UTILITY COMMITTEE
The Utility Committee Meeting was held on July 13, 2015 at 5:01 p.m. with Chairman Hutchison
presiding. Members present were Mr. Neil, Mr. Blakeman, and Ms. Stewart. Mr. Cole was absent.
Members of Council present were Mr. Anderson, Mr. Hare (arrived at 5:02 p.m.), and Mr. Slavin (arrived
at 5:36 p.m.). Mayor Christiansen was also present.
AGENDA ADDITIONS/DELETIONS
Mr. Blakeman moved for approval of the agenda, seconded by Mr. Neil and unanimously
carried.
North American Energy Services (NAES) Amended and Restated Operating Agreement
Mr. Scott Koenig, City Manager, introduced the City’s Power Supply Attorney, Mr. Kirk Betts,
Betts & Holt, LLP, who worked on the renegotiation of the North American Energy Services
(NAES) agreement.
Mr. Betts reviewed his memorandum dated July 13, 2015 regarding Proposed Agreement for Plant
Operating Services (Attachment #1). He advised that in 1996, the City entered into a contract with
Duke Energy and its subsidiaries to operate the power plant on the City’s behalf. He stated that the
Duke contract was unique because Duke assumed all of the responsibility for everything, including
fuels, and sold energy to the City. Mr. Betts stated that in 2006, Duke was no longer interested in
that type of service and the City had to change the contract style.
Mr. Betts explained that the 2006 contact bifurcated the services. Dispatch, design, fuel purchasing,
etc. were completed by PACE Global, while NAES operated the plant, integrated, and interfaced
every day to determine what the dispatch should be. He stated that all of the plant employees,
including former City employees who went to Duke and those that stayed with NAES, remained at
the plant; however, over time NAES managed the level of employees in order to operate the plant.
Mr. Betts informed members that, under the NAES contract, NAES provides an annual budget for
the operation of the plant, which City staff negotiates prior to budgeting any staffing or operating
costs. He stated that fuel costs and services are managed by The Energy Authority (TEA), and TEA
operates as a dispatching advisor to the plant. Mr. Betts explained that the current contract was a
four (4) year contract which the City let renew annually under an evergreen provision. In order for
the contract to be terminated, 18 months notice had to be given. He advised that one (1) of the
reasons that the City had a shorter contract was because it had an escalation provision in it that went
up according to a Bureau of Labor Statistics (BLS) standard for professional employees in this
region. Mr. Betts stated that, on average, the cost had escalated approximately 21%, since 2006.
He noted that the belief had been that the City would probably renew, renegotiate, or rebid that
contract prior to this time.
Mr. Betts explained that, after evaluating the quality of the services and the market for companies
that do this type of work, and given the age and the institutional knowledge that NAES has on
operating the plant, he and staff agreed that there is an inherent value in trying to sole source
negotiate the contract. He stated that he, Mr. Harry Maloney, Electric Director, who is an
Paj 2
UTILITY COMMITTEE MEETING OF JULY 13, 2015 PAGE 2
experienced power plant supervisor, and NAES worked together to develop a slightly different
contract that operates at a lower cost and has some new orientation on how the City wants the project
to be operated.
Mr. Betts informed members that the proposed agreement would be for five (5) years (2015 - 2020).
He explained that he, the City Manager, and the Controller/Treasurer agreed that five (5) years would
be a good transitional period for the City because it is toward the end of the age of this plant and also
a period of great transition for PJM. Mr. Betts stated that this proposal would allow the City to
capture and hold onto the institutional knowledge that exists, and provide some opportunity for
managing the longer term International Brotherhood of Electrical Workers (IBEW) labor contract.
He noted that the IBEW contract had been extended for one (1) year; however, staff had been
advised that the IBEW contract would now be finalized for a longer duration.
Mr. Betts explained that the proposed agreement provides for a fixed annual fee for management,
and the amount of this fee would decrease from the current fee. He stated that this fee would include
the management fee, home office support, which previously averaged at approximately $75,000 per
year, and operating incentives, employee bonuses, and burdens.
Mr. Betts informed members that, in the past, there was an incentive fee provision which provided
an annual bonus of several hundred thousand dollars if the plant achieved specific operational
parameters. He explained that the proposed contract includes a maximum performance reduction,
which would allow for a contract price reduction between $500,000 and $550,000 per year if they
fail to meet certain standards, such as availability and dependable capacity. Mr. Betts stated that the
City has to meet certain standards in order to get the full value out of the PJM Reliability Pricing
Model (RPM) payments, and this provision aligns the mutual interests of both parties in the
operations of the plant.
