UTILITY COMMITTEE
AGENDA
January 9, 2012 - 5:00 P.M. - Council Chambers - City Hall - City of Dover
Public comments are welcomed on any item and will be permitted at appropriate
times. When possible, please notify the City Clerk (736-7008 or e-mail at
CityClerk@dover.de.us) should you wish to be recognized.
AGENDA ADDITIONS/DELETIONS
1. Discussion - Dover East Pump Station
2. Review of Utility Related Capital Investment Plan (CIP) (Electric and Water/Wastewater)
3. Adjournment by 5:55 P.M.
/tm
S:\AGENDAS & MINUTES\Committee-Agendas\2012\01-09-2012 UTILITY.wpd
THE AGENDA ITEMS AS LISTED MAY NOT BE CONSIDERED IN SEQUENCE. THIS AGENDA IS SUBJECT TO CHANGE TO
INCLUDE THE ADDITION OR THE DELETION OF ITEMS, INCLUDING EXECUTIVE SESSIONS.
Paj 2
ACTION FORM
PROCEEDING: Utility Committee AGENDA ITEM: 1/9/2012
DEPARTMENT OF ORIGIN: Public Works DATE SUBMITTED: 12/30/2011
PREPARED BY: Sharon J. Duca, P.E., Interim Public Works Director for Scott D. Koenig, P.E., City Manager
SUBJECT: Disposition of City Owned Land and Sewer Infrastructure – Dover East Pump Station #12
REFERENCE: N/A
RELATED PROJECT: N/A
APPROVALS: City Manager, Controller/Treasurer
EXHIBITS: Exhibit A: Disposition of City Owned Land and Sewer Infrastructure – Dover East Pump Station #12 (Map)
Exhibit B: Kent County Sewage Disposal District No.1 (Map)
Exhibit C: Dover East Pump Station Abandonment & Sewer Line CIP (FY ’12 CIP)
Exhibit D: Procedure for Sale and Disposition of Real Property
EXPENDITURE REQUIRED: $ N/A AMOUNT BUDGETED: $ N/A
FUNDING SOURCE (Dept./Page in CIP & Budget): N/A
TIME TIMETABLE: Complete property and infrastructure transfer (Dover East Pump Station #12), if approved, upon Council
action. Associated electric and water accounts, as well as property maintenance, will be transferred immediately
thereafter.
RECOMMENDED ACTION: Authorize the City Manager to sell the property located within the Dover East Mobile
Home Community, in addition to the sanitary sewer pump station and associated infrastructure contained therein, to
Kent County for $1.00 under Exception C of the Land Disposal Policy.
BACKGROUND AND ANALYSIS
For over five (5) years, the Grandview, M&S and Oak Grove Mobile Home Communities have experienced various issues
related to the appropriate functioning of the private sewage facilities associated with these locations. These issues led
to environmental concerns as well as numerous investigations towards a means to preserve the low income housing
option in the area. In March 2011, Kent County proposed that the three (3) communities become an extension to Kent
County Sewage Disposal District No. 1, including the smaller Kent County parcels immediately adjacent to the
communities, as only M&S was located on a City of Dover parcel. The flow from these areas would discharge to the
City’s Dover East Pump Station #12. The flow would be deducted from the City’s monthly Kent County wastewater bill.
The City would also not lose any existing or future customers. This proposal was negotiated and accepted by the
previous administration which allowed the County to proceed with the District expansion and to apply for the
appropriate funding.
Since that time, the County has been informed that they will be unable to receive the necessary funding for the project
unless the scope changes. As such, they have requested to take ownership of Dover East Pump Station #12. They will
upgrade the station and reroute the flow directly to the Kent County Bypass Line. In turn, they would not be required to
pay City of Dover sanitary sewer impact fees for connection.
