CITY OF DOVER PLANNING COMMISSION
August 15, 2016
The Regular Meeting of the City of Dover Planning Commission was held on Monday, August 15,
2016 at 7:00 PM with Chairman Mr. Tolbert presiding. Members present were Mr. Holden, Mr.
Roach, Mr. Holt, Mr. Baldwin, Ms. Maucher and Mr. Tolbert. Dr. Jones and Mrs. Welsh were
absent.
Staff members present were Mrs. Ann Marie Townshend, Mrs. Dawn Melson-Williams, Mr. Bill
Cook, Mr. Eddie Diaz and Mrs. Kristen Mullaney. Also present were Mr. Ed Ide, Mr. Nick Thomas,
Mr. Sean Mace, Mr. Tom Barnett, Mr. Mark Prata and Ms. Monika Sloan. Speaking from the public
was Mr. Phil McGinnis.
APPROVAL OF AGENDA
Ms. Maucher moved to approve the agenda as submitted, seconded by Mr. Holt and the motion was
unanimously carried 6-0.
APPROVAL OF THE PLANNING COMMISSION MEETING MINUTES OF JULY 18,
2016
Mr. Baldwin moved to approve the Planning Commission Meeting minutes of July 18, 2016,
seconded by Mr. Holt and the motion was unanimously carried 6-0.
COMMUNICATIONS & REPORTS
Mrs. Townshend stated that they are not having a separate Quarterly Workshop this month; it’s
being combined with tonight’s agenda since there was not a very heavy agenda.
Mrs. Townshend stated that the next Planning Commission meeting is scheduled for Monday,
September 19, 2016 at 7:00pm in the City Council Chambers.
Mrs. Townshend provided an update on the regular City Council and various Committee meetings
held on June 27 & 28, July 11 & 12, July 25 & 26 and August 8 & 9, 2016.
OPENING REMARKS CONCERNING DEVELOPMENT APPLICATIONS
Mrs. Townshend presented the audience information on policies and procedures for the meeting.
OLD BUSINESS
1) Requests for Extensions of Planning Commission Approval: None
NEW BUSINESS Regarding APPLICATIONS
1) S-16-16 Eden Hill Farm Traditional Neighborhood Design: Professional Office, Medical &
Financial District – Phase 2, Eden Hill Skilled Nursing Facility (Building 4) – Review and
Consideration of Minor Amendments related to building size & form, parking requirements
and site improvements proposed with the Administrative Site Plan S-16-16 for Phase 2:
Building 4 of the Professional Office, Medical and Financial District component of the Eden
Hill Farm Traditional Neighborhood Design. The Implementation Plan S-06-26 for the
1
Page 2
CITY OF DOVER PLANNING COMMISSION AUGUST 15, 2016
POMF District as approved consists of nine buildings, parking areas, open space areas and
the street layout in multiple phases. The project is located on an overall parcel consisting of
25.47 acres ± of land and is zoned TND (Traditional Neighborhood Design). The project is
located on the south side of West North Street and west of the railroad corridor flanking
Banning Street. The owner of record is Eden Hill Medical Center, LLC. Tax Parcel: ED-05-
076.00-01-13.02-000. POMF Implementation Plan S-06-26 was granted final approval on
October 2, 2007 and Phase 1 of the POMF District was constructed under Administrative
Site Plan S-06-42.
Representatives: Mr. Ed Ide III, I3a Consulting Engineers; Mr. Nick Tomasi, BBL Construction
Services; Mr. Sean Mace, Eden Hill SNF; Mr. Tom Barnett, Eden Hill Medical Center
Mrs. Melson-Williams stated that this is an Administrative Site Plan. For the Commission members
who are not familiar with the Traditional Neighborhood Design process for the City, this will
enlighten them a little bit about a portion of that process.