Mr. Betts reminded members that two and one-half years ago, the City decided to allow for the
retirement of Units 1 and 2. He stated that these units are 50 year old, 17 MW steam units which
are difficult to find parts for, and they are not as reliable as they need to be. Mr. Betts advised that
the decision to retire these units would change the operations of the plant and, as a result, the City
would realize a several hundred thousand dollar reduction in operating costs in the proposed
contract.
Mr. Betts informed members that, between the changes in the way the management fee is structured,
the way the incentive fee and performance penalty pieces are constructed, and with the change in
how the plant will operate, he anticipates that the City will realize an annual cost reduction in excess
of $300,000 within a year and a half and will not reach the current contract price of $6M per year
within the next five (5) years. He explained that, overall, the objectives were to save the institutional
knowledge, preserve the operation of the plant, and reincentivize the plant in order to earn money
as opposed to keep costs down. Goals would be to operate more efficiently, dispatch more
frequently, reduce the number of outage days, change the scheduled outage, and raise performance
so the plant is not offline for as long as it has been in the past, and ultimately earn more money for
Paj 3
UTILITY COMMITTEE MEETING OF JULY 13, 2015 PAGE 3
the City by having this unit online. Mr. Betts stated that the proposed contract would provide the
City with a reduction in cost and provide the performance that the City needs to maintain a
competitive posture in the marketplace.
Responding to Mr. Hutchison, Mr. Betts stated that Units 1 and 2 would be retired on May 31, 2017.
Mr. Anderson stated that he had concerns regarding the contract, whether or not it should have been
put out for bid, the amount that the City is spending, and whether or not the City is getting the most
for its money. He questioned what the City’s five (5) year plan was and whether the City should lock
in a manager prior to deciding what to do with the City’s plants. Mr. Anderson stated that he liked
the inclusion of the six (6) month provision.
Mr. Anderson requested further explanation of the negotiated cost savings. Responding, Mr. Betts
stated that the biggest savings would be realized in the management fee costs and staff savings. He
reiterated that the fixed management fee, the amount held for performance, and bonuses that are part
of their compensation package would be lower. Additionally, he explained that there was an
expectation that there will be a change in how the plant is managed staff-wise, which would add
several hundreds of thousands of dollars in benefits. Mr. Betts noted that some of the City’s risk
associated with using back office personnel would also be mitigated by fixing that as part of the base
contract. He explained that the City would receive all of the services that are now prescribed,
without the risk of having hourly rates based upon how the City uses those services. Mr. Betts
reminded members that the proposed contract also included a maximum performance reduction. For
example, he explained that if the City is penalized through PJM for too many forced outages, NAES
would be penalized as well. Mr. Betts stated that this provision would help compensate the City in
the event that NAES fails to perform on those important criteria for availability, dependability, unit
capacity dependability, etc.
Mr. Betts stated that Mr. Anderson’s concerns regarding whether or not this agreement should have
gone out to bid were important. He explained that it would be difficult to find people in the
marketplace who have the skill sets to deal with a 40 to 50-year-old plant. Additionally, the people
who run a unit develop a sensitivity about the equipment, they know how an engine is supposed to
work, when the steam is supposed to be going through, and what it sounds like before you
synchronize, and Mr. Betts and staff believed that these skills could help negotiate the price down,
because they have mitigated some of the risk of not knowing how this plant functioned. Mr. Betts
explained that a new supplier may not want to guarantee the plant’s availability because of the
unknown factors; therefore, it was his recommendation to try to negotiate a fairer price to operate
the plant with the same entity, based on the City’s criteria, rather than going out to the marketplace
and bringing in an entity that would add to the risk premium for operating a plant like the City’s.
He believed it was wiser to stay with the same entity and the people who know how to operate the
plant rather than taking that risk at this point in the plant’s history.
Mr. Hare asked if NAES could provide an estimate of the maintenance costs for the next three (3)
or four (4) years. In response, Mr. Betts stated that NAES knows how the City’s plant functions,
noting that they have approximately six (6) steam plants of similar vintage within their system and
they have monthly manager meetings to discuss equipment. He explained that there are two (2)
types of maintenance, major maintenance and annual scheduled maintenance, and the annual
Paj 4
UTILITY COMMITTEE MEETING OF JULY 13, 2015 PAGE 4
scheduled maintenance is estimated for five (5) years. Mr. Betts expressed his opinion that, with the
experience of TEA and Mr. Maloney, there would be more than just an annual projection of plant
costs and types of maintenance.
