SAFETY ADVISORY AND TRANSPORTATION COMMITTEE
The Safety Advisory and Transportation Committee Meeting was held on January 30, 2013
at 5:00 p.m. with Chairman Hutchison presiding. Members present were Mr. Perza (arrived at 5:14 p.m.
and departed at 5:47 p.m.) , Mr. Davis, and Mr. Keller.
AGENDA ADDITIONS/DELETIONS
Mr. Hutchison moved to amend the agenda to allow for consideration of Item #2 prior to
Item #1, seconded by Mr. Keller and unanimously carried.
Safety Concerns - New Dover High School Pedestrian/Vehicular Traffic
Mrs. Ann Marie Townshend, Director of Planning and Community Development, reminded
members that staff had provided the Committee with regular updates regarding the progress of the
construction of the new Dover High School, and during the last update staff stated that they believed
strongly that a traffic signal was necessary at the east entrance of the school site. Mrs. Townshend
explained that the east entrance was directly across the street from a number of residential
developments where bus service will not be provided. She stated that without a traffic signal there
is no safe way for students who walk to cross Route 8. Per Delaware Department of Transportation
(DelDOT) requirements, a warrant analysis was performed; however, the results did not support a
signal at that location, thus DelDOT would not allow installation. Mrs. Townshend stated that a
traffic signal had been proposed and approved by DelDOT at the west entrance of the school;
however, she felt it unlikely that students coming from the east would walk an extra quarter of a mile
to cross at the signal on the west side. In addition, she added that the unsafe walking conditions
would likely result in more parents driving students to school, which would create more traffic on
an already heavily traveled road. Mrs. Townshend noted that the new Dover High School would be
a heavily utilized community facility throughout the day; therefore, a crossing guard would not be
an option.
Mrs. Townshend noted that these concerns had been discussed previously at the Committee and
Council levels and the consensus was that not allowing for a signal at the east entrance of the school
was unacceptable and unsafe; however, DelDOT refused to put up the signal based on their study.
She reminded members that the Committee had also recommended that sidewalks be constructed
along the north side of Route 8 to fill the gaps in the sidewalk network; however, DelDOT responded
that this would have to be included in the Capital Transportation Plan, which involves other funding
priorities. Noting that the new Dover High School was scheduled to open in the Fall of 2014,
Mrs. Townshend reminded members that the Committee had requested representatives from the
Capital School District to be present at the meeting to engage in dialogue regarding how the City
could work together with the District to have a signal placed at the east entrance.
Responding to Mr. Davis regarding the posting of a 15 mph speed limit restriction near the school,
Mr. Koenig was unsure if the speed limit in school zones was restricted to 15 or 20 mph; however,
he felt that this may depend on the type of school.
In response to Mr. Davis, Mrs. Townshend explained that locating a signal at the entrance of the
school was not a cost issue, since she believed that the Capital School District would construct it as
part of the project; however, DelDOT would not permit this signal on the road.
Página 2
SAFETY ADVISORY AND TRANSPORTATION COMMITTEE
MEETING OF JANUARY 30, 2013 PAGE 2
Mr. Hutchison called upon Dr. Michael Thomas, Superintendent of the Capital School District, for
his perspective on this issue. Dr. Thomas introduced Mr. Phil Martino, Vice-President of the Capital
School District Board of Education; Mr. Carl Krienen, Architect, ABHA Architects; and Mr. Gregg
Moore, Civil Architect, Becker Morgan Group. Dr. Thomas concurred with Mrs. Townshend’s
account of the issues at the new Dover High School, noting that the District shared the concerns
regarding safety and reiterating that the traffic would not be limited to the opening and closing hours
of the school due to the many activities surrounding the facility. Dr. Thomas stated that the traffic
has concerned the architects since the planning process for the project began. He noted that these
issues had been a focal point during discussions with DelDOT and that the traffic signal was needed
at the east entrance for safety.
