Anexo

Utility Committee. 27 de octubre de 2014.

Abrir el PDF

Este texto se extrajo de el PDF de forma automática y puede contener errores. El PDF es el registro oficial, así que consúltelo antes de confiar en esto.

1 página tiene poco o ningún texto legible aquí, a menudo por ser escaneos o dibujos. Para verla, consulte el PDF.

Página 1

UTILITY COMMITTEE AGENDA OCTOBER 27, 2014 - 5:15 P.M. CITY HALL COUNCIL CHAMBERS 15 LOOCKERMAN PLAZA DOVER, DELAWARE Public comments are welcomed on any item and will be permitted at appropriate times. When possible, please notify the City Clerk (736-7008 or e-mail at CityClerk@dover.de.us) should you wish to be recognized. AGENDA ADDITIONS/DELETIONS 1. DISPOSITION OF PUBLIC INFRASTRUCTURE TO KENT COUNTY - CENTRAL TRANSMISSION BYPASS NORTH (Staff recommends disposal of the referenced public infrastructure, and all easements necessary for the perpetual maintenance thereof, associated with the County's Central Transmission Bypass North project, to Kent County. The estimated replacement value of the referenced infrastructure is $770,000) 2. DEDICATION OF PRIVATE WALKWAY AS A PUBLIC WALKWAY - VILLAGE OF WESTOVER - MIFFLIN ROAD TO TRAFALGAR DRIVE (Staff recommends acceptance of the dedication of the existing concrete walkway and authorizing the City Manager to execute any documents necessary to ensure public funds can be used for future maintenance on the dedicated walkway) 3. ADJOURNMENT BY 5:55 P.M. /tm S:\AGENDAS-MINUTES-PACKETS-PRESENTATIONS-ATT&EXH\Committee-Agendas\2014\10-27-2014 UTILITY.wpd THE AGENDA ITEMS AS LISTED MAY NOT BE CONSIDERED IN SEQUENCE. THIS AGENDA IS SUBJECT TO CHANGE TO INCLUDE THE ADDITION OR THE DELETION OF ITEMS, INCLUDING EXECUTIVE SESSIONS.

Página 2

ACTION FORM PROCEEDING: Utility Committee AGENDA ITEM: DEPARTMENT OF ORIGIN: Public Works DATE SUBMITTED: 10/17/14 PREPARED BY: Sharon J. Duca, P.E., Public Works Director / City Engineer SUBJECT: Disposition of Public Infrastructure to Kent County – Central Transmission Bypass North REFERENCE: N/A RELATED PROJECT: N/A APPROVALS: City Manager EXHIBITS: Attachment A – List of Public Infrastructure to be disposed of by the City of Dover Attachment B – Map EXPENDITURE REQUIRED: $ N/A AMOUNT BUDGETED: $ N/A FUNDING SOURCE (Dept./Page in CIP & Budget): N/A TIME TABLE: All referenced public infrastructure will be disposed of by the City of Dover upon action by City Council and become the responsibility of Kent County. RECOMMENDED ACTION: Disposal of the referenced public infrastructure, and all easements necessary for the perpetual maintenance thereof, associated with the County’s Central Transmission Bypass North project, to Kent County. The estimated replacement value of the referenced infrastructure is $770,000. BACKGROUND AND ANALYSIS In accordance with information received from the Kent County Department of Public Works, a failure in the twenty-four inch (24”) concrete sewer force main (Kent County Central Transmission Main) surfaced causing a sanitary sewer overflow in the center of Route 13 in front of C.F. Schwartz on July 16, 2014. The root cause was corrosion of the pipe crown due to high hydrogen sulfide concentrations in the wastewater. Due to the thinned pipe wall, a slight pressure increase realized during a routine re-routing procedure resulted in triggering the failure. This occurred on one (1) of the few remaining sections of the Kent County transmission system, from Smyrna to the wastewater treatment plant in Frederica, that does not have a redundant pipeline or bypass capability. The above referenced failure is currently only temporarily repaired. In order to complete a permanent repair the flow must be rerouted to allow for the installation of a pipe liner. As a result there is an urgent need for a functioning bypass system. The proposed bypass is to be developed as depicted on the attached map. The project has been authorized by Levy Court and is currently being fast tracked due to the related urgency. As part of the project, portions of the City’s existing infrastructure, and all associated easements, must be disposed of by the City with ownership transferred to the County. The infrastructure to be transferred is provided in Attachment A. The County will assume ownership and maintenance responsibility of the new bypass force main from County Pump Station No. 2 to Crawford Carroll Avenue. Due to the above, the City of Dover Department of Public Works requests that the public infrastructure improvements referenced in Attachment A, and all associated easements, be disposed of with ownership and maintenance responsibilities transferred to Kent County.

