This text was pulled from the PDF automatically and may contain mistakes. The PDF is the official record, so check it before relying on this.
Page 1
SAFETY ADVISORY AND TRANSPORTATION COMMITTEE
AGENDA
APRIL 25, 2012 - 5:00 P.M.
CITY HALL CONFERENCE ROOM
15 LOOCKERMAN PLAZA
DOVER, DELAWARE
Public comments are welcomed on any item and will be permitted at appropriate times.
When possible, please notify the City Clerk (736-7008 or e-mail at CityClerk@dover.de.us)
should you wish to be recognized.
AGENDA ADDITIONS/DELETIONS
1. FY 2013 Five-Year Capital Investment Plan (CIP)
2. Update - Dover High School Construction
3. Briefing on Delaware Department of Transportation (DelDOT) Projects - Gary Laing
A. DelDOT Repaving Project
B. West Dover Connector
C. Wyoming Mill Road Project
D. Route 8/Hazlettville Road Connector
4. Briefing on Dover/Kent County Metropolitan Planning Organization (MPO) Projects - Rich Vetter
/tm
S:\AGENDAS & MINUTES\Committee-Agendas\2012\04-25-2012 SA&T.wpd
THE AGENDA ITEMS AS LISTED MAY NOT BE CONSIDERED IN SEQUENCE. THIS AGENDA IS SUBJECT TO CHANGE TO INCLUDE
THE ADDITION OR THE DELETION OF ITEMS, INCLUDING EXECUTIVE SESSIONS.
Page 2
City of Dover, Delaware
Fiscal 2013 DRAFT Capital Investment Plan
FY 13 thru FY 17
PROJECTS BY DEPARTMENT
Department Project# Priority FY 13 FY 14 FY 15 FY 16 FY 17 Total
Fire/Robbins Hose
Annual Contribution to Robbins Hose FR1201 1 238,524 238,524 324,238 319,185 319,185 1,439,656
Fire/Robbins Hose Total 238,524 238,524 324,238 319,185 319,185 1,439,656
Police
Police Station Main Electric Breaker Replacement PD1301 1 33,800 33,800
Repair/Micro Seal Police Station Parking Lots PD1302 2 25,300 25,300
Police Total 59,100 59,100
GRAND TOTAL
T
297,624 238,524 324,238 319,185 319,185 1,498,756
AF
R
D
Thursday, April 19, 2012
Page 3
City of Dover, Delaware
Fiscal 2013 DRAFT Capital Investment Plan
FY 13 thru FY 17
FUNDING SOURCE SUMMARY
Source FY 13 FY 14 FY 15 FY 16 FY 17 Total
General Fund 297,624 238,524 324,238 319,185 319,185 1,498,756
GRAND TOTAL 297,624 238,524 324,238 319,185 319,185 1,498,756
T
AF
R
D
Thursday, April 19, 2012
Page 4
Fiscal 2013 DRAFT Capital Investment Pla FY 13 thru FY 17
City of Dover, Delaware
Project # FR1201
Project Name Annual Contribution to Robbins Hose
Type Equipment Department Fire/Robbins Hose
Useful Life 15-20 years Contact Fire Chief
Category General Priority 1
New Project: No Account Number:
Time-Line:
Description Total Project Cost: $3,136,062
This contribution covers payments to the Robbins Hose Company to cover the Major Fire Apparatus Replacement Plan.
Justification
The Major Fire Apparatus Replacement Plan ensures loan payments for replacement according to a schedule which guarantees equipment will
not be outdated and unserviceable. This plan is based on replacing one of the Company's five engines and one rescue vehicle every three years
T
which would put the average replacement age at 18 years. The two ladder trucks would be replaced every 15 years depending on condition and
current needs. This schedule would reduce overall maintenance costs because fire apparatus would be replaced before major problems occur. By
providing the Robbins Hose Company with the needed payments for the Major Fire Apparatus Replacement Plan, the Robbins Hose Company
will be enabled to pay for a $2.5 million door rehabilitation of the Company Headquarters on Governors Avenue. This renovation is designed to
requirements and NFPA standards .
Prior
968,036
Total
Expenditures
Equip/Vehicle/Furnishings
Total
AF
handle 25 years of growth of the company and would preclude any need for an additional fire station in Dover. The Robbins Hose Company will
also cover costs associated with miscellaneous apparatus and equipment such as command units, utility vehicles, and large hose replacement.