Responding to Mr. Hutchison regarding the necessity for two (2) signals, Dr. Thomas expressed his
belief that both signals were needed. Since most of the walking traffic would be from the east side
of the school, he felt that most students would cross at the closest point (the east entrance). In
addition, Dr. Thomas advised members that the main baseball/softball complex was located behind
the east entrance; therefore, beginning in the spring, traffic at the end of the school day until after
dark would significantly increase annually.
Mr. Moore reviewed a map of the New Dover High School site (Attachment #1), noting that the road
at the west entrance was paid for by the Capital School District and was designed and installed to
meet DelDOT’s standards for becoming a future thruway to Hazlettville Road. He explained that
the majority of the buses from the City would be using the east entrance and that a light was needed
there to protect buses entering the school due to their slower speeds, larger size, and the oncoming
traffic from the west, as well as for the children crossing the road. Mr. Moore stated that the buses
themselves were not enough traffic to dictate a traffic signal through the warrant analysis process;
however, consultants to the district made it clear that a signal was warranted from a safety
perspective.
Responding to Mr. Hutchison, Dr. Thomas stated that he could provide an informed estimate of the
volume of foot traffic anticipated based on the number of students within the school’s radius who
are not eligible for transportation. Mr. Hutchison felt it was important that the City and School
District join forces to develop data regarding foot and vehicle traffic patterns to reinforce the need
for a traffic signal for submission to DelDOT.
Mr. Davis recalled that the original plan included the light at the east entrance with a plan to also
request a light at the west entrance. Responding, Mrs. Townshend explained that the decision to
signalize the east entrance (as opposed to the west entrance) was due to: 1) the fact that the west
entrance is a public street that will serve the apartment complex planned for construction west of the
school and will connect to Tribbett Street and possibly to Hazlettville Road; and 2) the safety
concern presented by the curve of Dover High Drive (the primary vehicle access entrance) as it
intersects with Route 8.
Concurring with Mrs. Townshend, Mr. Moore explained that the western intersection was designed
jointly with Leander Lakes (a 240-unit apartment complex to be constructed west of the school site),
which allowed the warrant analysis to be met easily due to the combination of expected traffic
Página 3
SAFETY ADVISORY AND TRANSPORTATION COMMITTEE
MEETING OF JANUARY 30, 2013 PAGE 3
between the complex and the entrance to the high school. He noted that the traffic pattern was
designed to segregate bus traffic (at the east entrance) from the student, teacher, and public traffic
at the west entrance. He expressed his opinion that it made sense for an additional traffic light to be
installed at the east entrance to allow buses to make a left turn (from the east) into the school
uninterrupted; because a striped crosswalk was needed at that location for walkers, which DelDOT
would not permit without a signal; and because a “T” intersection with significant traffic would be
created with Heatherfield Way.
Responding to Mr. Hutchison, Mr. Moore indicated that the property’s designation as a school would
not affect the warrant analysis. He noted that standards do not change based on the type of facility,
even if that facility is a school.
In response to Mr. Martino, Mr. Moore indicated that the amount of through traffic on Route 8 was
not sufficient to change the outcome of the analysis and that this problem had been anticipated prior
to the traffic study.
Mr. Hutchison suggested that numbers provided by Dr. Thomas, including the volume of walkers,
etc., coupled with the letters from the officials and school board members, district and the City of
Dover may cause DelDOT to reconsider the traffic signal for safety reasons. He felt that the fact that
the facility is a school should weigh into the analysis and that the entrance should not be treated as
a typical intersection.
Responding to Mr. Davis, Mrs. Townshend stated that she was not aware of any appeal process
available through DelDOT.
In response to Mr. Scott Koenig, City Manager, Mr. Moore stated that he was unaware of any factors
that would change the warrant analysis in the future, other than collisions at the location.
