Page 1
REGULAR COUNCIL MEETING
AGENDA
DECEMBER 9, 2013 - 7:30 P.M.
CITY HALL COUNCIL CHAMBERS
15 LOOCKERMAN PLAZA
DOVER, DELAWARE
OPEN FORUM - 15 MINUTES PRIOR TO OFFICIAL MEETING (7:15 p.m.)
The “Open Forum” segment is provided to extend the opportunity to the general public to share
their questions, thoughts, comments, concerns, and complaints. Discussion of any item appearing
on the agenda as a public hearing is prohibited during the Open Forum as an opportunity will
be provided during consideration of that item. Citizen comments are limited to three (3) minutes.
Council is prohibited from taking action since they are not in official session; however, they may
schedule such items as regular agenda items and act upon them in the future.
INVOCATION BY REVEREND THEODORE HENDERSON
PLEDGE OF ALLEGIANCE LED BY COUNCILMAN LYNN
AGENDA ADDITIONS/DELETIONS
* CONSENT AGENDA
Those items on the Council Agenda which are considered routine and non-controversial shall be marked
with an asterisk (*) and will be acted upon by a single roll call vote of the Council. There will be no
separate discussion of these items unless a member of Council so requests, in which event the matter shall
be removed from the Consent Agenda and considered a separate item.
* 1. Adoption of Minutes - Regular Council Meeting of November 25, 2013
2. Certificate of Appreciation - Albert W. (Bill) Holmes, Jr.
3. Recognition of Service - William M. Cooper, Jr.
A. Presentation by Silver Lake Commission
B. Proposed Resolution No. 2013-27
Page 2
Council Agenda - December 9, 2013 Page 2
4. Annexations
A. Property Located at 508 Acorn Lane, Owned by Raul M. Juarez
a-1. Public Hearing - Rezoning Related to Annexation
Property located at 508 Acorn Lane, consisting of two (2) parcels totaling
2.45 +/- acres (Parcel No. 1: located on the westerly side of Acorn Lane,
containing 1.315 +/- acres; and Parcel No. 2: located on the easterly side of
Acorn Lane, containing 1.135 +/- acres), owned by Raul M. Juarez. This
property is currently zoned RS-1 - Single Family Residence (Kent County
zoning classification) and the proposed zoning is R-8 - One-Family Residence
(City of Dover zoning classification).
(TAX PARCEL: ED-00-068.15-01-10.00-000; COUNCIL DISTRICT: 3; PLANNING REFERENCE: AX-13-02)
a-2. Adoption of Annexation Resolution No. 2013-28
a-3. Final Reading/Adoption of Rezoning Ordinance #2013-16 (The First Reading of
the Proposed Ordinance Was Accomplished During the Council Meeting of
October 14, 2013)
B. Property Located on the Westerly Side of Acorn Lane, Owned by the City of Dover
b-1. Public Hearing - Rezoning Related to Annexation
Property located on the westerly side of Acorn Lane, consisting of 0.075 +/- acres
(3,264 +/- s.f.), owned by the City of Dover. This property is currently zoned
RS-1 - Single Family Residence (Kent County zoning classification) and the
proposed zoning is R-8 - One-Family Residence (City of Dover zoning
classification).
(TAX PARCEL: ED-00-068.15-01-12.00-000; COUNCIL DISTRICT: 3; PLANNING REFERENCE: AX-13-03)
b-2. Adoption of Annexation Resolution No. 2013-29
b-3. Final Reading/Adoption of Rezoning Ordinance #2013-17 (The First Reading of
the Proposed Ordinance Was Accomplished During the Council Meeting of
October 14, 2013)
5. Presentation - Annual Report - Downtown Dover Partnership
* 6. Utility Committee Report - November 25, 2013
A. Electric Supply & Generation
a-1. McKee Run Units 1 & 2 - Cost/Benefit Analysis
(Committee Recommended Approval of Staff's Recommendations That, for the
Short Term, Units 1 and 2 Not Be Offered into PJM's Capacity Auction for the
2017/18 Delivery Year; That a Comprehensive Analysis Be Performed That Lays
Out All the Decision Options for the City of Dover; That a Similar Analysis on
Other Parts of the Generation Portfolio Be Completed; and That All Supply
Options Be Surveyed, Including New Generation Projects In and Around Dover
and Power Purchase Agreement (PPA) Opportunities)
a-2. VanSant Generating Station Capacity Increase - Cost/Benefit Analysis
(Committee Recommended That Staff Be Authorized to Continue to Proceed with
Project Implementation and Reassess Economics After Bids for Project
Installation Are Received and Before Submitting an Offer Into PJM for the
2017/18 Capacity Auction on May 12, 2014, Noting That PJM Must Be Notified
of Intent to Bid in Units 1 & 2 by March 1, 2014)
a-3. Purchase Power Agreement - Calpine
(Committee Action Not Required)
a-4. Discussion - Joint Agreement with the Delaware Municipal Electric Corporation
(DEMEC) for New Generation
(Committee Action Not Required)
Page 3
Council Agenda - December 9, 2013 Page 3
7. Legislative, Finance, and Administration Committee Report - November 25, 2013
A. Vehicle Purchase/Transfer - Mayor
(Committee Recommended Approval of the Vehicle Transfer, as Requested)
B. Request of Elizabeth W. Murphey School - Grant For Judo Mats
(Tabled by the Committee Until the Next Meeting So That More Information Could Be
Obtained Regarding Where the Money May Come From)
* 8. Monthly Reports - October 2013
A. City Assessor’s Report
B. City Manager’s Report
C. City Planner’s Report
D. Controller/Treasurer’s Budget Report
E. Economic Development Office Report
F. Dover Fire Department Report (April, May, June, July, August, September, and October)
G. Police Chief’s Report
9. Evaluation of Bids - Cable Puller
(Staff Recommends Purchasing the Replacement Cable Puller from Sherman & Reilly for
a Total Cost of $152,584)
10. Council Members’ Announcements
/tm
S:\AGENDAS-MINUTES-PACKETS\Council-Agendas\2013\12-09-2013.wpd
THE AGENDA ITEMS AS LISTED MAY NOT BE CONSIDERED IN SEQUENCE. THIS AGENDA IS SUBJECT TO
CHANGE TO INCLUDE THE ADDITION OR THE DELETION OF ITEMS, INCLUDING EXECUTIVE SESSIONS.
Page 4
REGULAR COUNCIL MEETING
The Regular Council Meeting was held on November 25, 2013 at 7:30 p.m. with Council President
Bonar presiding. Council members present were Mr. Dixon, Mr. Lynn, Mr. Perza, Mr. Slavin,
Mrs. Williams, Mr. Hare, and Mr. Hutchison. Mr. Anderson was absent.
Council staff members present were Police Chief Hosfelt, Mrs. Mitchell, Mr. Koenig, City Solicitor
Rodriguez, and Mrs. McDowell. Mayor Carey was also present.
OPEN FORUM
The Open Forum was held at 7:15 p.m., prior to commencement of the Official Council Meeting.
Council President Bonar declared the Open Forum in session and reminded those present that
Council was not in official session and could not take formal action.
Dr. Michael Casson, President of the Delaware Multi-Cultural and Civic Organization, relayed
appreciation to the Mayor and his staff for their support regarding a proposal that the organization
submitted to the Department of Health and Social Services to provide after school tutorials,
homework help, and enrichment activities. Due to this strong support, he announced that they were
selected for this funding and thanked the City for their continued support.
The invocation was given by Bishop Thomas L. Holsey, followed by the Pledge of Allegiance.
AGENDA ADDITIONS/DELETIONS
Mr. Hutchison moved for approval of the agenda, seconded by Mr. Dixon and unanimously
carried.
Mr. Lynn requested that Item #4C - Future Use of Dover Park Recreation Center be removed from
the consent agenda.
Mr. Hare moved for approval of the consent agenda, as amended, seconded by Mrs. Williams
and carried by a roll call vote of seven (7) yes (Dixon, Lynn, Slavin, Williams, Hare, Hutchison,
and Bonar), one (1) no (Perza), and one (1) absent (Anderson).
ADOPTION OF MINUTES - REGULAR COUNCIL MEETING OF NOVEMBER 12, 2013
The Minutes of the Regular Council Meeting of November 12, 2013 were approved by motion
of Mr. Hare, seconded by Mrs. Williams and bore the written approval of Mayor Carey.
PROCLAMATION - PANCREATIC CANCER AWARENESS MONTH
The City Clerk read the following Proclamation into the record:
WHEREAS, in 2013 an estimated 45,000 people will be diagnosed with pancreatic cancer in the
United States and approximately 38,000 people will die from the disease, with at least 120
pancreatic cancer related deaths occurring in Delaware; and
WHEREAS, the incidence and death rate for pancreatic cancer are increasing and it is anticipated
to move from the fourth to the second leading cause of cancer death in the United States by 2020;
and
Page 5
CITY COUNCIL MEETING OF NOVEMBER 25, 2013 PAGE 2
WHEREAS, the Pancreatic Cancer Action Network is the first and only national patient advocacy
organization that serves the pancreatic cancer community in the City of Dover and nationwide by
focusing its efforts on public policy, research funding, patient services, and public awareness and
education related to developing effective treatments and a cure for pancreatic cancer; and
WHEREAS, the Pancreatic Cancer Action Network and its affiliates in the City of Dover support
those patients currently battling pancreatic cancer, as well as to those who have lost their lives to
the disease, and are committed to nothing less than a cure; and
WHEREAS, the good health and well-being of the residents of the City of Dover are enhanced as a
direct result of increased awareness about pancreatic cancer and research into early detection,
causes, and effective treatments.
NOW, THEREFORE, I, CARLETON E. CAREY, SR., MAYOR OF THE CITY OF DOVER,
DELAWARE, do hereby proclaim November 2013 as Pancreatic Cancer Awareness Month in the
City of Dover and encourage all citizens to help increase public awareness and support for the
individuals and families who are affected by cancer.
PUBLIC HEARING - REQUEST FOR ABANDONMENT OF STREET (IMPROVED) -
HARMONY LANE/PROPOSED RESOLUTION NO. 2013-26 APPROVING
ABANDONMENT
A public hearing was duly advertised for this time and place to consider the abandonment of
Harmony Lane, which is an improved public street.
Mr. Scott Koenig, City Manager, reminded members that a petition had been received from Milford
Housing Development Corporation (MHDC) proposing to consolidate parcels within the Walker
Woods subdivision and renovate this development. The letter included a request for the
abandonment of Harmony Lane for a number of reasons, many beneficial to the developer but some
beneficial to the City. He referred to a table provided for information regarding the existing
infrastructure and the easements associated with the property. Mr. Koenig advised members that the
request was reviewed by the Development Advisory Committee (D.A.C.), Planning Commission,
and the Utility Committee.
Mr. Koenig assured members that staff, along with all committees and commissions, had
recommended approval of the abandonment of Harmony Lane with conveyance of sixty feet (60')
of said right-of-way to Milford Housing Development Corporation, with the following stipulations:
1) abandonment shall be conditioned upon the completion of the Site Development Plan and parcel
consolidation plan. Cross-access and public utility easements will be required for the existing
wastewater pump station and associated force main infrastructure located therein. Ownership shall
not be relinquished until such time as the parcel consolidation plan is recorded; and 2) abandonment
of all stormwater, street, wastewater, and water infrastructure to Milford Housing Development
Corporation in conjunction with the abandonment of Harmony Lane. The City shall retain
ownership of the existing pump station and associated force main only.
Council President Bonar declared the public hearing open.
Page 6
CITY COUNCIL MEETING OF NOVEMBER 25, 2013 PAGE 3
Mr. Russell Huxtable, Vice President of the Milford Housing Development Corporation (MHDC) -
977 East Madison Circle, Milford, Delaware, thanked the City for their consideration of the request
and stated that there were no objections regarding the stipulations as presented by City staff.
There being no one else wishing to speak, Mr. Bonar declared the public hearing closed.
Mr. Hare moved for approval of the request to abandon Harmony Lane, seconded by
Mrs. Williams and, by a unanimous roll call vote (Anderson absent), Council adopted
Resolution No. 2013-26 (Exhibit #1).
PARKS, RECREATION, AND COMMUNITY ENHANCEMENT COMMITTEE REPORT -
NOVEMBER 12, 2013
The Parks, Recreation, and Community Enhancement Committee met on November 12, 2013 with
Chairman Dixon presiding.
Benchmarks Established for the Economic Development Office
Mr. Bill Neaton, Economic Development Director, reviewed the benchmarks and results for the
Economic Development Office, including information regarding the Downtown Dover Partnership
(DDP), Downtown Dover Business Growth, and City-Wide Economic Development.
In reviewing the strategic objectives for Fiscal Year 2013-2014, Mr. Neaton advised members that
the site development master plan for Garrison Tract had been completed. He stated that the Garrison
Tract currently consisted of 15 parcels, with two (2) parcels either under construction or completed
(SunPark and Calpine Energy), and a third parcel recently sold to Uzin Utz for a manufacturing
facility. He stated that as a result of a recent meeting with Secretary Alan Levin, Delaware
Economic Development Office, a secured commitment was made to market the Garrison Tract. He
assured members that staff continued to assist Calpine and Kvaerner, the contractor, during the
construction phase, noting that conference calls were being held every Monday morning to discuss
any outstanding issues that needed to be resolved.
Regarding the infrastructure improvements at the Garrison Tract, Mr. Neaton indicated that the
selection process for the water tower had been completed and that negotiations continued with
Chesapeake Utilities to provide a four (4) inch gas line service to the remaining 13 parcels. He
advised members that a proposal from Chesapeake Utilities was received last week, after several
weeks of negotiations, and would be forwarded for legal review. Once reviewed, he planned to
present it to City Council for approval. Mr. Neaton stated that staff was working with Becker
Morgan Group to complete the construction documents and, once completed, bids would be solicited
for the infrastructure, which would include the roadway, sewer line, water line, and storm water
system. It was hoped that bids would be solicited by the end of the month with a due date in
December for presentation to City Council in January. This would allow for the contracts to be
awarded in February and construction to begin soon after.
Page 7
CITY COUNCIL MEETING OF NOVEMBER 25, 2013 PAGE 4
Mr. Neaton stated that, in an effort to promote City-wide economic development initiatives, a
commitment had been made by Uzin Utz to purchase Lot 12 at the Garrison Tract and that
discussions were currently taking place with two (2) other prospects for parcels at the Garrison Tract,
one (1) a very large utility user and the other a smaller utility user but major employer.
Mr. Neaton assured members that he continued to work with Mr. Jim Waddington, Kent County
Economic Development Office and Executive Director of the Kent Economic Partnership. With
regard to the Kent County AeroPark, he stated that there was a potential tenant for 150,000 square
feet of the SunRoc building. He reminded members that an update of the Job Growth Report for the
City’s 12 largest employers was being provided to City Council on a regular basis.
Mr. Neaton advised members that a breakfast meeting was held with the City’s top employers in
May 2013 and that an initial meeting of the Plant Managers Association was held in September 2013
with subsequent meetings to be held quarterly. Regarding the objective to partner with the Kent
Economic Partnership to develop a strategy for a Food Innovation District in Dover, he stated that
this project was continuing to move forward and that the Executive Director from a Food Innovation
District in upstate New York would participate in the next meeting via conference call to explain
how they established their Food Innovation District and what their successes and challenges were.
Responding to Mr. Hutchison regarding whether Calpine had adequate acreage to move to Phase II
under their current “footprint”, Mr. Neaton confirmed that Calpine had enough acreage on Lot 7 to
progress to Phase II and had been permitted to proceed to this phase. He noted that Eastern Shore
Natural Gas also had all permits and that all related studies had been completed.
In response to Mr. Hutchison regarding whether the Economic Development Office was informed
on the Kent County Economic Development Board’s activities related to the air cargo project,
Mr. Neaton stated that he met with Secretary Levin to discuss the progress this project. He stated
that all studies had been completed and that once a joint use agreement is finalized, bids would be
solicited and the project would begin to move forward.
Responding to Mrs. Horsey regarding the concept of a Food Innovation District, Mr. Neaton
explained that this would be a partnership with Delaware State University and that attempts were
being made to establish an area where companies that process food or conduct innovative studies on
food use could be located.
Noting that several of the economic benchmarks related to the DDP, Mr. Neaton requested that
Mr. Lou Colón, Executive Director, present the advance initiatives of the Partnership.
Mr. Colón advised members that he had been serving as the Executive Director for only eight (8)
months and distributed an event calendar for the year, including DDP-sponsored events (indicated
by bold font) and other partnerships with non-profit organizations. He stated that the DDP was in
the process of redoing marketing media in an effort to attract new businesses to the downtown area,
as well as updating their marketing brochure and website. He noted that these were ongoing
projects.
Page 8
CITY COUNCIL MEETING OF NOVEMBER 25, 2013 PAGE 5
Mr. Colón indicated that 238 Railroad Street was under demolition and the final inspection was
scheduled for Friday, November 15, 2013. He stated that since the City paid for the demolition,
there would be a lien on the property for the balance of the costs. With reference to 22-24 West
Loockerman Street, he stated that the EZ pass lease had been received, was being reviewed by legal
counsel, and would be routed for required signatures. Mr. Colón indicated that renovations for
EZ Pass were underway, with an expected completion date of February 2014. He advised members
that the DDP continued to share site information developed by the listing agent for the Acme site,
explaining that a partnership was being developed with an architect and a group performing
construction work in Middletown, Delaware.
Referring to vacancies in the downtown area, Mr. Colón stated that several conversations had been
held with individuals interested in the Loockerman Exchange building for a possible restaurant and
that he continued to have discussions with representatives of Starbucks, as well as individuals
interested in bringing a Jazz Club and Yoga Studio to the downtown area.
