UTILITY COMMITTEE
The Utility Committee Meeting was held on August 13, 2012 at 5:30 p.m. with Chairman Bonar
presiding. Members present were Mrs. Williams, Mr. Blakeman, and Mr. Snaman. Mr. Perza was
absent. Members of Council present were Council President Leary, Mr. Anderson (arrived at 5:44 p.m.),
Mr. Lynn, Mr. Hare (arrived at 5:33 p.m.), and Mr. Hutchison. Mayor Carey was also present.
AGENDA ADDITIONS/DELETIONS
By unanimous consent, the agenda was approved as presented.
Dedication of Rights-of-Way and Public Infrastructure - Clearview Meadow Subdivision,
Phase I
Members were advised that the Knollwood Development Corporation, responsible party for
completing the public infrastructure within Phase I of the Clearview Meadow Subdivision, has
requested that all public infrastructure improvements related to this phase be dedicated to the City
of Dover for permanent ownership and maintenance. Members reviewed a map depicting the general
location and configuration of the subject rights-of-way. The Knollwood Development Corporation
completed construction of the improvements within Phase I in accordance with City standards and
specifications. After construction was completed, staff inspected the public improvements and
developed a list of repairs to be made to meet the City of Dover Standards and Specifications for
Public Works Construction. As of this date, all work required has been completed. A one (1) year
Maintenance Agreement and associated Bond will be submitted as part of the dedication process.
All other requirements of dedication have already been provided to staff.
Staff recommended acceptance of the dedication of rights-of-way and public infrastructure in
Phase I of the Clearview Meadow Subdivision, with dedication to include all of the referenced public
improvements, as follows:
Sewer Utility Infrastructure (Construction Value = $166,221):
12” SDR-35 PVC Sanitary Sewer Main - 252 l.f.
8” SDR-35 PVC Sanitary Sewer Main - 2,094 l.f.
6” PVC Sanitary Sewer Laterals - 2,483 l.f. (75 laterals)
4’ Diameter Sanitary Sewer Manholes - 10 ea.
Water Utility Infrastructure (Construction Value = $180,016):
10”Ductile Iron (Class 52 Cement Lined) Water Main - 940 l.f.
8” Ductile Iron (Class 52 Cement Lined) Water Main - 2,363l.f.
6” Ductile Iron (Class 52 Cement Lined) Water Main - 75 l.f.
1” Type K Copper Water Services - 2,483 l.f. (75 services)
10” Gate Valves - 7 ea.
8” Gate Valves - 9 ea.
Fire Hydrants - 5 ea.
Storm Water Infrastructure (Construction Value = $85,697):
Catch Basins Type J - 18 ea.
Catch Basins Type JJ - 2 ea.
18” Type III Reinforced Concrete Pipe - 379 l.f.
15” Type III Reinforced Concrete Pipe - 958 l.f.
Paj 2
UTILITY COMMITTEE MEETING OF AUGUST 13, 2012 PAGE 2
Street Infrastructure (0.7685 miles) (Construction Value = $559,912):
John Hunn Brown Boulevard Station 0+00 to Station 12+14 1,214 l.f.
Mer Way Station 0+00 to Station 7+97 797 l.f.
Lady Bug Drive Station 0+00 to Station 6+60 660 l.f.
Nob Hill Road Station 28+00 to Station 33+50 550 l.f.
Babb Drive Station 2+50 to Station 5+35 285 l.f.
Nob Hill Road South Alley Babb Drive to JH Brown Blvd. 560 l.f.
Mr. Scott Koenig, City Manager, advised members that the total construction value of the public
improvements was $991,846.
Mr. Blakeman moved to recommend approval of staff’s recommendation for the acceptance
of the dedication of rights-of-way and public infrastructure for the Clearview Meadow
Subdivision Phase I, to include all of the referenced public improvements. The motion was
seconded by Mrs. Williams and unanimously carried.
Annual Review and Approval of Governing Policy for Energy Commodity Risk Management
Members reviewed the Governing Policy for Energy Commodity Risk Management.