Responding to Mr. Perza regarding access to the school for walkers, Mr. Moore explained that 7,000
feet of sidewalks and bike paths into all aspects of the school were included in the design. He felt
that DelDOT would not put a crosswalk on Route 8 unless there were a traffic light; therefore, the
only designated crossing areas would be intersection near WaWa and Mifflin Road and at the west
entrance of the school.
Mrs. Townshend reminded members that there would not be a continuous sidewalk on the south side
of Route 8.
Mr. Perza suggested that information be gathered regarding the number of students whose safety is
at risk and the distance they must travel to cross safely to establish a need for a traffic signal.
Mr. Davis suggested that the representatives a the State legislature also become involved and
suggested reintroducing the concept of a pedestrian bridge.
Mr. Hutchison suggested conducting open dialogue and gathering information, including the total
number of people going in and out of the school, as well as the total number of students walking and
Página 4
SAFETY ADVISORY AND TRANSPORTATION COMMITTEE
MEETING OF JANUARY 30, 2013 PAGE 4
driving. He felt that the Police Chief could contribute additional information pertaining to traffic
patterns, accidents, and safety information and that all of this information should be compiled,
perhaps including input from State officials, and presented to DelDOT with a request for further
review and consideration of the traffic signal at the east entrance of the facility.
Mrs. Townshend noted that assistance had not yet been requested from legislators; however, Senator
Bushweller and Representative Scott had been advised that this was an ongoing issue and that she
would keep them informed in the event that their involvement was needed.
Dr. Thomas said that he had also had discussions with Senator Bushwell and Representative Scott.
He noted that the Capital School District was attempting to exhaust every avenue to resolve the
matter with DelDOT through the proper channels and would continue these efforts.
In response to Mr. Koenig, Mr. Moore stated that he was uncertain if the design of the intersection
would have to be modified if a traffic signal were installed. Mr. Koenig noted that the Capital
School District must apply for a construction permit for the entrance very soon since the signal
design takes many months, which would make it increasingly difficult to have a signal installed in
time for the school opening. Mrs. Townshend stated her understanding that, from a geometric
standpoint, the intersection was to be designed so that if a signal was needed in the future it would
not require a new design. Mr. Moore shared Mrs. Townshend’s opinion; however, he stated that he
could not be certain because the traffic lights are designed by DelDOT.
Mr. Les Blakemen, 209 Falmouth Way, stated that he lives across the street from the school site and
expressed his concern with traffic. He noted that Heatherfield and Heatherfield East have turn lanes
off Route 8; however, there is no turn lane entering Cranberry Run. Due to the lack of a turn lane,
vehicles are required to slow down in the line of traffic to make a turn into the development, which
he felt complicates traffic patterns, stating that drivers tend to cross over the solid white line on the
shoulder to go around traffic. Mr. Blakeman explained that he currently has to wait for four (4) to
five (5) minutes on some mornings before he is able to get out into traffic and he sees people taking
risks because they have been waiting for so long. In response to Mr. Keller, Mr. Blakemen stated
that this dangerous situation exists going both east and west and that adding buses and traffic will
compound the situation. He noted that an additional problem exists at the intersection of Kenton
Road and Route 8, where drivers turning left onto Kenton Road stop in the intersection when the left
turn lane is full.
Mr. Moore indicated that the traffic light at the west entrance of the school should help to alleviate
some of the inbound traffic; however, an additional light at the east end would also help because it
would stop traffic from both directions.
Mr. Rich Vetter, Executive Director, Dover/Kent County Metropolitan Planning Organization
(MPO) inquired if a pedestrian-activated signal had been considered, which would be in use only
when pedestrians are present. Responding, Mr. Hutchison requested Mrs. Dawn Melson-Williams
to determine if this option had been considered.