Over the past few years, the abandonment of the Dover East Pump Station and the installation of associated gravity line
has been in within the capital investment plan. This project was to be coordinated with the construction of a new pump
station in the Rojan Meadows subdivision. The project, at a cost of $253, 800, is shown on Exhibit B. Due to the delay in
the construction of this subdivision, and the existing station’s pressing need for an upgrade, the CIP project was to be
converted from an abandonment project to an upgrade project at similar cost. Should the County’s proposal be
accepted, this CIP can instead be removed in its entirety, saving the City $253,800. Ownership of the pump station by
the County will eliminate all immediate and future operational, maintenance and capital costs. A parcel of land also
exists in conjunction with the pump station.
Based upon the above facts, the City Manager’s Office has determined that the pump station and associated parcel of
land are excess in nature and that the disposal of same would be beneficial to the City of Dover and hereby requests
that the Dover City Council consider the disposal in the amount of $1.00.
Paj 3
Disposition of City Owned Land and Sewer Infrastructure
Dover East Pump Station #12
Exhibit A
R ou 18
ndt r
ee D 15
r
14
119
118
117
116 13
115
12
114
105
106 107 113 11
108
Cir 10
ot
Pil
92
109
9
93 91
110 8
112
90
94
111 89 7
95
Pilot Ci r 6
88
96
87
99 98 97 5 Ú
[
Dover
4
86
East Pump
Station #12
85
182 183 3
184 84 2
83
186 1
82 254
187
81
r 188 253
Co o pe 252
Ci r 80 251
C ir 190 Cameo Ct
191 79
p er
78
Coo 77
246 247
76
75 248 249 250
0 75 150 300 Feet
¯
Date Printed: January 4, 2012 Legend
File: m:\gis_data\projects/tech_mxds
\disposition_of_city_owned_land_
and_sewer_infrastructure_dover_east
[ Pump Station
Ú
_pump_station_12 City Owned Property
Department: Public WorksGIS
City of Dover, Delaware Dover Parcels
Paj 10
City of Dover
Capital Investment Plan
Project Tracking Report
November 30, 2011
Points to Remember -
* Original Project Budget = Original Total Project Budget initially included in approved annual budget.
* Latest Project Budget = Revised Total Project Budget included in most recent approved annual budget or one of the following:
bond resolution, revolving fund loan agreement, Council approved budget amendment, or City Manager approved amendment as per
the Budget Amendment Procedure.
* Current Fiscal Year - Revised Fiscal Year Budget = Current Year approved project budgets plus carry forward balances of unspent
budgets in the prior fiscal year. Project Carry Forward balances will be submitted to City Council for amendment in January 2010.
Can also be amended with City Manager approval per the Budget Amendment Procedure.
* Water Quality, Inflow/Infiltration, Distribution Upgrades and New Development projects are budgeted as a blanket project and once
individual projects are identified and estimated they are created using an allocation of the overall budgeted amount.
* Status and Comments provided by City Manager.
* For Finance purposes projects are considered completed when placed in service and all charges have been processed.
Community Water & Total
Current Year Budget Funding Sources General Transportation Wastewater Electric CIP
Budget Balance $ 78,000 $ 118,588 $ 430,591 $ 360,333 $ 987,512
Library Funding - FY11 Budget Balance 100,962 - - 87,045 188,007
Federal and/or State Grants 7,422,183 1,400,000 - - 8,822,183
Library Green Energy/Bridge Loan 2,700,000 - - - 2,700,000
Friends of the Library Donation 210,000 210,000
Kent County Library Contribution 1,000,000 1,000,000
Library Reserve 2,590,784 - - - 2,590,784
Construction Loan 274,961 - - - 274,961
Community Transportation Fund - FY11 Balances - 678,612 - - 678,612
Revolving Fund Loans - - 4,309,821 - 4,309,821
Transfer from Capital Reserves - - - 370,730 370,730
Impact Fees - - 867,032 - 867,032
Loan Proceeds - Streets & City Hall 1,970,000 - - - 1,970,000
Transfer Loan Proceeds to CT Fund - Streets - 875,000 - - 875,000
Transfer from Operating Funds 623,847 - 1,750,000 3,500,000 5,873,847
Interest Earned 10,900 2,800 - 38,400 52,100
Total Funding Sources (Unaudited) $ 16,981,637 $ 3,075,000 $ 7,357,444 $ 4,356,508 $ 31,770,589
Paj 11
City of Dover
General Fund - Major CIP Projects
November, 2011
Hide TOTAL PROJECT - PAST, CURRENT & FUTURE BUDGETS CURRENT FISCAL YEAR
Original Latest Project Project Current Revised Fiscal
Project Project Project To Date Budget % Budget Fiscal Yr. Fiscal Yr. YTD % Budget
Code Type Description Budget Budget Expenses Balance Spent Budget Budget Expenses Spent Status Comments
1 FY2009
Bid Pack A - Done.