Mr. Betts reminded members that one (1) of the reasons the City decided to proceed with closing the
two (2) oldest units, aside from their inefficiency, was the high cost of performing the next level of
maintenance. He stated that the approximate cost was $500,000 and would have included opening
up the units, working on the turbines, and attempting to provide some life extension.
Mr. Betts stated that by looking at the five (5) year projection, the City can determine what expenses
are appropriate, given where it is in its life cycle. He expressed his opinion that NAES has very
sophisticated people and Mrs. Donna Mitchell, Controller/Treasurer, has done a great job of assuring
that the City receives a budget with accurate estimates.
Mr. Betts informed members that a major part of the discussions regarding the proposed contract
focused on ensuring that the City receives accurate estimates for the budget to ensure staff does not
have to request additional funds from Council and because it affects the customer’s rates.
Mr. Hare asked whether the City could provide a six (6) month notice and get these credits cheaper
elsewhere if PJM were to stop giving the City capacity credits. Responding, Mr. Betts explained that
there are a lot of strategies that the City would want to review prior to making that decision. He
advised that some municipal clients were looking at going behind the meter, explaining that the City
can take that capacity inside and plan against peaks to achieve similar results, so that the City is not
getting hit with the PJM charges. Mr. Betts stated that, with the proposed contract, the City would
have an option to terminate the agreement; however, the City would want to thoroughly study and
line up alternatives prior to providing a six (6) month notice.
Mayor Christiansen stated his appreciation for the work Mr. Betts had done and asked what he
projected may happen over the next five (5) years, particularly with the PJM grid requirements.
Noting that this is one (1) of the City’s major sources of revenue, Mayor Christiansen also
questioned if the City should be looking at the possibility of moving out of the utility business or
looking for another deal to keep the City as a competitive player in the business.
In response to Mayor Christiansen, Mr. Betts stated that Mr. Maloney has been proactive in looking
to the future and trying to determine different alternatives. He stated that technological
advancements are changing the market. Mr. Betts thought that some of the questions members
should ask are what the future would look like in terms of how the City will use and produce energy
and how its customers will use it. He explained that the City needs to understand how customers
will use energy in the future to ensure that whatever the City does matches the market and to ensure
that the City does not end up overbuilding and overcharging for services based on year 2000 ideas
that the City is trying to implement in 2020.
Mr. Betts informed members that he had recently read an article about a municipal utility in the
Midwest that is building a 40MW battery station instead of a power plant. He explained that it takes
in energy during the day, feeds it out at the night, and deals with solar and wind factors. Mr. Betts
noted that this balances the frequency problems that PJM and all the utilities are having today
because of the variety of sources coming in.
Paj 5
UTILITY COMMITTEE MEETING OF JULY 13, 2015 PAGE 5
Mr. Betts stated that Mr. Maloney has proposed reviewing everything comprehensively to determine
what would make sense for the future. He stated that this would include a review of fixing McKee
as a power plant, generation options, where to get the best deal on a unit, consideration of recent gas
issues on the peninsula, PJM requirements for two (2) forms of fuel, solar which is being
incentivized, renewable portfolio standards, etc. Mr. Betts noted that this was an exciting time to
be on the Utility Committee because there is so much going on, with many variables and ways to
look at how to solve customer needs.
Mr. Betts stated that there is a difference in thinking today from 20 or 30 years ago. He reminded
members that Kraft wanted to build a coal-fired plant 20 or 30 years ago and 10 years later it was
not a good idea; however, they kept it going and ultimately sold it to a third-party to operate.
Comparatively, he stated that P&G is currently considering building two (2) MW solar on some of
their properties. Mr. Betts stated that some of these decisions are driven by tax credits or the desire
to have a green energy facility. He explained that, in contrast, the City is trying to figure out how
to balance those interests and still provide the revenue that supports the City. Mr. Betts advised that
he would not encourage the City to get out of the business, if for no other reason than that the City
owns the distribution rights and can control all the electricity that goes out to the customers. He
stated that, even if the City got out of generation, it would still have a resource for revenue through
the distribution system. Mr. Betts expressed his opinion that the City has resources in place, a great
69kV loop, a good distribution system, and is in a really good spot, as an entity, to be in the utility
business.