In response to Mr. Hutchison regarding the EZ Pass Project, Mr. Colón stated that the project was
approximately $50,000 under budget and 60% complete. The initial lease agreement was for three
(3) years with a renewal for an additional three (3) years.
Mr. Colón indicated that the signage in the parking lots would be replaced with blue and white signs
to match other signage and provide uniformity throughout the City.
The Committee took no action.
Update - CDBG Program
Members were provided an Update of the Community Development Block Grant (CDBG) Program,
including the status of FY-2013 CDBG Projects - October 2013. In addition, members were
provided an update on the Neighborhood Stabilization Program (NSP).
The Committee took no action.
Future Use of the Dover Park Recreation Center
During their Regular Meeting of October 28, 2013, members of City Council considered the Parks,
Recreation, and Community Enhancement Committee Report of October 14, 2013. After much
discussion regarding the Committee’s recommendations for the future use of the Dover Park
Recreation Center, City Council postponed the demolition of the Center and referred the item back
to the Committee to consider programming a new building and its possible configuration, whether
it be a splash park, gym, or other proposal, for a recommendation to Council, employing special
meetings and experts in the community, within 60 days.
Mrs. Ann Marie Townshend, Director of Planning and Community Development, advised members
that after the last City Council Meeting, she met with Mr. George Krupanski, President and CEO of
the Boys & Girls Clubs of Delaware, and a “walk through” of the building was done. In addition,
she stated that a “walk through” was scheduled with Mr. Darrell Tingle from the Greater Dover Boys
and Girls Club. Mr. Krupanski felt that there could be a possibility for partnership; however, he felt
Page 9
CITY COUNCIL MEETING OF NOVEMBER 25, 2013 PAGE 6
that a needs assessment would be necessary to determine if there was a need for programming to be
offered at the facility and if the building would meet those needs. She explained that all discussions
led back to a needs assessment. She felt that similar discussions could be held with representatives
of the YMCA, who had utilized the facility for their camp this past summer and liked the facility;
however, they were aware that the building was in need of a lot of work. It was her opinion that any
organization, before investing any significant funds into renovating the facility, would require a
needs assessment.
At this time, Mrs. Townshend felt that a City-wide needs assessment for recreation should be
conducted and should include a lot of public involvement. Considering that the building was beyond
its functional life, if a need for indoor recreation at this location was identified, she questioned if the
current building could be utilized. By the time these needs are determined, she noted that the
building would have deteriorated further. She advised members that the building was recently
broken into and that it was currently serving as a nuisance attraction.
Responding to Mr. Hutchison, Mrs. Townshend stated that the YMCA enjoyed using the center as
a temporary facility for their summer camp; however, she indicated that the YMCA recently
completed a major capital project on State Street and had acquired the Kent Swim Club, which was
now considered a major capital project. She stated that the new Executive Director had not visited
the Dover Park site and that she would invite her and other members of the Board to visit the Center
for a “walk through”; however, she advised members that the YMCA was aware of this issue and
had not approached staff with any interest.
Understanding staff’s position and recommendations regarding the Center, Mr. Caldwell explained
his concerns regarding the public’s objections to demolishing the building due to their concerns
regarding a specific area of the community. He indicated assurance that the children were of great
concern for members but that consideration must be given to the entire City and not just a particular
area of the community. He felt that the Center could not be used as a recreation center and, although
the numbers dictated that the building should be demolished, if the City should choose to keep the
building in operation, he suggested that it be utilized as a learning center or small library. It was his
feeling that children were not in need of additional recreation programs but rather more learning
activities, such as learning to read, write, and do math, and that volunteers could be used so that there
would not be any costs to the City. Although he understood the objections to demolishing the
building, he also understood the safety issues and suggested the use of cameras to monitor the
activities around the building.
Since this matter had been discussed at length and considering all issues and public testimony,
Mr. Perza relayed his support for staff’s recommendation for the demolition of the building. It was
his opinion that the building represented the “wants” of the community rather than the “needs.” He
explained that the City was in the process of determining how to best spend the resources available
to develop the park systems City-wide. He indicated that investing in the White Oak Park area
would be a good idea, reflecting the needs of the community and helping the youth; however, his
concern was that the expenditures required to renovate the building ($110,000) would not be the best
Page 10
CITY COUNCIL MEETING OF NOVEMBER 25, 2013 PAGE 7
use of City funds. He supported the $30,000 expense to demolish the building and suggested that
the City earmark the $80,000 that would have otherwise been spent to repair the building, to be
committed to Dover Park and addressing the needs of the community. He noted that there had been
various ideas, such as a splash park, soccer fields, etc.
Concurring with Mr. Perza, Mrs. Horsey relayed support for investing in Dover Park, but not
necessarily the building. She suggested that staff conduct a survey of those that had attended the last
Committee meeting and relayed objections to the demolition of the building to determine if they
would use the building versus just wanting it to be kept. She indicated that demolition of the
building would go against her support for preservation; however, she relayed support for staff’s
original recommendation for the demolition of the building.
Mrs. Townshend reminded members that there were several other ideas for improvements at Dover
Park, such as providing electricity at the pavilions, installing public restrooms, etc. In addition, she
felt that it would be important to develop a strong vegetative management plan that would promote
visibility in order to address safety issues and concerns. She stated that limiting the number of
concealed areas in the park would allow users of the park to feel safer.
Mr. Dixon suggested that the City establish a task force to consist of volunteers from the community
and allow them to develop a recommendation for Dover Park.
The committee recommended acceptance of staff’s recommendation to demolish the Dover Park
Recreation Center and that the City Manager be authorized to earmark the balance of the
construction/demolition project up to $80,000 for future capital improvements, in the City’s future
budgets, to Dover Park after a needs assessment is accomplished.
For clarification, Mr. Perza stated that since the costs for the minimal renovations to the building
were estimated at $110,000 and demolition would cost approximately $30,000, there would be a
balance of $80,000 which would be committed to Dover Park once it is determined how that money
would be best spent. He stated that this expenditure would not have to be done in any specific fiscal
year; however, these funds would be reserved and earmarked to improve Dover Park once the needs
were determined.
Mr. Dixon encouraged staff to include the community in determining the needs.
During the Council Meeting, Mr. Lynn reiterated his objections, explaining his feeling that the
eastern side of Dover is not well served in regards to recreation needs. He relayed concerns
regarding the possibility of individuals having to ride bicycles or walk across the highway to Schutte
Park and concerns of the resultant effect that demolition of this property would have on that area of
the community. He indicated his belief that setting aside money to build a new facility was a good
idea; however, he stated his concerns with setting aside $80,000 with no concrete idea as to what
would occur next. He felt that the recommendation was a disservice to his constituents, specifically
those in the east side of Dover and, as such, he stated that he could not and would not support the
recommendation.
Page 11
CITY COUNCIL MEETING OF NOVEMBER 25, 2013 PAGE 8
Mr. Dixon explained that the intent of the Committee was to assure that another building would be
erected and that his support for the demolition was due to his concerns with criminal activities
associated with vacant buildings and the excessive costs to repair the building. Therefore, the
Committee recommended approval of its demolition, with the understanding that another building
would be erected to provide some type of recreation.
Mr. Perza moved for approval of the Committee’s recommendation to demolish the Dover
Park Recreation Center and that the City Manager be authorized to earmark the balance of
the construction/demolition project up to $80,000 for future capital improvements, in the
City's future budgets, to Dover Park after a needs assessment is accomplished. The motion
was seconded by Mr. Hutchison and carried by a roll call vote of five (5) yes (Dixon, Perza,
Williams, Hare, and Hutchison), three (3) no (Lynn, Slavin, and Bonar), and one (1) absent
(Anderson). (City Clerk’s Office Note: Subsequent to the meeting, official notification was received
of Mayor Carey’s veto of this motion.)
Mr. Dixon moved for acceptance of the Parks, Recreation, and Community Enhancement
Committee Report, seconded by Mr. Hutchison and unanimously carried (Anderson absent).
UTILITY COMMITTEE REPORT - NOVEMBER 12, 2013
The Utility Committee met on November 12, 2013 with Chairwoman Williams presiding.
Engineering Design and Projects - Engineering Design of Water and Wastewater Upgrades -
West Dover Connector
Mr. Scott Koenig, City Manager, stated that the Delaware Department of Transportation (DelDOT)
was planning to construct a new bypass road, the West Dover Connector, from the Rodney Village
subdivision to the intersection of Saulsbury Road and North Street. He reviewed a request from staff
regarding the engineering design of water and wastewater upgrades related to this project.
Mr. Koenig noted that DelDOT had approached the City regarding the City’s existing infrastructure
within the project boundary as it relates to Rodney Village. He explained that Rodney Village was
constructed in the late 1950s or early 1960s and the original water and sewer lines remained in place.
Mr. Koenig indicated that this project would provide an opportunity for the City to upgrade the
undersized water line and replace the aging sewer line in the area and that DelDOT recommended
that the City perform this work prior to the road construction entering this project area.
Staff recommended acceptance of the proposal from URS Corporation to perform the engineering
design work necessary for water and wastewater upgrades associated with the West Dover Connector
in the amount of $44,100. Mr. Koenig stated that if Council favored this proposal, construction
would begin next year as part of the water and sewer system upgrades that are routinely included in
the City’s budget.
In response to Mr. Perza, Mr. Koenig explained that the improvements in the Rodney Village area
would be outside the City boundaries but were in the southern portion of the City’s water and sewer
system. In addition, he confirmed that design standards inside and outside City limits were the same
and the project and related improvements would allow connection to the existing water system.
Page 12
CITY COUNCIL MEETING OF NOVEMBER 25, 2013 PAGE 9
Responding to Mr. Perza, Mr. Koenig confirmed that the $44,100 proposal would provide only
design work, not construction, and that he did not anticipate cost overages.
In response to Mr. Perza regarding whether the project had been budgeted, Mr. Koenig stated that
water quality upgrades, including pipe replacement and Inflow & Infiltration (I&I) upgrades, were
included in the five (5) year Capital Improvement Plan (CIP). He stated that the project would
technically qualify as an I & I upgrade because the old terra cotta sewer system has roots infiltrating
many of the joints and problems are constantly being reported in the Rodney Village area. He noted
that infiltration had not been quantified but that staff would try to quantify it as part of this
engineering study.
Responding to Mr. Slavin regarding the statement in the associated Committee Action Form (CAF)
that “Preliminary work has begun due to time constraints,” Mr. Koenig noted that preliminary work
had been done on the project for approximately one (1) week under an existing blanket contract with
URS Corporation and that this work would have to be halted if Council decided not to go forward.
He indicated that consulting services were included in the line item budget for the Operating Fund
and that the current request was being presented to Council because the amount would exceed
$25,000. Mr. Koenig stated that the expenses would be charged to the Capital Fund if the proposal
were to move forward as a capital project.
Mr. Slavin expressed concern that the City was obligated to the vendor for work that was already
performed before the matter was brought before Council and questioned if this was a violation of
policy. Responding, Mrs. Donna Mitchell, Controller/Treasurer, explained that fees under $25,000
could be charged to a consultant budget. Preliminary design work could be performed within that
budget; however, expenses toward the construction of the project could not be charged to a
consultant budget because it would technically be a violation of the policy to begin work before the
matter was approved. If the work were stopped, the portion of the work already completed would
be charged to the consulting budget. She explained that there are times when staff must address
matters that arise in an emergency. Mrs. Mitchell stated that she was uncertain if this project was
such an emergency.
Responding to Mrs. Williams, Mr. Koenig stated that the project was not currently budgeted. He
indicated that the request was for authorization for the engineering services agreement and the
project would be brought back as part of the CIP in the future. He noted that funds for the project
would come from water quality improvements and I & I improvements that are part of the City’s five
(5) year CIP.
In response to Mrs. Williams regarding the funding for the project, Mrs. Mitchell stated that funds
would be allocated from a carry-forward of approximately $867,000 for I & I from the previous year.
She noted that there was no carry-forward from water quality funds.
In response to Mr. Perza, Mrs. Mitchell stated that no other projects would be re-prioritized or
“bumped” as a result of approving this proposal since specific projects had not yet been identified
for the $867,000 carry-forward.
Page 13
CITY COUNCIL MEETING OF NOVEMBER 25, 2013 PAGE 10
Mr. Slavin questioned the City’s policy on maintaining a carry-forward balance. Mrs. Mitchell
explained that staff typically continues to move forward with projects from the previous year and she
tracks the figures to ensure that the carry-forward balance is not being exceeded. A budget ordinance
is subsequently brought forward that places the carry-forwards for all of the projects in the current
year’s budget.
In response to Mrs. Williams regarding the $867,000 carry-forward amount, Mrs. Mitchell stated that
this was a normal amount. She indicated that the City’s I & I and water quality projects had been
running slightly behind but were now “catching up” and she did not expect this amount of
carry-forward to continue.
The Committee recommend acceptance of the proposal from URS Corporation to perform
engineering design work necessary for water and wastewater upgrades associated with the West
Dover Connector in the amount of $44,100.
By consent agenda, Mr. Hare moved for approval of the Committee’s recommendation,
seconded by Mrs. Williams and carried by a roll call vote of seven (7) yes (Dixon, Lynn, Slavin,
Williams, Hare, Hutchison, and Bonar), one (1) no (Perza), and one (1) absent (Anderson).
Engineering Design - Miscellaneous Stormwater Projects
Mr. Scott Koenig, City Manager, reviewed a request for Engineering Design - Miscellaneous
Stormwater Projects. He advised members that a series of storm sewer and flooding issues had been
identified recently at Buttner Place, Susan Place, and Lakeview Drive. Mr. Koenig noted that, in
some cases, legislators were interested in contributing money to these projects once engineering
costs were developed. He noted that Buttner Place, leading to the City’s power plant and Electric
Administration Building, had been flooding for a number of years, which was causing traffic flow
problems, especially during the winter months when icing occurs. Susan Place, in the Persimmon
Park Place development, had flooding on the edge of the road adjacent to some of the lots because
of failing pipe that was believed to be privately owned and maintained. He indicated that legislators
were interested in possibly securing public easements so that these pipes could become public pipes,
which could be more easily maintained and brought up to current design standards. In addition,
constant complaints of flooding at the end of Lakeview Drive adjacent to Luther Towers had been
received. Mr. Koenig indicated that there was a connection to the existing storm drain system at that
location, but it was not working correctly and staff was looking for an alternative outfall, possibly
between two (2) houses and through Silver Lake Park.
Mr. Koenig indicated that the request for engineering design would provide the design parameters
as well as some construction estimates and that, as project specifications are developed, staff
intended to ask State legislators for funding for each of the projects. He noted that each project
would qualify for Community Transportation Funds (CTF) because they were drainage-related.
Mr. Koenig stated that if the legislators choose not to approve the projects, they may be included in
the General Fund budget or may be delayed until additional legislative interest could be obtained.
Page 14
CITY COUNCIL MEETING OF NOVEMBER 25, 2013 PAGE 11
Staff recommended the acceptance of three (3) proposals from URS Corporation to perform
engineering design work necessary for flooding issues at Buttner Place, Susan Place and Lakeview
Drive in the amounts of $9,450, $9,300 and $24,400 respectively ($43,200 total rounded to the
nearest $100).
Mr. Perza questioned if the design cost would be reimbursable if the legislature adopted these
projects. Responding, Mr. Koenig stated that if Council were to authorize the agreements, staff
would ask for the design costs to be rolled into potential construction costs to determine the numbers
for CTF funds. If there were a need to delay, some of the design costs may not qualify for
reimbursement, but the construction costs would definitely qualify. Mr. Koenig stated that a
consultant was being sought because, although the City had engineering staff in the budget and was
very close to hiring these employees, they would not be ready to get these projects underway in a
timely manner. He indicated that it was planned to move funds from the salary budget into
consulting, in accordance with financial policies.
In reference to the failing pipe at Susan Place that was privately owned, Mr. Perza inquired if it was
customary for the City to intercede in private matters rather than asking the property owner to make
these types of corrections. Responding, Mr. Koenig stated that it was not customary for the City to
review privately owned pipes; however, in this case the legislators were asking staff to evaluate
whether this was a project that would potentially alleviate the flooding. He explained that the City
owned the infrastructure within the right-of-way in Susan Place and that the storm drain systems
behind the properties in Persimmon Park Place were specifically excluded when the City dedicated
the roads in Persimmon Park Place because it was difficult to obtain easements and there were no
apparent problems at that time. Since there were now failing pipes in this area, Mr. Koenig stated
that it would be much easier for the City to get easements from property owners in order to resolve
the problem.
Mrs. Williams inquired why this matter would not be handled directly by the legislator involved and
why the City would be involved in a situation where the City’s expenses might not be reimbursed.
Responding, Mr. Koenig explained that when the City does road rehabilitation and paving, the City
acts as the designer and prepares construction contracts and estimates. In years past, the City had
not requested the legislators to reimburse for staff time because it was desired to maximize dollars
for construction. In this case, the City does not have the in-house staff to perform the project and,
because there would be actual out-of-pocket expenses, the City would try to have the design costs
encumbered into the project.
Responding to Mr. Perza regarding the replacement of staff engineers, Mr. Koenig stated that there
were three (3) positions open and three (3) final candidates who would be interviewed in the next
couple of weeks. It was his hope that the positions would be filled within the next 30 days. In
response to Mr. Perza’s inquiry as to whether these projects could be held for the new engineers to
handle, Mr. Koenig stated that he was unsure if new staff could be “up to speed” quickly enough and
it was necessary to put the funding in place for these projects. He indicated that the preference
would be to enter into the engineering services agreement associated with the projects.
Page 15
CITY COUNCIL MEETING OF NOVEMBER 25, 2013 PAGE 12
The Committee recommended acceptance of three (3) proposals from URS Corporation to perform
engineering design work necessary for flooding issues at Buttner Place, Susan Place and Lakeview
Drive in the amounts of $9,450, $9,300 and $24,400 respectively ($43,200), as recommended by
staff.