Mr. Scott Koenig, City Manager, reminded members that during their meeting of July 23, 2012,
Mr. Jamie Mahne, Chief Client Officer for The Energy Authority (TEA), gave a presentation
regarding Dover Risk Policy Modifications. As the City’s Energy Manager, TEA had
recommendations for modifications to the City’s Energy Risk Policy. Mr. Koenig indicated that the
Governing Policy for Energy Commodity Risk Management was inadvertently omitted from the
material presented for consideration during that meeting.
Mr. Koenig advised members that, in accordance with the policy, the Utility Committee must
conduct an annual review and approval of the Governing Policy For Energy Commodity Risk
Management. He stated that in the future staff would present the policy for review and approval in
April or May of each year to coincide with the annual budget process.
In response to Mr. Blakeman regarding minutes of the Executive Risk Management Committee
(ERMC), as indicated on Page 5, Mr. Koenig stated that although the minutes are not automatically
forwarded to the Utility Committee, they are available upon request. Mr. Bonar requested that he
be provided copies of the minutes as well as any presentations. Mr. Koenig indicated that two (2)
separate types of meetings are held: 1) Management Committee meetings with North American
Energy Services (NAES), TEA, and City staff, and 2) ERMC meetings with City staff and TEA.
Mrs. Donna Mitchell, Controller/Treasurer, explained that the ERMC meetings are not public since
counterparties, hedges, etc., are discussed; however, the Management Committee meetings have
always been public. She stated that, although minutes are maintained for both committees, the
ERMC minutes are not public.
Referring to Page 13, Mr. Blakeman questioned if the limit of $60M was a total limit or applied to
each company. Mrs. Mitchell confirmed that the policy mandates that at no time will the City incur
a credit exposure with any one (1) counterparty greater than $60M; therefore, the City’s credit
Paj 3
UTILITY COMMITTEE MEETING OF AUGUST 13, 2012 PAGE 3
exposure could be much higher than $60M. However, she explained that the City diversifies the
portfolio and tries to obtain more counterparties. She assured members that the City’s limit was
never that high with any one (1) counterparty and noted that the City did not need that many hedges
for its load; therefore, it would never reach the maximum allowed. She stated that the City’s credit
exposure has never exceeded $10M to $15M for any counterparty. Mr. Blakeman suggested the
possibility of revising the limit to a total of $60M (or other amount recommended).
Mrs. Mitchell explained that this matter was negotiated individually by PACE with each
counterparty in accordance with the countparties’ requirements, so each counterparty may desire a
different threshold. She noted that they might not all accept a certain limit.
Responding to Mr. Snaman regarding the cost of producing solar energy, Mr. Koenig stated that
members had been provided a spreadsheet that reflected the cost of SunPark activity. Mr. Snaman
noted that the data reflected only what the City was charged. He explained that if the Sun Park was
being subsidized by the Federal Government and if that subsidy ends, the City would be exposed.
He requested that staff determine the City’s exposure. For clarification, Mr. Bonar indicated that
staff should provide members with the cost of producing one (1) kilowatt of solar energy versus the
amount being reimbursed from the Federal Government.
Mrs. Mitchell explained that the solar energy issues are separate from the Policy, since the Policy
regulates the City’s hedge program and solar is a separate Purchased Power Agreement (PPA).
Mr. Snaman moved to recommend approval of the Governing Policy for Energy Commodity Risk
Management. The motion failed for the lack of a second.
In response to Mrs. Williams’ concerns, Mr. Koenig indicated that no additional information had
been requested that was related to consideration of the Policy, explaining that solar energy was a
separate issue. He stated that, as previously explained by Mrs. Mitchell, there is a $60M risk per
party; however, since the City needs to purchase only $60M of power per year, the City’s risk is only
$60M annually.
Mrs. Mitchell stated that the exposure, by counterparty, is included in the Comprehensive Annual
Financial Report (CAFR) in the financial disclosure notes.
Mr. Bonar requested that staff respond to the questions and concerns of members during their next
meeting scheduled for August 27, 2012.
Review of Utility Related Capital Investment Plan (CIP) (Electric and Water/Wastewater)
Members reviewed a Project Tracking Report, as of June 30, 2012 (preliminary), for the Utility
(Electric and Water/Wastewater) Related Capital Investment Plan (CIP).