2 LB0901 M/G New Library Project $ 18,200,000 $ 20,469,080 $ 6,208,327 $ 14,260,753 30.3% $ 11,195,009 $ 14,298,890 $ 2,038,137 14.3% Started Bid Pack B - Construction Started.
3 Totals - FY09 $ 18,200,000 $ 20,469,080 $ 6,208,327 $ 14,260,753 30.3% $ 11,195,009 $ 14,298,890 $ 2,038,137 14.3%
4
5 FY2012
6 --- Ann FD Truck Payment $ 244,820 $ 244,820 $ 216,794 $ 28,026 88.6% $ 244,820 $ 244,820 $ 216,794 88.6%
7 --- Vehicles & Equipment 377,927 377,927 - 377,927 0.0% 377,927 377,927 - 0.0%
Roof Replacement @
8 PR1201 Dover Park 30,000 30,000 - 30,000 0.0% 30,000 30,000 - 0.0%
9 CT Fund B/L Streets & Alleys Program 1,000,000 1,750,000 - 1,750,000 0.0% 1,000,000 1,750,000 - 0.0%
10 ST1202 Concrete Program 30,000 30,000 - 30,000 0.0% 30,000 30,000 - 0.0%
Streets Dump Truck
11 ST1203 Refurbishment 30,000 30,000 - 30,000 0.0% 30,000 30,000 - 0.0%
12 City Hall Sprinkler System - - - - 0.0% - 220,000 - 0.0%
13 Totals - FY12 $ 1,712,747 $ 2,462,747 $ 216,794 $ 2,245,953 8.8% $ 1,712,747 $ 2,682,747 $ 216,794 8.1%
14
15 Grand Totals $ 19,912,747 $ 22,931,827 $ 6,425,121 $ 16,506,706 28.0% $ 12,907,756 $ 16,981,637 $ 2,254,931 13.3%
Legend
M = Multi-year project - a project with a specific schedule to occur over multiple years.
R = Recurring project - a project that begins and ends each fiscal year and is rebudgeted to start over each fiscal year.
G = Grant funded project
B/L = To be financed through bonds or commercial loan; Projects will be completed through CT Fund, therefore the loan proceeds will be transferred from Capital Fund into the Community Transportation Fund
Paj 12
City of Dover
Community Transportation & General Fund Street Funds - Major CIP Projects
November, 2011
Hide TOTAL PROJECT - PAST, CURRENT & FUTURE BUDGETS CURRENT FISCAL YEAR
Original Latest Project Project Current Revised Fiscal
Project Project Project To Date Budget % Budget Fiscal Yr. Fiscal Yr. YTD % Budget
Code Type Description Budget Budget Expenses Balance Spent Budget Budget Expenses Spent Status Comments