By consent agenda, Mr. Hare moved for approval of the Committee’s recommendation,
seconded by Mrs. Williams and carried by a roll call vote of seven (7) yes (Dixon, Lynn, Slavin,
Williams, Hare, Hutchison, and Bonar), one (1) no (Perza), and one (1) absent (Anderson).
Rate Classification/Tariff Amendment for Churches
During the Utility Committee meeting held on September 23, 2013, members reviewed a request
from the Presbyterian Church of Dover (the Church) to consider a change in tariff language to have
the wording “or have instrument rated metering” removed from the C/C1 (Small Commercial)
classification description. Members recommended that this matter be referred back to staff to
determine, if the requested change were granted, based on a possible amendment to the tariff that
would eliminate the phrase “or have instrument rated metering,” what impact it would have on the
City in terms of revenue or other unforeseen possibilities; how many customers would be impacted
(including other non-profits, churches, commercial customers, etc.); and, historically, how similar
changes had been made in the past, for a report back to the Utility Committee by no later than their
meeting scheduled for October 28, 2013. Council accepted the Committee’s recommendation during
their meeting held on October 14, 2013.
The matter was tabled by members during the Utility Committee meeting held on October 28, 2013.
Mr. Scott Koenig, City Manager, advised members that staff had been working with the Presbyterian
Church of Dover regarding their request to amend the tariff language. He noted that staff had
examined the billing system and estimated that making this amendment could change the City’s tariff
revenue estimates by $75,000 - $125,000 per year, based on the type of classification and amount
of usage. He indicated that staff did not recommend amending the tariff since it was believed that
there would be unintended consequences and there was concern in regard to the revenue projection
in the five (5) year plan. Staff had been trying to work with the Green Energy Grant application and
steering the Church toward filing an application under energy efficiency that would allow them to
replace their electric service and metering, reduce the size of the service, and be placed in a
classification that does not have the demand charge since their load profile would allow them to fit
into a smaller classification if the metering were changed. Mr. Koenig stated that the last estimate
he received from Mr. Gary Patterson, Secretary of the Trustees of the Presbyterian Church of Dover,
regarding changing the meter ranged from roughly $900 to $4,000. Staff estimated that it could cost
as much as $5,000 to make this change; however, staff believed that this would be a more viable
alternative for meeting the need of the Church to reduce its overall energy budget and costs, while
still maintaining the integrity of the tariffs.
Staff recommended that no action be taken on amending the current electric rate tariffs and that staff
be directed to assist the Presbyterian Church of Dover with a Green Energy Grant Application to
facilitate energy efficiency within the City’s electric system.
Page 16
CITY COUNCIL MEETING OF NOVEMBER 25, 2013 PAGE 13
Mr. Slavin noted that the matter had been tabled two (2) weeks ago to allow additional
communication with the Church and inquired if this had taken place. Mr. Koenig stated that he had
been attempting to get a copy of the application for the Church to fill out or for the City to fill out
on their behalf, but there had been no additional conversation.
Mr. Slavin noted that the Committee’s recommendation was to have communication before returning
to this item.
In response to Mr. Hutchison, Mr. Koenig stated that no other similar requests had been received.
Mr. Perza stated his recollection that the Committee had considered this matter two (2) months ago,
the Church was represented at that time, and the matter was tabled. He recalled that a Church
representative was unable to attend the previous meeting; therefore, the matter was tabled. It was
his feeling that the burden should be on the applicant to come to the City to work out the
arrangements rather than on the City to reach out to them. He noted that if the Church needed
assistance in applying for the Green Energy grant, this matter could be approved and the application
process could commence.
Mr. Koenig stated that staff had committed to working with the Church to provide assistance with
a grant application.
The Committee made no recommendation on this matter.
During the Council Meeting, Mr. Koenig advised members that he met with representatives of the
Presbyterian Church and reviewed the draft Energy Efficiency Grant for the replacement of the
metering at their location. He stated that the Church had obtained a local contractor to conduct the
work and were in the process of preparing an application to submit to the City. He indicated that
staff would review the application once it is received and it was anticipated that the application
would be approved in the next few weeks. Mr. Koenig noted that the Church would be able to
proceed with the metering replacement and accomplish the same goals without amending the tariff.
Based on further discussions with staff, he stated that they continue to feel that the tariff is
appropriate and that any amendment may have unintended consequences. Staff maintained their
recommendation that no action be taken on the tariff amendment. Mr. Koenig explained that the
Church was interested in reducing their electric bill and that they seemed to have been pleased with
the application since it would accomplish the goal they were originally seeking.
Council took no further action.
Temporary Suspension of Acceptance of Solar Applications - Green Energy Fund
Mr. Scott Koenig, City Manager, advised members that the City had been contacted by
Mr. Scott Lynch, the Energy Services Manager for the Delaware Municipal Electric
Corporation (DEMEC), which administers the Green Energy Fund Program for the City of Dover.
He noted that this program offers incentives and grants to applicants for photovoltaic systems, solar
water heaters, solar water heating integrated into radiant heating, small wind turbines, fuel cells, and
geothermal heat pump systems. He stated that the solar photovoltaic systems were one (1) of the
Page 17
CITY COUNCIL MEETING OF NOVEMBER 25, 2013 PAGE 14
most common grant requests for the City’s program. Mr. Koenig stated that, due to proposed
changes in the incentives offered by the State of Delaware and at Mr. Lynch’s request, staff
recommended a temporary suspension of applications to the Green Energy Fund Program for solar
photovoltaic systems until the impact of proposed changes could be determined. Suspension of the
program would be a preemptive action to prevent a mass of applications being received due to
concerns about the potential changes. Staff, with the assistance of DEMEC, would be evaluating
the potential impact of the changes and would bring forth recommendations in the future.
Mr. Koenig noted that Mr. Lynch had not articulated the exact changes being proposed; however,
his concern was that if this measure were not taken, a flood of applications could be received because
the City’s program could be considered “rich” compared to the State. Mr. Koenig expected that this
matter would be brought back to the Committee within the next three (3) months and noted that not
many applications had been received recently.
The Committee recommended acceptance of staff’s recommendation to temporarily suspend solar
photovoltaic applications to the City and Green Energy fund.
By consent agenda, Mr. Hare moved for approval of the Committee’s recommendation,
seconded by Mrs. Williams and carried by a roll call vote of seven (7) yes (Dixon, Lynn, Slavin,
Williams, Hare, Hutchison, and Bonar), one (1) no (Perza), and one (1) absent (Anderson).
TEA/NAES Report (August and September)
The TEA/NAES Monthly Reports for August and September were provided to members to enable
them to monitor electric sales and revenues received, which will provide a better understanding of
any fluctuations that occur and allow the opportunity to make improvements if deemed necessary.
Mr. Scott Koenig, City Manager, advised members that the margins had tightened up considerably
with the new budget figures and that the numbers were being monitored closely month to month.
Referring to Page 10 of the August report, under Power Supply, PJM - ARR, Transmission, and
Fees, he noted that this number was not running in the City’s favor and that staff was concerned
about PJM charges. He informed members that some funds had been reallocated as the City moved
into the current budget year and this was impacting the City’s variances. Mr. Koenig stated that
The Energy Authority (TEA), the City’s energy provider, was trying to understand all the changes
in order to communicate them effectively to staff. Mr. Koenig anticipated that staff would return to
the Committee to articulate these charges and it was likely that someone from TEA would be present
to explain in detail how they were being assessed and how they would impact the City. He noted
that all other budget items seemed to be tracking appropriately; however, these charges were higher
than anticipated and were a “red flag” to staff.
Responding to Mrs. Williams regarding whether TEA had attempted to explain this to staff already,
Mr. Koenig stated that TEA had been working with PJM to understand what the charges were and
that this was being discussed during monthly meetings. TEA indicated their belief that they had
found an error of approximately $11,000 in the charges; however, the City was hoping for an error
in the magnitude of approximately ten times this amount. He explained that this was not an easy
formula to understand; therefore, it was his opinion that the professionals that handle these matters
regularly should come to brief Council on the charges.
Page 18
CITY COUNCIL MEETING OF NOVEMBER 25, 2013 PAGE 15
Mrs. Williams stated her understanding that it was unknown whether the problem was with PJM or
the formula. Mr. Koenig responded that costs that were previously assigned to power producers had
been reassigned to those who purchase power; therefore, the City was bearing larger costs than
originally anticipated when the budget was developed last year.
Responding to Mrs. Williams regarding whether PJM had provided notification of these changes,
Mrs. Donna Mitchell, Controller/Treasurer stated that neither TEA nor City staff were aware of the
changes. Mr. Koenig explained that PJM had made a change in the method of calculating cost
allocations during the last six (6) months that was now affecting the City.
Mrs. Mitchell explained that the Delaware Municipal Electric Corporation (DEMEC) was
experiencing the same issue and was attempting to get answers from PJM.
UPDATES
Green Energy Funding and Programming
Members were provided information on this item.
National Pollution Discharge Elimination System (NPDES) Municipal Separate Storm Sewer
Systems (MS4) Permit
No update was provided for this item.
Calpine Energy Center
No update was provided for this item.
Dover Sun Park
Members were provided information on this item.
Garrison Oak Technical Park Project
No update was provided for this item.
The Committee recommended acceptance of the updates as presented.
By consent agenda, Mr. Hare moved for approval of the Committee’s recommendation,
seconded by Mrs. Williams and carried by a roll call vote of seven (7) yes (Dixon, Lynn, Slavin,
Williams, Hare, Hutchison, and Bonar), one (1) no (Perza), and one (1) absent (Anderson).
Mrs. Williams moved for acceptance of the Utility Committee Report, seconded by Mr. Slavin
and unanimously carried (Anderson absent).
LEGISLATIVE, FINANCE, AND ADMINISTRATION COMMITTEE REPORT -
NOVEMBER 12, 2013
The Legislative, Finance, and Administration Committee met on November 12, 2013 with Chairman
Lynn presiding.
Page 19
CITY COUNCIL MEETING OF NOVEMBER 25, 2013 PAGE 16
“Safe Whistles” - National Recreation and Park Association Recommended Guidelines for
Credentialing Volunteers (Background Screening for Youth Coaches and Sports Officials for
All City Recreation Offerings) (Lynn and Slavin)
During the Legislative, Finance, and Administration Committee meeting held on September 9, 2013,
members discussed the issue of background checks for Parks and Recreation volunteers working
with youth and members recommended that staff, specifically Mrs. Ann Marie Townshend, Director
of Planning and Community Development, and Mrs. Kim Hawkins, Human Resources Director, be
directed to review the National Recreation and Park Association Recommended Guidelines to
conduct an analysis and formulate a recommendation regarding the scope and depth of the
background checks that should be required, the cost and how it would be addressed, the period of
time the background check would remain valid, and some type of roll-out implementation strategy
to be brought back to the Committee within one (1) month for their review and recommendation to
City Council. City Council approved the Committee’s recommendation during their meeting held
on September 23, 2013.
During the Committee meeting held on November 12, 2013, Mrs. Townshend advised members that
the Parks and Recreation staff surveyed other recreation providers in Delaware to find out how they
address the issue of background checks for youth coaches and other volunteers for youth activities.
She reviewed the “Background Check Comparison Results” table previously provided to members
and noted that all of the organizations contacted require background checks for youth coaches and
other volunteers who work in youth activities. The costs for these background checks vary
depending on the entity that performs the checks. In all cases, the organization providing the
recreation program pays the cost of the background check.
Mrs. Townshend indicated that the Human Resources Department also performed some research and
contacted the City’s insurance carrier for their input. She reviewed the “Parks and Recreation Sports
Programs – Coaching and Youth Protection” information from Travelers Insurance which was
previously provided to members. She explained that Travelers had provided this information to the
City in the past and recommended implementation; however, it was deferred for budgetary reasons.
Travelers also included contact information for IntelliCorp, a nationwide provider of background
checks with whom Travelers has a relationship. Mrs. Townshend stated that the Criminal Search
Bundle provided by IntelliCorp includes: 1) Social Security Number Verification/Address History
Trace; 2) Multistate (Nationwide) Criminal SuperSearch; 3) Nationwide Sex Offender Registry;
4) Government Sanctions; and 5) Single County Search Recommendations. The cost per subject for
the background check ranges from $9.95 to $29.95, depending on the number of single county search
recommendations (ranges from one (1) to unlimited).
Mrs. Townshend explained that, using the assumption that the Parks and Recreation Department has
50 youth volunteers per year and the most costly of the background check options provided by
IntelliCorp is selected, the cost would be approximately $1,500 per year. If this were extended to
contractors, such as fitness instructors or arts and craft contractors, this cost may be a little higher.
She expressed her opinion that the service provided by IntelliCorp seemed very thorough and was
comparable to the costs paid by the organizations that were surveyed.
Page 20
CITY COUNCIL MEETING OF NOVEMBER 25, 2013 PAGE 17
Mrs. Townshend explained that the IntelliCorp system would allow City staff access to enter the
search information and, subsequently, receive the search results. She stated that she had begun
working with staff to implement the background checks for volunteers, since they were in the
process of recruiting for coaches for the upcoming basketball season.
Mrs. Townshend noted the budget estimate provided did not include extending the requirement of
background checks to sports officials. Of the organizations surveyed who contract with outside
organizations for sports officials, only the City of Harrington indicated that officials are required to
have background checks, and these are provided under a national organization that oversees their
youth soccer and football programs. She stated that officials are typically not alone with the youth
and do not spend as much time with them; therefore, staff did not believe that the need for
background check was as strong in this area. If City Council wished to extend the requirement to
sports officials, it could be done; however, she noted that it would take more time to implement,
since staff would need to work with the organizations that provide the officials, and would also
increase the cost of providing background checks. If Council wished to do so, staff would work with
the officiating organizations to build the requirement into the City’s contracts with them.
Staff recommended that background checks be performed for all Parks and Recreation volunteers
and contractors who will be working directly with youth.
Responding to Mr. Lynn, Mrs. Townshend confirmed that $29.95 was the cap for unlimited county
searches, and explained that staff used the cap to calculate the cost estimate at $30 per person for
50 people.
In response to Mr. Hare, Mrs. Townshend stated that the City pays the organization that provides the
officials and would probably not be able to obtain a letter from the organization because they do not
currently require background checks.
Mr. Hare questioned if the City would request a nationwide background check on each individual
or whether the City of Dover Police Department could perform a search in Delaware. Responding,
Mrs. Townshend explained that it would be best to use a consistent method for all individuals. She
also stated that some of the organizations surveyed who utilize local police departments indicated
that this becomes a burden on the police department and a diversion of their staff time, especially
at times during the year when there is an influx of volunteers. She expressed her opinion that the
price and service provided by IntelliCorp was a good deal.
Mr. Slavin noted that people often move from the locations where they commit crimes, especially
when there is a stigma attached to the crime (i.e., sex offenders and child predators); therefore,
nationwide background checks should be performed for City-related programs. In response,
Mrs. Townshend stated that the City of Newark only performs State level background checks but that
IntelliCorp background checks would be nationwide.
Mr. Slavin shared that he is an official for two (2) different sports and, although officials may not
spend as much time off the field or court with the youth, they serve in an authority position. He
stated that the City has an obligation as a provider of recreation opportunities to ensure that the entire
environment is safe, including everyone involved in providing services to constituents. He indicated
Page 21
CITY COUNCIL MEETING OF NOVEMBER 25, 2013 PAGE 18
that if the City establishes this requirement, it would be incumbent upon the officiating groups to
then do the background check. He stated that all of the officiating groups are aware that this is
becoming a nationwide trend but are waiting for a mandatory requirement before proceeding. He
expressed his hope that the Committee would recommend a requirement for background checks for
all volunteers as well as contractors, meaning the officials.
Mrs. Townshend explained that adult sports would not be included in this requirement and softball
leagues would be excluded because softball is considered to be an adult sport and participants
between the ages of 16 and 18 are required to obtain a parent signature.
Responding to Mr. Hare, Mrs. Townshend confirmed that the City would either charge the officiating
organizations for each background check completed by the City or require the organizations to
complete a nationwide search for each official. She stated that the results of each background check
would be reviewed by staff, and that she and the Human Resources Department would make final
determinations.
Mrs. Williams reminded members that all childcare workers in the State of Delaware are vigorously
screened and are provided a letter by the State Secretary as to whether they can or cannot work with
children. She stated that some of these individuals will subcontract with the City of Dover, and
suggested that the City accept the letter provided by the State Secretary in lieu of performing an
additional background check.
In addressing some of the concerns relayed by Mr. Hare, Mr. Slavin stated that the National
Recreation and Park Association recommendations include structured guidelines for specific waiting
periods related to offenses and suggested that staff review and adopt these guidelines.
In response to Mr. Slavin, Mrs. Townshend stated that the survey results indicated that most
organizations perform the checks every three (3) years.
Mr. Slavin stated that while the City may select a certain provider to perform the background checks,
staff may also want to consider reciprocity of checks performed by other organizations which are
comparable to those performed by the City. He noted that the officiating organizations would pass
the cost on to the officials and, since many officials may be screened for their jobs, a reciprocity
agreement would save the officials $29.95.
Responding to Mr. Slavin, Mrs. Townshend confirmed that the City would use a third party to
perform the background check and that there would be no record keeping of the content of the check
by the City of Dover, except for documentation related to searches which result in an individual
being prohibited from participating in a City program. Mr. Slavin suggested that an appeal process
be established. In addition, he wished to ensure that individuals understand that the City would not
be collecting files on people.
Mr. Lynn suggested that, in drafting the language that would include crimes that would exclude
individuals from employment and volunteering, staff review the Delaware Code pertaining to the
offenses which preclude an individual from becoming a teacher.
