 1,822,100 5,299,100 2,021,200 11%
TOTAL EXPENDITURES $ 2,618,120 $ 1,648,428 $ 5,068,446 $ 2,790,700 $ 6,117,700 $ 2,983,600 7%
OPERATING BUDGET STATS $ 802,551 $ 913,389 $ 790,525 $ 968,600 $ 818,600 $ 962,400
ACTUAL % OF OPER BUDGET 100% 100% 100% 100% 100% 100%
BUDGET % CHANGE -9% 14% -13% 23% -15% 18%
REVENUES
WATER/WASTEWATER FUND $ 802,551 $ 913,389 $ 790,525 $ 968,600 $ 818,600 $ 962,400
WATER/WASTEWATER I & E FUND 1,815,569 735,039 4,277,921 1,822,100 5,299,100 2,021,200
PERSONNEL
BUDGETED FULL-TIME POSITIONS 10.0 10.0 11.0 11.0 11.0 11.0
285
Página 292
FY 2017 DRAFT ANNUAL OPERATING BUDGET - DOVER, DELAWARE
WATER TREATMENT PLANT
412/417-7600-576
2012-2013 2013-2014 2014-2015 2015-2016 2015-2016 2016-2017 %
ACCT DESCRIPTION ACTUAL ACTUAL ACTUAL BUDGET REVISED PROPOSED CHANGE
10-11 SALARIES $ 411,080 $ 450,665 $ 456,846 $ 576,500 $ 558,800 $ 589,400 2%
10-12 OVERTIME 34,107 24,591 26,750 32,300 49,300 30,000 -7%
10-14 FICA TAXES 32,751 34,229 34,787 46,500 47,000 47,400 2%
10-15 HEALTH INSURANCE 113,941 122,400 121,656 173,900 163,900 189,600 9%
10-16 L I D INSURANCE 2,272 2,395 2,441 3,100 3,100 3,200 3%
10-17 WORKERS COMPENSATION 18,052 15,697 16,044 24,600 24,900 31,200 27%
10-19 PENSION 20,019 127,835 114,908 112,600 124,600 127,100 13%
10-20 OPEB 28,426 36,227 37,429 45,100 45,100 22,200 -51%
PERSONNEL COSTS 660,649 814,038 810,861 1,014,600 1,016,700 1,040,100 3%
20-23 PRINTING AND DUPLICATING 399 565 - - - - 0%
20-25 CUSTODIAL 185 181 348 600 600 600 0%
20-29 UNIFORMS/UNIFORM ALLOW 3,316 2,704 3,266 5,100 5,100 5,100 0%
20-31 BOOKS 155 98 - - - - 0%
20-32 SECURITY/SAFETY MATERIALS 4,056 3,030 1,815 2,000 2,000 2,000 0%
20-33 SMALL TOOLS 1,156 3,826 4,492 4,500 4,500 4,500 0%
20-35 CHEMICALS & ADDITIVES 107,414 106,699 111,699 150,000 135,000 130,000 -13%
20-38 COMPUTER HARDWARE - - - 400 400 3,100 675%
20-46 CITY BLDG MAINT SUPPLIES 1,467 3,295 2,354 2,500 2,500 2,500 0%
20-49 WELL SUPPLIES/REHAB 12,041 10,982 8,645 12,000 12,000 12,000 0%
MATERIALS & SUPPLIES 130,189 131,381 132,618 177,100 162,100 159,800 -10%
30-21 TELEPHONE/FAX 182 188 190 500 500 500 0%
30-23 ELECTRICITY 431,649 361,885 382,997 600,000 450,000 440,000 -27%
30-24 HEATING OIL/GAS 1,565 5,544 8,130 6,000 6,000 6,000 0%
30-25 ADVERTISEMENT - - 517 500 500 500 0%
30-27 SUBSCRIPTIONS AND DUES 400 500 400 700 700 700 0%
30-28 TRAINING/CONF/FOOD/TRAVEL 180 180 412 700 700 700 0%
30-31 CONTRACTUAL SERVICES 147,493 156,908 99,030 88,600 88,600 59,800 -33%
30-62 GASOLINE 12,031 10,992 9,376 11,000 7,000 9,000 -18%
30-66 OTHER EQUIP REPAIRS/MAINT 1,558 7,357 7,350 10,000 10,000 10,000 0%
30-67 RADIO REPAIRS/MAINTENANCE 4,443 491 438 300 300 300 0%
ADMINISTRATIVE EXPENDITURES 599,501 544,046 508,839 718,300 564,300 527,500 -27%
OPERATING EXPENDITURES 1,390,340 1,489,465 1,452,318 1,910,000 1,743,100 1,727,400 -10%
40-23 TRUCKS - PURCHASE 29,208 - 33,771 - - - 0%
40-31 CONSTRUCTION PURCHASES - - - - 284,400 1,200,000 0%
CAPITAL OUTLAY 29,208 - 33,771 - 284,400 1,200,000 0%
TOTAL EXPENDITURES $ 1,419,548 $ 1,489,465 $ 1,486,089 $ 1,910,000 $ 2,027,500 $ 2,927,400 53%
OPERATING BUDGET STATS $ 1,390,340 $ 1,489,465 $ 1,452,318 $ 1,910,000 $ 1,743,100 $ 1,727,400
ACTUAL % OF OPER BUDGET 100% 100% 100% 100% 100% 100%
BUDGET % CHANGE -4% 7% -2% 32% -9% -1%
REVENUES
WATER/WASTEWATER FUND $ 1,390,340 $ 1,489,465 $ 1,452,318 $ 1,910,000 $ 1,743,100 $ 1,727,400
WATER/WASTEWATER I & E FUND 29,208 - 33,771 - 284,400 1,200,000
PERSONNEL
BUDGETED FULL-TIME POSITIONS 10.0 10.0 11.0 13.0 13.0 13.0
286
Página 294
ELECTRIC FUND
BUDGET REVIEW
Fiscal Year 2016-2017
May 2016 – Budget Review Hearing
288
Página 295
Electric Administration
Personnel Costs 479,700 29%
Materials & Supplies 149,500 2%
Administrative Expenditures 300,500 6%
Overall Operating Expenses 929,700 11%
Highlights:
Personnel Costs increased due to the transfer from General Fund – Customer Service
the Key Account position. Originally budgeted for in FY16. This position is currently
being recruited.
Materials and Supplies increased $3,000 in city building maintenance supplies and a
small decrease of $600 in computer hardware.
Administrative expenses increased by $29,400 for consulting fees and contractual
services offset by a decrease of $50,000 in legal expenses.
289
Página 296
Electric T&D
Personnel Costs 2,652,500 14%
Materials & Supplies 434,600 2%
Administrative Expenditures 518,600 6%
Overall Operating Expenses 3,605,700 11%
Capital Outlay 1,975,000 32%
Total Expenditures 5,580,700 20%
Highlights:
Personnel costs decreased $474,600 due to decrease in pension expense and OPEB
of $466,400 and $8,200 in overtime. Increase of $53,900 wage increases and health
insurance.
Materials & Supplies increased $10,000 in meters with an offsetting decrease of
$18,400 in electric material/supplies and computer hardware.
Administrative Expenses decreased $33,800 in gasoline, training/travel, and
environmental expenses.
Capital Outlay decreased $1,000,000 for New Developments and $397,600 for
vehicles. Increased $450,000 for Public Works wetlands project and $25,000 in
other equipment. 290
Página 297
Electric Engineering
Personnel Costs 941,500 11%
Materials & Supplies 61,000 5%
Administrative Expenditures 245,400 15%
Overall Operating Expenses 1,247,900 7%
Capital Outlay 910,700 47%
Total Budget 2,158,600 29%
Highlights:
Personnel Costs decreased $117,000 related to lower pension and OPEB expenses.