Mr. Betts stated that he was very encouraged and excited by all of the changes in the industry, noting
that there are new ideas every day that are changing the way people use energy and the way energy
can be produced and delivered more efficiently. It was his opinion that the City is almost in a perfect
spot by having a facility that can be given up to switch to something that would allow the City to
leap ahead from where it would otherwise have been (5) years ago.
Mr. Neil questioned how long the bid process would take and what effect it would have on the City
if the proposed contract were not accepted and the City put this out to bid. Responding, Mr. Betts
estimated that it would take a minimum of six (6) to eight (8) months. He reminded members that
the City would remain under the old contract, which has an 18-month notice period; therefore, the
City would probably want to give notice right away and take the risk of completing that process in
time. Mr. Betts stated that he did not have the same confidence that he had 10 years ago when he
suggested that there were a lot of people out in the marketplace that are providing these types of
services and are willing to take the type of risks that the City would ask them to assume. He noted
that he is an advocate of RFPs; however, the current market is narrow, which creates a greater risk.
Mr. Betts reiterated that it was his recommendation to try to negotiate a sole-source deal, due to
where the City is with the cycle of this plant and the knowledge of the type of plant it is.
Mr. Hutchison reminded members that the City had been working on this for a while and the playing
field will be changing in 2017. He stated his support for Mr. Betts’ recommendation and the
proposed contract. Although he recognized members’ concerns, Mr. Hutchison expressed his
opinion that dealing with a known partner was critical.
Paj 6
UTILITY COMMITTEE MEETING OF JULY 13, 2015 PAGE 6
Mr. Betts advised that one (1) of the challenges that the City has faced since transitioning out of
operating the plant relates to employees. He explained that, in the past, the City has negotiated a
responsible transition for those individuals to have the first opportunity for positions; however, he
was not certain how that would work in today’s market. Mr. Betts stated that there is a value to those
people and it is potentially disruptive to put this out to bid. He reminded members that over a year
ago when the City discussed whether or not to continue in the utility business or sell to Delaware
Electric Cooperative, it had an effect on the morale of the people who work in the utility part of the
City, which always affects how a system functions. Mr. Betts stated that settling this issue had
provided real value to the City. He stated that the uncertainty of the bid process has a potential
impact on the City’s capacity to operate as efficiently as it does now and also on what happens to
those employees.
Mr. Hare expressed his opinion that the City’s value is not in the plants but the network, noting that
if the City has to shut the plants down, it will still be in the business of supply through the network.
Mr. Betts stated that he had previously discussed the net benefit of the utility with Council. He
advised members that half of the cost of the NAES contract is for labor and the management fee,
while the other half is the traditional costs for operation and maintenance. He stated that there is an
approximate cost of $6M with PJM; therefore the City makes approximately $3M by having the
plant, whether or not it is working, and the City makes money because of the capacity value, as long
as it functions. Mr. Betts explained that the City needs to ensure that the plant is ready to operate,
because if the City has a forced outage at a really bad time, the City gets penalized. He reiterated
that the proposed contract is meant to ensure that the plant is always ready to operate over the next
five (5) years, with the inclusion of the maximum performance penalty. Mr. Betts stated that there
are now weekly meetings between Mr. Maloney, as the owner’s representative, and the plant
manager. He noted that there is not a separate entity operating with TEA telling them when to run,
the City is in the middle of the process now to ensure the plant is ready, able, and capable of
producing, so that the City gets the optimum value for the plant. Mr. Betts informed members that
the City is also in a good position because the City is connected to a gas line and has oil. He stated
that in the new capacity product that PJM is requiring, you have to have alternative fuel if you are
on gas. Mr. Betts explained that the City has the potential to get the optimal value in PJM for the
plant, at least until the City decides to shut it down, based on the differential between the operating
costs and what the City can get in terms of capacity payments from PJM.
Mr. Neil explained that he did not doubt that this was a good contract and that his question
pertaining to an RFP was intended to ensure that the City had looked at the alternatives and this was
the best alternative. He noted that if the City were going to do an RFP, it should have been done
eight (8) months ago, not now. Mr. Neil expressed his support for the contract, noting that it is the
alternative that serves the citizens well.
Mr. Neil moved to recommend approval of the contract, seconded by Mr. Blakeman and
unanimously carried.