Page 22
CITY COUNCIL MEETING OF NOVEMBER 25, 2013 PAGE 19
The Committee recommended that background checks be performed for all Parks and Recreation
volunteers and contractors, including officials, who will be working directly with youth, every
three (3) years, and that staff implement a staggered approach that would require compliance by
officials by a certain date in 2014.
By consent agenda, Mr. Hare moved for approval of the Committee’s recommendation,
seconded by Mrs. Williams and carried by a roll call vote of seven (7) yes (Dixon, Lynn, Slavin,
Williams, Hare, Hutchison, and Bonar), one (1) no (Perza), and one (1) absent (Anderson).
Request for Economic Inclusion Study (Clayton Hammond)
Mr. Clayton Hammond II, 505 Troon Road, Delmarva Black Chamber of Commerce Chairman,
reviewed a request for funding for the Delaware State University Center for Economic Development
and Trade to conduct an economic inclusion study for the City of Dover. He explained that he had
been an economic development professional for approximately 30 years, working in various public
sector, non-profit sector, and private sector positions, and that during that time, it has become clear
that the economic development activities in the City of Dover are very limited. Mr. Hammond stated
that historically, economic development throughout the country has been used to address a myriad
of issues; however, the current economic activities in the City of Dover were limited to infrastructure
development, the Garrison Tract, and commercial revitalization related to the Downtown Dover
Partnership (DDP). He stated that there are certain parts of the Dover community which have
historically been detached from the economy and expressed his opinion that an economic inclusion
study, similar to the “Inclusion in the Workforce” study conducted by the City of Pittsburgh, would
examine the issues and impediments and provide recommendations for increasing the involvement
of parts of the Dover community, specifically the African American community, in the economy.
Mr. Hammond emphasized that participation from all sectors of the community, whether through
entrepreneurship, workforce development, or jobs, is important for the long-term viability of a
vibrant economy.
Mr. Hammond noted that he had lived in Dover during several different periods throughout his life
and noticed that the area around Queen, Kirkwood, and New Streets had never changed. It was his
understanding that there had been different entities addressing economic development downtown;
however, this specific area had been neglected in terms of economic development activity. He
explained that the lack of economic activity in this area has social costs, including public safety
related issues and the detachment of residents. He felt that an economic inclusion study would
provide recommendations for involving all sectors of the community in the economic vitality and
long-term economic development of the City of Dover.
Referencing the request for funding detailed in the email previously provided to members,
Mr. Hammond explained that he had recently spoken to Dr. Michael Casson, Director for the
Delaware State University Center for Economic Development and Trade, and the City’s cost for the
study had increased to $6,000 because an additional graduate assistant would be required. He
reiterated that this would be a simple study to examine issues that relate to impediments,
opportunities, and resources that relate to the historic African American community in the City of
Dover becoming more economically viable.
Page 23
CITY COUNCIL MEETING OF NOVEMBER 25, 2013 PAGE 20
Mr. Hare expressed his agreement for the need to address the problems noted but recommended that
this may be a good project for the staff of the City’s Economic Development Office. Responding,
Mr. Hammond stated that, based on conversations with Mr. William Neaton, Economic
Development Manager, and Mr. Ed Perez, Downtown Coordinator, this matter did not seem to be
part of the City’s short or long-term economic development strategy.
In response to Mr. Slavin, Mr. Hammond confirmed that the request was for funding in the amount
of $6,000 for the Delaware State University Center for Economic Development and Trade to
facilitate the study.
Responding to Mr. Lynn, Mr. Hammond stated that Dr. Casson had indicated that the Center for
Economic Development and Trade would be willing to participate in the study and the initial cost
would be approximately $24,000. Delaware State University has a grant from the U.S. Economic
Development Administration which will cover the majority of the cost and that the $6,000 would
pay for two (2) graduate interns to work on the project. Mr. Hammond was uncertain why the cost
had increased from $4,000 to $6,000 and had anticipated that Dr. Casson would be present to answer
questions.
Mr. Lynn questioned whether the Center for Economic Development and Trade had experience
conducting studies of this type. Mr. Hammond stated that the Center had conducted a study for the
City of Dover regarding Garrison Tract projections and that Dr. Casson and Mr. Neaton were
discussing the possibility of conducting a future study as well. He was uncertain whether the Center
had any experience with economic inclusion studies but indicated that it was involved in studies
regarding manufacturing in the State of Delaware and had conducted significant research in different
areas. He confirmed that Dr. Casson would be the faculty member responsible for the study.
Mr. Lynn noted that members had received email correspondence from Ms. Deb Brown, dated
November 12, 2013, (as on file in the City Clerk’s Office) regarding this matter.
In response to Mr. Slavin, Mr. Hammond stated that Dr. Casson had indicated being able to begin
the study within the next 60 days but was uncertain how long it would take to complete the study.
The Committee recommended approval of the request to fund the economic inclusion study in the
amount of $6,000.
Mr. Lynn requested Mr. Hammond to arrange for Dr. Casson to attend the City Council meeting
scheduled for November 25, 2013 when this matter was scheduled for consideration.
In response to Mr. Hare, Mr. Lynn requested that the City Clerk’s Office arrange for the staff of the
City’s Economic Development Office to attend.
During the Council Meeting, Mr. Hare questioned what action the City had taken thus far to review
the economic development in the area mentioned. Mr. Bill Neaton, Director of Economic
Development, introduced Mr. Ed Perez, Downtown Coordinator, and referred to the letter received
by Mr. Lynn from Mr. Hammond. He noted that several of the issues included in the inclusion study
conducted by Pittsburgh had been addressed by the City of Dover Economic Development Office.
Page 24
CITY COUNCIL MEETING OF NOVEMBER 25, 2013 PAGE 21
Although he was not opposed to an economic inclusion study, he wanted members to be aware that
staff was already in the process of implementing several of those suggestions. Referring to the
“infrastructure spending” that was mentioned in the inclusion study, Mr. Neaton explained the
importance of infrastructure spending. He advised members that the infrastructure spending being
done in the City, specifically at the Garrison Tract, would impact all segments of the economy and
all peoples within the City of Dover. As the City improves its infrastructure (specifically at the
Garrison Tract), he stated that people in the City would be employed to work on the infrastructure
improvement, regardless of race.
In addition, Mr. Neaton referred to the item included in the inclusion study for “Generating Demand
of Diverse Employees” and advised members that the Economic Development Office had been
working on workforce development and engaging in all the activities. He explained that the City had
partnered with Delaware Technical and Community College, the Service Core of Retired Executives
(SCORE), the YWCA, Small Business Administration, Delaware Economic Development Office,
Chamber of Commerce, and the Kent County Economic Development Office to improve the job
opportunities for all of the people in Kent County.
Mr. Neaton noted that another recommendation included in the Pittsburgh Study was to help African
Americans overcome systemic barriers to employment by investing in youth workforce internship
programs. At Mr. Neaton’s request, Mr. Perez advised members that within the last year alone, in
an effort to support both existing and potential businesses throughout the downtown district, there
were nine (9) business development workshops held that provided information on marketing, social
media, business planning, economic e-commerce, access to funding, and credit awareness. He stated
that during 2012 there were 16 businesses within the downtown area, three (3) of which were
African American owned and, in 2013 there were nine (9) new businesses, seven (7) of which were
owned by minorities and four (4) of which were African American owned businesses. In addition,
he stated that there were 43 referrals made from 2011 through 2012 for minorities needing assistance
with business plan development. He explained that these were just a few of the initiatives instituted
as a result of the USDA Grant to assist the community and the downtown district. Mr. Perez stated
that a Request for Proposals (RFP) was submitted to the Community Development Office for
economic development and a grant was received to provide part-time employment for the youth of
the community. There were 20 youth employed for approximately nine (9) months, all of whom
were African American students.
Mr. Neaton referred to the recommendation included in the Pittsburgh Study to generate demand for
diverse employees by supporting entrepreneurship programs and capacity building programs for
minority and women business enterprises. He stated that the City works closely with the YWCA to
provide business development plans for a cross-section of all potential entrepreneurs, regardless of
race. He assured members that the YWCA had done a great job in counseling several diverse people
who wish to open businesses.
Mr. Neaton explained that the letter indicated that the City never develops initiatives that target
issues other than New, Kirkwood, and Queen Streets. He reminded members that the Downtown
Dover Partnership (DDP) and Dover Economic Development Office partnered with the National
Council on Agricultural Life and Labor Research (NCALL), United Way, City of Dover Police
Department, Greater Kent Committee, Interfaith Mission, Interdenominational Alliance, Bayhealth,
Page 25
CITY COUNCIL MEETING OF NOVEMBER 25, 2013 PAGE 22
and Wesley College and were awarded a $90,000 planning grant from Wells Fargo. This planning
grant was for an area that includes South Street (south of Bayhealth) to Walker Road and State
Street to Salisbury Road. He stated that the study is designed for the following reasons: to discuss
land use, home ownership, security and safety, community building, crime data, and the economic
development issues that are important to the area. Although he was not suggesting that the economic
inclusion study would be a duplication, Mr. Neaton wanted members to know that the City’s
Economic Development Office was already doing many of the actions included in the inclusion
study; therefore, members should decide if there were a need for additional studies at the cost of
$6,000.
Responding to Mr. Hare, Mr. Hammond explained that although there had been some efforts to
address some of the issues in a larger perspective, the African American community had discovered
that if the specific needs of the community are not targeted, they tend to get “lost.” Mr. Hammond
stated that their concern was, and always has been, how their needs are addressed. He noted that
there were approximately 28 members serving on the DDP and only two (2) are African Americans.
He requested that there be a process and study to review what those desperate needs are for the
African American community.
With regard to the grants and initiatives, Mr. Hammond stated that the DDP’s target area had not
always been the historic black community in the City and they had not been focused on work force
development or other issues related to the economic viability of the African American community.
Referring to the Pittsburgh Study, he suggested that the study proposed for the City would be specific
and tailored to address the issues that relate to what is important to the African American community
in the City of Dover. Mr. Hammond advised members that the black unemployment rate was almost
double the unemployment rate of others. He felt sure that there were issues that are germane just to
the African American community that need the City’s attention and consideration. Mr. Hammond
stated that there were very significant factors needed to be addressed.
Dr. Casson felt that the issue involved identifying some of the economic development challenges that
affect the African American community and stated that the Center for Economic Development at
Delaware State University had the capacity to conduct such a study. He suggested that the question
before City Council was to determine if they felt the study was necessary and to determine what
economic development opportunities exist in the African American community and what actions
could be taken to provide improvements.
Responding to Mr. Lynn, Dr. Casson confirmed that he originally estimated a cost of $4,000 to
conduct the study, estimating the use of only one graduate student to support the project, and that
it was increased to $6,000 to acquire additional support since the project could go beyond the six (6)
to eight (8) month time frame for completion. Considering the importance of completing the study,
he felt that the additional graduate student would be necessary, for a total expense of $6,000.
Mr. Slavin moved for approval of the Committee’s recommendation to approve the request
to fund the Economic Inclusion Study in the amount of $6,000. The motion was seconded by
Mr. Hare and carried by a roll call vote of seven (7) yes (Dixon, Lynn, Slavin, Williams, Hare,
Hutchison, and Bonar), one (1) no (Perza), and one (1) absent (Anderson).
Page 26
CITY COUNCIL MEETING OF NOVEMBER 25, 2013 PAGE 23
Request for Property Revaluation - Wild Meadows
Mr. Fred Neil, 521 Weaver Drive, President of the Wild Meadows Home Owners Association, read
the following statement into the record:
I wish to thank you for permitting me to testify on this subject. I have written to each
member of the City Council listing the reasons why our community should either be
reevaluated prior to the 2015 evaluation period designated by law or permitted to
have a reassessment based on conditions not previously in evidence.
According to City Assessor Cheryl Russell, “All property shall be valued as to its
status; as of its ownership; as of its current market value as of the January 1
assessment date and shall reflect fair market value.”
I am very sensitive to the tax base the city needs to properly provide services and
protection to its citizens because of my role as Press Officer for a Baltimore Mayor.
I can rightfully brag on the impact of the 55 Plus Wild Meadows Residents on the
quality of life in Dover and Kent County. Most of the City Council has seen those
efforts in the email and printed news letters we provide. However, that does not pay
the city's Bills.
As Miss Russell pointed out, “The City as a whole was reassessed in 2010 and
sale/income/cost information from 2007; 2008; and 2009 was used to determine
values for ALL of the properties within the City limits.” ... and there is the hub of
my request for new assessments before 2015. Reassessment requests in April 2014
of our current assessment should be based on changed conditions, or apply a
community wide decrease in current assessments.
The evidence to do so is based on:
• Fair Market value - currently it is no longer fair.
• Evidence readily available to you is the original purchase price of
the homes versus the sale prices of the homes in the period from
2010-2012. Not reported is the long, long time period to sell a
home. I was recently informed by Mr. Paul McDonald, Vice
President of the Wild Meadows Home Owners Association, and
Mr. Bob Schmidt, Wild Meadows Home Owners Association
Board Member and responsible for the Associations email
newsletter, that the home that he originally paid $130,000 for and
added $20,000 worth of improvements to, is assessed for $119,000
and a home with the same identical space/model recently sold for
$84,000.
• Conditions that did not exist in the 2007- 2009 time period, the
Calpine Plant and The Fire Fly Festival.
Page 27
CITY COUNCIL MEETING OF NOVEMBER 25, 2013 PAGE 24
Calpine and Firefly are unique to a very specific area of homes including the Wild
Meadows Community.
While it is easy to say, “Let us wait until 2015”, but the law says Fair Market value.
Wild Meadows a 55 Plus community is carrying an extra and unfair burden because
this is not 2010.
I would also like to point out the Calpine Power plant and the Fire Fly Festival will
add money to the City coffers which may more than off-set the drop in a lower tax
and fairer assessment of our properties.
I will also point out, while the proposed power plant on the old Chrysler property in
Newark drew many protestors and negative publicity, the City of Dover was not
subjected to that. Please do not take the lack of a protest movement as lack of
discontent with having the power plant literally in our back yard or the accepting the
inconvenience of The Fire Fly Festival. Let's just say, the residents of the Wild
Meadows Community are responsible citizens.
I hope we are not punished for being so.
Mr. Neil also complimented the City of Dover, members of Council, Red Frog Productions, and
Dover Downs in regard to the amenable relationship regarding the Firefly Music Festival. He
expressed his opinion that the festival is an essential benefit to the health of the community,
explaining that he had shared his views with his community and believes that this is one (1) of the
reasons that there had not been more protest from the residents.
Members were provided information from Ms. Cheryl Russell, Tax Assessor, regarding the early
reassessment request from Wild Meadows, including a memo from Ms. Russell dated
November 12, 2013, Section 102-1 of the Dover Code, and an opinion from Mr. William Pepper,
Deputy City Solicitor. Ms. Russell reviewed the memo and stated that, in accordance with the
opinion provided by Mr. Pepper, staff recommended denial of the request for early reassessment as
submitted by Wild Meadows.
Ms. Russell stated that the City receives numerous appeals every year on the basis that the property
is not currently worth the assessed value. She explained that each appeal is considered by the Board
of Assessment Appeals, which confirms for each appellant that the City has to use 2007 - 2009 sales
information for residential properties and 2007 - 2009 income and expense information for
commercial properties to maintain uniformity and fairness throughout the City. The City’s
reassessments are revenue neutral; therefore, if the values increased as a result of reassessment, the
tax rate would be rolled back down to keep the tax revenue amount the same. She was uncertain
how the City could maintain tax revenue neutrality if portions of the City were reassessed at different
times. She stated that the Tax Office was currently preparing for the 2015 revaluation.
Page 28
CITY COUNCIL MEETING OF NOVEMBER 25, 2013 PAGE 25
Mr. Hare questioned why the City funds a reassessment if the tax rate does not change as a result.
Responding, Ms. Russell explained that the information is valuable to ensure that the tax burden is
placed on the appropriate properties when the fair market value changes and that values are viable
for homeowners in the event of catastrophe.
In response to Mr. Hare, Ms. Russell clarified that a retrospective appraisal is required for an
assessment appeal.
Ms. Russell stated that the cost for the previous assessment was approximately $785,000; however,
staff would not need to conduct a comprehensive revaluation in 2015 since they had been diligent
in reviewing the properties to verify that the characteristics have not changed, so the cost will be
approximately $100,000. The consultant will only need to do sales ratio studies, changes to the land
tables, and ensure that the neighborhoods are aligned.
Responding to Mr. Slavin, Ms. Russell stated that if the reassessment appeal were approved, staff
would need to draft legislation for consideration and approval by the Delaware General Assembly
to change the City’s Charter. She noted that many municipalities do not include language regarding
the scheduling of tax valuation and assessment within their Charters, with the exception of Milford,
which she believed was on a ten-year cyclical schedule. She explained that changing the schedule
to every two (2) or (3) years may not address the problem because it depends on the market. She
reminded members that the current assessments are below the current market value; however, that
situation could reverse, and valuations require a great deal of time and money.
Mr. Slavin noted that the appeal process is time consuming for staff and questioned whether it would
be advantageous to allow for a class action type of appeal to be filed by property owners from a
particular neighborhood, since individual assessments can be adjusted based on appeals and the
revenue neutrality would be waived. Responding, Ms. Russell reminded members that the
information considered during an appeal must be based on retroactive, not current market values.
Mr. Lynn noted that the five (5) year increment was reasonable to account for normal economic
turbulence; however, did not account for the novel situations that Wild Meadows has been affected
by, including the construction of the City-sponsored Calpine power plant. He felt that there were
no other neighborhoods facing the same types of issues as Wild Meadows. Concurring with
Mr. Slavin, he suggested addressing all of the properties in Wild Meadows as one (1) appeal. He
stated that the owners probably should have appealed in 2010; however, the Calpine plant had not
fully come to fruition as it did in 2011 and 2012. He expressed his support for the request and stated
that a Charter change would be required in order to provide an early reassessment for Wild
Meadows.