Materials & Supplies decreased by $10,900 for electric materials/supplies and computer hardware
and increased $7,600 for computer software.
Administrative Expenses increased by $39,200 for training/travel and contractual services and
decreased $6,800 in gasoline, other equipment repairs and electricity.
Capital Outlay decreased $813,600 overall mainly due to reduction in distribution upgrades and
69 kV wire replacements.
291
Página 298
Meter Reading
Personnel Costs 350,600 8%
Materials & Supplies 14,900 11%
Administrative Expenditures 13,100 28%
Overall Operating Expenses 378,600 5%
Highlights:
Personnel costs increased by $25,200 overall for an on-call employee to fill-in during
absences and increased health insurance attributed to a budget miss of one employee’s
coverage in the prior year.
Materials and Supplies decreased by $2,200 for meter reading supplies,
security/safety materials and furniture/fixtures offset by a small increase of $300 in
uniforms. (Note – Percentage appears high because this is not a large budget.)
Administrative Expenses decreased $5,000 in gasoline and $200 in radio repairs and
maintenance.
292
Página 299
Systems Operations
Personnel Costs 651,700 4%
Materials & Supplies 0 0%
Overall Operating Expenses 651,700 4%
Highlights:
Personnel Costs related to overtime and health insurance increased. These items
were offset by decreases in pension and OPEB cost.
293
Página 300
Power Plant Operations
Personnel Costs 3,654,000 14%
Materials & Supplies 244,200 1%
Administrative Expenditures 2,317,500 20%
Overall Operating Expenditures 6,215,700 3%
Capital Outlay 1,842,800 11%
Total Expenditures 8,058,500 0%
Highlights:
Personnel Costs reflect a decrease attributed to contract changes in which the employee
incentives are now included with the NAES incentive in a separate line item, as well as
some personnel cost decrease as a result of retirements and personnel changes.
Materials & Supplies increased by $10,700 due to increases in security and safety
materials, computer hardware and software, and city building maintenance expense
offset by decreases totaling $9,000 in water treatment chemicals and uniform expense.
Administrative Expenses decreased by $385,300 mainly due to an increase of $564,400
in operator management fee and a decrease of $170,000 in operator incentive.
Capital Outlay increased $187,800 mainly due to the increase in vehicles and equipment.
7
294
Página 301
Power Supply
65 Series Supply Mgmt and Incentive Fees 996,000 0%
95 Series Purchases, capacity, and PJM Charges 41,510,600 3%
98 Fuel 431,900 68%
Total Expenditures 42,938,500 1%
Highlights:
The budget includes power supply & risk management services, estimated power supply and
fuel costs for Fiscal 2017.
295
Página 302
Final Discussion and Wrap-Up
296
Página 303
FY 2017 ANNUAL OPERATING BUDGET— DOVER, DELAWARE
Electric Division
Fiscal Year 2017 Organizational Chart
City Manager
Electric
Electric Director Key Accounts Representative
1 1
Electric Transmission
Administration System Operations Electric Engineering & Distribution Generation
Administrative Assistant System Ops Crew Leader Eng Svcs & System Ops Super. Line Crew Superintendent Generation Manager
1 1 1 1 1
Electric Meter Tech Crew Leader
Account Clerk II System Operators II Electrical Engineer I 1
1 4 1
Electric Meter Tech II
Electrical Engineer I 1
1
Electric Meter Tech I
1
SCADA Tech
1 Journeyman-1st Class Lineman
8
Substation Tech. Crew Leader
1
Lineman Second Class
5
Substation Technician II
2
Lineman Third Class
Electric Draftsman III 2
1
Lineman Crew Leader
Engineering Crew Leader 3
1
Groundworker
Engineering Fieldworker 2
1
T & D/Engineering Coordinator
1
297
Página 304
FY 2017 DRAFT ANNUAL OPERATING BUDGET - DOVER, DELAWARE
POWER PLANT OPERATIONS
480/487-8101-591
2012-2013 2013-2014 2014-2015 2015-2016 2015-2016 2016-2017 %
ACCT DESCRIPTION ACTUAL ACTUAL ACTUAL BUDGET REVISED PROPOSED CHANGE
10-11 SALARIES & WAGES $ 2,239,601 $ 2,221,763 $ 2,323,591 $ 2,558,900 $ 2,558,900 $ 2,400,400 -6%
10-12 OVERTIME 195,419 226,536 238,045 209,200 209,200 185,500 -11%
10-13 TEMPORARY HELP 20,992 14,067 - - - - 0%
10-18 EDUCATIONAL ASSISTANCE 2,874 432 - 2,500 2,500 2,500 0%
10-22 INCENTIVE ACUMULATOR 284,203 264,297 83,860 337,500 - - -100%
10-23 INCENTIVE BURDEN (21.0%) 52,288 45,705 21,417 70,900 - - -100%
10-24 BURDEN @ 40% 689,526 698,720 729,739 1,080,900 1,080,900 1,065,600 -1%
PERSONNEL COSTS 3,484,903 3,471,521 3,396,652 4,259,900 3,851,500 3,654,000 -14%
-
20-22 OFFICE SUPPLIES/SUBSCRIPT 11,083 6,876 7,099 7,000 7,000 7,000 0%
20-23 PRINTING & DUPLICATING 3,258 1,431 2,418 2,500 2,500 2,500 0%
20-25 JANITORIAL SERV/SUPPLIES 36,280 34,692 32,797 35,000 35,000 35,000 0%
20-28 MEDICAL SUPPLIES - 1,789 2,117 2,400 2,400 2,400 0%
20-29 UNIFORMS/UNIFORM ALLOW 5,856 12,544 14,612 13,000 13,000 10,000 -23%