1 FY 2007
2 CT0708 M E. Water Street Brick $ 65,000 $ 65,000 $ - $ 65,000 0.0% $ - $ 65,000 $ - 0.0% Specialty contract needed.
3 Totals $ 65,000 $ 65,000 $ - $ 65,000 0.0% $ - $ 65,000 $ - 0.0%
4
5 FY 2009
6 CT0977 M Schutte Parking Lot $ 21,950 $ 21,950 $ - $ 21,950 0.0% $ - $ 21,950 $ - 0.0% Deferred
7 CT1165 M Rt 13,N. State -Kings Hwy 591,662 591,662 - 591,662 0.0% - 591,662 - 0.0%
8 Totals $ 613,612 $ 613,612 $ - $ 21,950 0.0% $ - $ 613,612 $ - 0.0%
9
10 FY2012
11 CT M Street Projects - State Funds $ 950,000 $ 800,000 $ - $ 800,000 0.0% $ 950,000 $ 121,388 $ - 0.0%
12 Various B/L Street Projects - General Fund 350,000 1,750,000 15,300 1,734,700 0.9% 350,000 875,000 15,300
13 CT1201 M North Street Roundabout - 500,000 - 500,000 0.0% - 500,000 - 0.0%
14 TE1201 M Lincoln Park Center 900,000 900,000 1,854 898,146 0.0% 900,000 900,000 1,854 0.2%
15 Totals $ 2,200,000 $ 3,950,000 $ 17,154 $ 3,932,846 0.4% $ 2,200,000 $ 2,396,388 $ 17,154 0.8%
16
17 Grand Totals $ 2,878,612 $ 4,628,612 $ 17,154 $ 4,019,796 0.4% $ 2,200,000 $ 3,075,000 $ 17,154 0.8%
Legend
M = Multi-year project - a project with a specific schedule to occur over multiple years.
R = Recurring project - a project that begins and ends each fiscal year and is rebudgeted to start over each fiscal year.
C = Project funded by combination of CT Funds and General Fund
B/L = To be financed through bonds or commercial loan; Projects will be completed through CT Fund, therefore the loan proceeds will be transferred from Capital Fund into the Community Transportation Fund;
Paj 13
City of Dover
Water/Wastewater Improvement & Extension Fund - Major CIP Projects
November, 2011
TOTAL PROJECT - PAST, CURRENT & FUTURE BUDGETS CURRENT FISCAL YEAR
Original Latest Project Project % Approved Revised Fiscal %
Project Project Project To Date Budget Budget Fiscal Yr. Fiscal Yr. YTD Budget
Code Type Description Budget Budget Expenses Balance Spent Budget Budget Expenses Spent Status Comments
1 FY 2008
Land site selected, starting
2 WD0804 M
1.0 MG Elevated Water Storage $ 4,196,600 $ 2,590,000 $ 29,099 $ 2,560,901 1.1% $ - $ 178,916 $ 8,015 4.5% Started negotiations
3 WD0805 M
Piney Point Well 398,800 665,000 69,316 595,684 10.4% - 147,319 1,634 1.1% Started DNREC permitting ongoing
US 13 East Sanitary Sewer
4 WW0810 M/SL Interceptor 2,376,800 3,022,562 3,228,383 (205,821) 106.8% - 295,722 282,783 95.6% Complete Complete
5 Totals - FY08 $ 6,972,200 $ 6,277,562 $ 3,326,798 $ 2,950,764 53.0% $ - $ 621,957 $ 292,432 47.0%
6
7 FY2009
8 WQ0905 M/SL Bayard Avenue $ 590,910 $ 490,910 $ 470,015 $ 20,895 95.7% $ - $ 239,121 $ 183,225 76.6% Started Installation is 85% complete
9 WQ0907 M/SL Route 13 Water Main 1,058,700 2,282,682 1,876,157 406,525 82.2% - 1,869,872 1,463,346 78.3% Started Installation is 60% complete
10 Totals - FY09 $ 1,649,610 $ 2,773,592 $ 2,346,171 $ 427,421 84.6% $ - $ 2,108,993 $ 1,646,571 78.1%
11
12 FY2010
Work is complete for phase 1, close-
13 WW1001 M/SL Inflow/Infiltration Removal $ 1,800,000 $ 2,122,536 $ 1,585,638 $ 536,898 74.7% $ 1,800,000 $ 766,201 $ 228,082 29.8% Started out documents in progress
