Ale nan kontni prensipal la
AskDover

Òdonans ak rezolisyon

Òdonans #2026-14

Proposed Ordinance #2026-14 - Data Center Moratorium

Tit yo ak tèks ki soti nan ajanda yo ak pwosèvèbal yo parèt an anglè, jan Vil la te pibliye yo.

Rezime sa a parèt an anglè. Yo te konpare chak fraz ak tèks anglè òdonans lan oswa rezolisyon an, se poutèt sa li pa tradui.

An mo senp

Se IA ki ekri rezime a apati tèks òdonans lan. Nou te konpare l ak tèks la nan dat 10 novanm 2026.

Sa li ta chanje

  • This ordinance stops the City from accepting or approving applications for new Large Energy Use Facilities and data centers.
  • It defines a Large Energy Use Facility by set levels of monthly maximum demand in megawatts.
  • Applications that were complete before the effective date are put on hold unless the applicant chooses to withdraw.
  • The moratorium lasts eighteen (18) months from the effective date unless Council repeals it sooner.

Ki moun li konsène

It applies to new Large Energy Use Facilities and data centers as defined in Section 2.

Nan ki etap li ye

Nan ajanda a, 12 oktòb 2026.

Se tèks ofisyèl la ki konte. Li tèks òdonans lan (paj 142). Fichye Vil la (fichye PDF)

Gade tèks ki dèyè chak fraz
  • This ordinance stops the City from accepting or approving applications for new Large Energy Use Facilities and data centers.

    "The purpose of this Ordinance is to temporarily suspend the acceptance and approval of applications for new Large Energy Use Facilities" Paj 142
    "The City shall not:" Paj 142
  • It defines a Large Energy Use Facility by set levels of monthly maximum demand in megawatts.

    "Large Energy Use Facility means a facility that does any of the following:" Paj 142
    "Uses or is projected to use a monthly maximum demand of 75 megawatts or greater at a load factor of 85% or greater." Paj 142
    "Uses a monthly maximum instantaneous demand of 100 megawatts or greater." Paj 142
  • Applications that were complete before the effective date are put on hold unless the applicant chooses to withdraw.

    "Applications deemed complete before the effective date shall be stayed unless the applicant elects to withdraw." Paj 143
  • The moratorium lasts eighteen (18) months from the effective date unless Council repeals it sooner.

    "This moratorium shall remain in effect for eighteen (18) months from the effective date unless sooner repealed by Council." Paj 144
  • It applies to new Large Energy Use Facilities and data centers as defined in Section 2.

    "for any new Large Energy Use Facility or Data Center as defined in Section 2." Paj 143

Tout etap yo

  1. 12 oktòb 2026: Nan ajanda a

    Regular City Council Meeting

    Proposed Ordinance #2026-14 - Data Center Moratorium

    Ajanda reyinyon an (fichye PDF)

Chak etap soti nan yon pwen nan ajanda a oswa nan yon mosyon nan pwosèvèbal la. Nimewo òdonans lan oswa rezolisyon an parèt tou nan ajanda oswa pwosèvèbal reyinyon sa a, epi gen yon lyen pou li. Nou te li pwen ajanda yo ak mosyon yo nan dokiman Vil la ak entèlijans atifisyèl, kidonk tcheke dokiman ki nan lyen an pou nenpòt bagay ki enpòtan. Pou kounye a, nou kouvri reyinyon depi novanm 2025.