UTILITY COMMITTEE
The Utility Committee Meeting was held on July 27, 2015 at 5:00 p.m. with Chairman Hutchison
presiding. Members present were Mr. Cole, Mr. Neil, Mr. Blakeman, and Ms. Stewart. Members
of Council present were Mr. Hosfelt (departed at 5:11 p.m.) and Mr. Slavin (departed at 5:10 p.m.).
Mayor Christiansen was also present.
AGENDA ADDITIONS/DELETIONS
Mr. Blakeman moved for approval of the agenda, seconded by Mr. Neil and unanimously carried.
Contract Award - North American Energy Services (NAES) Amended and Restated Operating
Agreement
Due to time constraints, this item was placed on the Council agenda for consideration during their
meeting scheduled for later in the evening.
Mr. Scott Koenig, City Manager, informed members that the City's power supply attorney,
Mr. Kirk Betts, Betts & Holt, LLP; Mr. Harry Maloney, Electric Director; and Mrs. Donna Mitchell,
Controller/Treasurer, worked to negotiate an agreement with North American Energy
Services (NAES) on behalf of the City of Dover to ensure that the City is getting the most out of the
existing power plant with a third-party vendor operating it.
Members reviewed the Amended and Restated Operation and Maintenance Agreement dated
July 1, 2015 between the City of Dover and North American Energy Services (NAES). Mr. Betts
provided members with a revised Page B-1, Appendix B - Performance Adjustment Provisions
(Attachment #1), explaining that the Environmental factor was previously omitted. He advised that
this revision did not affect the weight of the other factors in the performance adjustment section.
Mr. Betts stated that the section for environmental protection was a major issue for plant
performance and this correction clarifies that NAES is penalized for each violation that occurs. He
explained that, essentially, 25% of the 20% would be taken away each time there is a violation until
four (4) violations occur, and they would be completely wiped out at 20%, which is about $100,000
on average over the five (5) year term of the contract.
Mr. Betts informed members that changes were occurring in the PJM environment and the entire
energy market. He advised that PJM had changed the way power plants are treated for capacity
purposes. Mr. Betts explained that, beginning in 2018/19, every plant will have to be a capacity
performance resource, which means that each plant has to be available anytime a maximum
emergency is declared. He reminded members that during the polar vortex there were several plants
that were unable to dispatch when ordered, either because they had interruptible gas contracts and
there was no gas available because of the temperatures, or they were unable to crank up the oil.
Mr. Betts stated that, during this maximum emergency, PJM still had enough capacity but the margin
was very narrow and, as a result, PJM went through a process, then went to the Federal Energy
Regulatory Commission (FERC) with a recommendation that plants be called capacity performance
resources and receive a premium. He explained that the premium is supposed to be a way to
guarantee performance and would reimburse the entity for having both oil and natural gas back-up
fuel or a firm contract, noting that it costs more to have a firm gas contract than an interruptible
contract.
Page 2
UTILITY COMMITTEE MEETING OF JULY 27, 2015 PAGE 2
Mr. Betts advised that the premium is still unknown at this time but would be presented in the
auction beginning on August 10, 2015, for the 2018/2019 market period. He stated that the
expectation is that the price for capacity will be much higher than the current price, in order to ensure
that plants will operate on maximum emergency days. Mr. Betts noted that the current market price
for capacity is $118 per MW day and it is expected to increase to more than $180 per MW day, with
some predictions indicating that it could be between $200 and $220 per MW day at this first auction.
Mr. Betts explained that the other side of the issue is that the penalties are outrageous if there is a
failure of performance. He stated that the interim rules are still subject to rehearing at the FERC;
however, since the penalties are significant, The Energy Authority (TEA) and the City of Dover have
begun discussing whether the performance adjustments in the proposed NAES contract align with
where the City currently is with PJM.
Referring to revised Page B-1, Appendix B - Performance Adjustment Provisions, Mr. Betts noted
that under Commercial Unavailability and Capacity, if the plant does not perform, there is a
reduction in NAES’ compensation. He stated that Commercial Unavailability is 35% of more than
$500,000, which is a significant reduction and more than what the City had in prior contracts;
however, it would not come close to the penalties for failure to perform. Mr. Betts reminded
members that while a primary objective of the proposed contract was to ensure that the plant
performs, there is a mismatch between the value of the contract and the penalties and, as a result,
staff had discussed the possibility of adjusting the weights for Commercial Unavailability and
Capacity in the coming year. Mr. Betts advised that in terms of the capacity performance
requirement, the City is okay for this year but there will be a transitional capacity performance
requirement and then the full requirement will begin in 2018/2019.