14 WW1007 M/SL Fox Hall Pump Station 427,900 392,044 50,491 341,553 12.9% - 360,687 278 0.1% Started Bid Awarded
15 WW1008 M/SL Heatherfield F/M Rerouting 220,400 324,916 48,973 275,943 15.1% - 237,506 278 0.1% Started Bid Awarded
Reviewing design and easement
16 WW1010 I Tar Ditch Interceptor Upgrade 518,230 518,230 28,014 490,216 5.4% - 495,359 5,143 1.0% Started issue.
17 Totals - FY10 $ 2,966,530 $ 3,357,726 $ 1,713,116 $ 1,644,610 51.0% $ 1,800,000 $ 1,859,753 $ 233,781 12.6%
18
19 FY2011
20 WQ1103 WQI - Ross Street - 71,840 - 71,840 0.0% 71,840 36,840 - 0.0% Preliminary design complete
21 WW1101 M/SL Inflow/Infiltration Removal 500,000 500,000 123,712 376,288 24.7% - 457,601 81,312 17.8% Started 30% complete
22 WW1104 SL Lepore Road P/S Replacement 52,000 402,000 66,854 335,146 16.6% 350,000 350,000 11,318 3.2% Complete Bidding in November
23 Totals - FY11 $ 552,000 $ 973,840 $ 190,566 $ 783,274 19.6% $ 421,840 $ 844,441 $ 92,630 11.0%
24
25 FY2012
26 --- Vehicles & Equipment $ 115,000 $ 115,000 $ 29,985 $ 85,015 26.1% $ 115,000 $ 115,000 $ 29,985 26.1% Ordered through State Contract
27 WD1201 Pay-As-You-Go Water Station 30,240 30,240 - 30,240 0.0% 30,240 30,240 - 0.0%
28 WD1202 R Misc. Distribution Upgrades 60,000 60,000 5,706 54,294 9.5% 60,000 60,000 5,706 9.5% Ongoing
29 WD1203 R Wellhead Redevelopment Program 65,000 65,000 42,821 22,179 65.9% 65,000 65,000 42,821 65.9% Well #1 under rehabilitation
30 WD1204 R Emergency Generators 80,000 80,000 - 80,000 0.0% 80,000 - - 0.0% Grant dependent
Design complete, late spring const.
31 WQ1201 WQI - Wesley Campus 51,200 51,200 - 51,200 0.0% 51,200 51,200 - 0.0%
32 WQ1202 WQI - New Street 97,120 97,120 4,650.00 92,470 4.8% 97,120 97,120 4,650 4.8% Design started, early spring const.
Design complete, November const.
33 WQ1203 WQI - Silver Lake 279,840 279,840 31,826.34 248,014 11.4% 279,840 279,840 31,826 11.4%
34 WW1201 M/SL Inflow/Infiltration Removal 1,000,000 1,000,000 8,540 991,460 0.9% 1,000,000 1,000,000 8,540 0.9% Design started, early spring const.
35 WW1202 R SCADA Equipment Replacement 84,900 84,900 61,696 23,204 72.7% 84,900 84,900 61,696 72.7% Materials ordered, spring const.