Paj 7
UTILITY COMMITTEE MEETING OF JULY 13, 2015 PAGE 7
Annual Engineering Consultant's Report on the Operation and Maintenance (O & M) of the
Electric System - Fiscal Year 2014
Mrs. Donna Mitchell, Controller/Treasurer, reviewed the conclusions of the Annual Engineering
Consultant’s Report on the Operation and Maintenance (O & M) of the Electric System - Fiscal Year
2014, prepared by Burns & McDonnell Engineering Company, Inc. She reminded members that the
Annual Engineering Consultant’s Report was required by the 1985 Bond Resolution for the electric
utility.
Mr. Blakeman noted that the Engineering Consultant had endorsed the fact that the electric system
has been well run and well maintained. He advised that Page 1-3 of the Report stated that
“specifically, the generation facilities have demonstrated a high level of availability despite the
dispatching of the units primarily for peak demand.” Additionally, in regard to the transmission and
distribution (T&D) system, the Report stated that “In recent years, the City has made appropriate
upgrades and improvements which the Engineering Consultant has observed while conducting the
reviews and assessments to complete the annual reports.”
Mrs. Mitchell informed members that the City’s debt calculation requirement was 1.5%. Referring
to Page 4-6 of the Report, she noted that in FY14 the City had a net loss of $2.3M. She explained
that although the City met the debt calculation, the loss was a result of the polar vortex which caused
the City to increase the transfer from the Rate Stabilization Reserve from the budgeted amount of
$4M to $7M. Mrs. Mitchell stated that the City’s sales were $2M under the estimated amount and
that created the net loss. She advised that she was in current conversation with Moody’s and they
have some concerns with the transfer because there is a clause in the City’s resolution that indicates
if the transfer will cause the City to miss the covenant, the City is to hold that transfer. Mrs. Mitchell
explained that the City has the Rate Stabilization Reserve for that purpose, noting that if the power
supply spikes, the City covers it. She stated that she had another call with Moody’s scheduled for
Tuesday, July 14, 2015 and would keep members apprised.
Mayor Christiansen asked if it would be convenient for the Chairman of the Utility Committee,
himself and, perhaps, the Council President to sit in on that call as well. In response, Mrs. Mitchell
stated that this was not typical; however, they could sit in on the call if they wished. She explained
that she simply wanted to make members aware of the discussion, noting that staff had already had
two (2) discussions with Moody’s. Mrs. Mitchell advised that she had also sent Moody’s several
pieces of information, one (1) of which was the balance in the Rate Stabilization Reserve as of
June 2013, which was 35% of revenue. She explained to Moody’s that the policy is 10% and the
City was more than well enough funded, had set aside those funds to cover volatile issues such as
this, and was following financial procedures.
Mayor Christiansen questioned how it would affect the City’s bond rating if Moody’s does not
understand the reason why the City increased the transfer. Responding, Mrs. Mitchell stated that,
based on her previous conversations with Moody’s, she did not think that they would downgrade the
City; however, rather than putting the City on a positive outlook, they may put the City on a stable
or a watch, or possibly a negative.
Paj 8
UTILITY COMMITTEE MEETING OF JULY 13, 2015 PAGE 8
Mayor Christiansen asked if the City of Dover was the only utility that they deal with that had to take
such action because of the change in the weather. In response, Mrs. Mitchell stated that she could
not answer that question; however, she stated that Moody’s would be reviewing the credit of many
other entities at a meeting scheduled with a utility review committee, not just the City of Dover’s
credit. [City Clerk’s Office Note: Subsequent to the meeting, members were informed that Moody’s
had affirmed the Aa2 rating of the City of Dover’s electric bonds.]
Responding to Mayor Christiansen, Mrs. Mitchell stated that on a scale of one (1) to 10, the City’s
concern regarding this matter should be around three (3).
In response to Mr. Hutchison’s question regarding the additional $6M or $7M expense last winter
related to peaking time, Mrs. Mitchell explained that the City was required to run the plant and could
not because there was no oil available. In addition, she stated that the City had to purchase off the
open market, through PJM, and the price escalated because of the cold weather. As a result of these
factors, the City had to transfer an additional $3M from the reserve to the operating fund.
Responding to Mr. Hutchison, Mrs. Mitchell advised that everyone under PJM, including the City,
has the same reliability standards and must be able to run when they are called on or be penalized.
She explained that there was not a problem with the operation of the plant or the people who operate
it; the plant was unable to run when called on because there was a problem with oil deliveries across
the peninsula.
