SAFETY ADVISORY AND TRANSPORTATION COMMITTEE
The Safety Advisory and Transportation Committee Meeting was held on January 25, 2012
at 5:01 p.m. with Chairman Hutchison presiding. Members present were Mr. Lynn, Mrs. Russell
(arrived at 5:02 p.m.), and Mr. Davis. Mayor Carey was also present (departed at 5:29 p.m.).
Mr. Hutchison was absent.
AGENDA ADDITIONS/DELETIONS
Mr. Lynn moved for approval of the agenda, seconded by Mr. Davis and unanimously carried.
Discussion - Establishing City Emergency Operations Center
Members reviewed correspondence from Mr. Dave Truax, 35 Upland Avenue, who serves as the
City’s Fire Marshal, relaying his concerns regarding the City’s lack of emergency preparedness
awareness (outside of emergency services and emergency management personnel) and the need for
an operational Emergency Operations Center (EOC) in the City.
Mr. Scott Koenig, City Manager, stated that the City’s emergency management function has
progressed through various departments throughout the years, beginning as a part of the Grounds
Department, then the Police Department, and ultimately an Emergency Management Coordinator
position was created in the Public Services Department. As a part of the Emergency Management
Plan developed for the City, the City Hall Conference Room was designated to serve as an
Emergency Operations/Information Center. He reminded members that this Center was utilized as
such during a recent hurricane and during snowstorms and met the needs for these types of
emergencies.
Mr. Koenig explained that the City has a basic Emergency Management Plan which has been
certified as meeting minimum requirements by the Delaware Emergency Management Agency
(DEMA). He advised members that emergency operations functions are currently distributed among
a number of staff members, including the City Manager, the Public Information Officer, the Fire
Marshal, a representative of the Police Department, etc. He indicated that he would like to maintain
an open position for an emergency management planner. It was his understanding that during the
recent Police Department accreditation process, a previous Emergency Operations Center (EOC)
located at the Police Department was reestablished. Members were provided a photo of the Center
and a diagram depicting the seating arrangements.
Mr. Koenig questioned if the intent of the discussion was to determine if members wished to
designate the Police Department versus City Hall as the EOC for the City of Dover.
Responding to Mr. Hutchison, Mr. Koenig confirmed that there are no backup generators currently
serving City Hall and that if power was lost during an emergency situation, it would be necessary
to utilize the facility at the Police Department to conduct emergency operations. He noted that
backup power is available at the Administration Building for the Electric Department.
Mr. Truax explained the necessity for the City to have an Emergency Operations “mindset,”
beginning with members of Council, and for each department to have a better understanding of their
responsibilities. In addition, he relayed the importance of an EOC.
Página 2
SAFETY ADVISORY AND TRANSPORTATION COMMITTEE
MEETING OF JANUARY 25, 2012 PAGE 2
Mr. Koenig suggested a review of the parameters of the two (2) rooms proposed for use as an EOC.
He recalled there being a $2,400 activation fee for the phone lines at the Police Department EOC and
noted that this was one of the reasons City Hall was selected to serve as the EOC during the recent
snowstorms and hurricane.
Responding, Police Captain Stump stated that he was not aware of such fees and indicated that the
phone lines were recently activated.
Mr. Hutchison suggested that this issue be referred back to staff for the development of policies and
procedures. Concurring, Mr. Lynn requested that staff develop recommendations for the
Committee’s review to forward to City Council for approval.
Mr. Truax requested that consideration be given to the installation of a generator at City Hall,
regardless of its use as an EOC, due to the need for electric service at City Hall during an emergency.
Mr. Hutchison requested that staff determine the costs involved for each of the rooms to become
fully used as an EOC.
Captain Mark Hall, attending on behalf of Fire Chief Fortney, noted that ambulance services for the
City are provided by PrimeCare; therefore, he suggested that staff request the participation of a
representative of PrimeCare in the development of their recommendations.
Responding to Mr. Davis, Mayor Carey indicated that Dover High School currently serves as the
City’s emergency shelter and has been used as such in the past.
Mr. Laing, Community Relations Officer and Public Relations Liaison, Delaware Department of
Transportation (DelDOT), suggested that space be allocated in the City’s EOC for the City’s Public
Information Officer.
Mr. Lynn moved to recommend referral back to staff for a report to the Committee at the next
meeting, seconded by Mrs. Russell and unanimously carried.
Update - Dover High School Construction
Mrs. Ann Marie Townshend, Director of Planning and Community Development, provided an
update on the construction of the new Dover High School. She advised members that, in December,
the City issued a foundation only permit for the building. The City continues to work with the
Delaware Department of Transportation (DelDOT), Kent Conservation District, and Capital School
District on completing the site development plans. She noted that building construction drawings
were recently submitted and the building permit application has been completed. She anticipated
that the building permit would be issued by the first week in March 2012 for the remainder of the
main structure, noting that the stadium and other buildings will require separate permits.
Página 3
SAFETY ADVISORY AND TRANSPORTATION COMMITTEE
MEETING OF JANUARY 25, 2012 PAGE 3
Mrs. Townshend reminded members that City staff attends monthly coordination meetings with
representatives of DelDOT and the consultants for the Capital School District to ensure that the
project stays on track, since there are many site and location issues. She stated that, during the last
coordination meeting, there was discussion regarding the east entrance (which lines up with
Heatherfield East) which had been planned as a signalized intersection with a pedestrian crossing;
however, the most recent submission did not show it as a signalized intersection. She explained that
installation of signals typically requires a warrant analysis which documents traffic volume and is
accomplished through DelDOT and she suggested that the Capital School District begin working
with DelDOT on this issue. However, she noted that there are additional political and safety issues
involved, explaining that there are multiple housing communities directly across the street from the
school. She suggested that the City go on record in support of the signalization of the intersection
at the east entrance and a pedestrian crossing, even if the traffic volume does not meet warrants since
there is no other way to enable children to cross the street to access the school safely.