36 WW1203 R Misc. Sewer System Improve 37,000 37,000 9,935 27,065 26.9% 37,000 37,000 9,935 26.9% Ongoing
Design started - actually Baltray PS
37 WW1204 M Wilmington College Pump Station 25,000 25,000 - 25,000 0.0% 25,000 25,000 - 0.0%
Design started
38 WW1205 M Dover Brook Gardens P/S Replace 15,000 15,000 - 15,000 0.0% 15,000 15,000 - 0.0%
Design started
39 WW1206 M Brandywine Pump Station Replace 52,000 52,000 1,432.13 50,568 2.8% 52,000 52,000 1,432 2.8%
McKee Rd Pump Station Design started
40 WW1207 M Communator Replacement 10,000 10,000 - 10,000 0.0% 10,000 10,000 - 0.0%
41 $ 2,002,300 $ 2,002,300 $ 196,591.24 $ 1,805,709 0.0% $ 2,002,300 $ 1,922,300 $ 196,591 10.2%
42
43 Grand Totals $ 14,142,640 $ 15,385,020 $ 7,773,242 $ 7,611,778 50.5% $ 4,224,140 $ 7,357,444 $ 2,462,006 33.5%
Legend
M = Multi-year project - a project with a specific schedule to occur over multiple years.
R = Recurring project - a project that begins and ends each fiscal year and is rebudgeted to start over each fiscal year.
SL = State Loan Project - construction phase is financed
I = Impact Fee (partially) financed project
Paj 14
City of Dover
Electric Improvement & Extension Fund - Major CIP Projects
November, 2011
TOTAL PROJECT - PAST, CURRENT & FUTURE BUDGETS CURRENT FISCAL YEAR
Original Latest Project Project % Current Revised Fiscal %
Project Project Project To Date Budget Budget Fiscal Yr. Fiscal Yr. YTD Budget
Code Type Description Budget Budget Expenses Balance Spent Budget Budget Expenses Spent Status Comments
1 FY2011
Work will be completed
2 EG1102 M Units 1 & 2 Cooling Tower 372,400 199,140 134,538 64,602 67.6% 25,410 25,410 400 1.6% during the fall outage
work will be completed during
3 EG1107 M Units 1 & 2 Life Extension 802,000 409,000 267,775 141,225 65.5% 184,000 196,331 55,106 28.1% the fall outage
Will be competed by Feb.
4 EG1112 M Unit 3 Heat Expansion Joint - 150,000 141,168 8,832 94.1% 70,000 82,807 73,975 89.3% Started 2012
Work will be completed
5 EG1113 Units 1 & 2 Control Modifications - 150,000 131,345 18,655 87.6% - 25,700 7,044 27.4% Started during the fall outage
Work will be completed
6 EG1114 Unit 3 Gas Line Modification - 60,000 30,737 29,263 51.2% - 36,207 6,943 19.2% Started during the fall outage
7 $ 1,174,400 $ 968,140 $ 705,562 $ 262,578 72.9% $ 279,410 $ 366,455 $ 143,469 39.2%
8
9 FY2012
All vehicles on order from
10 --- Vehicles & Equipment $ 168,828 $ 168,828 $ 23,003 $ 145,825 13.6% $ 168,828 $ 144,328 $ 23,003 15.9% State Contract
11 EE1201 Substation PT & CT Replacement 267,715 267,715 119,122 148,593 44.5% 267,715 267,715 119,122 44.5% Materials ordered
12 EE1202 R Lighting Project & Rehabilitation 50,000 50,000 49,832 168 99.7% 50,000 50,000 49,832 99.7% Materials ordered
13 EE1203 R Equipment Replacement 40,000 40,000 10,525 29,475 26.3% 40,000 40,000 10,525 26.3% Equipment ordered
14 EE1204 Generator Replacement 50,000 50,000 30,961 19,039 61.9% 50,000 50,000 30,961 61.9% 75% complete
15 EE1205 M Frazier Substation Upgrade 765,247 155,000 72,981 82,019 47.1% 155,000 155,000 72,981 47.1% Materials ordered