Mr. Blakeman noted that this was not the first time that the City had to take units offline because of
fuel unavailability.
Mr. Kirk Betts, Betts & Holt, LLP and the City’s Power Supply Attorney, reviewed background
information regarding some of the market forces involved in what happened during that polar vortex
period. He stated that he has other clients who require gas and they have had more interruptions in
the past two (2) years than in the past 15 years. In terms of their demand on the system, gas supplies
on Delmarva have gone down and the pipes have not been able to supply it. He advised that many
people are relying on oil during that time of year and the City should pay in advance or have a
contract to ensure they have oil deliveries scheduled. Mr. Betts noted that this is a new way for them
to exercise their market power to guarantee that they receive payment.
Additionally, Mr. Betts informed members that PJM has lifted the cap on pricing. He explained that,
previously, there was always a market price based on dispatched prices; however, during the first
polar vortex, it capped out at $1,000 and people complained that they could not get the gas or oil and
pay for it, even at $1,000 per megawatt hour (MWh). Mr. Betts stated that $1,000/MWh equated
to $1.00 per kilowatt hour (KWh), noting that the City normally pays $0.04 per KWh.
Mr. Betts advised that many companies were affected when PJM lifted the cap on pricing because
they did not have contracts that allowed them to float through the extraordinary costs. He stated that
it was done very quickly in order to get the market back in balance and many utilities could not
recover that cost. Mr. Betts explained that some companies may have had a guaranteed price of
Paj 9
UTILITY COMMITTEE MEETING OF JULY 13, 2015 PAGE 9
$0.09 per kilowatt hour in the wholesale market and had to take a loss on the other $0.91 because
their contracts did not allow it. He stated that companies like Washington Gas Energy Services have
gone out of the business because of that year and all of the changes that happened suddenly.
Mr. Betts advised that one (1) of the things that Moody’s and others are looking at is if the City is
able to pass through and recover extraordinary costs, noting that if an entity’s rate structure allows
for that, the entity is in a better position.
Mr. Betts advised members that last year The Energy Authority (TEA) assumed that the City’s plant
was not going to dispatch and then it needed to dispatch. He stated that having Mr. Harry Maloney,
Electric Director, onsite will add insight to the plant since he can probably predict when the plant
is going to run. Mr. Betts noted that TEA’s dispatching gas, the plant being ready, and onsite
understanding regarding what to do next will really help the City in the future.
Mr. Blakeman questioned whether the cap had been reinstalled. Responding, Mr. Betts stated his
understanding that the cap was now at $1,800, which is pretty high. He expressed his excitement
about where the City is in terms of planning the next set of generation, noting that gas is one (1) of
the factors in the mix but it is not the whole answer.
Mr. Blakeman moved to recommend acceptance of the report as presented, seconded by
Mr. Neil and unanimously carried.
TEA/NAES Report (May)
The TEA/NAES Monthly Report for May 2015 was provided to members to enable them to monitor
electric sales and revenues received, which will provide a better understanding of any fluctuations
that occur and allow the opportunity to make improvements if deemed necessary.
Referring to the year-to-date summary on Page 12 of the TEA Report, Mr. Scott Koenig, City
Manager, stated that the Variance indicated that the Actual YTD was approximately $1.3M more
than the Budget YTD, noting that this was in part due to the City’s load being up slightly. He
advised that the variance had decreased fairly substantially over the last couple of months and he was
hopeful that the variance would continue to close, as he expected that the numbers for June would
be relatively strong because it was warm.
Mr. Koenig advised that the Final Cost of Service to City of Dover Ratepayers was budgeted at
$63.42 per megawatt hour (MWh) and the Actual YTD was approximately $64.02 per MWh. Noting
that there was only a slight variance, he stated that this was a good indication that things were
tracking as expected throughout the year.
Referring to the Generation Summary on Page 4 of the TEA Report, Mr. Blakeman noted that the
actual revenue had come in below budget for seven (7) out of the 11 months. He questioned if the
City would be able to recover that revenue during the last month, or if it would even out since the
actual revenue far exceeded the budgeted amount during a couple of the months. Responding,
Mr. Koenig stated it would be very close.
Paj 10
UTILITY COMMITTEE MEETING OF JULY 13, 2015 PAGE 10
Mr. Neil moved to recommend acceptance of the TEA/NAES Report for May 2015, seconded
by Mr. Blakeman and unanimously carried.
Updates (Deferred during the meeting of June 22, 2015)
By unanimous consent, Item #4 - Updates was deferred.