Mr. Hare stated his support for the filing of a community-wide appeal within the current guidelines;
however, he expressed concern with fairness to other communities and questioned if there would be
certain circumstances which would allow for this type of appeal.
Page 29
CITY COUNCIL MEETING OF NOVEMBER 25, 2013 PAGE 26
Ms. Russell stated that the only appeals filed by property owners from Wild Meadows were four (4)
which were filed in 2010. In response to Mr. Lynn, she explained that appeals can be submitted
every April with documentation for the 2010 value. She relayed her concern with allowing the
revaluation of communities which would lead to communities submitting appeals every year and the
possibility of revaluing the City in pieces.
In response to Mr. Lynn, Ms. Russell stated that she would need to consult the City Solicitor’s Office
to ensure that an appeal could be filed by a community as a group. She confirmed that appeal
hearings were typically scheduled for the end of May and beginning of June each year, to have them
complete prior to approval of the final budget for the following fiscal year.
Mr. Lynn stated that the time frame may be the same for a Charter change to be enacted as it would
take for an appeal hearing next year. He stated that the sticking point could be how viable Calpine
was in 2007, 2008 and 2009.
Ms. Russell stated that the current sales would be reflected in the 2015 revaluation. The sales history
for homes in Wild Meadows showed that from 2007 - 2009 sale prices ranged from $96,000 to
$187,000, which may have been first time purchases from the developer. She expressed her
understanding that the sales prices since 2010 have decreased, as they have in other parts of the City,
as a result of the status of the market and economy.
Mr. Shevock expressed concern that other communities may request revaluation if it is allowed for
Wild Meadows. Responding, Ms. Russell stated that this would cause a fluctuation in the values
across the City and a loss of uniformity in the timing of the revaluations.
Mr. Hare noted that when an appeal is granted and a property assessment is reduced, it is not revenue
neutral.
Ms. Russell stated that there has been discussion regarding State legislation which will require all
municipalities and counties to perform valuations on a cyclical basis.
Mr. Slavin stated that the assumption seemed to be that this would result in many communities filing
appeals but reminded members that not all would be successful since there would have to be a
compelling reason for a community to come forward, such as the construction of the Calpine plant.
He indicated that the revenue neutral provision was a preventative against City Council “sneaking”
a tax increase through. If the City wants to adjust the tax rate, it must be done separately from the
revaluation.
In response to Mr. Slavin, Ms. Russell confirmed that when an individual is reassessed based on an
appeal, the City does not establish a new tax rate for them, so there is no revenue neutrality on
appeals.
Responding to Mrs. Williams, Mrs. McDowell, City Clerk, confirmed that a request for a Charter
change requires approval by two-thirds of all members elected to each House of the General
Assembly.
Page 30
CITY COUNCIL MEETING OF NOVEMBER 25, 2013 PAGE 27
Mr. Neil stated that the current prima facie evidence is what the houses are currently selling for
versus what they were purchased for in 2002.
Mr. Hare questioned the type of Charter change that would be required. He suggested that
Section 102-1 of the Code be changed to reflect that the assessment ‘may’ be conducted every five
(5) years, to eliminate the cost of revaluation when it is not necessary.
Clarifying, Mr. Lynn stated that the necessary change would be the extraction of the word “all” from
“true, just, and impartial valuation and assessment of all real property within the city” in Section 47
of the Charter; however, he recommended making an ambiguous motion to pursue the Charter
change necessary to effectuate the intent of the motion and requesting Mr. Pepper to address the
exact change required.
The Committee recommended that the Wild Meadows neighborhood be permitted this request for
reassessment and that the City pursue this change in two (2) ways: 1) by allowing a group appeal on
behalf of the community in April 2014; and 2) by pursuing the Charter change necessary to
effectuate the Committee’s intent and requesting Deputy City Solicitor Pepper to address the
required change.
During the Council meeting, in response to Mr. Perza, Ms. Cheryl Russell, City Assessor, explained
that in April of each year, every property owner in Dover is allowed to go before the Board of
Assessment Appeals and, if not successful at that level, they are afforded the right to go to Superior
Court, which is the next level in the appeal process. It was her understanding that the proposed
amendment (Item #2 of the Committee’s recommendation), would provide a Charter change to allow
evaluations of communities if they came forward. She explained that the Committee included
Item #1 in their recommendation since it was felt that the Charter change, if approved, would not be
finalized in time for the next tax cycle.
Mr. Lynn moved for approval of the Committee’s recommendation, seconded by Mr. Slavin.
Mr. Hutchison reminded members of the memorandum dated November 12, 2013 indicating staff’s
recommendation to deny the request for early reassessment for Wild Meadows. It was also noted
that an additional memorandum dated November 25, 2013 from the City Assessor was provided
(Exhibit #2) indicating staff’s recommendation that the Wild Meadows Community come in as a
whole to appeal to the Board of Assessment Appeals (maybe with a few spokesmen for the
community). If they are not satisfied or successful at this level of appeal, then they could move
forward to Superior Court. It also indicated that staff did not recommend any changes be made to
the City Ordinance or Charter.
In response to Mrs. Williams, Ms. Russell stated that implementation of the Committee
recommendation could become chaotic and result in staff performing piecemeal revaluations
multiple times between prescribed revaluation cycles, depending on whether a community appealed
their valuation on either current conditions or a factor that would cause a change in their value before
the next valuation. Mrs. Williams questioned the need to change a system that had been used for
several years and relayed concern that the possible changes were unknown and that the City would
Page 31
CITY COUNCIL MEETING OF NOVEMBER 25, 2013 PAGE 28
be making such a change just to satisfy a few. Ms. Russell stated that the current level of staffing
would not be able to handle the results of such a change and that there would be a need for additional
staff to conduct the necessary research.
Mr. Hare explained his understanding that the recommendation would have no effect on City staff
since the burden of proof would be on the property owner, who would then be presenting their
findings to the Appeals Board. Responding, Ms. Russell advised members that, as a member of the
International Association of Assessing Officers (IAAO) and being State certified, she is required by
law to conduct the same research that the appellants are conducting. When the issue is brought
before the Appeals Board, although the burden of proof is on the property owner, the City Assessor
must conduct research and provide information, as well a recommendation, for the Board’s review
and consideration of the appeal. She assured members that a lot of work that would be required by
her, as well as the residential technician, to prove that the values are correct.
Regardless of Council’s decision regarding this matter, Mr. Lynn noted that property owners would
be well within their rights to submit 300 appeals to the City. Therefore, he stated that
Mrs. Williams’ concerns regarding the need for additional staffing could be required regardless of
the action taken by City Council on this matter. Responding, Ms. Russell stated that there was sales
information that supports the City’s property values that would be provided to the Appeals Board.
She stated that property owners would be permitted to present whatever information they may want.
Although it would provide a better opportunity for a few property owners to represent the whole
community, they would still be required to go through the correct process and prove the value as of
2010 and, if they were not successful or satisfied at the Appeals Board level, they would have the
right to go before the Superior Court and present the same facts to a judge. To her knowledge, there
was no consideration given to the property currently owned by Calpine in making a determination
of property values for Wild Meadows; however, they used sales information during the analyzed
years that supported the values, as well as other properties within the City limits.
Responding to Mr. Lynn, Ms. Russell stated that if a few individuals came in representing all 300
property owners for the entire Wild Meadows neighborhood, staff would be reviewing the
community as a whole and not individually; however, if there were 18 communities submitting an
appeal, it would become a “nightmare” for staff.
Mrs. Williams stated that although the Calpine project may have been an unknown factor at the time,
those purchasing or leasing property in Wild Meadows would have been advised that their property
would be located adjacent to an industrial and manufacturing production site. Confirming,
Ms. Russell stated that they would have also been made aware of the Dover Downs property.
In response to Mrs. Williams, Ms. Russell stated that the memorandum submitted was as strong as
it was due to fairness and equity issues and was based on their professional organization’s
requirements and rules, as well as the City Charter.
The motion to approve the Committee’s recommendation that the Wild Meadows neighborhood be
permitted their request for reassessment and that the City pursue this change in two (2) ways: 1) by
allowing a group appeal on behalf of the community in April 2014; and 2) by pursuing the Charter
change necessary to effectuate the Committee's intent and requesting Deputy City Solicitor Pepper
Page 32
CITY COUNCIL MEETING OF NOVEMBER 25, 2013 PAGE 29
to address the required change, failed by a roll call vote of five (5) no (Perza, Williams, Hare,
Hutchison, and Bonar), three (3) yes (Dixon, Lynn, and Slavin), and one (1) absent (Anderson).
Mr. Lynn moved for acceptance of the Legislative, Finance, and Administration Committee
Report, seconded by Mr. Hare and unanimously carried (Anderson absent).
EVALUATION OF BIDS - TREE TRIMMING CONTRACT
Mr. Scott Koenig, City Manager, advised members that the Electric Department maintains blanket
contracts with potential contractors to ensure that the bidding rules are adhered to for contractors that
are hired to perform work for the Department, which are priced as a “time and material” contract and
may exceed $25,000 annually. He explained that this proposal is for a tree trimming contract used
to maintain clearance around the city’s overhead electric lines. This is the single most important
maintenance project as it relates to the reliability of the City’s overhead system. Typically, there are
two (2) full-time crews working throughout the system to perform this maintenance. Additionally,
this company has crews available to assist during storm events and the proposal provided included
pricing for these potential events.
Staff recommended awarding a three (3) year (2014, 2015, 2016) Tree Trimming Contract to the low
bidder, Asplundh Tree Experts, with a City option to extend for an additional two (2) years (2017,
2018), for a total of five (5) years. The contract work would be adjusted to stay within the budget
each year (the current budget year was estimated at an expense of $350,000).
Mr. Hare moved for approval of staff’s recommendation, seconded by Mr. Hutchison and
carried by a unanimous roll call vote (Anderson absent).
AMENDMENT TO INTENDED PURCHASES - FUND TO COMBAT VIOLENT CRIME -
FY14 GRANT APPROVED ON SEPTEMBER 23, 2013
Members were reminded that the fund to Combat Violent Crime Program is a new grant program
managed by the Department of Safety and Homeland Security for use by local law enforcement
agencies in connection with initiatives to combat violent felonies pursuant to Section 4201(c) of
Title 11 of the Delaware Code. The first increment of funding was released during FY13; however,
it was uncertain at that point whether the program would be recurring. During the last quarter of
FY13, staff learned that an FY14 grant was anticipated and the amount appropriated ($75,523.53)
was much higher than the previous year’s amount ($46,785.34). As a result, there were not enough
funds budgeted in FY14 for the total amount of the grant, so a budget adjustment would also be
needed to cover the unbudgeted portion.
Police Chief Hosfelt explained that the Police Department was requesting approval to use its grant
allocation from this program, as follows: 1) a portion of the funds will be used to upgrade the duty
weapons for all police officers in the amount of $17,649 and to purchase rifles for supervisors’
vehicles in the amount of $16,067.94; and 2) for the remaining portion, in the amount of $41,806.59,
to be used to target violent crime throughout the city with extra duty overtime patrols and to provide
education to citizens on measures they can take to avoid or cope with violent crime related activities.
Page 33
CITY COUNCIL MEETING OF NOVEMBER 25, 2013 PAGE 30
Chief Hosfelt reminded members that in the original request, the Police Department programed a
portion of the funding for a technology upgrade to provide wireless connectivity for Police vehicles
to the station’s computer systems; however, the State committee that met to review and approve all
of the grant applications for this program did not approve of this intended purchase. As a result, the
funds were diverted on the spot for additional extra duty overtime patrols.
Staff recommended approval of the grant and intended purchases.
Mr. Slavin moved for approval of staff’s recommendation, seconded by Mr. Dixon and carried
by a unanimous roll call vote (Anderson absent).
ELECTION OF OFFICERS - ROBBINS HOSE COMPANY - YEAR 2014 FIRE LINE
OFFICERS
The Fire Line Officers of the Robbins Hose Company are elected annually on the third Monday of
November. Members were provided the results from the November 18, 2013 Robbins Hose
Company Election for consideration as follows:
Fire Chief - Matthew Carey
Deputy Fire Chief - Jack Fortney (unopposed)
First Assistant Fire Chief - David Carey
Second Assistant Fire Chief - Mark Hall (unopposed)
Third Assistant Fire Chief - Carl Troubetaris, Sr. (unopposed)
Fourth Assistant Fire Chief - Duane Reeder (unopposed)
First Fire Line Captain - Ben Smetana (unopposed)
Second Fire Line Captain - William Kelly II
By consent agenda, Mr. Hare moved for acceptance of the Fire Line Officers for Robbins Hose
Company No. 1 for the Year 2014, as submitted. The motion was seconded by Mrs. Williams
and carried by a roll call vote of seven (7) yes (Dixon, Lynn, Slavin, Williams, Hare, Hutchison,
and Bonar), one (1) no (Perza), and one (1) absent (Anderson).
COUNCIL MEMBERS’ ANNOUNCEMENTS
Mr. Hare wished Council President Bonar a happy birthday (December 1st).
Mrs. Williams advised members that she visited the online site for crime detection and felt that it
was very well developed and would be helpful to those concerned about safety. She thanked Police
Chief Hosfelt for making the information available.
Council President Bonar announced that the Tree Lighting Ceremony was scheduled for
December 4th and would be held at Loockerman Way.
Council President Bonar noted his involvement with a couple of complaints to the Police Department
and stated that officers responded promptly and efficiently. He stated that there were some
significant problems in Dover and requested that everyone lock their doors, lock their vehicles, do
not keep packages in vehicles, and be alert to surroundings at all times.
Page 34
CITY COUNCIL MEETING OF NOVEMBER 25, 2013 PAGE 31
Mayor Carey announced that on December 7th there would a “Home for the Holiday” parade down
Loockerman Street at 12:00 noon and invited all to attend the Lighting of the Tree, as previously
mentioned by Council President Bonar. He wished everyone a happy thanksgiving.
Mayor Carey also congratulated the Central Delaware Chamber of Commerce for being designated
as a five (5) star accredited Chamber of Commerce, one of only 79.
By unanimous consent, the meeting adjourned at 8:33 p.m.
TRACI A. McDOWELL
CITY CLERK
All orders, ordinances, and resolutions adopted by City Council during their Regular Meeting of
November 25, 2013, are hereby approved (with the exception of the following motion: Approval of
the Parks, Recreation, and Community Enhancement Committee's recommendation to demolish the
Dover Park Recreation Center and that the City Manager be authorized to earmark the balance of
the construction/demolition project up to $80,000 for future capital improvements, in the City's
future budgets, to Dover Park after a needs assessment is accomplished).
CARLETON E. CAREY, SR.
MAYOR
/TM/jg
S:\AGENDAS-MINUTES-PACKETS\Council-Minutes\2013\11-25-2013.wpd
Exhibits
Exhibit #1 - Resolution No. 2013-26, Abandonment of Street - Harmony Lane
Exhibit #2 - City Assessor Memorandum Dated November 25, 2013
Page 35
EXHIBIT #1
Regular Council Meeting of 11/25/2013
Page 39
EXHIBIT #2
Regular Council Meeting of 11/25/2013
MEMO
TO : City Council
FROM: Cheryl A. Russell, AAS City Assessor
DATE: November 25, 2013
RE : Early Reassessment Request - Wild Meadows
To allow a partial re-valuation of a portion of the City would create inconsistency in how
properties are valued related to how other properties are valued within the City limits.
At this time, all assessments are based on the 2010 base year. Any economic changes (positive
or negative) after January 1 of the base year cannot be used to adjust the assessment. Only
clerical errors; information obtained by building permit or changes in property characteristics
that were missed by the revaluation or done without a permit can cause an assessment change.
However, these changes still must be consistent with the base year. An example is a new
construction built in 2013 would have to be treated as being built within the time period
analyzed for 2010 using the same sales information.
The Charter and Reassessment process works because it defines the valuations of the
properties throughout the City as a whole, so the Roll Back tax can be determined. Determining
the Roll Back Tax Rate, allows us to spread the burden of taxes equitably throughout the City
based on the values as of the base year. If a partial revaluation is done, the tax burden would
not be spread equitably, as some properties would be based on current factors that were not
analyzed during the time period allowed for the base year. If an appellant is successful at any
of the appeal levels, it would need to be based on the 2010 year and adjustments could be
made without a Roll Back Tax being determined, because essentially, these new numbers
should reflect the base year.
The City Ordinance and Charter protect all property owners in the City so that there is fairness
in all areas of the City as to how their values were calculated .... as of a given date. Potentially,
could these proposed changes to the Charter positively impact the City if the Market begins to
rise after the next revaluation but before the next cyclical revaluation? Could someone from
one area of the City that is aware of rising market values from another area of the City come
into an appeal hearing requesting that that particular area be revalued because of either the
Page 40
market, or some compelling information that positively affects their value? This would cause a
shift of burden that can be directed to another area of the City?
It is staff's belief that the current guidelines for appeal with the unbiased board members of the
Assessment Appeals Board is working adequately. The process for Appeal is: first, Informal
(with the Assessor); second, Formal (with the Board of Appeals); and then Superior Court. If
changes are made at these levels, it is because there is enough evidence to make the change
without a partial revaluation and the adjustments to the values would be made. To begin
partial valuations within the City, would require different base years being utilized for different
areas ofthe City.
Staff has looked back at some of the sales in Wild Meadows, from May 2007 through May 2009.
All properties, with the exception of one, were a resale. The sales ranged from 96,000 to
187,000. Our values for these sales currently range from 90,200 to 126,400. Also, there have
been comments from the property owners of a sale that occurred later in 2009, for around
$70,000. Our office receives notification from Wild Meadows of the sale, and they provide the
new owner. (Ownership changes are done by title and not deed) We have to contact local real
estate agencies for the sale prices, since they are no longer provided to us and the State will not
provide this information to us. There was also a period of time, when we did not receive any
notification of ownership change, but we were able to get Wild Meadows to change this policy
so that the new property owners could receive their tax documentation in a timely fashion. For
this particular sale, we have the ownership change, but it was noted that this change was made
per Kent County PRIDE system information.