Página 5
SAFETY ADVISORY AND TRANSPORTATION COMMITTEE
MEETING OF JANUARY 30, 2013 PAGE 5
Mr. Davis moved to request staff to gather information from the Capital School District,
including the number of people going in and out of the school and the total number of students
walking and driving, as well as information from the Police Chief pertaining to traffic
patterns, accidents, and safety information, and that this information be compiled, perhaps
including input from State officials, and presented to the Delaware Department of
Transportation with a request for further review and consideration of a traffic signal at the
east entrance of the New Dover High School. The motion was seconded by Mr. Keller and
unanimously carried.
Request for Waiver of Appendix A - Subdivisions, Article VI - Subdivision - General
Requirements and Design Standards, Section E - Lots (5) - Requirement for Lot Frontage on
a Public Street - 1151-1155 Walker Road, LLC (SB-13-01)
Ms. Dawn Melson-Williams, Principal Planner, reviewed a Petition to Waive Subdivision Standards
to allow the creation of a lot without public street frontage for property located at 1151-
1155 Walker Road, on the north side of Walker Road, west of Saulsbury Road, owned by 1151-1155
Walker Road, LLC. Mrs. Melson-Williams explained that the Minor Subdivision Plan proposed to
create two (2) parcels consisting of 0.6594 acres (Lot 1) and 1.1196 acres (Lot 2) from the existing
parcel of land consisting of 1.779 acres. The subject parcel is zoned IO (Institutional and Office
Zone). The proposed subdivision of Lot 2 in the rear of the property would result in a lot without
frontage on a public street.
Ms. Melson-Williams advised members that, in accordance with Appendix A - Subdivisions,
Article VI - General Requirements and Design Standards, Section E - Lots, Item 5 requires that “All
lots in a subdivision shall have frontage on a public street” and, per Appendix B - Zoning,
Article 8 - Enforcement and Penalties, Section 1 - Building Permits, Section 1.1 states that a building
permit cannot be issued for the construction or alteration of any building upon a lot without frontage
upon, or legal permanent access to, a public street. She stated that the applicant had requested a
waiver under the provisions of Appendix A - Subdivisions, Article VII - Special Provisions, A -
Variance and Waiver and that a cross-access easement was proposed to provide permanent access
to Lot 2 from Walker Road.
Staff recommended approval of the request to waive the requirement to provide lot frontage on a
public street for Lot 2. Staff found that, due to the location of the existing buildings and the existing
layout of the property, in order to achieve the required lot frontage on Walker Road (the public
street) an irregular shaped lot would have to be created and would require variances for setbacks.
This proposal would simplify the parcel shapes and present a series of proposed easements for
access, utilities, parking and shared stormwater management facilities between the two (2) lots.
The Planning Commission recommended approval of the request for a waiver of lot frontage on a
public street for Minor Subdivision Plan SB-13-01, Lands of 1151-1155 Walker Road, LLC.
Responding to Mr. Perza, Ms. Melson-Williams confirmed that a maintenance agreement pertaining
to the easements had been established.
Mr. Terry Jaywork, representing the Dover Interfaith Mission for Housing, stated that there would
Página 6
SAFETY ADVISORY AND TRANSPORTATION COMMITTEE
MEETING OF JANUARY 30, 2013 PAGE 6
be a large reduction in the number of vehicles at the property when the rear building (currently
designated for office space) becomes transitional housing.
Mr. Keller moved to recommend approval of the request for a waiver of the lot frontage
requirement on a public street for Minor Subdivision Plan SB-13-01, Lands of 1151-1155
Walker Road, LLC, seconded by Mr. Dixon and unanimously carried.
Briefing on Delaware Department of Transportation (DelDOT) Projects
Mr. Scott Koenig, City Manager, provided on update on Delaware Department of Transportation
(DelDOT) Projects, as follows:
DelDOT Repaving Project
Mr. Koenig indicated that the DelDOT repaving project, including the repaving of Loockerman
Street and portions of Governors Avenue through the City, was delayed in the fall mainly because
of the impact on the downtown merchants on Loockerman Street. The project was expected to
resume in the March/April timeframe.