This is application S-16-16 for the Eden Hill Farm Traditional Neighborhood Design project. It’s
actually the only TND we have in the City. It consists of three (3) different districts. Specifically,
tonight they are looking at the Professional Office Medical and Financial District. Most people
would probably recognize that district area if she mentioned the Eden Hill Medical Center which is
a very large building on the south side of North Street just west of Banning Street where multiple
offices are housed in that facility. This application tonight is focusing on Phase 2 of that district
which is a proposal for a skilled nursing facility, it’s labeled as Building 4. As part of the TND
process, once an implementation plan is established for the district the development of each phase
of that district is subject to an Administrative Site Plan review process. Meaning that it is a Staff
level and agency level review. With the financial district, the implementation plan which was
previously reviewed and approved by the Planning Commission consisted of a total of nine (9)
buildings. This is a plan that focuses on what was constructed in Phase 1. The large Building 1 and
2 which is the Eden Hill Medical Center, the associated parking lot areas and the access including
Banning Street and the access to the building.
Tonight we are dealing with what is now called Phase 2 which is the southern square just to the
west of Banning Street. For the Administrative review process, they submitted a plan for what is a
proposed three (3) story building in this Phase 2 area. As mentioned, it’s been moving through and
Administrative process and what Staff does during that Administrative process is compare the
proposal for that phase with the Implementation Plan that has been established for the district as
well as the Pattern Book which is kind of the rules and guidelines for development in the district.
With this project there are a number of things that Staff has identified that are either minor or
clarifying amendments to the Implementation Plan and to the Pattern Book and they’ve summarized
them for the Commission. Staff is basically presenting them to the Commission to update them on
the process that this project is going through. In the report summary beginning on Page 3 there is a
chart that identifies these series of clarifying amendments which are slight changes to original
proposal that we are focused on tonight.
The first one is a change of phase order. Phase 2 will now consist of Building 4. Originally, it was
proposed for Phase 2 to consist of Building 3 which is the building area that is closer to North
Street. The second revision is related to building size. The original plan for the district identified
2
Page 3
CITY OF DOVER PLANNING COMMISSION AUGUST 15, 2016
Building 4 as a three (3) story building just over 35,000 square feet. With this proposal, Building 4
remains as a three (3) story building; however, the size has increased to 65,000 square feet. While
the building size has increased, they believe that it is mainly related to the type of facility that is
proposed for this building. The skilled nursing facility is one of the allowable uses in this zone. The
specific uses for each of the buildings throughout the district were not fully identified at the time of
Implementation Plan. We anticipate some types of changes to the building shape as a particular
phase gets ready to come online. The maximum floor area in total for the district would not be
exceeded; we are just at Phase 2 of this. There is a maximum building footprint limitation in this
district; however, this proposal likewise does not exceed that. Staff is comfortable with while the
building appears to be increasing in size, it’s certainly within the intent of the overall district.
The next item is related to building height. It is a three (3) story building. They have the initial color
rending for a concept for this building. You can see that it is three (3) stories. The Pattern Book
establishes guidelines for height for construction the district with those limitations being three (3)
story and forty (40) feet. Their proposal, and they’ve gotten some clarifying information from the
applicant’s representatives recently, is that the height to the roof level is actually forty-six (46) feet
and then there is a taller parapet wall system of varying heights as you can see on the building. The
top of the parapet is just over fifty-two (52) feet in height. The Pattern Book does account for this
concept of roof top areas that are unoccupied space. They may be steeples or dealing with
mechanical systems and it does allow for those types of areas to extend to a height of sixty-five (65)
feet. Staff is comfortable with this proposal with a building roof height being forty-six (46) which
does exceed the forty (40) feet; however, it’s related to floor to ceiling heights within the building
which accommodate increased mechanical system spaces between floors. It is not unlike Buildings
1 and 2 that exist on the property. While it looks like it is four (4) stories with a set of dormers and
the mansard roof system that is not occupyable space on that existing building. There is certainly
some precedent that’s set for a slightly taller building that’s focused on dealing with the systems
that the building needs to have. Staff is comfortable with what they are proposing with this Phase 2
building.