20-32 SECURITY/SAFETY MATERIALS 10,162 12,006 9,614 8,200 8,200 13,200 61%
20-33 SMALL TOOLS 1,385 2,116 1,029 1,900 1,900 1,900 0%
20-35 WATER TREATMENT CHEMICALS 33,093 26,817 26,059 37,900 37,900 31,900 -16%
20-37 COMPUTER SOFTWARE 13,010 5,945 10,238 8,800 8,800 9,100 3%
20-38 COMPUTER HARDWARE 7,260 6,536 11,585 4,300 4,300 4,700 9%
20-46 CITY BUILDING MAINTENANCE 18,382 23,923 36,580 37,500 37,500 42,500 13%
20-58 WATER/SEWER 62,523 82,777 117,349 84,000 84,000 84,000 0%
MATERIALS & SUPPLIES 202,291 217,451 271,497 242,500 242,500 244,200 1%
30-19 OPERATOR INSURANCE 400,253 413,302 415,500 415,000 415,000 405,500 -2%
30-21 TELEPHONE 15,429 9,354 8,230 10,200 10,200 9,000 -12%
30-22 POSTAGE 13,483 9,878 9,170 9,000 9,000 9,000 0%
30-23 ELECTRICITY 584,726 604,747 748,178 550,000 550,000 550,000 0%
30-24 HEATING OIL/GAS 11,825 29,451 13,695 26,000 26,000 40,000 54%
30-28 TRAINING/CONF/FOOD/TRAVEL 49,591 36,719 56,799 68,000 68,000 66,500 -2%
30-31 CONTRACTUAL SERVICES 156,971 97,223 98,680 74,300 74,300 76,300 3%
30-43 ENVIRONMENT EXPENSES 58,856 146,170 94,960 109,700 109,700 104,000 -5%
30-45 OPERATOR MANAGEMENT FEE 203,484 207,552 211,908 216,900 797,400 781,300 260%
30-46 OPERATOR INCENTIVE 162,788 160,984 54,493 170,000 - - -100%
30-47 HOME OFFICE LABOR 91,795 60,372 95,275 63,900 10,100 15,000 -77%
30-51 RIGHT OF WAY/PERMITS 44,410 44,365 37,465 36,900 36,900 36,900 0%
30-62 GASOLINE 4,930 3,599 4,191 3,400 3,400 2,000 -41%
30-66 OTHER EQUIPT/MAINTENANCE 58,319 56,151 42,277 34,600 34,600 41,700 21%
30-67 RADIO REPAIRS/MAINTENANCE 700 2,461 4,080 6,500 6,500 6,500 0%
30-80 AUXILLARY SYSTEMS 39,528 62,328 47,573 43,600 43,600 44,600 2%
30-81 BOILER SYSTEMS 60,587 34,217 242,908 21,000 21,000 47,000 124%
30-82 CONTINUOUS EMISSIONS MONI 13,082 15,529 15,374 4,000 4,000 4,000 0%
30-83 DCS CONTROL SYSTEM 4,508 7,584 68 9,700 9,700 9,700 0%
30-84 FIRE PROTECTION SYSTEM 11,846 6,689 11,958 14,500 14,500 22,500 55%
30-85 COOLING TOWER 5,233 5,421 2,090 5,000 5,000 5,000 0%
30-86 FUEL OIL/GAS SYSTEMS - - 1,136 3,000 3,000 3,000 0%
30-87 COMBUSTION TURBINE MAINT 19,879 14,728 13,039 13,000 13,000 18,000 38%
30-88 POWER DISTRIBUTION SYSTEM 8,447 5,215 67,394 12,000 12,000 10,000 -17%
30-89 TURBINE GENERATOR SYSTEMS 11,221 6,911 4,194 12,000 12,000 10,000 -17%
ADMINISTRATIVE EXPENDITURES 2,031,889 2,040,950 2,300,635 1,932,200 2,288,900 2,317,500 20%
OPERATING EXPENDITURES 5,719,083 5,729,922 5,968,784 6,434,600 6,382,900 6,215,700 -3%
40-23 TRUCK - PURCHASES - - - - - 65,800
40-25 OTHER EQUIP-PURCHASE - 80,370 - - - 59,000 0%
40-31 CONSTRUCTION-PURCHASE 929,027 1,466,647 1,899,229 1,655,000 2,299,800 1,718,000 4%
CAPITAL OUTLAY 929,027 1,547,017 1,899,229 1,655,000 2,299,800 1,842,800 11%
TOTAL EXPENDITURES $ 6,648,110 $ 7,276,939 $ 7,868,013 $ 8,089,600 $ 8,682,700 $ 8,058,500 0%
OPERATING BUDGET STATS $ 5,719,083 $ 5,729,922 $ 5,968,784 $ 6,434,600 $ 6,382,900 $ 6,215,700
ACTUAL % of OPER BUDGET 100% 100% 100% 100% 100% 100%
BUDGET % CHANGE 4% 0% 4% 8% -1% -3%
REVENUES
ELECTRIC FUND - OPERATING $ 5,719,083 $ 5,729,922 $ 5,968,784 $ 6,434,600 $ 6,382,900 $ 6,215,700
ELECTRIC I & E FUND - CIP 929,027 1,547,017 1,899,229 1,655,000 2,299,800 1,842,800
298
Página 305
FY 2017 DRAFT ANNUAL OPERATING BUDGET - DOVER, DELAWARE
POWER SUPPLY
480/487-8102-592
2012-2013 2013-2014 2014-2015 2015-2016 2015-2016 2016-2017 %
ACCT DESCRIPTION ACTUAL ACTUAL ACTUAL BUDGET REVISED PROPOSED CHANGE
65-31 CONTRACTUAL SERVICES $ 157,955 $ 28,074 $ 266,856 $ - $ - $ - 0%
65-44 OPERATOR/SUPPLY MGMT FEE 996,000 996,000 996,000 996,000 996,000 996,000 0%
65 SERIES TOTAL 1,153,955 1,024,074 1,262,856 996,000 996,000 996,000 0%
95-48 3RD PARTY HEDGE PURCHASES 37,698,282 29,484,681 26,170,504 23,402,600 23,402,600 16,557,600 -29%
95-49 CAPACITY CHARGES 11,587,934 15,504,095 9,617,562 10,225,100 10,225,100 10,160,600 -1%
95-50 CAPACITY CREDITS (14,318,588) (15,065,472) (8,706,981) (10,472,100) (10,472,100) (7,355,100) -30%
95-58 SOLAR POWER SUPPLY 1,595,826 1,821,037 1,976,577 2,313,900 2,313,900 2,313,900 0%
95-59 SOLAR RENEWAL ENERGY CREDIT 370,255 337,741 372,329 363,400 363,400 363,400 0%
95-60 REC'S (Renewable Energy Credits) - - 572,515 673,400 673,400 673,400 0%
95-90 PJM CHARGES - TRANS. & FEES 7,103,571 7,433,120 5,389,169 7,932,500 7,932,500 7,603,800 -4%
95-91 PJM CHARGES - ENERGY 6,024,702 14,855,117 8,681,190 7,966,100 7,966,100 12,357,900 55%
95-92 PJM CREDITS (2,433,494) (5,946,189) (560,450) (360,000) (360,000) (360,000) 0%
95-93 PJM SPOT MARKET ENERGY - (862,233) (2,560,292) (1,708,300) (1,708,300) (804,900) -53%
95 SERIES TOTAL 47,628,490 47,561,896 40,952,122 40,336,600 40,336,600 41,510,600 3%
98-90 RGGI (Regional Greenhouse Gas Init.) - - 59,670 175,000 175,000 129,300 -26%
98-91 GAS FUEL 1,023,574 1,534,434 1,129,932 1,167,300 1,167,300 302,600 -74%