Mr. Neil moved for adjournment, seconded by Mr. Blakeman and unanimously carried.
Meeting adjourned at 5:55 p.m.
James Hutchison, Sr.
Chairman
JLH/TM/dd
S:\AGENDAS-MINUTES-PACKETS-PRESENTATIONS-ATT&EXH\Committee-Minutes\2015\07-13-2015 UTILITY.wpd
Attachments
Attachment #1 - Memorandum dated July 13, 2015 from Kirk Betts Regarding Proposed Agreement for Plant
Operating Services
Paj 11
ATTACHMENT #1
BETTS ~ HOLT LLP Utility Committee Meeting of 07/13/2015
COUNSELLORS AT LAW
1100 l 7"' STREET• SUITE 901 • WASHINGTON, DC 20036
TELEPHONE 202.530.3380 • FAX 202.530.3389
July 13, 2015
To: Scott Koenig, City Manager; Donna Mitchell, Controller/Treasurer;
Harry Maloney, Electric Director
From: Kirk Howard Betts, Betts & Holt LLP
RE: Proposed Agreement for Plant Operating Services
Background
On May 4, 2006, the City of Dover entered into an Operations & Maintenance
Agreement with North American Energy Services (NAES) to maintain and operate Dover's
generation. 1 The contract had an initial four year term and it was extended four times
automatically for one year terms.
Dover's generation consists of three steam units in the McKee Run plant and one
combustion turbine at VanSant. NAES is responsible for operating and maintaining Dover's
generation, staffing and collective bargaining, managing dispatch, environmental controls and
complying with permits, guaranteeing capacity performance, maintaining records, preparing
budgets, outage plans, and reports to governmental authorities.
The current contract provides for a management fee and reimbursement for all other
costs, including staffing, relocation, insurances, training, permit fees, and advisors. All other
plant operating costs (consumables, tools, spare parts, equipment, capital improvement projects,
etc.) are paid directly by Dover. NAES management fee started at $175,000/year in 2006 and
has escalated annually to almost $212,000 in 2015.
The contract also provides an incentive bonus (which started at $140,000 and is now
approx. $173,000 for 2015-16) structure that rewards NAES and its personnel for achieving
certain goals, such as commercial availability, dependable capacity, safety, and environmental
performance. With the exception of 2014, NAES regularly achieved the full incentive bonus.
Both the management fee and the bonus escalated annually based on the Employment
Cost Index for private industry works by industry and occupational group, published by the
Bureau of Labor Statistics. The minimum was fixed at 1% per year. Since inception, escalation
has increased the fixed fee and incentive fee components by 21.1 %.
Negotiation Objectives
Discussions with Dover representatives produced the following objectives:
1
The Agreement has been amended three times, June 1, 2006, July 1, 2007, and July 1, 2008.
Paj 12
Memorandum
July 13, 2015
Page 2
• Update contract to address changes in operations, law, PJM, and
decommissioning of McKee Units 1 and 2.
• Reduce the cost of NAES services.
• Address Dover financial concerns, including training, cost estimates for special
services, cost of "home office services," qualifying suppliers and bidders,
compliance with Dover procurement policies and practices.
• Address issues around performance incentives and accountability
• Incorporate market conditions affecting revenue and load growth
• Set new term and provide more flexibility for termination
Proposed Amended and Restated Operation and Maintenance Agreement
The proposed agreement addresses Dover's express objectives.
1. Lower the annual costs. The proposed agreement provides for a fixed annual
management fee, paid monthly, that will have a starting cost $43,000 lower than the current
agreement, but will be reduced further during the second and third years as staffing changes are
implemented corresponding to the scheduled decommissioning of McKee Units 1 and 2. See
Section 2.2 Management Fee. The fixed fee portion of the proposed agreement will be less than
the current agreement costs in 2015-16 when it expires in 2020. Overall, fixed fee and
reimbursable staffing expenses are estimated to reduce annual expenditures by more than
$300,000/year compared to the current agreement, in addition to O&M costs avoided by closing
Units 1 and 2. Some of these reductions start immediately, but the major reductions will be
realized in 2017. The proposed effective date is July 1, 2015.
A major change in the proposed agreement is the shift to a fixed annual fee for
management. The fee includes the management fee (which is decreased from the current fee),
and home office support (previously billed hourly as a reimbursable expense), operating
incentives, employee bonuses, and burdens (previously computed and reimbursed by Dover). In
this agreement, if NAES needs more staff or if Dover require more home office support, the risk
of higher costs reside with NAES. In other words, this agreement provides greater predictability.