The building footprint itself did change. It was previously kind of an “L”’ shaped building that
presented a main façade to Banning Street. The presentation to Banning Street as a front does
continue. The building is more “T” shaped now and there is another main entrance on what is the
parking lot side of the building. But the building still presents a streetscape to Banning Street which
is the public street in this district and has this corner element as you enter the overall complex that is
maintained.
The next amendment is related to parking. This plan proposes construction of about ninety-five (95)
parking spaces. Staff notes that Phase 1 actually constructed more parking than it was required to so
there’s access parking available that can certainly accommodate any parking needs for both the
existing facility that is there as well as other ones such as this that begin to come online. The
applicant also presented information on what their typical parking needs are related to staffing and
visitors that are expected. With a skilled nursing facility, much of the space is occupied by beds and
not necessarily everyone in a bed needs a place to park. The Implementation Plan for the district
actually established a parking space rate based on floor area. When the calculation is done for this
building it result in what Staff believes is an over-parking requirement based on the function of this
building. Staff is comfortable with the proposal of ninety-five (95) parking spaces, recognizing the
fact that the TND Project is intended to be walkable, pedestrian friendly and multi-modal access
3
Page 4
CITY OF DOVER PLANNING COMMISSION AUGUST 15, 2016
which this project overall has. There are opportunities for shared parking to be able to walk between
buildings or arrive on-site via bicycle or bus as well. Staff is comfortable for their proposal for the
ninety-five (95) parking spaces. Ultimately, there are other areas of the district to be constructed and
if parking becomes an issue that can be addressed in other methods.
The project does include an entrance from Banning Street on the far south end of the building. It’s
intended to be sort of a service drive. It accesses what would be the loading areas of the building so
that those types of vehicles providing service needs to the building don’t have to make the entrance
drive loop that comes in off of Banning Street.
The last item that is noted is the community walking trail. The overall district includes a walking
trail system in the far eastern portion of the district near the train tracks. A portion of that trail near
the stormwater management pond was constructed initially in Phase 1. The applicant has asked to
delay construction of that walking trail
2) C-15-04 The Grande, Building 4: Planned Neighborhood Design – Senior Citizen Housing
Option: Review of Cash-in-lieu of Active Recreation Area Payment – Review of the
payment amount for Cash-in-lieu of Active Recreation Area construction as associated with
the Conditional Use Site Plan to establish The Grande: Planned Neighborhood Design
development of Senior Citizen Housing. The Active Recreation Area Plan for The Grande,
an apartment complex to consist of a total of 192 apartment units of Senior Housing, is
comprised of 22,569 SF of recreation area with amenities and a deficit of 6,231 SF of
recreation area. This application detailed construction of Building 4 on The Grande property
which consists of a total of 6.7326 acres ± and is zoned RG-5 (General Residence Zone for
Mid-Rise Apartments) and subject to the COZ-1 (Corridor Overlay Zone). The property is
located on the north side of Forrest Avenue (Route 8) just west of the Saulsbury Road
intersection. The owner of record is Doveview Investors, LLC. Property Addresses: 101-405
Doveview Drive. Tax Parcel: ED05-076.07-01-30.00-000. Council District 1. Cash-in-lieu
amount of $22,914 was accepted by the Parks, Recreation & Community Enhancement
Committee on July 12, 2016 and by City Council on July 25, 2016.
Representatives: Mr. Mark Prata, Doveview Investors, LLC
NEW DEVELOPMENT APPLICATIONS
1) C-16-04 90 Saulsbury Road Clubhouse and Pool, Associated with The Grande: Planned
Neighborhood Design – Senior Citizen Housing Option – Public Hearing and Review of a
Conditional Use Site Plan application to permit the construction of a 2,500 S.F. ± clubhouse
building, pool, parking and access walkway connecting to The Grande apartment complex.