Again, we believe that the status quo is working, and as stated at the Legislative and Finance
th
Committee Meeting on November, 12 , four (4) property owners from Wild Meadows have
formally appealed their value since the 2010 revaluation, and all were in 2010. To this date, we
have not received further appeal requests.
Staff recommends that the Wild Meadows Community come in as a whole to the Board of
Assessment Appeals (maybe with a few spokesmen for the community) and appeal to the
Board. If they are not satisfied or successful at this level of appeal, then they could move
forward to Superior Court. (per the First Recommendation of the Legislative Finance and
Administrative Committee)
Staff does not recommend any changes be made to the City Ordinance or Charter.
Page 42
PETITION TO AMEND AND ZONING DISTRICT
Public Hearing before the City Council
December 9, 2013
Applicants/Owners: Raul Juarez
Property Address: 508 Acorn Lane
Tax Parcel ID #: ED-00-068.15-01-10.00-0001
Size: 1.315 acres
Present Use: Residential
Proposed Use: Residential
Comprehensive Plan Designation: Category 1 – High Priority Annexation Areas
Comprehensive Plan Land Use Designation: Residential Low Density
Present Zoning: RS-1 (Single Family Residential)
Proposed Zoning: R-8 (One Family Residence Zone)
Planning Commission
Recommendation: Following a public hearing on November 18, 2013, during which
no members of the public spoke regarding the application, the
Planning Commission unanimously recommended in favor of the
annexation and zoning.
File Number: AX-13-02
Page 43
AX-13-02 Lands of Juarez
Report to City Council
Page 2
This application is for the annexation and rezoning of property located at 508 Acorn Lane. The
property is owned by Raul Juarez. The Tax Parcel Identification Number is ED-00-068.15-01-
10.00-0001.
Existing Property:
The property is located on Acorn Lane and is bisected by Acorn Lane. The east side of the
property includes a house. The west side of the property is undeveloped. It is located in an
enclave area that is in Kent County but surrounded by the City of Dover. The residential portion
of the property needs to connect to the City’s water and sanitary sewer system, and annexation is
required to be eligible to receive City services.
Surrounding Land Uses:
The surrounding uses are residential properties. The property to the west is Manchester Square,
which is zoned RG-2. To the southeast is the undeveloped portion of Patriot Village, which is
zoned RM-1. The remaining lots are one-family residential lots, zoned R-15 and R-20 (One
Family Residence Zones) and RS-1 (Single Family Residential) in Kent County.
Comprehensive Plan:
In the 2008 Comprehensive Plan, this property is identified as a Category 1 (High Priority)
Annexation Area with a land use classification of Residential Low Density.
Request for R-8 (One Family Residence Zone)
The types of permitted uses in the R-8 (One Family Residence) zone include primarily one
family detached residences, but also agricultural uses and public uses. A series of conditional
uses and accessory uses, generally deemed compatible with the residential uses, are also
permitted in the One Family Residence Zones.
Recommendation of the Planning Staff and Planning Commission:
Staff recommended that annexation of the property and the rezoning to R-8 (One Family
Residence Zone) be approved as submitted. This recommendation was made without that benefit
of hearing the comments of surrounding landowners and residents. Following a public hearing
on November 18, 2013, the Planning Commission voted unanimously to recommend approval of
the annexation and rezoning as submitted.
Page 44
C F
I I
CITY OF DOVER T R
Y E
DEVELOPMENT ADVISORY COMMITTEE
O M
APPLICATION REVIEW COMMENTARY F A
R
D.A.C. MEETING DATE: October 30, 2013 D S
O H
V A
E L
R
APPLICATION: Lands of Raul Juarez at 508 Acorn Lane
FILE #: AX-13-02 REVIEWING AGENCY: City of Dover, Office of the Fire Marshal
CONTACT PERSON: Jason Osika, Deputy Fire Marshal PHONE #: (302) 736-4457
THE SUBJECT PROPOSAL HAS BEEN REVIEWED FOR CODE COMPLIANCE, PLAN CONFORMITY,
AND COMPLETENESS IN ACCORDANCE WITH THIS AGENCY’S AUTHORITY AND AREA OF
EXPERTISE.
THE FOLLOWING ITEMS HAVE BEEN IDENTIFIED AS ELEMENTS WHICH NEED TO BE ADDRESS BY
THE APPLICANT:
CITY AND STATE CODE REQUIREMENTS:
Currently the address number is 508 for the parcels on the East and West side of Acorn Lane.
One of the parcels needs to be assigned a new address number.
Address numbers of at least 6 inches in height must be placed on the street side of the building
visible from the street.
Project to be completed per approved Site Plan.
ADVISORY COMMENTS TO THE APPLICANT:
After any application has been approved by the Planning Commission, the applicant has a
maximum of thirty (30) days to appeal to the Code Board of Appeals Committee.
All comments from this office, approved by the Planning Commission are at the expense of the
owner/applicant.
The City of Dover uses the 2012 NFPA Life Safety Code, 2009 IBC, latest editions of all other
NFPA Codes and the 2012 Delaware State Fire Prevention Regulations.
If you have any questions or need to discuss any of the above comments, please call the
above contact person and the Planning Department as soon as possible.
Page 45
CITY OF DOVER
DEVELOPMENT ADVISORY COMMITTEE
APPLICATION REVIEW COMMENTARY
STAFF D.A.C. MEETING DATE: OCTOBER 30, 2013
APPLICATION: LANDS OF RAUL JUAREZ, 508 ACORN LANE
FILE #: AX-13-02
REVIEWING AGENCY: City of Dover Electric and Public Works Departments
CONTACT PERSON: Steve Enss - Electric
Jason A. Lyon, P.E. – Public Works
CONTACT PHONE #: Electric - 302-736-7070 Public Works – 302-736-7025
T HE S UBJECT P ROPOSAL HAS BEEN R EVIEWED FOR C ODE C OMPLIANCE , P LAN C ONFORMITY AND C OMPLETENESS IN
A CCORDANCE WITH THIS A GENCY ’ S A UTHORITY AND A REA OF E XPERTISE .
T HE F OLLOWING I TEMS HAVE BEEN I DENTIFIED AS E LEMENTS W HICH N EED TO BE A DDRESSED BY THE A PPLICANT :
CITY AND STATE CODE REQUIREMENTS
ELECTRIC / WATER / WASTEWATER / STORMWATER / SANITATION / STREETS / GROUNDS
1. Our office has no objections to the proposed annexation of tax parcel ED-00-068.15-01-10.00-0001.
RECOMMENDATIONS SUGGESTED AS CONDITIONS OF APPROVAL TO MEET CODE OBJECTIVES
ELECTRIC / WATER / WASTEWATER / STORMWATER / SANITATION / STREETS / GROUNDS
1. None
ADVISORY COMMENTS TO THE APPLICANT
ELECTRIC
1. None.
WATER
1. As per the Petition to Annex and Rezone Property, as heard by the City of Dover Utility Committee, October 28, 2013,
please find the following:
a. There is no water service to the property; however, a water main runs in Acorn Lane in front of the property. The
property owner would be responsible for the costs associated with tapping the water main, payment of impact
fees, and obtaining permits associated with such improvements. Water infrastructure must be installed in
accordance with the requirements of the City of Dover Water / Wastewater Handbook and DelDOT.
b. The owner / developer is responsible for submitting a plan to the Department of Public Works that depicts the
required information for a DelDOT State Utility Permit.
Page 46
Lands of Raul Juarez, 508 Acorn Lane
File #: AX-13-02
October 30, 2013
Page 2 of 2
WASTEWATER
1. As per the Petition to Annex and Rezone Property, as heard by the City of Dover Utility Committee, October 28, 2013,
please find the following:
a. There is no sewer service to the property; however, a sanitary sewer main runs in Acorn Lane in front of the
property. The property owner would be responsible for the costs associated with connecting to the sanitary
sewer main, payment of impact fees, and obtaining permits associated with such improvements. Wastewater
infrastructure must be installed in accordance with the requirements of the City of Dover Water / Wastewater
Handbook and DelDOT.
b. Additionally, per a special assessment for a sewer line along Acorn Lane, dated January 13, 1992, “All property
owners outside the City limits whose property adjoins said sewer line shall pay the equivalent assessment of
$40.00 per front foot adjoining the said sewer line at such time as the property is connected to the City’s sewer
system.” The owner / developer is responsible for paying the special assessment fee.
c. The owner / developer is responsible for submitting a plan to the Department of Public Works that depicts the
required information for a DelDOT State Utility Permit.
SANITATION
1. The City of Dover will only provide sanitation service to residential properties.
STORMWATER / STREETS / GROUNDS
1. None.
I F Y OU H AVE A NY Q UESTIONS OR N EED TO D ISCUSS ANY OF THE A BOVE C OMMENTS , P LEASE C ALL THE A BOVE
C ONTACT P ERSON AND THE P LANNING D EPARTMENT AS S OON AS P OSSIBLE .
Page 47
CITY OF DOVER
DEVELOPMENT ADVISORY COMMITTEE
APPLICATION REVIEW COMMENTARY
November 2013
APPLICATION: Lands of Raul Juarez 508 Acorn lane
FILE #: AX-13-02
REVIEWING AGENCY: Kent Conservation District
CONTACT PERSON: David C. Cahill PHONE #: 741-2600 ext.3
THE SUBJECT PROPOSAL HAS BEEN REVIEWED FOR CODE COMPLIANCE, PLAN CONFORMITY AND
COMPLETENESS IN ACCORDANCE WITH THIS AGENCY’S AUTHORITY AND AREA OF EXPERTISE. THE
FOLLOWING ITEMS HAVE BEEN IDENTIFIED AS ELEMENTS WHICH NEED TO BE ADDRESSED BY THE
APPLICANT:
CITY AND STATE CODE REQUIREMENTS:
1. Kent Conservation District has no objection to the annexation of the above referenced site.
ADVISORY COMMENTS TO THE APPLICANT:
The Following comments are advisory and apply to the development of a detailed site plan for this project.
1. If at any time expansion or earth disturbing activity (clearing, grubbing tree clearing etc.) takes place and
exceeds 5000 square feet; a detailed Sediment and Stormwater Management Plan must be submitted and
approved to the Kent Conversation District.
Page 48
CITY OF DOVER D
E
DEVELOPMENT ADVISORY COMMITTEE
L
APPLICATION REVIEW COMMENTARY D
O
D.A.C. MEETING DATE: October 29, 2013 T
===============================================================
APPLICATION: Lands of Raul Juarez at 508 Acorn Lane
FILE#: X-13-02 REVIEWING AGENCY: DelDOT
CONTACT PERSON: Julio F. Seneus PHONE#: 760-2145
===============================================================
THE SUBJECT PROPOSAL HAS BEEN REVIEWED FOR CODE COMPLIANCE, PLAN CONFORMITY AND COMPLETENESS IN
ACCORDANCE WITH THIS AGENCY'S AUTHORITY AND AREA OF EXPERTISE.
THE FOLLOWING ITEMS HAVE BEEN IDENTIFIED AS ELEMENTS WHICH NEED TO BE ADDRESSED BY THE APPLICANT:
CITY & STATE CODE REQUIREMENTS:
1. The Department has no comments on the proposed annexation and/or rezoning.
RECOMMENDATIONS SUGGESTED AS CONDITIONS OF APPROVAL TO MEET CODE
OBJECTIVES:
ADVISORY COMMENTS TO THE APPLICANT:
In order to be issued a Letter of No Objection (LONO), the department will require the applicant
to provide the proper forms, fees, and plans.
A Traffic Impact Study (TIS) will be required if the proposed business exceeds 50 VPH (vehicle
per Peak Hour) or 400 VPD (vehicle per day). When the study is completed, DelDOT will review
it and send recommendations of the improvements to Kent County. The improvements contained
in the study will be implemented by the developer per DelDOT's discretion. Please, contact Mr.
Troy Brestel at (302) 760-2167 or via e-mail at Troy.Brestel@state.de.us to set up a scoping
meeting for this project.
A pre-submittal meeting with the applicant will be required, if the proposed development
generates 200 vehicles per day (VPD).
The applicant is required to obtain a utility permit from the DelDOT Central District for this
project prior to performing any construction works within the right-of-way.
If you have any questions or need to discuss any of the above comments, please call the
above contact person and the planning department as soon as possible.
Page 50
City of Dover Application No.: AX-13-02
Department of Planning & Inspections
A
D DRIV E
WI N
C-2A
D
R OA
AK
IT EO
D WH
OL
D
VAN
Y DR R-15
AWA
RM-2
R-15 IVE
BAY
AD
RO
TR
Site
K
OA
EE
RO E
AD H IT
W
508
RM-2
Aco
rn L Site
ane 508
VE
STE
O RG-3
NS RG-2
N
IV E
DR RM-1
R-20
WA
LN
UT R-10
D RI
VE
LN
WA
ROS
UT
RG-2 C IR R-10
CL
E
Plan Title: Lands of Juarèz Legend
Location: 508 Acorn Lane
Plan Type: Annexation Zoning
Tax Parcel: ED00-068.15-01-10.00-000
Proposed Zoning: R-8 Dover Parcels
Proposed Land Use Classification: Residential Low Density Kent County Parcels
Annexation Classification: Catergory 1 Priority
Owners: Raul Juarèz Adjacent Right-of-Way
Date: 10-1-13 Dover Boundary
« 0 150 300 600 Feet
Page 51
PREPARED BY: TAX MAP PARCEL NO.
City of Dover ED-00-068.15-01-10.00-000
PO Box 475
Dover, DE 19903-0475
MAYOR AND COUNCIL
COUNCIL RESOLUTION NO. 2013-28
APPROVING THE INCLUSION OF AN AREA WITHIN THE LIMITS OF THE CITY OF DOVER.
WHEREAS, the Charter of the City of Dover authorizes Council to extend the boundaries of the said City
in accordance with Title 22, Chapter 1, Section 101 of the Delaware Code (22 Del.C.§ 101); and
WHEREAS, the Mayor and Council deem it to be in the best interest of the City of Dover to include an area
contiguous to the present City limits, and hereinafter more particularly described, within the limits of the
City of Dover; and
WHEREAS, the Charter of the City of Dover provides that if an annexation is petitioned by all owners of
all property considered for annexation, no election shall be required. For an annexation petition not
requiring an election, such petition shall be processed in accordance with procedures established for
amendments to the zoning map, specified in Dover Code, Appendix B - Zoning. All annexation petitions
shall be processed concurrently with the rezoning of the property considered for annexation and shall be
subject to public hearing before City Council. Public notice shall be completed in accordance with the
provisions of the Dover Code relating to amendment of the zoning map.
NOW, THEREFORE, BE IT RESOLVED BY THE MAYOR AND COUNCIL OF THE CITY OF
DOVER, IN COUNCIL MET:
1. That the following described area, situated in East Dover Hundred, Kent County, State of Delaware,
along with all adjacent paths, sidewalks, roadways, and rights-of-way in their entirety, shall be annexed to
and included within the limits of the City of Dover:
PARCEL NO. 1 (Westerly Parcel)
Beginning at an iron pipe situate on the westerly side of Acorn Lane (50' wide), said pipe
being further located 644' +/- southerly of the centerline of White Oak Road and being a
corner for these lands and lands of the City of Dover; thence by and with said City of Dover
lands the following three (3) courses and distances: S 83° 24' 00" W, 35.05' to an iron pipe;
thence N 19° 51' 00" W, 123.17' to an iron pipe; thence N 20° 33' 00" W, 478.80' to an iron
pipe on the southerly side of White Oak Road (50' wide), said pipes being corners for these
lands and said City of Dover lands; thence by and with the southerly side of White Oak Road
N 70° 55' 00" E, 155.56' to an iron pipe located at the intersection of the southerly side of
White Oak Road with the westerly side of Acorn Lane, said pipe being a corner for these
lands; thence by and with the westerly side of Acorn Lane S 09° 05' 00" E, 618.76' to an iron
pipe, said pipe being the point and place of beginning.
The above-described parcel contains 1.315 acres of land, more or less.
Page 52
ANNEXATION RESOLUTION - 508 ACORN LANE PAGE 2
PARCEL NO. 2 (Easterly Parcel)
Beginning at an iron pipe situate on the easterly side of Acorn Lane (50' wide), said pipe
being located 644' +/- southerly of the centerline of White Oak Road and being further
located N 83° 24' 00" E, 50.05' from the Point of Beginning of PARCEL NO.1 and being a
corner for these lands and lands of C. Robert Probst; thence by and with the easterly side of
Acorn Lane N 09° 05' 00" W, 220.00' to an iron pipe, said pipe being a corner for these lands
and lands of Florence Garrison; thence by and with said Florence Garrison lands N 83° 24'
00" E, 225.00' to an iron pipe on line of lands of Bangalore T. Laksham, said pipe being a
corner for these lands and said Florence Garrison lands; thence by and with said
Bangalore T. Laksham lands S 09° 05' 00" E, 220.00' to an iron pipe, said pipe being a
corner for these lands and lands of C. Robert Probst; thence by and with said C. Robert
Probst lands S 83° 24' 00" W, 225.00' to an iron pipe on the easterly side of Acorn Lane, said
pipe being the point and place of beginning.
The above-described parcel contains 1.135 acres of land, more or less.
Being the same lands and premises which were conveyed unto Gamaliel E. Garrison and
Mary R. Garrison, by deed of Trailer Village, Inc. dated February 15, 1979, and recorded in the
Office of the Recorder of Deeds in and for Kent County, Delaware, on February 23, 1979, in Deed
Book P, Volume 33, Page 137.