However, while also putting full responsibility on NAES to manage down the size of the staff
while maintaining reliability, it also puts more of NAES' fee at risk, as described below.
2. Changed the focus from incentive bonus paid at year-end to performance based reduction
where NAES pays Dover. The prior agreement had an incentive fee that had escalated to
approximately $173,000 that would be awarded to NAES if it met certain criteria for availability,
commercial unavailability, dependable capacity, safety performance, and environmental
performance. Each performance standard had a dollar value. The proposed agreement contains
objective performance standards that if not achieved penalize NAES. Under the proposed
agreement, Dover negotiated a substantially higher amount of compensation at risk, defined as
Paj 13
Memorandum
July 13, 2015
Page 3
the Maximum Performance Adjustment, if NAES does not the performance standards. See
Section 2.2 Definition of Maximum Performance Adjustment and Appendix B. The
performance adjustment puts more of NAES' fee at risk every year of the contract--over
$500,000/year compared to $172,000 now. NAES's bottom line will "feel" the implications of a
plant failure and share in the cost that would be imposed on Dover by PJM and aligns the
performance interests of both parties more closely.
3. Clarifies scope of services included. The proposed agreement clarifies staffing and home
office staff responsibilities that are included in the monthly fee. These services have been billed
on an hourly basis and averaged about $75,000/year. They will be included in the Management
Fee going forward. See Appendices A and F.
4. Procurement obligations. There is a positive tension on how costs are managed and
contracts awarded. This tension also creates conflicting objectives between lowering costs and
increasing plant operating revenue. The current draft seeks to focus on increasing revenue
through more attention to reliability to maximize the generating resource and the City's
investment in those resources. We have heard during these negotiations an appreciation for
oversight and a concern about micro-management and mixed signals. The approach that is being
recommended necessarily involves the terms of the contract and the collaboration of NAES and
the City's finance office, particularly procurement, to make it work smoothly. 2
The original and current agreement are based on having a third party operate and
maintain Dover's generation. The agreement provides for an annual operating and capital budget
and regular consultation concerning plant performance and costs. The plant operating and
maintenance budget is provided as part of the Dover budget development cycle. A substantial
part of the budget is for staffing, planned maintenance, and capital repairs and replacements (also
planned). We are recommending a contingency in the budget for unplanned work. It is not
intended to be a fund for cost overruns or discretionary projects, but it is intended to address the
reality that generating plants, particularly of this vintage, experience equipment failures.
The procurement process follows the 2012 procurement procedures, Administrative
Manual, AMP 501, latest edition, which was approved by the City. Although this appears to be a
parallel procurement system, our recommendation is to continue using these procedures since the
equipment and services are within NAES' particular expertise and it has the greatest knowledge
of suppliers for the types of equipment and services needed. Moreover, planned maintenance
and CIPs would all be reviewed as part of the budget process and also during periodic meetings
with Dover's Representative, Electric Utility Director Harry Maloney. We believe his presence
provides a day-to-day awareness of the utility, oversight, and qualified point of contact for
NAES and the City who also is in regular consultation with the City Manager and Finance
2
A recent inquiry involving cell phone service highlights the overlapping work and interests of
the parties. It may expedite matters ifthe City and NAES clarify the scope of procurements, i.e.,
which are general services and which require specific plant expertise, to determine which
services and types of procurements may be most efficiently managed by the City and by NAES.
Paj 14
Memorandum
July 13, 2015
Page 4
Director. Mr. Maloney provides a level of technical capability regarding plants, PJM, and
municipal procurement that has not been present in recent years.
Another consideration is that the agreement and PJM impose substantial penalties for
failure to dispatch (availability). Consequently, both NAES and the City have an aligned interest
in assuring the generating plants are ready to be dispatched and that unplanned outages, as well
as planned outages, are as short as possible.
5. Duration of Agreement. The proposed agreement is for five years (2015-2020). Notice
for termination or renewal has been shorted to six months for Dover, and twelve months if
requested by NAES. The agreement expires in 2020.
6. Updated Agreement. The proposed agreement deletes all references to the transition
period when NAES assumed responsibility for plant operations. It incorporates the changes
anticipated by the scheduled withdrawal of McKee Units I and 2 from service in 2017. All the
appendices have been updated.