The project may include a Parcel Consolidation Plan to join the clubhouse property to the
main Grande property. The clubhouse property consists of 1.48 acres and is located on the
west side of Saulsbury Road near Carver Road. The property is zoned C-2A (Limited
Central Commercial Zone) subject to the COZ-1 (Corridor Overlay Zone), and will become
part of The Grande PND-SCHO. The owner of record is 90 Saulsbury Road. Tax Parcel:
ED-05-076.07-01-28.00-000. Council District 1. Waiver Request: Partial Elimination of
Upright Curbing. This application is associated with development applications for The
Grande (previously known as Doveview Apartments) at 101-405 Doveview Drive, including
4
Page 5
CITY OF DOVER PLANNING COMMISSION AUGUST 15, 2016
C-15-04 (Building 4), S-11-12 (Building 1-3) and C-06-02 (for establishment of the Planned
Neighborhood Design – Senior Citizen Housing Option).
Representatives: Ms. Monika Sloan, Northpoint Engineering
NEW BUSINESS
1) MI-16-12 Text Amendment: Height in COZ-1 (Corridor Overlay Zone) – Public Hearing
and Review for Recommendation to City Council on a Text Amendment to the Zoning
Ordinance, Article 3, Section 27.66 – Building Height. The proposed amendment would
revise the building height limitation for a defined area on properties within the Corridor
Overlay Zone (COZ-1). Specifically, areas within one hundred (100) feet of a right-of-way
line of the roadways referenced in the Zoning Ordinance, Article 3, Section 27.3 – Zone
Boundaries would remain subject to the current two-story, 35-foot height limitation, while
areas outside this buffer would have no height restrictions other than those applying to
underlying zoning. Ordinance #2016-18. Final Reading/Public Hearing is scheduled before
City Council for September 12, 2016.
A. A copy of the proposed Ordinance #2016-18 is available on the City’s website
http://www.cityofdover.com/ under the Government Heading: Ordinances, Resolutions
& Tributes.
Representatives: None
Mrs. Townshend stated that this is an amendment to the Corridor Overlay Zone. The area
highlighted in green on the display that goes from the railroad tracks along Route 8 to Artis Drive
and then up and down Saulsbury Road and McKee Road is subject to the provisions of the Corridor
Overlay Zone. The Corridor Overlay Zone is principally design guidelines for how properties are
developed. There is quite a bit regarding buildings and what you see from the road, i.e. the location
of parking and landscaping. It is just an improvement over what you would see along Route 13. One
of the provisions of the Corridor Overlay Zone is that it limits the height of buildings to thirty-five
(35) feet and two stories. This proposed amendment would take that restriction of height only to one
hundred (100) feet of the lot depth. For a lot that is deeper than one hundred (100) feet from the
road, the remainder of that parcel would be subject to the height restrictions of the zone. There are
some zones where you might be able to do six (6) stories; some might be three (3) stories depending
on the zone. At this point, regardless of what the zoning underneath says because of the way the
Corridor Overlay Zone is written everything in the COZ-1 zone is limited to thirty-five (35) feet and
two stories. This would simply allow beyond one hundred (100) feet from the road to be taller than
that based on whatever the zoning of the parcel is.
Ms. Maucher stated that she was looking at the Kent County Association of Realtors letter and the
Corridor Overlay Zone is a twenty-five (25) year old ordinance. Was there a specific request for this
or is this just an effort to update the Ordinance all together? Responding to Ms. Maucher, Mrs.