Responding to Mrs. Williams regarding the Troon Road Pump Station, Mr. Scott Koenig, City
Manager, stated that the project was complete, the grass had not grown due to dry weather and would
be re-seeded in September, and repaving of the roadway would be a part of a street program.
Paj 4
UTILITY COMMITTEE MEETING OF AUGUST 13, 2012 PAGE 4
In response to Mr. Anderson regarding the Lincoln Park Center, Mr. Koenig explained that the
project was funded through a planning and transportation grant from the Federal Government. The
preliminary engineering phases were complete and the project was now entering the final engineering
phase. A report was submitted to the Federal Highway Administration and the City was waiting for
a finding of no significant impact so that the City could move on to the final design phase and begin
purchasing rights-of-way.
No further action was taken by the Committee.
Update - National Pollution Discharge Elimination System (NPDES) Municipal Separate
Storm Sewer Systems (MS4) Permit
Mr. Scott Koenig, City Manager, stated that the Director of Planning and Community Development
indicated that an intern had been working for the City on the National Pollution Discharge
Elimination System (NPDES) Municipal Separate Storm Sewer Systems (MS4) Permit, to help keep
the City permit compliant. He stated that once the new library opens, a lecture and presentation are
planned for an informational meeting on the MS4 Permit. In addition, he stated that there were
several projects taking place in the watershed related to the MS4, including Delaware Department
of Natural Resources and Environmental Control (DNREC) projects and actions being taken by the
City to reach compliance. He noted that the City does not have an active permit and is waiting for
DNREC to respond to the City’s application for a new permit.
Update - Garrison Oak Technical Park Project
Mr. Scott Koenig, City Manager, stated that an air permit hearing was held regarding the Calpine
Project and the record has been closed. He advised members that Calpine received comments from
the Federal Government as well as LS Power. He noted that during the Council Meeting scheduled
for later in the evening, members would be considering revisions to the Engineering Services
Agreement to finish design of the sewer system and other land planning related items that were not
definitively known at the time the original contract was signed.
Mr. Koenig advised members that Calpine was moving ahead with their project and the City was
working on finalizing the City’s issues with the project in order to begin construction on or about
the same time the Calpine project moves forward.
In response to Mrs. Williams, Mr. Koenig stated that he had spoken with residents of Wild Meadows
recently and that the Garrison Oak Technical Park Project was not mentioned. He felt that the
majority of the residents were now relatively satisfied with the project and noted that Calpine had
made tremendous efforts to interact with the residents and consider their concerns with the project.
To his knowledge, Calpine had cleared all of their federal requirements and were working with the
Federal Emergency Regulatory Commission (FERC) on the gas line extension.
Mr. Koenig stated that, to the best of his recollection, there would be a certificate or document in
approximately October that would solidify what Calpine will need to do for the PJM, which would
be their final hurdle. During the air permit hearing, he stated that there was no public testimony
against the project; however, LS Power submitted a letter relaying concerns related to the
Paj 5
UTILITY COMMITTEE MEETING OF AUGUST 13, 2012 PAGE 5
construction of the power plant, dust, water vapors, “film” buildup on solar array, etc. He noted that
these concerns were being worked out between LS Power and Calpine.
Responding to Mr. Hutchison, Mr. Koenig stated that Calpine was hoping that all permitting would
be completed and planned to obtain a City building permit in January 2013. It was their desire to
begin testing in February or March 2015, with full operation to the PJM Grid in June 2015 since that
is the auction for which they have bid.
Update - Dover Sun Park
Mr. Scott Koenig, City Manager, noted that members received a summary of Dover Sun Park activity
for Fiscal Year 2012 and offered to respond to any questions. As indicated, he stated that the Sun
Park cost the City approximately $367,000 more than if the power were purchased off the grid.
Responding to Mrs. Williams, Mrs. Donna Mitchell, Controller/Treasurer, stated that $1.6M was
budgeted for purchased power in FY2012, which netted out to be a $366,850 cost for the City. She
stated that she would provide members with the budget details.
Mr. Blakeman requested that staff provide members with the cost per kilowatt or megawatt hour for
what the City is paying and also the costs for kilowatt or megawatt hour that is being bought off the
grid each month. Responding, Mrs. Mitchell indicated that she would forward the requested
information to members.
By unanimous consent, the meeting adjourned at 6:01 P.M.