98-92 FUEL OIL PURCH FOR INVENT - - 4,276 - - - 0%
98-93 NO. 2 FUEL OIL - 1,180,850 535,166 - - - 0%
98 SERIES TOTAL 1,023,574 2,715,284 1,729,044 1,342,300 1,342,300 431,900 -68%
OPERATING EXPENDITURES 49,806,020 51,301,254 43,944,022 42,674,900 42,674,900 42,938,500 1%
TOTAL EXPENDITURES $ 49,806,020 $ 51,301,254 $ 43,944,022 $ 42,674,900 $ 42,674,900 $ 42,938,500 1%
OPERATING BUDGET STATS $ 49,806,020 $ 51,301,254 $ 43,944,022 $ 42,674,900 $ 42,674,900 $ 42,938,500
ACTUAL % OF OPER BUDGET 100% 100% 100% 100% 100% 100%
BUDGET % CHANGE -6% 3% -14% -3% 0% 1%
REVENUES
ELECTRIC FUND $ 49,806,020 $ 51,301,254 $ 43,944,022 $ 42,674,900 $ 42,674,900 $ 42,938,500
299
Página 306
FY 2017 DRAFT ANNUAL OPERATING BUDGET - DOVER, DELAWARE
ELECTRIC TRANSMISSION & DISTRIBUTION
480/487-8200-562
2012-2013 2013-2014 2014-2015 2015-2016 2015-2016 2016-2017 %
ACCT DESCRIPTION ACTUAL ACTUAL ACTUAL BUDGET REVISED PROPOSED CHANGE
10-11 SALARIES $ 1,433,173 $ 1,354,491 $ 1,357,167 $ 1,539,100 $ 1,555,200 $ 1,562,500 2%
10-12 OVERTIME 172,288 110,376 111,864 115,000 115,000 106,800 -7%
10-14 FICA TAXES 120,210 109,291 108,478 126,500 127,700 127,700 1%
10-15 HEALTH INSURANCE 255,422 242,437 207,713 271,500 271,500 283,500 4%
10-16 L I D INSURANCE 6,106 5,610 5,751 6,400 6,400 6,400 0%
10-17 WORKERS COMPENSATION 65,087 48,348 48,663 66,800 67,500 84,100 26%
10-19 PENSION 64,874 923,539 736,737 836,100 454,800 451,200 -46%
10-20 OPEB 86,687 94,699 97,309 111,800 36,800 30,300 -73%
PERSONNEL COSTS 2,203,848 2,888,791 2,673,682 3,073,200 2,634,900 2,652,500 -14%
20-26 PROGRAM EXPENSES/SUPPLIES 383 - - - - - 0%
20-29 UNIFORMS/UNIFORM ALLOW 24,177 24,680 36,916 23,000 23,000 23,000 0%
20-32 SECURITY/SAFETY MATERIALS 18,456 18,280 33,706 18,000 18,000 18,000 0%
20-33 SMALL TOOLS 24,415 26,712 23,615 25,000 25,000 25,000 0%
20-38 COMPUTER HARDWARE 2,500 1,655 8,855 12,700 12,700 12,000 -6%
20-53 METERS/METER SUPPLIES 15,211 13,611 13,897 14,000 14,000 24,000 71%
20-58 WATER/SEWER 693 1,479 405 300 300 300 0%
20-61 ELEC MATERIALS/SUPPLIES 375,087 267,025 296,235 350,000 350,000 332,300 -5%
MATERIALS & SUPPLIES 460,922 353,443 413,628 443,000 443,000 434,600 -2%
30-21 TELEPHONE/FAX 1,236 1,025 922 1,400 1,400 1,400 0%
30-23 ELECTRICITY 533 454 424 600 600 600 0%
30-24 HEATING OIL/GAS 5,963 7,519 7,592 6,000 6,000 6,000 0%
30-28 TRAINING/CONF/FOOD/TRAVEL 7,985 3,521 2,234 12,700 12,700 8,900 -30%
30-31 CONTRACTUAL SERVICES 413,599 422,675 420,025 410,900 410,900 410,900 0%
30-39 IN-HOUSE TRAINING 1,933 - - - - - 0%
30-43 ENVIRONMENTAL EXPENSES 30,065 22,728 31,184 30,000 30,000 28,000 -7%
30-51 RIGHT OF WAY 5,955 5,955 5,955 6,000 6,000 6,000 0%
30-62 GASOLINE 61,986 58,891 45,633 60,000 40,000 32,000 -47%
30-64 TRUCK REPAIRS/MAINTENANCE 15,640 15,927 15,350 15,000 15,000 15,000 0%
30-66 OTHER EQUIP REPAIRS/MAINT 7,572 6,661 6,708 7,500 7,500 7,500 0%
30-67 RADIO REPAIRS/MAINTENANCE 13,236 2,363 2,124 2,300 2,300 2,300 0%
ADMINISTRATIVE EXPENDITURES 565,703 547,720 538,151 552,400 532,400 518,600 -6%
OPERATING EXPENDITURES 3,230,473 3,789,954 3,625,462 4,068,600 3,610,300 3,605,700 -11%
40-23 TRUCKS - PURCHASE 145,718 7,421 397,581 387,600 397,600 - -100%
40-25 OTHER EQUIP - PURCHASE - 152,584 - - 150,000 25,000 0%
40-31 CONSTRUCTION - PURCHASE - - - - - 450,000 0%
60-31 UG TRANSFORMERS 163,528 52,766 115,481 500,000 568,600 500,000 0%
60-34 UG CONDUCTORS/DEVICES 805,707 239,859 712,852 1,900,000 2,295,600 900,000 -53%
60-46 METERS 68,651 14,514 7,917 100,000 113,100 100,000 0%
70-28 STREET LIGHT REPLACEMENT - - - - - - 0%
CAPITAL OUTLAY 1,183,603 467,144 1,233,831 2,887,600 3,524,900 1,975,000 -32%
TOTAL EXPENDITURES $ 4,414,076 $ 4,257,098 $ 4,859,293 $ 6,956,200 $ 7,135,200 $ 5,580,700 -20%
OPERATING BUDGET STATS $ 3,230,473 $ 3,789,954 $ 3,625,462 $ 4,068,600 $ 3,610,300 $ 3,605,700
ACTUAL % OF OPER BUDGET 100% 100% 100% 100% 100% 100%
BUDGET % CHANGE 9% 17% -4% 12% -11% 0%
REVENUES
ELECTRIC FUND $ 3,230,473 $ 3,789,954 $ 3,625,462 $ 4,068,600 $ 3,610,300 $ 3,605,700
ELECTRIC I & E FUND 1,183,603 467,144 1,233,831 2,887,600 3,524,900 1,975,000
PERSONNEL
BUDGETED FULL-TIME POSITIONS 24.0 24.0 24.0 24.0 24.0 24.0
300
Página 307
FY 2017 DRAFT ANNUAL OPERATING BUDGET - DOVER, DELAWARE
ELECTRIC ENGINEERING
480/487-8300-563
2012-2013 2013-2014 2014-2015 2015-2016 2015-2016 2016-2017 %
ACCT DESCRIPTION ACTUAL ACTUAL ACTUAL BUDGET REVISED PROPOSED CHANGE
10-11 SALARIES $ 553,596 $ 571,424 $ 516,013 $ 637,700 $ 640,300 $ 616,000 -3%
10-12 OVERTIME 18,570 10,912 7,792 11,000 11,000 11,100 1%
10-13 TEMPORARY HELP - - - - - 10,600 0%
10-14 FICA TAXES 42,299 42,926 38,038 49,600 49,800 48,000 -3%
10-15 HEALTH INSURANCE 100,730 100,431 97,662 136,500 136,500 124,100 -9%
10-16 L I D INSURANCE 2,708 2,508 2,125 3,100 3,100 2,800 -10%
10-17 WORKERS COMPENSATION 16,217 12,960 12,703 18,900 19,000 22,900 21%