Página 3

DISPOSITION OF PUBLIC INFRASTRUCTURE CENTRAL TRANSMISSION BYPASS - NORTH ATTACHMENT A The following is a list of all public infrastructure improvements which are to be disposed of by the City of Dover: Sewer Utility Infrastructure:  16” Ductile Iron Force Main and appurtenances and easements - 2,260 l.f.  from Mudstone Branch project, located within easements along Dennys Road from KC PS #2 to Dover Products Site  16” Ductile Iron Force Main and appurtenances - 915 l.f.  from Route 13 Interceptor project  8” Force Main (various materials) and appurtenances - 2,175 l.f.  Originally from Kent County’s Sub-regional Sewer System project for the Delaware State College Area  Located within easements on the lands of Sam’s Club and the Delaware Civic Center Corp/Frazier Pit  Force main will be abandoned with the construction of the new sixteen-inch (16”) bypass force main The estimated replacement value of the above referenced infrastructure is $770,000.

Página 4

RD H O UG OR ARB SC 555 Bay Road (302) 744-2430 Dover, DE 19901 RD Y S ) " ENN D KC PS #2 W . 13 " ) " Kent County Central Transmission Bypass - North EX 16" MCKEE PS FM TO BE " ) TRANSFERRED TO THE COUNTY (APPROX 2200') RD Kent County Public Works Department EX FORCEMAIN Dover Area - August 21, 2014 TO BE ABANDONED UG H BOR O EX KC 24" CONCRETE SCA FORCEMAIN R Engineering Division N D U PO N T H W CONNECTION Y TO EX FORCEMAIN REPAIR SITE COD - DELTECH " ) PS " ) Feet 1,000 EX COD - MCKEE PS LN FORCEMAIN ST IC RU W 500 PROPOSED FORCEMAIN CONNECTION BY-PASS TO EX FORCEMAIN EX 16" RUSTIC LANE FORCEMAIN TO BE TRANSFERRED TO THE COUNTY 0 (APPROX 900') COD GRAVITY LINE TO ROUTE 13 PS EX COD - F DELSTATE PS FORCEMAIN

Página 5

ACTION FORM PROCEEDING: Utility Committee DEPARTMENT OF ORIGIN: City Manager’s Office DATE SUBMITTED: October 22, 2014 PREPARED BY: Scott D. Koenig, P.E., City Manager SUBJECT: Dedication of Private Walkway as a Public Walkway – Village of Westover – Mifflin Road to Trafalgar Drive REFERENCE: N/A RELATED PROJECT: N/A REVIEWED BY: Scott D. Koenig, P.E., City Manager EXHIBITS: Attachment A – Letter from Representative Scott; Attachment B – Map of the walkway area. EXPENDITURE REQUIRED: $0 AMOUNT BUDGETED: $0 FUNDING SOURCE (Dept./Page in CIP & Budget): N/A TIME TIMETABLE: Upon Council Approval. RECOMMENDED ACTION: Accept the dedication of the existing concrete walkway and authorize the City Manager to execute any documents necessary to ensure public funds can be used for future maintenance on the dedicated walkway. BACKGROUND AND ANALYSIS As part of the approved subdivision plan for the Village of Westover, the City of Dover required the construction of a private sidewalk connection from Trafalgar Drive to Mifflin Road to guarantee the pedestrian interconnection of the existing developments in this area and the newly constructed Village of Westover Subdivision. Prior to the construction of the new Dover High School, this sidewalk connection primarily served as a connection for the residents of the Village of Westover and the Village of Cannon Mill to access local businesses in the vicinity of Route 8. The Village of Westover Homeowner’s Association has inquired for a number of years about dedicating this walkway for public maintenance; however, staff had previously not favored such a dedication. With the construction of the new Dover High School, the pedestrian patterns have changed. This walkway now represents a safe path to the new Dover High School and related facilities so the “public” interest with respect to this walkway has changed. Attached (see Attachment A) is a written request from Representative Darryl Scott requesting consideration of the public dedication of this walkway. Each of the points outlined in Representative Scott’s correspondence support the City Manager’s reconsideration of this request. Based upon the current and projected use of the walkway, the City Manager has no objections to the dedication of the walkway as public walkway. The estimated maintenance cost of the walkway is $1,000 per year which would include costs associated with winter maintenance. The existing private walkway is approximately 770 linear feet long and six (6’) feet in width. Therefore, the estimate value of the dedication is $23,100.00 (770 l.f. x 6 ft. x $5.00 per square feet). Attachment B is a map of the proposed dedication.

Página 7

ATTACHMENT B Sidewalk to be Dedicated From Trafalgar Drive to Mifflin Road ffl in Mi Rd Tr af alg a rD r 0 45 90 180 Feet Legend ¯ Date Printed; October 21, 2014 File: m:\gis_data\projects\tech_mxds \sidewalk_trafalgar_to_mifflin Dover Parcels Department: Public Works GIS City of Dover, Delaware Sidewalk to be Dedicated