CONSEQUENCES OF DELAYING OR ELIMINATING THIS PROJECT result in increased maintenance costs; possibility of not meeting ISO
FY 13
238,524
238,524
FY 14
238,524
238,524
FY 15
324,238
324,238
FY 16
319,185
319,185
FY 17
319,185
319,185
Total
1,439,656
1,439,656
Future
728,370
Total
Prior
968,036
Funding Sources
General Fund
R FY 13
238,524
FY 14
238,524
FY 15
324,238
FY 16
319,185
FY 17
319,185
Total
1,439,656
Future
728,370
Total
D
Budget Impact/Other
Total 238,524 238,524 324,238 319,185 319,185 1,439,656 Total
Thursday, April 19, 2012
Page 5
Fiscal 2013 DRAFT Capital Investment Plan
City of Dover, Delaware
Fiscal Year 2013 2014 2015 2016 2017
Ladder 2 92,910 92,910 92,910 - -
Engine 2 ($555,000) - - - - -
Engine 7 ($585,000) - - - - -
Ladder 1 ($920,000) 145,614 145,614 145,614 145,614 145,614
Engine 3 ($600,000) - - 85,714 85,714 85,714
Engine 6 ($615,000) - - - 87,857 87,857
Engine 4 ($630,000) - - - - -
TOTALS 238,524 238,524 324,238 319,185 319,185
Page 6
Fiscal 2013 DRAFT Capital Investment Pla FY 13 thru FY 17
City of Dover, Delaware
Project # PD1301
Project Name Police Station Main Electric Breaker Replacement
Type Equipment Department Police
Useful Life Unknown Contact Police Chief
Category General Priority 1
New Project: Yes Account Number:
Time-Line:
Description Total Project Cost: $33,800
The main circuit breaker in the Police Station must be replaced. The breaker failed twice already, the first time was during June 2010 and again
in August 2011. The breaker was removed and tested in 2010 by EnergTest, a company that specializes in the testing and overhaul of building
electrical equipment; however the breaker passed all tests. During the interim period when the breaker was removed and sent away for testing,
Tudor Electric loaned us a breaker until the testing was completed because the breaker model is obsolete. The loaner breaker was returned to
Tudor Electric when our original breaker was returned and reinstalled in the electrical panel. However, the breaker failed again in August 2011
and was removed again. The same breaker from Tudor Electric is now being rented on a monthly basis until the main electrical box can be
modified to accommodate a new breaker. Since we do not know what caused the breaker to fail, a comprehensive review of the building’s
electrical systems is needed to determine the actual loads on all circuits and whether there are any faults in any of the circuits. The study was
T
contracted and should be completed during Fiscal 2012. The results of this study are needed before the main breaker project can be started in
Fiscal 2013. Square D is the brand for our power panel and mixing brands within the same electrical panel is not an option so this is a sole vendor
project. United Electric is the vendor/distributor for our area. In addition, when the breaker fails, operations in the whole building are disrupted.
Although the building generator automatically starts up in a power failure, the whole building does not resume power. The generator cannot
AF
accommodate all the power requirements in the building, so during power outages, only Dispatch and the Executive Staff are 100% powered.
Administrative functions such as Records and other support areas not on generator power, so personnel in those functions are left idle and unable
to perform their normal work
Justification
This is a key system in maintaining public safety operations both within the Police Station and to our officers in the community serving the
public. Although we can maintain basic operations using the emergency power generator, its use is inefficient since only a few functions can be
sustained while the building’s power is disabled. In addition, we are currently renting an older model used breaker on a recurring basis until this
project is approved and implemented. We do not know how much useful life actually remains on the rented breaker since it is old and has no
warranty.
Expenditures R
Equip/Vehicle/Furnishings
FY 13
33,800
FY 14 FY 15 FY 16 FY 17 Total
33,800
D
Funding Sources
General Fund
Total
Total
33,800
FY 13
33,800
33,800
FY 14 FY 15 FY 16 FY 17
33,800
Total
33,800
33,800
Budget Impact/Other
Fiscal 2009 Repairs cost $4,980.75 and FY12 costs are estimated at $8,255.75 and include a $300 monthly rental fee for the old breaker in place
until it is replaced with the new breaker on this project. Once the project is completed, there should be no additional costs to the budget.
Thursday, April 19, 2012
Page 7
Fiscal 2013 DRAFT Capital Investment Pla FY 13 thru FY 17
City of Dover, Delaware
Project # PD1302
Project Name Repair/Micro Seal Police Station Parking Lots
Type Maintenance Department Police
Useful Life Unknown Contact Police Chief
Category General Priority 2
New Project: Account Number:
Time-Line:
Description Total Project Cost: $25,300
The southeast and southwest lots have several cracks that need to be filled and micro-sealed. If this is done during FY13, there should be no need
to completely redo the station lots (milling down, repaving, and restriping of the parking lots) for another five to ten years. The city crews came
over and put cold patches down on the southwest side during FY08, but the current cracks need to be addressed to prevent further damage to
department vehicles as well as the vehicles owned by department personnel and visitors who use those lots.
Justification
If the repair isn’t completed, the additional cracks & potholes that develop over the winter could cause damage to department and personal
vehicles and become a liability issue to the city.