2. That the above described property shall be annexed into the City of Dover with a zoning
classification as set by City Council and in accordance with the zoning map and environs then in force,
effective upon such lands being included within the limits of the City of Dover.
3. That the certified copy of this resolution of annexation, together with a plot of the area annexed,
shall be filed for record with the Recorder of Deeds of Kent County.
4. That the effective date of this resolution shall be the 10th day of December, 2013 at 12:01 a.m.
ADOPTED: *
S:\ANNEXATIONS\Annex-2013\508 Acorn Lane\Approval Resolution 2013-28 for Packet - 508 Acorn Lane - No Referendum.wpd
CARLETON E. CAREY
MAYOR
DAVID L. BONAR
COUNCIL PRESIDENT
Page 53
FINAL READING
CITY OF DOVER PROPOSED ORDINANCE #2013-16
1 AN ORDINANCE AMENDING THE ZONING ORDINANCE AND ZONING MAP OF THE
2 CITY OF DOVER BY CHANGING THE ZONING DESIGNATION OF PROPERTY
3 LOCATED AT 508 ACORN LANE
4 WHEREAS, the City of Dover has enacted a zoning ordinance regulating the use of property within
5 the limits of the City of Dover; and
6 WHEREAS, it is deemed in the best interest of zoning and planning to change the permitted use of
7 property described below from RS-1 - Single Family Residence (Kent County zoning classification)
8 to R-8 - One-Family Residence (City of Dover zoning classification).
9 NOW, THEREFORE, BE IT ORDAINED BY THE MAYOR AND COUNCIL OF THE CITY
10 OF DOVER, IN COUNCIL MET:
11 1. That from and after the passage and approval of this ordinance the Zoning Map and Zoning
12 Ordinance of the City of Dover have been amended by changing the zoning designation from
13 RS-1 - Single Family Residence (Kent County zoning classification) to R-8 - One-Family
14 Residence (City of Dover zoning classification) on that property located at 508 Acorn Lane,
15 consisting of two (2) parcels totaling 2.45+/- acres (Parcel No. 1: located on the westerly
16 side of Acorn Lane, containing 1.315+/- acres; and Parcel No. 2: located on the easterly side
17 of Acorn Lane, containing 1.135+/- acres), owned by Raul M. Juarez.
18 (TAX PARCEL: ED-00-068.15-01-10.00-000; COUNCIL DISTRICT: 3; PLANNING REFERENCE: AX-13-02)
19 ADOPTED: *
20 S:\ORDINANCES\2013\Draft\2013-16 Rezoning-Annexation-508 Acorn Lane-FINAL RDG.wpd
21 ACTIONS HISTORY
22 December 9, 2013 - Scheduled for Final Reading/Adoption
23 October 14, 2013 - First Reading/Referral
Page 54
PETITION TO AMEND AND ZONING DISTRICT
Public Hearing before the Planning Commission
November 18, 2013
Applicants/Owners: City of Dover
Property Address: West side of Acorn Lane
Tax Parcel ID #: ED-00-068.15-01-12.00-0001
Size: 0.075 acres (3,264 SF)
Present Use: Vacant
Proposed Use: Vacant
Comprehensive Plan Designation: Category 1 – High Priority Annexation Areas
Comprehensive Plan Land Use Designation: Residential Low Density
Present Zoning: RS-1 (Single Family Residential)
Proposed Zoning: R-8 (One Family Residence Zone)
Planning Commission
Recommendation: Following a public hearing on November 18, 2013, during which
no members of the public spoke regarding the application, the
Planning Commission unanimously recommended in favor of the
annexation and zoning.
File Number: AX-13-03
Page 55
AX-13-03 Lands of City of Dover
Report to City Council
Page 2
This application is for the annexation and rezoning of property located on Acorn Lane. The
property is owned by the City of Dover. The Tax Parcel Identification Number is ED-00-068.15-
01-12.00-0001.
Existing Property:
The property is located on Acorn Lane and is directly south of the western portion of the
property located at 508 Acorn Lane.
Surrounding Land Uses:
The surrounding uses are residential properties. The property to the west is Manchester Square,
which is zoned RG-2. To the southeast is the undeveloped portion of Patriot Village, which is
zoned RM-1. The remaining lots are one-family residential lots, zoned R-15 and R-20 (One
Family Residence Zones) and RS-1 (Single Family Residential) in Kent County.
Comprehensive Plan:
In the 2008 Comprehensive Plan, this property is identified as a Category 1 (High Priority)
Annexation Area with a land use classification of Residential Low Density.
Request for R-8 (One Family Residence Zone)
The types of permitted uses in the R-8 (One Family Residence) zone include primarily one
family detached residences, but also agricultural uses and public uses. A series of conditional
uses and accessory uses, generally deemed compatible with the residential uses, are also
permitted in the One Family Residence Zones.
Recommendation of the Planning Staff and Planning Commission:
Staff recommended that annexation of the property and the rezoning to R-8 (One Family
Residence Zone) be approved as submitted. This recommendation was made without that benefit
of hearing the comments of surrounding landowners and residents. Following a public hearing
on November 18, 2013, the Planning Commission voted unanimously to recommend approval of
the annexation and rezoning as submitted.
Page 56
CITY OF DOVER
DEVELOPMENT ADVISORY COMMITTEE
APPLICATION REVIEW COMMENTARY
STAFF D.A.C. MEETING DATE: OCTOBER 30, 2013
APPLICATION: LANDS OF CITY OF DOVER, ACORN LANE
FILE #: AX-13-03
REVIEWING AGENCY: City of Dover Electric and Public Works Departments
CONTACT PERSON: Steve Enss - Electric
Jason A. Lyon, P.E. – Public Works
CONTACT PHONE #: Electric - 302-736-7070 Public Works – 302-736-7025
T HE S UBJECT P ROPOSAL HAS BEEN R EVIEWED FOR C ODE C OMPLIANCE , P LAN C ONFORMITY AND C OMPLETENESS IN
A CCORDANCE WITH THIS A GENCY ’ S A UTHORITY AND A REA OF E XPERTISE .
T HE F OLLOWING I TEMS HAVE BEEN I DENTIFIED AS E LEMENTS W HICH N EED TO BE A DDRESSED BY THE A PPLICANT :
CITY AND STATE CODE REQUIREMENTS
ELECTRIC / WATER / WASTEWATER / STORMWATER / SANITATION / STREETS / GROUNDS
1. Our office has no objections to the proposed annexation of tax parcel ED-00-068.15-01-12.00-000.
RECOMMENDATIONS SUGGESTED AS CONDITIONS OF APPROVAL TO MEET CODE OBJECTIVES
ELECTRIC / WATER / WASTEWATER / STORMWATER / SANITATION / STREETS / GROUNDS
1. None
ADVISORY COMMENTS TO THE APPLICANT
ELECTRIC
1. None.
WATER
1. As per the Petition to Annex and Rezone Property, as heard by the City of Dover Utility Committee, October 28, 2013,
please find the following:
a. There is no water service to the property; however, a water main runs in Acorn Lane in front of the property. The
property owner would be responsible for the costs associated with tapping the water main, payment of impact
fees, and obtaining permits associated with such improvements. Water infrastructure must be installed in
accordance with the requirements of the City of Dover Water / Wastewater Handbook and DelDOT.
b. The owner / developer is responsible for submitting a plan to the Department of Public Works that depicts the
required information for a DelDOT State Utility Permit.
Page 57
Lands of City of Dover, Acorn Lane
File #: AX-13-03
October 30, 2013
Page 2 of 2
WASTEWATER
1. As per the Petition to Annex and Rezone Property, as heard by the City of Dover Utility Committee, October 28, 2013,
please find the following:
a. There is no sewer service to the property; however, a sanitary sewer main runs in Acorn Lane in front of the
property. The property owner would be responsible for the costs associated with connecting to the sanitary
sewer main, payment of impact fees, and obtaining permits associated with such improvements. Wastewater
infrastructure must be installed in accordance with the requirements of the City of Dover Water / Wastewater
Handbook and DelDOT.
b. Additionally, per a special assessment for a sewer line along Acorn Lane, dated January 13, 1992, “All property
owners outside the City limits whose property adjoins said sewer line shall pay the equivalent assessment of
$40.00 per front foot adjoining the said sewer line at such time as the property is connected to the City’s sewer
system.” The owner / developer is responsible for paying the special assessment fee.
c. The owner / developer is responsible for submitting a plan to the Department of Public Works that depicts the
required information for a DelDOT State Utility Permit.
SANITATION
1. The City of Dover will only provide sanitation service to residential properties.
STORMWATER / STREETS / GROUNDS
1. None.
I F Y OU H AVE A NY Q UESTIONS OR N EED TO D ISCUSS ANY OF THE A BOVE C OMMENTS , P LEASE C ALL THE A BOVE
C ONTACT P ERSON AND THE P LANNING D EPARTMENT AS S OON AS P OSSIBLE .
Page 58
CITY OF DOVER
DEVELOPMENT ADVISORY COMMITTEE
APPLICATION REVIEW COMMENTARY
November 2013
APPLICATION: Lands of the City of Dover Acorn Lane
FILE #: AX-13-03
REVIEWING AGENCY: Kent Conservation District
CONTACT PERSON: David C. Cahill PHONE #: 741-2600 ext.3
THE SUBJECT PROPOSAL HAS BEEN REVIEWED FOR CODE COMPLIANCE, PLAN CONFORMITY AND
COMPLETENESS IN ACCORDANCE WITH THIS AGENCY’S AUTHORITY AND AREA OF EXPERTISE. THE
FOLLOWING ITEMS HAVE BEEN IDENTIFIED AS ELEMENTS WHICH NEED TO BE ADDRESSED BY THE
APPLICANT:
CITY AND STATE CODE REQUIREMENTS:
1. Kent Conservation District has no objection to the annexation of the above referenced site.
ADVISORY COMMENTS TO THE APPLICANT:
The Following comments are advisory and apply to the development of a detailed site plan for this project.
1. If at any time expansion or earth disturbing activity (clearing, grubbing tree clearing etc.) takes place and
exceeds 5000 square feet; a detailed Sediment and Stormwater Management Plan must be submitted and
approved to the Kent Conversation District.
Page 59
CITY OF DOVER D
E
DEVELOPMENT ADVISORY COMMITTEE
L
APPLICATION REVIEW COMMENTARY D
O
D.A.C. MEETING DATE: October 29, 2013 T
===============================================================
APPLICATION: Lands of City of Dover on Acorn Lane
FILE#: AX-13-03 REVIEWING AGENCY: DelDOT
CONTACT PERSON: Julio F. Seneus PHONE#: 760-2145
===============================================================
THE SUBJECT PROPOSAL HAS BEEN REVIEWED FOR CODE COMPLIANCE, PLAN CONFORMITY AND COMPLETENESS IN
ACCORDANCE WITH THIS AGENCY'S AUTHORITY AND AREA OF EXPERTISE.
THE FOLLOWING ITEMS HAVE BEEN IDENTIFIED AS ELEMENTS WHICH NEED TO BE ADDRESSED BY THE APPLICANT:
CITY & STATE CODE REQUIREMENTS:
1. The Department has no comments on the proposed annexation and/or rezoning.
RECOMMENDATIONS SUGGESTED AS CONDITIONS OF APPROVAL TO MEET CODE
OBJECTIVES:
ADVISORY COMMENTS TO THE APPLICANT:
In order to be issued a Letter of No Objection (LONO), the department will require the applicant
to provide the proper forms, fees, and plans.
A Traffic Impact Study (TIS) will be required if the proposed business exceeds 50 VPH (vehicle
per Peak Hour) or 400 VPD (vehicle per day). When the study is completed, DelDOT will review
it and send recommendations of the improvements to Kent County. The improvements contained
in the study will be implemented by the developer per DelDOT's discretion. Please, contact Mr.
Troy Brestel at (302) 760-2167 or via e-mail at Troy.Brestel@state.de.us to set up a scoping
meeting for this project.
A pre-submittal meeting with the applicant will be required, if the proposed development
generates 200 vehicles per day (VPD).
The applicant is required to obtain a utility permit from the DelDOT Central District for this
project prior to performing any construction works within the right-of-way.
If you have any questions or need to discuss any of the above comments, please call the
above contact person and the planning department as soon as possible.
Page 61
City of Dover Application No.: AX-13-03
Department of Planning & Inspections
A
D DRIV E
WI N
C-2A
D
R OA
AK
IT EO
D WH
OL
D
VAN
Y DR R-15
AWA
RM-2
R-15 IVE
BAY
AD
RO
TR
K
OA
EE
RO E
AD H IT
W
508
RM-2
rn
Aco
Lane 508
VE
STE
Site
RG-3
NS O
N RG-2
IV E
DR RM-1
R-20
WA
LN
UT R-10
D RI
VE
LN
WA
ROS
UT
RG-2 C IR R-10
CL
E
Plan Title: City of Dover Legend
Location: West Side of Acorn Lane
Plan Type: Annexation Zoning
Tax Parcel: ED00-068.15-01-12.00-000
Proposed Zoning: R-8 Dover Parcels
Proposed Land Use Classification: Residential Low Density Kent County Parcels
Annexation Classification: Catergory 1 Priority
Owners: City of Dover Adjacent Right-of-Way
Date: 10-1-13 Dover Boundary
« 0 150 300 600 Feet
Page 62
PREPARED BY: TAX MAP PARCEL NO.
City of Dover ED-00-68.15-01-12.00-000
PO Box 475
Dover, DE 19903-0475
MAYOR AND COUNCIL
COUNCIL RESOLUTION NO. 2013-29
APPROVING THE INCLUSION OF AN AREA WITHIN THE LIMITS OF THE CITY OF DOVER.
WHEREAS, the Charter of the City of Dover authorizes Council to extend the boundaries of the said City
in accordance with Title 22, Chapter 1, Section 101 of the Delaware Code (22 Del.C.§ 101); and
WHEREAS, the Mayor and Council deem it to be in the best interest of the City of Dover to include an area
contiguous to the present City limits, and hereinafter more particularly described, within the limits of the
City of Dover; and
WHEREAS, the Charter of the City of Dover provides that if an annexation is petitioned by all owners of
all property considered for annexation, no election shall be required. For an annexation petition not
requiring an election, such petition shall be processed in accordance with procedures established for
amendments to the zoning map, specified in Dover Code, Appendix B - Zoning. All annexation petitions
shall be processed concurrently with the rezoning of the property considered for annexation and shall be
subject to public hearing before City Council. Public notice shall be completed in accordance with the
provisions of the Dover Code relating to amendment of the zoning map.
NOW, THEREFORE, BE IT RESOLVED BY THE MAYOR AND COUNCIL OF THE CITY OF
DOVER, IN COUNCIL MET:
1. That the following described area, situated in East Dover Hundred, Kent County, State of Delaware,
along with all adjacent paths, sidewalks, roadways, and rights-of-way in their entirety, shall be annexed to
and included within the limits of the City of Dover:
All that certain piece and parcel of land situated on the west side of Acorn Lane just south
of White Oak Road, bounded on the east by Acorn Lane, on the north by lands now or late
of Gamaliel Garrison, and on the west by other lands of the City of Dover, more particularly
described as follows, to-wit:
Beginning at a point on the east side of Acorn Lane (a 50 foot street) at a corner for this
parcel and other lands of the City of Dover; thence and binding with City of Dover land
North nineteen (19) degrees fifty-one (51) minutes West 194.99 feet to a corner for this
parcel and lands now or late of Gamaliel Garrison; thence and binding with Garrison land
in an easterly direction 34 feet to a point on the west side of Acorn Lane; thence and binding
with the west side of Acorn Lane, South nine (9) degrees five (5) minutes East 192 feet to
the place of beginning, and containing approximately .075 acres of land, be the same more
or less.
Page 63
ANNEXATION RESOLUTION - WESTERLY SIDE OF ACORN LANE (CITY OF DOVER) PAGE 2
2. That the above described property shall be annexed into the City of Dover with a zoning
classification as set by City Council and in accordance with the zoning map and environs then in force,
effective upon such lands being included within the limits of the City of Dover.
3. That the certified copy of this resolution of annexation, together with a plot of the area annexed,
shall be filed for record with the Recorder of Deeds of Kent County.
4. That the effective date of this resolution shall be the 10th day of December, 2013 at 12:01 a.m.
ADOPTED: *
S:\ANNEXATIONS\Annex-2013\Westerly Side of Acorn Lane - City of Dover\Approval Resolution No. 2013-29 for Packets.wpd
CARLETON E. CAREY
MAYOR
DAVID L. BONAR
COUNCIL PRESIDENT
Page 64
FINAL READING
CITY OF DOVER PROPOSED ORDINANCE #2013-17
1 AN ORDINANCE AMENDING THE ZONING ORDINANCE AND ZONING MAP OF THE
2 CITY OF DOVER BY CHANGING THE ZONING DESIGNATION OF PROPERTY
3 LOCATED ON THE WEST SIDE OF ACORN LANE
4 WHEREAS, the City of Dover has enacted a zoning ordinance regulating the use of property within
5 the limits of the City of Dover; and
6 WHEREAS, it is deemed in the best interest of zoning and planning to change the permitted use of
7 property described below from RS-1 - Single Family Residence (Kent County zoning classification)
8 to R-8 - One-Family Residence (City of Dover zoning classification).
9 NOW, THEREFORE, BE IT ORDAINED BY THE MAYOR AND COUNCIL OF THE CITY
10 OF DOVER, IN COUNCIL MET:
11 1. That from and after the passage and approval of this ordinance the Zoning Map and Zoning
12 Ordinance of the City of Dover have been amended by changing the zoning designation from
13 RS-1 - Single Family Residence (Kent County zoning classification) to R-8 - One-Family
14 Residence (City of Dover zoning classification) on that property located on the westerly side
15 of Acorn Lane, consisting of 0.075+/- acres (3,264 s.f.), owned by the City of Dover.