After much discussion, Mr. Gary Laing, Community Relations Officer and Public Relations Liaison,
DelDOT, suggested that the City submit a letter to Secretary Bhatt and that Mr. Laing be copied so
that he may have the opportunity to interject himself to work with the City in this regard.
Responding, Mr. Hutchison suggested that such a letter be drafted and signed by the Mayor and City
Manager.
Mrs. Townshend offered to draft a letter in support of the signalization of the intersection at the east
entrance of the new Dover High School and the inclusion of a pedestrian crossing. Due to
Mr. Laing’s suggestion that this letter be submitted as expeditiously as possible, Mr. Koenig
indicated that the letter would be sent by staff if there were no objections (Attachment #1).
Mr. Davis moved to recommend that staff be authorized to send a letter to Secretary Bhatt
relaying support of the signalization of the east entrance intersection, with pedestrian crossing,
for the new Dover High School. The motion was seconded by Mr. Lynn and unanimously
carried.
Briefing on Delaware Department of Transportation (DelDOT) Projects - Gary Laing
Mr. Gary Laing, Community Relations Officer and Public Relations Liaison, Delaware Department
of Transportation (DelDOT), provided members a briefing on DelDOT Projects, as follows:
West Dover Connector
Mr. Laing stated that DelDOT is currently in the midst of a 30-day public comment and review
period (which will end on February 2, 2012) related to the environmental assessment of the West
Dover Connector. If there are public comments, a period of time will be provided for response. In
late February to mid-March, DelDOT plans to issue the final version of the environmental
assessment. Mr. Laing stressed the need for a finding of “no significant impact” in order to proceed
with the project. He indicated that DelDOT will then need to address the issue of a preferred
alternative for termination of the Connector at Route 13, south of Rodney Village, and acquisition
of 15 properties along the route.
Página 4
SAFETY ADVISORY AND TRANSPORTATION COMMITTEE
MEETING OF JANUARY 25, 2012 PAGE 4
Mr. Laing advised members that several years ago, there were picketers with signs that read “don’t
take my home” in front of DelDOT’s workshop and at working group meetings associated with this
project; however, more recently DelDOT has received phone calls from these individuals who are
now eager to sell. He explained that DelDOT’s planning process has made it difficult for affected
homeowners to market their homes. Mr. Laing assured members that DelDOT cannot offer a
homeowner an amount less than the assessed value of their property, can assist a homeowner in
finding a new home with a similar value, and can provide assistance with moving expenses in cases
of hardship.
Mr. Laing stated that the specifics regarding the location and design of the preferred route will be
finalized and presented to the public in April 2012. He advised members of the tentative schedule
DelDOT has established moving forward, as follows: 1) July 2012 - semi-final right-of-way
acquisitions to be completed by November 2012 (if there are no objections and eminent domain
condemnation procedures are not necessary); and 2) Summer of 2014 - begin construction.
South Governors Avenue Improvements
Mr. Laing stated that the improvements to the South Governors Avenue roadway are substantially
complete. He indicated that DelDOT has had a recent issue regarding a signal at the intersection of
South Governors Avenue and South Street, noting that the original plan included such a signal.
Since federal funds were utilized for the project, when DelDOT was ready to have the signals turned
on, the Federal Highway Administration (FHA) indicated that the intersection did not meet the
warrants for a signal and a new study was required. DelDOT completed the new study in late
fall/early winter of 2011 and it was determined that the intersection meets warrants at only certain
times of day. He advised members that there are safety concerns, noting that there is an employee
parking area located across the street.
Most recently, Mr. Laing stated that DelDOT’s Director of Traffic Operations sent a letter to the
FHA indicating that DelDOT planned to post signs indicating that the signals would become
operational on January 27, 2012 and was awaiting a response.
Water Street Railroad Crossover
Mr. Laing stated that the Water Street Railroad Crossover is not a project that will come to fruition
anytime in the near future due to the involvement of the railroad.
Wyoming Mill Road Project
Mr. Laing advised members that only the paving of the roadway was required for the completion of
the Wyoming Mill Road Project and it is hoped that this will begin in early spring when the asphalt
plants reopen.
Mrs. Ann Marie Townshend, Director of Planning and Community Development, suggested that,
in the future, a briefing on the Route 8/Hazlettville Road Connector (formerly identified as
North/South Road between Route 8 and Hazlettville Road on the West Side of the Capital School
District Property and the Village of Cannon Mills) be provided to the Committee.
Página 5
SAFETY ADVISORY AND TRANSPORTATION COMMITTEE
MEETING OF JANUARY 25, 2012 PAGE 5
Briefing on Dover/Kent County Metropolitan Planning Organization (MPO) Projects -
Rich Vetter
Due to the absence of Mr. Richard Vetter, Executive Director of the Dover/Kent County
Metropolitan Planning Organization, there was no briefing on Dover/Kent County Metropolitan
Planning Organization (MPO) projects.
Mrs. Russell moved for adjournment, seconded by Mr. Davis and unanimously carried.
Meeting Adjourned at 6:01 P.M.
Respectfully submitted,
James L. Hutchison
Chairman
JLH/JS/jg/dd/tm
S:\AGENDAS & MINUTES\Committee-Minutes\2012\01-25-2012 SA&T.wpd
Attachment
Attachment #1 - Letter of Support, to Transportation Secretary Bhatt, for the Signalization of the East Entrance
Intersection, with Pedestrian Crossing, for the new Dover High School
Página 6
ATTACHMENT #1
SA&T Committee Meeting of 01/25/2012