Townshend stated that in this case there was a specific request. The Corridor Overlay Zone came
about after a study of the Route 8 Corridor and the Saulsbury/McKee Road Corridor back in the
early 1990’s and then the Corridor Overlay Zone was adopted. They did a pretty significant change
in 2007 but there are probably other amendments that are due like this one in particular. As they
have tried to urbanize things more, they are less intimidated than they might have been twenty-five
5
Page 6
CITY OF DOVER PLANNING COMMISSION AUGUST 15, 2016
(25) years ago by a building that is over two stories. This was actually brought forward by the real
estate community and has Council sponsors. This was not Staff’s review of the Ordinance; it was
something that was brought forward for practical reasons and had support from members of Council
to take it forward. The Planning Office is also in support because it does make sense.
Mr. Tolbert opened a public hearing.
Mr. Phil McGinnis – McGinnis Realty, 555 E Loockerman Street Dover DE 19901
Mr. McGinnis stated that he supports the text amendment because he supports anything that
improves the way we do things around town. The Corridor Overlay Zone is actually illegal. You
don’t have overlay zones; the Chancellery Court has told Levy Court that. They are trying to
preserve the first one hundred (100) feet and then after that, let the zoning districts do what the
zoning districts are supposed to do which is help develop the City properly.
Mr. Holt stated that this certainly gives a lot more flexibility to the builders and real estate people to
develop a property. Responding to Mr. Holt, Mr. McGinnis stated yes, it absolutely does. It actually
makes that area with all of the infrastructure that’s already in place a little more appealing because
you are not limited by an artificial restriction.
Mr. Tolbert stated that Mr. McGinnis cited a legal issue that has been resolved by Kent County.
Responding to Mr. Tolbert, Mr. McGinnis stated that Levy Court did an overlay zone out by Route
9 where as you went further east your lot sizes had to be larger and larger. The farmers sued the
County about that and the Chancellery Court overturned overlay zones.
Mrs. Townshend stated that the Chancellery Court overturned “that” overlay zone not all overlay
zones. No other overlay zones were nullified and the others that were in place at that time are
somewhat protected by virtue of the Statute of Repose. It prevents us from enacting additional
overlay zones in the future.
Mr. Baldwin stated that looking at the wording where it says “roadways”, will that create a problem
for people on corner properties? Responding to Mr. Baldwin, Mrs. Townshend stated no more than
it already does. When something is on a corner lot it is already treated as having two fronts: so, it
doesn’t make it any more challenging to lay those properties out than it is now. For instance, if you
look at the CVS and the Walgreen’s; they are both on corner lots. In Walgreen’s case, she thinks
they did get a variance but the CVS complies with the requirements of the Corridor Overlay Zone as
a corner building.
Mr. McGinnis stated that there are only two intersections in that zone and all four (4) corners are
fully developed and no change is expected during his lifetime.
Mrs. Melson-Williams stated that there was a letter dated July 12, 2016 addressed to Tim Slavin,
the Council President. It was received from the Kent County Association of Realtors and signed by
their current year President, Michael Harrington, Jr. It indicates in the text of the letter that the Kent
County Association of Realtors supports to text amendment to the Corridor Overlay Zone which
would modify the height limitations.
Mr. Tolbert closed the public hearing.
6
Page 7
CITY OF DOVER PLANNING COMMISSION AUGUST 15, 2016
Mr. Holt recommended approval to City Council for MI-16-12 Text Amendment: Height in COZ-1
(Corridor Overlay Zone) as submitted, seconded by Mr. Holden and the motion was unanimously
carried 6-0 by roll call vote. Mr. Holden voting yes; it’s a wise update to an older regulation and it
makes sense. Mr. Roach voting yes. Mr. Holt voting yes; it’s a very much needed addition for the
real estate market and to the whole area on the overlay zones. Mr. Baldwin voting yes; it allows
some flexibility for new building heights. Ms. Maucher voting yes; it’s a modernization of
ordinances as well as increases possibility for new development. Mr. Tolbert voting yes; after
hearing the comments and the overview the passage will facilitate development in the City for
buildings that need this kind of amendment.
8:06:20
Meeting adjourned at 8:47 PM.
Sincerely,
Kristen Mullaney
Secretary