Mr. Betts stated that staff recommended authorizing the City Manager to execute the Amended and
Restated Operation and Maintenance Agreement dated July 1, 2015 between the City of Dover and
North American Energy Services (NAES), as presented with the inclusion of revised Page B-1,
Appendix B - Performance Adjustment Provisions.
Mr. Blakeman questioned if it would take six (6) months to terminate the agreement if there was a
catastrophic failure, especially after 2017 when the City is down to one (1) generating unit.
Responding, Mr. Betts stated that the six (6) month termination notification would still apply;
however, he indicated that something could always be worked out. He expressed his hope that the
City would not have a catastrophic failure that would wipe out Unit 3 and the VanSant plant.
Mr. Betts noted that the expectation is, with the improvements that are being made at VanSant, that
the City would continue to bid that unit in, and he would recommend a modification of the contract
rather than a complete termination.
Mr. Blakeman noted that the City would be losing Units 1 and 2, which would drop the City below
the installed capacity to cover the peak load. He asked if there were still requirements to have
enough capacity to cover the load and what the impact would be if the City only had the VanSant
plant. In response to Mr. Blakeman, Mr. Betts stated that there was still a requirement to have
enough capacity to cover the load and explained that the purchase power agreement with
Calpine Energy Services, L.P. for 40 MW would be considered by City Council during their meeting
Page 3
UTILITY COMMITTEE MEETING OF JULY 27, 2015 PAGE 3
scheduled for later in the evening. He explained that 40 MW would cover the loss of Units 1 and
2 as well as the additional increment the City needs. Mr. Betts informed members that the City
would also go out in the periodic markets to pick up any other difference the City may have to cover.
Mr. Blakeman moved to recommend authorizing the City Manager to execute the Amended
and Restated Operation and Maintenance Agreement dated July 1, 2015 between the City of
Dover and North American Energy Services (NAES), as presented with the inclusion of revised
Page B-1, Appendix B - Performance Adjustment Provisions, as recommended by staff. The
motion was seconded by Mr. Cole and unanimously carried.
Mr. Blakeman moved for adjournment, seconded by Mr. Cole and unanimously carried.
Meeting adjourned at 5:14 p.m.
James L. Hutchison, Sr.
Chairman
JLH/TM/dd
S:\AGENDAS-MINUTES-PACKETS-PRESENTATIONS-ATT&EXH\Committee-Minutes\2015\07-27-2015 UTILITY.wpd
Attachments
Attachment #1 - Revised Page B-1, Appendix B - Performance Adjustment Provisions, to the Amended and Restated
Operation and Maintenance Agreement dated July 1, 2015 between the City of Dover and North
American Energy Services (NAES)
Page 4
ATTACHMENT #1
Utility Committee Meeting of 07/27/2015
APPENDIX B - PERFORMANCE ADJUSTMENT PROVISIONS
Commercial 1---o_f_d_is..._a_tc_h_e_d_+-___h_o_u_rs_ _--1 CU Calculatlon: CU={(F0u 1+ Eu1)*(17MW) + (FOu2+EU2)*(17MW)
35.00% Commercial Unavailability (CU)
Unavallabiity hours
+ (F0u3+Eu3)*(102MW) +
(F0 011 +Eu 11 t(39MW)} / 8760 hours*(175MW)
All tests assed No tests assed The a<fustment is wei hied b size of the um subject to the test.
Capacity 25.00% Demonstrated PJM Dependable Capacity
98% 90%
Required Safety Training Complete 98 % 90% Equal weights
Safety Performance 15.00'4 Required NAES Housekeeping Inspections 1----=-=--"-"----+----.;;,.:_:.:....._ _-+=;;_,;.-'---=---------- - -- - - - - - ---t
Required NAES Safety Observations
98% 90%
Environmental 20.00%
Number of Notice of Violations In budget - - --1-- --- 4-
0
year
Plant Manager meets with City
Representative monthly and keeps Subjective Subjective Operator keeps Owner Rep informed monthly of plant issues
Communications 5.00"/o
Representative infonned of CIP budget
changes
ATTACHMENT #1
100.00%
Results that fall between No Adjustment and Full Adjustment will be calculated on a straight-line interpolation.
Available hours = total hours per year when units are available for dispatch, excluding scheduled and unscheduled outage hours.
Utility Committee Meeting of 07/27/2015