Proposed Ordinance #2026-14 - Data Center Moratorium

Los títulos y el texto citado de las agendas y las actas se muestran en inglés, tal como los publicó la Ciudad.

Este resumen se muestra en inglés. Cada oración se comparó con el texto en inglés de la ordenanza o resolución, por eso no está traducido.

En palabras sencillas

Resumen escrito por IA a partir del texto de la ordenanza. Se comparó con el texto el 10 de noviembre de 2026.

Qué cambiaría

  • This ordinance stops the City from accepting or approving applications for new Large Energy Use Facilities and data centers.
  • It defines a Large Energy Use Facility by set levels of monthly maximum demand in megawatts.
  • Applications that were complete before the effective date are put on hold unless the applicant chooses to withdraw.
  • The moratorium lasts eighteen (18) months from the effective date unless Council repeals it sooner.

A quién afecta

It applies to new Large Energy Use Facilities and data centers as defined in Section 2.

En qué estado está

En la agenda, 12 de octubre de 2026.

El texto oficial es el que vale. Leer el texto de la ordenanza (página 142). El archivo de la Ciudad (archivo PDF)

Ver el texto que respalda cada oración
  • This ordinance stops the City from accepting or approving applications for new Large Energy Use Facilities and data centers.

    "The purpose of this Ordinance is to temporarily suspend the acceptance and approval of applications for new Large Energy Use Facilities" Página 142
    "The City shall not:" Página 142
  • It defines a Large Energy Use Facility by set levels of monthly maximum demand in megawatts.

    "Large Energy Use Facility means a facility that does any of the following:" Página 142
    "Uses or is projected to use a monthly maximum demand of 75 megawatts or greater at a load factor of 85% or greater." Página 142
    "Uses a monthly maximum instantaneous demand of 100 megawatts or greater." Página 142
  • Applications that were complete before the effective date are put on hold unless the applicant chooses to withdraw.

    "Applications deemed complete before the effective date shall be stayed unless the applicant elects to withdraw." Página 143
  • The moratorium lasts eighteen (18) months from the effective date unless Council repeals it sooner.

    "This moratorium shall remain in effect for eighteen (18) months from the effective date unless sooner repealed by Council." Página 144
  • It applies to new Large Energy Use Facilities and data centers as defined in Section 2.

    "for any new Large Energy Use Facility or Data Center as defined in Section 2." Página 143

Todos los pasos

  1. 12 de octubre de 2026: En la agenda

    Regular City Council Meeting

    Proposed Ordinance #2026-14 - Data Center Moratorium

    La agenda de la reunión (archivo PDF)

Cada paso viene de un punto de la agenda o de una moción en el acta, y el número de la ordenanza o resolución también aparece en la agenda o en el acta de esa reunión, que está enlazada. Los puntos de la agenda y las mociones se leyeron de los documentos de la Ciudad con inteligencia artificial, así que revise el documento enlazado para cualquier cosa importante. Por ahora se cubren las reuniones desde noviembre de 2025 en adelante.