10-18 EDUCATIONAL ASSISTANCE - 2,108 4,250 - - - 0%
10-19 PENSION 28,691 264,224 160,382 155,200 95,300 93,900 -39%
10-20 OPEB 33,649 39,539 37,522 46,500 16,500 12,100 -74%
PERSONNEL COSTS 796,459 1,047,032 876,487 1,058,500 971,500 941,500 -11%
20-29 UNIFORMS/UNIFORM ALLOW 6,602 7,015 11,305 7,000 7,000 7,000 0%
20-31 BOOKS - 36 - 200 200 200 0%
20-32 SECURITY/SAFETY MATERIALS 4,029 4,452 6,057 4,600 4,600 4,600 0%
20-33 SMALL TOOLS 3,493 1,269 2,082 2,000 2,000 2,000 0%
20-37 COMPUTER SOFTWARE 230 - 10,095 3,000 3,000 10,600 253%
20-38 COMPUTER HARDWARE 2,297 - 4,010 3,500 3,500 2,600 -26%
20-61 ELEC MATERIALS/SUPPLIES 47,335 24,576 20,911 44,000 44,000 34,000 -23%
MATERIALS & SUPPLIES 63,986 37,348 54,461 64,300 64,300 61,000 -5%
30-21 TELEPHONE/FAX 19,988 19,112 19,269 20,000 20,000 20,000 0%
30-23 ELECTRICITY 1,849 1,434 1,192 2,000 2,000 1,700 -15%
30-27 SUBSCRIPTIONS AND DUES 185 - - 400 400 400 0%
30-28 TRAINING/CONF/FOOD/TRAVEL 7,382 7,506 7,120 6,800 7,300 20,000 194%
30-31 CONTRACTUAL SERVICES 109,766 108,718 119,815 100,000 100,000 126,000 26%
30-39 IN-HOUSE TRAINING 2,055 - - - - - 0%
30-43 ENVIRONMENTAL EXPENSES 59,800 62,564 71,915 60,000 60,000 60,000 0%
30-61 OFF EQUIP/REPAIRS & MAINT 54 - - - - - 0%
30-62 GASOLINE 14,331 15,070 12,433 15,000 9,000 10,000 -33%
30-64 TRUCK REPAIRS/MAINTENANCE - - - - - - 0%
30-66 OTHER EQUIP REPAIRS/MAINT 14,165 12,119 2,598 7,500 7,500 6,000 -20%
30-67 RADIO REPAIRS/MAINTENANCE 8,293 1,161 913 1,300 1,300 1,300 0%
ADMINISTRATIVE EXPENDITURES 237,869 227,683 235,254 213,000 207,500 245,400 15%
OPERATING EXPENDITURES 1,098,314 1,312,062 1,166,201 1,335,800 1,243,300 1,247,900 -7%
40-22 AUTOMOBILES - PURCHASE - 34,985 28,514 - - - 0%
40-23 TRUCKS - PURCHASE - - - - - 33,200 0%
40-25 OTHER EQUIP - PURCHASE - 8,200 - 30,000 30,000 35,000 17%
40-31 CONSTRUCTION - PURCHASE - - - 201,800 201,800 167,500 -17%
50-55 MCKEE RUN SUBSTATION REPAIR - 35,820 - - - - 0%
50-76 LIGHTING IMPROVEMENTS 99,916 46,920 - 67,000 67,000 50,000 -25%
50-83 UG CABLE REPLACEMENT - - - 50,000 135,000 - -100%
50-85 WIRE REPLACEMENT 69KV - - 12,029 255,500 318,500 - -100%
50-86 BATTERY BANK REPLACEMENT - 23,185 10,875 - - - 0%
60-82 CAPICITOR INSTALLATIONS 125,053 31,484 - 50,000 50,000 50,000 0%
60-89 DAFB SUBSTATION UPGRADE - - - 30,000 30,000 - -100%
70-27 SUBSTATIONS 487,736 588,719 314,588 - - - 0%
70-35 TRANSMISSION/SWITCHES 73,938 17,374 30,421 75,000 1,182,200 75,000 0%
80-38 UPGRADE SCADA - - - - - 150,000 0%
90-25 DISTRIBUTION UPGRADES 508,030 426,584 313,788 965,000 865,000 350,000 -64%
90-78 WHITEOAK 69KV REBUILD - - 141,526 - 408,500 - 0%
CAPITAL OUTLAY 1,294,674 1,213,271 851,741 1,724,300 3,288,000 910,700 -47%
TOTAL EXPENDITURES $ 2,392,988 $ 2,525,333 $ 2,017,942 $ 3,060,100 $ 4,531,300 $ 2,158,600 -29%
OPERATING BUDGET STATS $ 1,098,314 $ 1,312,062 $ 1,166,201 $ 1,335,800 $ 1,243,300 $ 1,247,900
ACTUAL % OF OPER BUDGET 100% 100% 100% 100% 100% 100%
BUDGET % CHANGE 11% 19% -11% 15% -7% 0%
REVENUES
ELECTRIC FUND $ 1,098,314 $ 1,312,062 $ 1,166,201 $ 1,335,800 $ 1,243,300 $ 1,247,900
ELECTRIC I & E FUND 1,294,674 1,213,271 851,741 1,724,300 3,288,000 910,700
PERSONNEL
BUDGETED FULL-TIME POSITIONS 10.0 10.0 10.0 10.0 10.0 10.0
301
Página 308
FY 2017 DRAFT ANNUAL OPERATING BUDGET - DOVER, DELAWARE
ELECTRIC ADMINISTRATION
480/487-8400-564
2012-2013 2013-2014 2014-2015 2015-2016 2015-2016 2016-2017 %
ACCT DESCRIPTION ACTUAL ACTUAL ACTUAL BUDGET REVISED PROPOSED CHANGE
10-11 SALARIES $ 77,140 $ 83,844 $ 198,128 $ 250,900 $ 250,900 $ 346,700 38%
10-12 OVERTIME 2,021 - 91 2,000 2,000 - -100%
10-14 FICA TAXES 5,983 6,134 14,613 19,300 19,300 26,500 37%
10-15 HEALTH INSURANCE 14,039 13,553 26,443 38,500 38,500 60,500 57%
10-16 L I D INSURANCE 533 533 1,140 1,300 1,300 1,800 38%
10-17 WORKERS COMPENSATION 415 173 415 800 800 1,100 38%
10-19 PENSION 2,914 33,894 35,736 39,700 26,400 33,000 -17%
10-20 OPEB 5,149 6,368 14,660 18,400 8,000 10,100 -45%
PERSONNEL COSTS 108,195 144,499 291,226 370,900 347,200 479,700 29%
20-22 OFFICE SUPPLIES 1,071 997 1,109 1,000 1,000 1,000 0%
20-23 PRINTING AND DUPLICATING 8,744 7,073 10,568 9,000 9,000 9,000 0%
20-28 MEDICAL SUP & PHYSICALS 95 35 75 100 100 100 0%
20-37 COMPUTER SOFTWARE - - 100 200 200 200 0%
20-38 COMPUTER HARDWARE - - 1,295 2,600 2,600 2,000 -23%
20-46 CITY BLDG MAINT SUPPLIES 128,119 131,699 153,429 133,300 148,300 136,300 2%
20-58 WATER/SEWER 853 699 686 900 900 900 0%
MATERIALS & SUPPLIES 138,881 140,503 167,263 147,100 162,100 149,500 2%
30-21 TELEPHONE/FAX 1,263 1,000 1,030 1,000 1,000 1,000 0%
30-23 ELECTRICITY 18,563 16,382 16,172 17,000 17,000 17,000 0%
30-27 SUBSCRIPTIONS AND DUES 66,158 67,127 37,018 67,300 67,300 67,300 0%
30-28 TRAINING/CONF/FOOD/TRAVEL 947 - 43 2,500 2,000 2,500 0%
30-29 CONSULTING FEES 35,480 15,270 - - - 25,000 0%