West Dover Connector
Mr. Koenig advised members that DelDOT indicated that their Right-of-Way Section was in the
process of actively acquiring the necessary real estate to build the West Dover Connector, and it was
believed that this would take until mid to late 2014. The design team was working on design and
engineering documents, which they believed would be completed in late 2013, to facilitate the final
review, and construction was scheduled to take place after this. According to DelDOT, the project
had been fully funded for construction and it was hoped that construction would begin coming out
of 2014.
Route 8/Hazlettville Road Connector
Mr. Koenig stated that DelDOT indicated that the preliminary engineering for the
Route 8/Hazlettville Road Connector had been postponed until FY2017 and final engineering and
construction would not take place for several years after that.
Briefing on Dover/Kent County Metropolitan Planning Organization (MPO) Projects - Rich
Vetter
Mr. Rich Vetter, Executive Director, Dover/Kent County Metropolitan Planning Organization
(MPO) reviewed a map entitled “City of Dover West Street Bike/Pedestrian Improvements” and
advised members of the goal was to fill in some of the gaps in sidewalks and bike paths for
pedestrians and bikers. He explained that interest was expressed in extending the bike trail that runs
from Schutte Park past the Eden Hill Medical Center to run along West Street to the Dover Transit
Center with a 10-foot wide shared use sidewalk (areas depicted in red). Mr. Vetter stated that this
project was in the conceptual planning stage and Century Engineering was preparing a cost estimate.
In response to Mr. Hutchison, Mr. Vetter advised that the project was still in the planning stage;
however, he felt that it could be accomplished through the Transportation Enhancements Program,
which currently had some funding. He indicated there was no target date for the project at this time.
Página 7
SAFETY ADVISORY AND TRANSPORTATION COMMITTEE
MEETING OF JANUARY 30, 2013 PAGE 7
Mr. Vetter reviewed a map entitled “West StreetTraffic Study,” noting that discussions were
beginning regarding the conversion of West Street to a one-way, south-bound street, which was an
idea that had been presented in connection with the 2008 Comprehensive Plan. Mr. Vetter indicated
that a traffic analysis would be performed by a consultant to see if the concept made sense.
Responding to Mr. Hutchison’s inquiry regarding subsequent steps in the process, Mr. Vetter advised
that there would be many steps involved, including receiving input from DelDOT, the City, the
public, and business owners and he noted that the West Dover Connector may also impact traffic in
the area.
Update on the Creation of Bicycle/Pedestrian Subcommittee
Mr. Hutchison advised members that a Workshop was held on January 22, 2013 regarding the
establishment of a Bicycle/Pedestrian Subcommittee and a tremendous amount of interest was
expressed. Mr. Hutchison stated that, based on the large turnout, he felt that a committee of seven
(7) would be appropriate, rather than five (5) members as initially proposed. He indicated that after
all of the information is gathered from attendees at the meeting, a subcommittee would be selected
for members to approve.
Ms. Greta Whittendale, Hartly, Delaware, indicated that she was in attendance at the
Bicycle/Pedestrian Subcommittee meeting and was concerned that many of the attendees had a
vested interest in spending the funds that would be made available for promoting their own private
enterprises, such as bicycle shops. It was her understanding that less than 2% of the attendees were
actual bicyclists. Ms. Whittendale expressed her hope that the subcommittee would be comprised
of residents throughout Kent County, since County residents use City streets. In response,
Mr. Hutchison noted that the Committee will be diverse and include walkers and cyclists, as well
as those concerned with safety interests.
Mr. Davis moved for adjournment, seconded by Mr. Keller and unanimously carried.
Meeting Adjourned at 5:56 p.m.
James L. Hutchison
Chairman
JLH/JS/mk/dd/tm
S:\AGENDAS-MINUTES-PACKETS\Committee-Minutes\2013\01-30-2013 SA&T.wpd
Attachment
Attachment #1 - Map - New Dover High School Site