Expenditures FY 13 FY 14
T FY 15 FY 16 FY 17 Total
Construction/Maintenance
Funding Sources
General Fund
Total
Total
AF 25,300
25,300
FY 13
25,300
25,300
FY 14 FY 15 FY 16 FY 17
25,300
25,300
Total
25,300
25,300
Budget Impact/Other
R
D
Thursday, April 19, 2012
Page 8
City of Dover, Delaware
Fiscal 2013 DRAFT Capital Investment Plan
FY 13 thru FY 17
PROJECTS BY DEPARTMENT
Department Project# Priority FY 13 FY 14 FY 15 FY 16 FY 17 Total
Police
2007 Ford Crown Victoria (201) 13Veh# 201 n/a 23,800 23,800
1999 Ford Taurus (204) 13Veh# 204 n/a 18,900 18,900
2007 Ford Crown Victoria (216) 13Veh# 216 n/a 23,800 23,800
2007 Ford Crown Victoria (220) 13Veh# 220 n/a 23,800 23,800
2006 Ford Crown Victoria (232) 13Veh# 232 n/a 23,800 23,800
2007 Ford Crown Victoria (236) 13Veh# 236 n/a 23,800 23,800
2000 Ford Taurus (241) 13Veh# 241 n/a 18,900 18,900
2000 Ford Taurus (242) 13Veh# 242 n/a 18,900 18,900
2008 HD Motorcycle FHP (256) 13Veh# 256 n/a 18,800 18,800
2006 Ford Crown Victoria (217)
2007 Ford Crown Victoria (228)
2007 Ford Crown Victoria (238)
2008 Ford Crown Victoria (239)
14Veh# 217
14Veh# 228
14Veh# 238
14Veh# 239
n/a
n/a
n/a
n/a
T 23,782
23,782
23,782
23,782
23,782
23,782
23,782
23,782
2008 HD Motorcycle FHP
2008 Ford Crown Victoria (258)
2007 Ford Crown Victoria (278)
2007 Ford Crown Victoria (292)
2008 Ford Crown Victoria (293)
2002 Ford Taurus (206)
2007 Ford Crown Victoria (227)
2000 Ford Crown Victoria (234)
AF
14Veh# 257
14Veh# 258
14Veh# 278
14Veh# 292
14Veh# 293
15Veh# 206
15Veh# 227
15Veh# 234
n/a
n/a
n/a
n/a
n/a
n/a
n/a
n/a
18,803
23,782
23,782
23,782
23,782
18,880
23,782
23,782
18,803
23,782
23,782
23,782
23,782
18,880
23,782
23,782
2009 HD Motorcycle FHP (266)
2005 Ford Crown Victoria (277)
2005 Ford Crown Victoria (279)
2007 Ford Crown Victoria (280)
R 15Veh# 266
15Veh# 277
15Veh# 279
15Veh# 280
n/a
n/a
n/a
n/a
18,803
23,782
23,782
23,782
18,803
23,782
23,782
23,782
2005 Ford Crown Victoria (288)
2010 Ford Crown Victoria (203)
1998 Ford E250 (207)
D
2007 Ford Crown Victoria (290)
2008 Ford Crown Victoria (291)
2010 Ford Crown Victoria (202)
2000 Ford Taurus (210)
15Veh# 288
15Veh# 290
15Veh# 291
16Veh# 202
16Veh# 203
16Veh# 207
16Veh# 210
n/a
n/a
n/a
n/a
n/a
n/a
n/a
23,782
23,782
23,782
23,782
23,782
17,265
23,782
23,782
23,782
23,782
23,782
23,782
17,265
23,782
2005 Ford F150 Pick Up (245) 16Veh# 245 n/a 18,420 18,420
2008 Ford Crown Victoria (259) 16Veh# 259 n/a 23,782 23,782
2007 HD FHC Motorcycle 16Veh# 267 n/a 18,803 18,803
2009 HD Motorcycle FHP (268) 16Veh# 268 n/a 18,803 18,803
2002 Dodge Ram 1500 (296) 16Veh# 296 n/a 18,420 18,420
2001 Ford E350 SD (299) 16Veh# 299 n/a 46,585 46,585
2010 Dodge Charger (209) 17Veh# 209 n/a 18,880 18,880
2010 Ford Crown Victoria (243) 17Veh# 243 n/a 23,782 23,782
2011 Ford Crown Victoria 17Veh# 251 n/a 23,782 23,782
2007 Ford Fusion (260) 17Veh# 260 n/a 18,880 18,880
2010 Ford Crown Victoria (271) 17Veh# 271 n/a 23,782 23,782
2010 Ford Crown Victoria (273) 17Veh# 273 n/a 23,782 23,782
2010 Ford Crown Victoria (275) 17Veh# 275 n/a 23,782 23,782
2010 Ford Crown Victoria (285) 17Veh# 285 n/a 23,782 23,782
Thursday, April 19, 2012
Page 9
Department Project# Priority FY 13 FY 14 FY 15 FY 16 FY 17 Total
2010 Ford Crown Victoria (289) 17Veh# 289 n/a 23,782 23,782
2005 Ford E250 (295) 17Veh# 295 n/a 17,285 17,285
Police Total 194,500 209,059 227,939 233,424 221,519 1,086,441
GRAND TOTAL 194,500 209,059 227,939 233,424 221,519 1,086,441