30-31 CONTRACTUAL SERVICES 20,352 19,250 64,838 55,300 107,000 59,700 8%
30-32 LEGAL EXPENSES - 143,365 32,045 175,000 175,000 125,000 -29%
30-35 COMMUNITY RELATIONS EXP 3,107 - - 2,500 2,500 2,500 0%
30-62 GASOLINE 721 660 184 700 700 500 -29%
ADMINISTRATIVE EXPENDITURES 146,590 263,053 151,331 321,300 372,500 300,500 -6%
OPERATING EXPENDITURES 393,666 548,055 609,819 839,300 881,800 929,700 11%
TOTAL EXPENDITURES $ 393,666 $ 548,055 $ 609,819 $ 839,300 $ 881,800 $ 929,700 11%
OPERATING BUDGET STATS $ 393,666 $ 548,055 $ 609,819 $ 839,300 $ 881,800 $ 929,700
ACTUAL % OF OPER BUDGET 100% 100% 100% 100% 100% 100%
BUDGET % CHANGE -40% 39% 11% 38% 5% 5%
REVENUES
ELECTRIC FUND $ 393,666 $ 548,055 $ 609,819 $ 839,300 $ 881,800 $ 929,700
PERSONNEL
BUDGETED FULL-TIME POSITIONS 3.0 3.0 3.0 4.0 4.0 5.0
302
Página 309
FY 2017 DRAFT ANNUAL OPERATING BUDGET - DOVER, DELAWARE
METER READING
480/487-8500-565
2012-2013 2013-2014 2014-2015 2015-2016 2015-2016 2016-2017 %
ACCT DESCRIPTION ACTUAL ACTUAL ACTUAL BUDGET REVISED PROPOSED CHANGE
10-11 SALARIES $ 125,654 $ 129,075 $ 174,207 $ 181,200 $ 183,000 $ 193,200 7%
10-12 OVERTIME 11,168 9,377 13,155 11,100 11,100 19,100 72%
10-13 TEMPORARY HELP - - 588 - - 12,500 0%
10-14 FICA TAXES 10,183 10,177 13,711 14,700 14,800 17,200 17%
10-15 HEALTH INSURANCE 27,342 27,477 42,501 32,500 32,500 55,500 71%
10-16 L I D INSURANCE 758 758 909 900 900 1,000 11%
10-17 WORKERS COMPENSATION 5,548 4,564 6,121 5,800 5,900 8,000 38%
10-19 PENSION 6,333 68,813 79,494 66,100 37,800 40,400 -39%
10-20 OPEB 7,736 8,990 12,493 13,100 6,100 3,700 -72%
PERSONNEL COSTS 194,722 259,231 343,180 325,400 292,100 350,600 8%
20-21 FURNITURE/FIXTURES - - - 300 300 - -100%
20-29 UNIFORMS/UNIFORM ALLOW 2,597 2,694 4,738 4,400 4,400 4,700 7%
20-32 SECURITY/SAFETY MATERIALS 340 400 - 500 500 100 -80%
20-33 SMALL TOOLS - - 5,445 6,100 6,100 6,100 0%
20-38 COMPUTER HARDWARE 1,401 - - - - - 0%
20-55 METER READING SUPPLIES 2,713 3,972 3,936 5,500 5,500 4,000 -27%
MATERIALS & SUPPLIES 7,050 7,066 14,119 16,800 16,800 14,900 -11%
30-21 TELEPHONE/FAX 1,605 1,610 2,082 2,100 2,100 2,100 0%
30-28 TRAINING/CONF/FOOD/TRAVEL - - - 500 500 500 0%
30-62 GASOLINE 10,527 10,532 7,129 10,000 5,000 5,000 -50%
30-66 OTHER EQUIP REPAIRS/MAINT 5,106 5,463 5,057 5,300 5,300 5,300 0%
30-67 RADIO REPAIRS/MAINTENANCE - 326 91 400 400 200 -50%
ADMINISTRATIVE EXPENDITURES 17,238 17,931 14,359 18,300 13,300 13,100 -28%
OPERATING EXPENDITURES 219,010 284,229 371,658 360,500 322,200 378,600 5%
40-23 TRUCKS - PURCHASE - - - - - 41,800 0%
40-25 OTHER EQUIP - PURCHASE - - - - 23,000 - 0%
40-26 RADIO - PURCHASE - - - - - - 0%
CAPITAL OUTLAY - - - - 23,000 41,800 0%
TOTAL EXPENDITURES $ 219,010 $ 284,229 $ 371,658 $ 360,500 $ 345,200 $ 420,400 17%
OPERATING BUDGET STATS $ 219,010 $ 284,229 $ 371,658 $ 360,500 $ 322,200 $ 378,600
ACTUAL % OF OPER BUDGET 100% 100% 100% 100% 100% 100%
BUDGET % CHANGE 6% 30% 31% -3% -11% 18%
REVENUES
ELECTRIC FUND $ 219,010 $ 284,229 $ 371,658 $ 360,500 $ 322,200 $ 378,600
ELECTRIC I & E FUND - - - - 23,000 41,800
PERSONNEL
BUDGETED FULL-TIME POSITIONS 3.0 3.0 3.0 4.0 4.0 4.0
303
Página 310
FY 2017 DRAFT ANNUAL OPERATING BUDGET - DOVER, DELAWARE
SYSTEM OPERATIONS
480/487-8600-526
2012-2013 2013-2014 2014-2015 2015-2016 2015-2016 2016-2017 %
ACCT DESCRIPTION ACTUAL ACTUAL ACTUAL BUDGET REVISED PROPOSED CHANGE
10-11 SALARIES $ 336,359 $ 366,841 $ 349,537 $ 335,800 $ 343,700 $ 344,000 2%
10-12 OVERTIME 61,029 68,038 77,426 50,000 50,000 72,900 46%
10-14 FICA TAXES 29,061 31,760 30,967 29,500 30,100 31,900 8%
10-15 HEALTH INSURANCE 65,495 71,204 66,497 81,900 81,900 92,800 13%
10-16 L I D INSURANCE 1,356 1,356 1,356 1,300 1,300 1,300 0%
10-17 WORKERS COMPENSATION 13,366 11,575 11,631 15,600 15,900 21,000 35%
10-19 PENSION 16,773 164,302 141,706 141,200 79,300 81,000 -43%
10-20 OPEB 20,666 24,030 24,611 24,500 10,500 6,800 -72%
PERSONNEL COSTS 544,105 739,107 703,731 679,800 612,700 651,700 -4%
20-32 SECURITY/SAFETY MATERIALS 300 300 (300) - - - 0%
MATERIALS & SUPPLIES 300 300 (300) - - - 0%
TOTAL EXPENDITURES $ 544,405 $ 739,407 $ 703,431 $ 679,800 $ 612,700 $ 651,700 -4%
OPERATING BUDGET STATS $ 544,405 $ 739,407 $ 703,431 $ 679,800 $ 612,700 $ 651,700
ACTUAL % OF OPER BUDGET 100% 100% 100% 100% 100% 100%
BUDGET % CHANGE 9% 36% -5% -3% -10% 6%
REVENUES
ELECTRIC FUND $ 544,405 $ 739,407 $ 703,431 $ 679,800 $ 612,700 $ 651,700
PERSONNEL
BUDGETED FULL-TIME POSITIONS 5.0 5.0 5.0 5.0 5.0 5.0
304
Página 311
MUNICIPAL STREET AID
REALTY TRANSFER TAX
WORKERS’ COMPENSATION
COMMUNITY TRANSPORTATION
LIBRARY GRANTS
POLICE GRANTS
ELECTRIC RED LIGHT PROGRAM
CDBG
SUBSTANCE ABUSE PREVENT. PROGRAM
Página 312
FY 2017 DRAFT OPERATING BUDGET - DOVER, DELAWARE
MUNICIPAL STREET AID FUND
CASH RECEIPTS
$ DIFFERENCE % CHG
2014/2015 2015/16 2015/16 2016/17 FY 17 PP VS FY17 VS
ACTUAL BUDGET REVISED PROPOSED FY16 BUDGET FY16