16 EE1206 R Disb. Feeder Replacement 377,510 377,510 236,642 140,868 62.7% 377,510 377,510 236,642 62.7% On-going
17 EE1207 R Disb. Capacitors & Controls 100,000 100,000 26,494 73,506 26.5% 100,000 100,000 26,494 26.5% Materials ordered
18 EE1208 R Transmission Line Maintenance 75,000 75,000 - 75,000 0.0% 75,000 75,000 - 0.0% Materials ordered
Scada Master Hardware
19 EE1209 Replacement 75,000 75,000 - 75,000 0.0% 75,000 75,000 - 0.0% Materials ordered
20 EE1210 Substation Battery - 24,500 15,251 9,249 62.2% 24,500 24,500 15,251 62.2%
21 EE1212 R UG Transformers 70,536 70,536 42,053 28,483 59.6% 70,536 70,536 42,053 59.6% On-going
22 EE1212 R UG Conductors 479,464 479,464 167,208 312,256 34.9% 479,464 479,464 167,208 34.9% On-going
23 EE1212 R Meters 50,000 50,000 17,652 32,348 35.3% 50,000 50,000 17,652 35.3% On-going
Developing contract
24 EG1201 Unit 3 Boiler Air Heater 440,000 440,000 - 440,000 0.0% 440,000 440,000 - 0.0% documents
Developing contract
25 EG1202 M Unit 3 Boiler Systems 390,000 130,000 - 130,000 0.0% 130,000 130,000 - 0.0% documents
Unit 3 FD & ID Fan Control Damper Developing contract
26 EG1203 Upgrade 92,000 92,000 1,393 90,607 1.5% 92,000 92,000 1,392.70 1.5% documents
Unit 3 DCS Computers & Software Developing contract
27 EG1204 Upgrades 85,000 85,000 - 85,000 0.0% 85,000 85,000 - 0.0% documents
28 EG1205 R Misc. Equipment Replacement 70,000 70,000 21,280 48,720 30.4% 70,000 70,000 21,280.01 30.4% On-going
Demineralizer Control Replace @ Developing contract
29 EG1206 McKee Run 65,000 65,000 - 65,000 0.0% 65,000 65,000 - 0.0% documents
Unit 11 Component Replacement @ Developing contract
30 EG1207 M Van Sant 50,000 50,000 17,180 32,820 34.4% 50,000 50,000 17,179.58 34.4% documents
Switchyard Blast Walls @ McKee Developing contract
31 EG1208 Run 50,000 50,000 5,328 44,672 10.7% 50,000 50,000 5,327.76 10.7% documents
Developing contract
32 EG1209 M Building Preservation @ McKee Run 38,000 38,000 5,650 32,350 14.9% 38,000 38,000 5,650.00 14.9% documents
Unit 3 Cooling Water Line Life Developing contract
33 EG1210 M Extension 25,000 25,000 - 25,000 0.0% 25,000 25,000 - 0.0% documents
Developing contract
34 EG1211 M Unit 3 Stack Repairs 25,000 25,000 - 25,000 0.0% 25,000 25,000 - 0.0% documents
35 EG1212 M Unit 3 Turbine Inspection 1,021,000 348,000 - 348,000 0.0% 348,000 348,000 - 0.0% Deferred Construction in FY12.
36 EG1213 M Unit 3 Aux System Components 542,000 113,000 - 113,000 0.0% 113,000 113,000 - 0.0% Deferred Deferred to FY12.
37 EU1201 R Distribution Upgrades 500,000 500,000 210,677 289,323 42.1% 500,000 500,000 210,677 42.1% On-going
38 $ 5,962,300 $ 4,014,553 $ 1,073,231 $ 2,941,322 0.0% $ 4,014,553 $ 3,990,053 $ 1,073,231 26.9%
39
40 Grand Totals $ 7,136,700 $ 4,982,693 $ 1,778,793 $ 3,203,900 31.6% $ 4,293,963 $ 4,356,508 $ 1,216,699 27.9%
Legend
M = Multi-year project - a project with a specific schedule to occur over multiple years.
R = Recurring project - a project that begins and ends each fiscal year and is rebudgeted to start over each fiscal year.
B = Bonded Project
S = State fully or partially reimbursed project