BEGINNING BALANCE 100 100 100 100 - 0.0%
STATE GRANT 664,194 564,200 673,100 673,100 108,900 0.0%
INTEREST EARNED 107 - - - - 0.0%
TOTALS 664,401 564,300 673,200 673,200 108,900 0.0%
BUDGET SUMMARY
$ DIFFERENCE % CHG
2014/2015 2015/16 2015/16 2016/17 FY 17 PP VS FY17 VS
ACTUAL BUDGET REVISED PROPOSED FY16 BUDGET FY16
TRANSFER TO GENERAL FUND 664,266 564,200 673,100 673,100 108,900 0.0%
CURRENT YEAR BALANCE 135 100 100 100 - 0.0%
TOTALS 664,401 564,300 673,200 100 (564,200) 0.0%
306
Página 313
FY 2017 DRAFT OPERATING BUDGET - DOVER, DELAWARE
ELECTRIC RED LIGHT PROGRAM
CASH RECEIPTS
$ DIFFERENCE % CHG
2014/2015 2015/16 2015/16 2016/17 FY 17 PP VS FY17 VS
ACTUAL BUDGET REVISED PROPOSED FY16 BUDGET FY16
BEGINNING BALANCE 100 - 100 100 100 0.0%
POLICE FINES 495,182 450,000 450,000 496,900 46,900 0.0%
TOTALS 495,282 450,000 450,100 497,000 47,000 0.0%
BUDGET SUMMARY
$ DIFFERENCE % CHG
2014/2015 2015/16 2015/16 2016/17 FY 17 PP VS FY17 VS
ACTUAL BUDGET REVISED PROPOSED FY16 BUDGET FY16
TRANSFER TO GENERAL FUND 495,182 450,000 450,000 496,900 46,900 0.0%
CURRENT YEAR BALANCE 100 - 100 100 100 0.0%
TOTALS 495,282 450,000 450,100 497,000 47,000 0.0%
307
Página 314
FY 2017 DRAFT OPERATING BUDGET - DOVER, DELAWARE
REALTY TRANSFER TAX
CASH RECEIPTS
$ DIFFERENCE % CHG
2014/2015 2015/16 2015/16 2016/17 FY 17 PP VS FY17 VS
ACTUAL BUDGET REVISED PROPOSED FY16 BUDGET FY16
REALTY TRANSFER TAXES 1,713,505 1,340,000 1,340,000 1,672,700 332,700 0.0%
INTEREST EARNED 292 - - - - 0.0%
TOTALS 1,713,797 1,340,000 1,340,000 1,672,700 332,700 0.0%
BUDGET SUMMARY
$ DIFFERENCE % CHG
2014/2015 2015/16 2015/16 2016/17 FY 17 PP VS FY17 VS
ACTUAL BUDGET REVISED PROPOSED FY16 BUDGET FY16
TRANSFER TO GENERAL FUND 1,713,788 1,340,000 1,340,000 1,672,700 332,700 0.0%
CURRENT YEAR BALANCE 9 - - - - 0.0%
TOTALS 1,713,797 1,340,000 1,340,000 1,672,700 332,700 0.0%
308
Página 315
FY 2017 DRAFT OPERATING BUDGET - DOVER, DELAWARE
WORKER'S COMPENSATION FUND 662
OPERATING REVENUES
$ DIFFERENCE
2014/2015 2015/16 2015/16 2016/17 FY 17 PP VS %
ACTUAL BUDGET REVISED BUDGET FY16 BUDGET CHANGE
BEGINNING BALANCE 1,123,247 1,052,600 1,248,200 1,256,300 203,700 19.4%
INTEREST INCOME 15,994 10,600 20,700 25,000 14,400 135.8%
PREMIUM FROM CITY 513,666 642,500 620,000 855,400 212,900 33.1%
MISCELLANEOUS REVENUE 12,595 - 9,400 - - 0.0%
TOTALS 1,665,502 1,705,700 1,898,300 2,136,700 431,000 25.3%
OPERATING EXPENSES
$ DIFFERENCE
2014/2015 2015/16 2015/16 2016/17 FY 17 PP VS %
ACTUAL BUDGET REVISED BUDGET FY16 BUDGET CHANGE
PROGRAM EXPENSE - CLAIMS 269,762 475,000 475,000 475,000 - 0.0%
INSURANCE 102,766 103,900 103,900 105,500 1,600 1.5%
BANK FEES 1,284 1,300 - - (1,300) -100.0%
STATE OF DEL - SELF INSURANCE TAX 34,966 37,000 38,100 39,000 2,000 5.4%
CONTRACTUAL SERVICES 8,560 25,000 25,000 25,000 - 0.0%
TOTAL EXPENSES 417,338 642,200 642,000 644,500 200 0.4%
CURRENT YEAR BALANCE 1,248,164 1,063,500 1,256,300 1,492,200 428,700 40.3%
TOTALS 1,665,502 1,705,700 1,898,300 2,136,700 431,000 25.3%
309
Página 316
FY 2017 DRAFT OPERATING BUDGET - DOVER, DELAWARE
COMMUNITY TRANSPORTATION IMPROVEMENT FUND
OPERATING REVENUES
$ DIFFERENCE
2014/2015 2015/16 2015/16 2016/17 FY 17 PP VS %
ACTUAL BUDGET REVISED BUDGET FY16 BUDGET CHANGE
PRIOR YEAR BALANCE 143,532 144,000 57,800 92,100 (51,900) -36.0%
GRANTS REVENUE 105,890 500,000 839,300 500,000 - 0.0%
INTEREST INCOME 248 500 500 - (500) -100.0%
TOTALS 249,670 644,500 897,600 592,100 (52,400) -8.1%
OPERATING EXPENSES
$ DIFFERENCE
2014/2015 2015/16 2015/16 2016/17 FY 17 PP VS %
ACTUAL BUDGET REVISED BUDGET FY16 BUDGET CHANGE
PROGRAM EXP. GRANT RELATED 191,872 644,000 805,500 500,000 (144,000) -22.4%
CURRENT YEAR BALANCE 57,798 500 92,100 92,100 91,600 18320.0%
TOTALS 249,670 644,500 897,600 592,100 (52,400) -8.1%
310
Página 317
FY 2017 DRAFT OPERATING BUDGET - DOVER, DELAWARE
LIBRARY GRANT
OPERATING REVENUES
$ DIFFERENCE
2014/2015 2015/16 2015/16 2016/17 FY 17 PP VS $
ACTUAL BUDGET REVISED BUDGET FY16 BUDGET CHANGE
PRIOR YEAR BALANCE 44,810 17,300 30,600 17,300 - 0.0%
STATE GRANT 278,813 278,900 305,500 305,500 26,600 9.5%
FEDERAL GRANT 2,500 2,500 2,500 2,500 - 0.0%
TOTALS 326,123 298,700 338,600 325,300 26,600 8.9%
OPERATING EXPENSES
$ DIFFERENCE
2014/2015 2015/16 2015/16 2016/17 FY 17 PP VS $
ACTUAL BUDGET REVISED BUDGET FY16 BUDGET CHANGE
STATE GRANTS
FURNITURE/FIXTURES 7,353 3,100 7,000 10,500 7,400 238.7%
OFFICE SUPPLIES 27,855 24,000 30,800 30,800 6,800 28.3%
PRINTING AND DUPLICATING 12,161 13,200 12,500 12,500 (700) -5.3%
PROGRAM EXPENSES/SUPPLIES 33,381 24,100 27,500 27,500 3,400 14.1%
BOOKS 126,972 129,200 133,300 150,600 21,400 16.6%
AUDIO VISUAL SUPPLIES 73,543 75,100 77,200 77,200 2,100 2.8%
POSTAGE 39 100 100 100 - 0.0%
TRAINING/CONF/FOOD/TRAV 4,229 2,000 8,800 5,300 3,300 165.0%
CONTRACTUAL SERVICES - 900 - - (900) -100.0%
OFF EQP/REPAIRS & MAINT 4,946 6,000 6,300 6,300 300 5.0%
OTHER EQUIP - PURCHASE 1,105 - - 0.0%
OTHER EQUIP - LEASE 1,468 1,200 2,000 2,000 800 66.7%
SUBTOTAL EXPENSES STATE GRANTS 293,052 278,900 305,500 322,800 43,900 15.7%
FEDERAL GRANTS
PROGRAM EXPENSES/SUPPLIES 2,500 2,500 2,500 2,500 - 0.0%
SUBTOTAL EXPENSES FEDERAL GRANTS 2,500 2,500 2,500 2,500 - 0.0%
GRAND TOTAL EXPENSES 295,552 281,400 308,000 325,300 43,900 15.6%
CURRENT YEAR BALANCE 30,571 17,300 30,600 - (17,300) -100.0%
TOTALS 326,123 298,700 338,600 325,300 26,600 8.9%
311
Página 318
FY 2017 DRAFT OPERATING BUDGET - DOVER, DELAWARE
POLICE GRANTS
OPERATING REVENUES
$ DIFFERENCE
2014/2015 2015/16 2015/16 2016/17 FY 17 PP VS %
ACTUAL BUDGET REVISED BUDGET FY16 BUDGET CHANGE
PRIOR YEAR BALANCE 172,062 125,000 154,900 642,700 517,700 414.2%
GRANTS RECEIVED 327,717 527,300 1,106,900 319,000 (208,300) -39.5%
INTEREST INCOME 810 - - - - 0.0%
TOTALS 500,589 652,300 1,261,800 961,700 309,400 47.4%
OPERATING EXPENSES
$ DIFFERENCE
2014/2015 2015/16 2015/16 2016/17 FY 17 PP VS %
ACTUAL BUDGET REVISED BUDGET FY16 BUDGET CHANGE
EXPENDITURES
PERSONNEL EXPENDITURES
CADET PROGRAM SALARIES 12,895 71,400 71,400 71,400 - 0.0%
CADET PROGRAM FICA 986 5,400 5,500 5,500 100 1.9%
CADET PROGRAM W/COMP 516 3,500 4,200 4,200 700 20.0%
MATERIALS AND SUPPLIES
POLICE EQUIPT & PROG SUPP 137,014 410,600 379,600 313,000 (97,600) -23.8%
TECHNOLOGY EQUIPMENT 21,293 20,000 20,000 - (20,000) -100.0%
ADMINISTRATIVE EXPENDITURES
CELL PHONE CHARGES 15,864 15,000 15,000 16,000 1,000 6.7%
TRAINING 22,018 17,000 45,000 17,000 - 0.0%
AUDIT FEES 737 1,000 1,000 1,000 - 0.0%
CONTRACTUAL SERVICES 7,192 - 3,000 210,000 210,000 0.0%
TOTAL EXPENDITURES 218,515 543,900 544,700 638,100 94,200 17.3%
OTHER FINANCING USES
OPERATING TRANSFERS-OUT 127,130 74,400 148,400 82,000 7,600 10.2%
TOTAL FINANCING USES 127,130 74,400 148,400 82,000 7,600 10.2%
CURRENT YEAR BALANCE 154,944 34,000 642,700 241,600 207,600 610.6%
TOTALS 500,589 652,300 1,335,800 961,700 309,400 47.4%
THE ABOVE BUDGET INCLUDES THE POLICE GRANTS FUND, USDOJ
BYRNE GRANTS FUND AS WELL AS THE OTHER FEDERAL POLICE
GRANTS FUND.
312
Página 319
FY 2017 DRAFT OPERATING BUDGET - DOVER, DELAWARE
COMMUNITY DEVELOPMENT BLOCK GRANT (CDBG)
OPERATING REVENUES
$ DIFFERENCE
2014/2015 2015/16 2015/16 2016/17 FY 17 PP VS %
ACTUAL BUDGET REVISED BUDGET FY16 BUDGET CHANGE
PRIOR YEAR BALANCE CDBG 2,013 2,100 2,100 2,100 - 0.0%
PRIOR YEAR BALANCE NSP 77,860 - - - - 0.0%
CDBG GRANTS RECEIVED 235,731 256,800 272,800 272,800 16,000 6.2%
REVENUE FROM NSP 8,091 - - - - 0.0%
TOTALS 323,695 258,900 274,900 274,900 16,000 6.2%
OPERATING EXPENSES
$ DIFFERENCE
2014/2015 2015/16 2015/16 2016/17 FY 17 PP VS %
ACTUAL BUDGET REVISED BUDGET FY16 BUDGET CHANGE
Prior year Closing cost/down payment program 193 - 900 - - 0.0%
Prior year MHDC home repair 1,881 - - - - 0.0%
Prior year Elizabeth W Murphey school 1,135 - - - - 0.0%
Prior year Ncall Research Inc. 2,237 - 6,500 - - 0.0%
Prior year Milford housing H/O rehab 2,934 - - - - 0.0%
Current year closing cost/down payment program 101,875 60,000 60,000 50,000 (10,000) -16.7%
Current year Connection Comm Supp program - 7,400 7,400 7,200 (200) -2.7%
Current year Dover interfaith ministry 27,500 27,000 27,000 22,000 (5,000) -18.5%
Current year MHDC emergency home repair - 35,300 35,300 25,000 (10,300) -29.2%
Current year Habitat for Humanity - 40,000 40,000 30,000 (10,000) -25.0%
Current year MHDC homeowner rehab. - - - 55,000 55,000 0.0%
Current year Peoples Place - 6,800 6,800 - (6,800) -100.0%
Current year Elizabeth W Murphey school 50,000 - - - - 0.0%
Current year Ncall Research Inc. 1,263 - - - - 0.0%
Current year Milford housing H/O rehab - 52,900 52,900 - (52,900) -100.0%
Current year salaries - - - 36,000 36,000 0.0%
Current program expenses 46,713 36,000 36,000 47,300 11,300 31.4%
NSP program expenditures 674 - - - - 0.0%
CURRENT YEAR BALANCE CDBG 2,013 (6,500) 2,100 2,400 8,900 -136.9%
CURRENT YEAR BALANCE NSP 85,277 - - - - 0.0%
TOTALS 323,695 258,900 274,900 274,900 16,000 6.2%
313
Página 320
FY 2017 DRAFT OPERATING BUDGET - DOVER, DELAWARE
SUBSTANCE ABUSE PREVENTION PROGRAM
OPERATING REVENUES
$ DIFFERENCE
2014/2015 2015/16 2015/16 2016/17 FY 17 PP VS %
ACTUAL BUDGET REVISED BUDGET FY16 BUDGET CHANGE
PRIOR YEAR BALANCE 77,913 41,000 98,200 41,000 - 0.0%
GRANTS REVENUE 28,030 55,600 28,000 55,700 100 0.2%
RECREATION REVENUE 66,038 33,000 33,000 33,000 - 0.0%
TOTALS 171,981 129,600 159,200 129,700 100 0.1%
OPERATING EXPENSES
$ DIFFERENCE
2014/2015 2015/16 2015/16 2016/17 FY 17 PP VS %
ACTUAL BUDGET REVISED BUDGET FY16 BUDGET CHANGE
TEMPORARY HELP/BENEFITS 40,211 54,000 60,200 60,200 6,200 11.5%
PROGRAM EXPENSES/SUPPLIES 33,589 55,600 55,600 55,700 100 0.2%
CURRENT YEAR BALANCE 98,181 20,000 43,400 13,800 (6,200) -31.0%
TOTALS 171,981 129,600 159,200 129,700 100 0.1%