16 (TAX PARCEL: ED-00-068.15-01-12.00-000; COUNCIL DISTRICT: 3; PLANNING REFERENCE: AX-13-03)
17 ADOPTED: *
18 S:\ORDINANCES\2013\Draft\2013-17 Rezoning-Annexation-Acorn Lane-City of Dover-FINAL RDG.wpd
19 ACTIONS HISTORY
20 December 9, 2013 - Scheduled for Final Reading/Adoption
21 October 14, 2013 - First Reading/Referral
Page 65
Downtown
Dover Partnership
developing the economic,
The purpose of the
cultural and historic
Downtown Dover
resources of downtown
Partnership is to develop the
economic, cultural and
historic resources of
downtown Dover, to
increase business/job
opportunities and to develop
the commercial and
residential potential of the
Central Dover area. The
DDP strives to protect and
enhance the historic
architectural and community
qualities of the downtown
consistent with the guiding
principles of the National
Main Street Program.
Page 66
Board Members Director’s Note…
Gregory V. Moore, P.E.,
President
As we report on the Downtown Dover Partnership’s financial and operational performance of fiscal
Gerald I.H. Street, Esq., Vice
President year 2013, I want to take this opportunity to reflect on our strategy, our progress and our future as
Timothy Slavin, Secretary we continue to focus on the original purpose and mission of the DDP.
Cynthia Small, Treasurer
Councilman David Anderson In 2012, we reported that the DDP created two First Class retail spaces at 22-24 W. Loockerman
Councilman David Bonar Street. What a difference a year makes! This same building has been selected as the next home for
Senator Brian Bushweller Delaware EZ Pass and is currently undergoing a $1.3 million state of the art renovation with its new
Councilman Wallace Dixon occupants arriving in the first quarter of 2014.
Anita Evans
Lucy Findlay
On March 27, 2013, Governor Jack Markell cut the ribbon to celebrate the completion of the $3
Michael Harrington, Sr.
Dr. William Johnston Million North Street Area and Loockerman Way Improvements, which included burial of utility
Scott Koenig lines, the redesign of the North Street parking lots and the completion of the public space and
Diane Laird metered parking lot on Loockerman Way with funding provided by the Delaware Legislature.
Paul E. Lakeman Spring 2013 bore witness to the opening of the Bayard Pharmacy, downtown Dover’s first
Maxine Lewis pharmacy in fifteen years; approval for the construction of a new Family Dollar; and much more.
Joseph McDaniel It’s clear that the DDP’s performance continues to be solid.
Gary Patterson
Representative Darryl Scott As the DDP enters its sixth year, our Board and Committees will
Laura Simmons
continue their planning and hard work to help Downtown Dover
Ann Marie Townshend
Mayor Carleton Carey, grow and become a destination. We also want to extend our
Ex Officio appreciation to William G. Neaton for his leadership and
commitment to the DDP’s mission and goals as the Executive
Design Committee Director from October 2008 through February 2013.
Laura Simmons, Chairperson
Carrie Hart
Ann Baker Horsey
Sincerely, Louis Colón, Executive Director
Susan Johnston
Dawn Melson-Williams
Kristin Pleasanton
Elena Stewart
Committee
Economic Development &
Accomplishments Organization Committee Promotions Committee
Restructuring Committee • Held Fundraising Workshop • Held committee work plan
• Created Fundraising Plan development workshops
Gerald I. H. Street, Esq., • Coordinated Volunteer • Held Shop Talk seminar courtesy
Chairperson Design Committee Recognition & Annual Report of DEDO
Robert Berglund • Implemented Annual • 4th Annual Safe, Spooky
Councilman David Bonar Community Art Project Parking & Safety Halloween Parade
Gary Cecchett • Completed Two Facade Projects Committee • Capital Holiday Celebration
Anthony DePrima • Installed New Parking Meters • 5th Annual Home for the
Councilwoman Wallace Dixon Economic Development & • Offered Free Metered Parking in Holidays Parade
Michael Harrington, Sr. Restructuring Committee the Bradford Street Lot during • Supported First Fridays
Dr. William Johnston • Renovations of 22-24 W. Holidays • Established Farmer’s Market on
Scott Koenig Loockerman St. completed. • Completed Phase II of Loockerman Way
Paul E. Lakeman Currently under consideration as “Historically Happening” Banner • Distributed 60+ media releases
Joseph McDaniel future home of Delaware EZ Pass. Project and generated significant positive
Kevin Mitten • 238 Railroad Ave pre-demolition • Installed “Way Finding” Banners press for downtown Dover
Gregory V. Moore, P.E. asbestos abatement completed; fall • Installed Phase I of “Farmer’s • Created “Winter Wonderland” on
William Neaton demolition pending Market” Banners Loockerman Way
Ted Nutter • North Street Improvements • Installed Five (5) Additional • St. Patrick’s Day Parade
Gary Patterson completed Surveillance Cameras • First Friday Gives Back Program
Charlie Rodriguez • Loockerman Way and Parking • Striped\Stenciled Bradford St • Implemented Social Media
Laura Simmons lot completed and Governors Avenue parking Campaign
Jonathan Street • Construction of new Family lots
Ann Marie Townshend Dollar approved • Installed new Parking Banners
Page 67
FY 2013
Downtown Dover Partnership
Economic Impact Highlights
$30,625,965 Dollars Invested in FY 2013
Facade Grants Awarded - $2,960
Total value of Facade Improvements - $5,420
Building Renovations $126,114
North Street Improvements $1,791,471
Dover Public Library $20,800,000
Wesley College $2,100,000
Bayard Plaza $5,800,000
1500 + Volunteer Hours
Our Support System
1669 hours valued at $22.02/hr = $36,751
Nine New Businesses Opened
Tea for Two
Many Things
A Touch of Glass Organization Committee
Bayard Pharmacy
Pure Luxury Salon Jocelyn McBride, Chairperson
Tresses Salon Valerie A. Christ
Rouge Women’s Apparel Marjorie Cyr
Cheveux Salon Georgeanna Windley
Amore Bridal Chris Wood
A total of nine (9) new Woman/Minority owned businesses opened during this reporting period
yielding eighteen(18) FTE. Parking Committee
Anita Evans, Chairperson
Increasing Competitiveness of Downtown Businesses David Affholder
In our efforts to support both existing and potential businesses in the downtown, the DDP hosted Michael Ambruso
nine (9) Business Development Workshops that provided information on marketing techniques, Jed Hatfield
developing a business plan, loan seminars, social media, e-commerce, and other topics that were Christopher Hayes
attended by 163 individuals. Ted Nutter
Michael Riemann
Business Assistance Provided Ron Poliquin, Esq.
Two businesses received loans through our technical assistance loan referral program. These loans
totaled $230,000 and created 7FTE’s and sustained 3 FTE’s.
Promotions Committee
Partnership Real Estate Holdings Tonda Parks, Chairperson
Kim Aigle
Jennifer Bailey
120 S. Governors Avenue – Acme site ..........................................$ 1,239,345 Elaine Brenchley
22-24 W. Loockerman Street ................................................................278,809 Gary Chaffee
Helen Downing
133-135 S. Governors Avenue ..............................................................248,745 Maxine Lewis
139-143 S. Governors Avenue ..............................................................295,184 Lucy Findlay
222 Railroad Avenue................................................................................56,746 Andy Ryan
Nancy Pikulik
238 Railroad Avenue..............................................................................151,091 Jan Crumpley
East side of N. West Street parcel #1 ....................................................243,000 Christy Rawlins
680 & 684 Forest Street ........................................................................674,267 Jennifer Bailey
Kathy Jo Robbins
114-128 W Loockerman Street..............................................................412,857 Katrina Sullivan
Clarissa Williams
Total Buildings & Land ......................................................$ 3,600,044 Tammy Miller
Page 68
Special Thanks to the following Individuals and Organizations who contributed time,
talent and resources to make our fifth year a great success:
First Friday 2012 Winter Wonderland Support for Multiple Activities
Jean Francis Committee Alex Vaughan Mobile
Susan Johnston Dawne Nickerson-Banez Entertainment
Jeremy Gibb Benhje Benton Bayhealth Medical Center
Friends of Folk Darin Dell City of Dover
Lucy Findlay Judy Diogo DE Economic Development
Valla Rogers Dover Interfaith Mission for Office
Board Members Downtown Dover Merchants Housing, Inc. DE Technical & Community
Michael Harrington, Sr., College
Capital Holiday Celebration Harrington ERA Realty Dover City Council
Central Delaware Chamber of Joe Parks Dover Community Partnership
Special thanks to Commerce Tonda Parks Dover Fire Department
the Dover City Council, Bayhealth Medical Center Mary Ressler, Quality Builders Dover Housing Authority
Mayor Carleton E. Carey, Sr., Heritage at Dover Justin Strickland Dover Parks & Recreation
Dover Kiwanis Steph Berkich-Ryan Dover Police Department
and City Manager Scott Koenig
Wesley Pre-School Kristin Coker Stonesifer Downtown Dover Businesses
for their support of the First State Community Loan
The Little School
Downtown Dover Fund
Dover High Select Ensemble 2012 Winter Wonderland
Partnership. St John’s Lutheran School First State Heritage Park
Contributors
Delaware State News Amore Bridal Friends of Folk
Thanks to Diane Laird, State Rev. Dr. Norman Hutchins Axia Management Friends of Old Dover
Coordinator, Delaware Main Street, Frontline Ministries Choir BayHealth Greater Dover Committee
for technical assistance provided Mary Borger Bel Boutique CenDel Foundation
throughout the year. Cristal Brenneman Crystal Carey Kent County Amateur Radio
Sherwanda Rachal-Speaks Lucy & George Findlay Club
Becky Norton George & Lynch Kent County Tourism
A very Special Thanks to our friends SCORE
Michelle Hughes Harrington Foundation
at Becker Morgan Group. Small Business Development
A team of professionals that define Donna Josefowski
Home for the Holidays Joe McDaniel Center
dedication, expertise and talent . A Gary Chaffee, Parade STACKS Entertainment
Mitten & Winters
team that made many of these Coordinator Pettinaro Management, LLC U.S. Small Business
accomplishments possible. Santa & Mrs. Claus: Rev. Louie Phillips Administration
William and Marty Downing PNC Bank USDA Rural Development
And to Gary Patterson, Sen. Brian Tami Wilson Street & Ellis Wesley College
YWCA Delaware
Bushweller and Rep. Darryl Scott, Rosemary Twilley
whose unwavering support Quality Builders
and dedication to Dover
knows no bounds.
About the Downtown Dover Partnership
Downtown Dover Partnership is a non-profit organization dedicated to revitalizing the Downtown District.
DDP works hand in hand with the National Trust for Historic Preservation’s National Main Street Center and
Partnership Staff the Downtown Delaware initiative to create a variety of programs that serve to improve our downtown district.
Louis Colón, Executive Director
C. Edwin Perez 101 W Loockerman St, Suite 1A – Dover DE 19904
Beverly Latimer Jackson 302.678.2940 (p) - 302.678.2132 (f) www.downtowndoverpartnership.com
Page 69
UTILITY COMMITTEE
The Utility Committee Meeting was held on November 25, 2013 at 5:00 p.m. with Mr. Slavin
presiding until the arrival of Chairwoman Williams (5:03 p.m.). Members present were Mr. Perza
(arrived at 5:07 p.m.), Mr. Blakeman, and Mr. Snaman. Members of Council present were Mr. Dixon
(arrived at 5:09 p.m.) and Mr. Hutchison. Mayor Carey was also present.
AGENDA ADDITIONS/DELETIONS
Mr. Blakeman moved for approval of the agenda as presented, seconded by Mr. Snaman and
unanimously carried.
Electric Supply & Generation
Members were provided information regarding Electric Supply and Generation, as follows:
McKee Run Units 1 & 2 - Cost/Benefit Analysis
Mr. Scott Koenig, City Manager, reviewed a Presentation - Cost/Benefit Analysis for City of Dover
for McKee Run Units 1 & 2, as prepared by Mr. Robert Trinnear, The Energy Authority (TEA).
Referring to Slide 13, Mr. Blakeman questioned if there were a means of quantifying the risk of
operational failure. Responding, Mr. Koenig stated that he would contact representatives of both
TEA and North American Energy Services (NAES) to obtain this information.
In response to Mr. Blakeman with reference to Slide 14, Mr. Koenig stated that borescope inspection
logs did not indicate any required repairs and/or improvements that were not already included in the
City’s Capital Improvement Plan (CIP). Based on current knowledge, he assured members that the
only repairs and/or improvements anticipated were those listed in the CIP.
Responding to Mrs. Williams regarding the cost of “mothballing” these Units, Mr. Koenig stated that
TEA and NAES had been requested to provide a price; however, staff anticipated that this amount
would be costly (in the high six to low seven figure range) due to asbestos and other issues
associated with the Units.
Mr. Snaman questioned if the new power plant (Calpine) could affect the details regarding Units 1
and 2. Responding, Mr. Koenig explained that if the City entered into a purchase power agreement
with Calpine, the City could replace the capacity of Units 1 and 2 with capacity from the Calpine
Project, which would be a negotiated item and was scheduled for discussion later in the meeting,
under Item #1C.
Mrs. Williams relayed concern with proceeding since there were so many uncertainties.
Mr. Kirk Betts, Betts & Holt LLP, the City’s Energy Attorney, stated that there was not as much
uncertainty as there appeared to be but there were several risks. He explained that some life
extensions were previously done to Units 1 and 2 to keep them “alive;” however, prior to the Calpine
project, the lease arrangement at the Garrison Tract included the opportunity to purchase 50 MW of
capacity based on the belief that Units 1 and 2 would not survive. He stated that the Units are not
as reliable as needed, which poses a risk. When the Units are supposed to come up and they do not,
the City is penalized financially as well as with regard to reserve requirements and does not get the
capacity credits needed. While these costs have not yet been quantified, they exist. He advised
Page 70
UTILITY COMMITTEE MEETING NOVEMBER 25, 2013 PAGE 2
members that another risk was the capacity price of $119 per megawatt day (MWd) which was
expected to be in the range of $150, $180, and $200 per MWd, but noted that this was not fully
quantified because the PJM market only extends out three (3) years. He explained that this type of
spread reduces the value of the plant and, with the addition of the costs for operating those Units
including the NAES costs and the capital costs indicated in the CIP, there is a very low margin.
With a low margin area of approximately $250,000, for example, the City would be totally at risk
and one (1) or more operational failure or forced outage could result in the City being “in the hole.”
While these numbers had not been quantified, he explained that they appear more and more
threatening in terms of the value of the plant.
Mr. Betts explained that another issue with old units such as these is that spare parts are not available
and must be manufactured. He explained that manufacturing parts for an antique piece of equipment
costs more and the value is not recovered; therefore, the cost just to repair Units 1 and 2 would be
extraordinarily high. He reminded members that Units 1 and 2 were being kept for capacity plays,
and when the capacity market goes down, the value disappears. Although the City does not need the
Units for energy, they must be able to operate. He noted that the heat rate for these Units is very
high, at least 13,000 btu’s per kilowatt hour, whereas the competing Calpine unit is approximately
half of that. Therefore, the Units are a non-competitive resource that the City pays a lot of money for
in order to have capacity and the value is continuously decreasing. While not fully quantified, these
are the real risks involved with these two (2) Units.
Responding to Mrs. Williams, Mr. Betts explained that maintenance for Units 1 and 2 should have
been done gradually over time but was deferred in previous years to avoid the additional capital cost,
which is the reason for the major $2.4M “hit” in budget for Fiscal Year 2018. He stated that the
capacity market has dropped significantly, and the PJM capacity market has many components. He
advised members that Converge, an Arrow Electronic Company, has been working, primarily with
refrigeration, to find ways to replace capacity in the marketplace by allowing customers to go offline
for a couple of minutes at a time. In the past, customers had generation in reserve or brought up
generation to meet the voltage requirements; however, since customers are able to meter the load
precisely and changes are computerized, they are able to go offline and reduce load instead of
bringing capacity on. He stated that last summer in this region, more than 1,000 MW(the amount
of a nuclear plant) were taken offline voluntarily by customers who received a notice the day before
indicating if they went offline the next day between certain hours, they would be compensated a
certain amount per kilowatt hour not used, which had a huge impact on the marketplace. The current
market is very different and continuously changing; therefore, the way in which customers invest and
adapt to the changes are also different. Mr. Betts expressed his opinion that the market is not fixed
but in some areas it is very tight; for example, in New Jersey the current capacity price is almost
$300 per MWd, whereas in Dover it has dropped. He explained that the Garrison Plant’s 300 MW
has a huge impact on costs on the Delmarva Peninsula because it is gas operated, fast, has relatively
low personnel costs, and can bid into the market very aggressively.
In regard to transmission costs, Mr. Betts explained that there has been a huge amount of
transmission expansion in PJM, which has resulted in a reduction of the number of power plants
constructed. It is a very dynamic market and, with 13,000 heat rate units, the City must consider
whether, even if investment were made in Units 1 and 2, there would be value going forward and
how much value that investment would have in the next five (5) to 10 years.
Page 71
UTILITY COMMITTEE MEETING NOVEMBER 25, 2013 PAGE 3
Mrs. Donna Mitchell, Controller/Treasurer, advised members that the 2016/2017 forecast was
completed last May and, at that time, the capacity price was $193 per MWd. The price was now at
$119 per MWd; therefore, she stated that the capacity revenue would change accordingly. She noted
that a leak on a gasket on Unit 1 had to be repaired last year and the costs were over budget. In
addition, she expressed concern regarding costs involving Unit 3. She stated that it had been
borescoped and will be opened up for repair. This was scheduled as a three (3) year project which
started with a $1.21M budget for the turbine repair and generator; however, the bids received for the
turbine were excessive, so the generator was done separately at a cost of $276,000. The costs for
the turbine repairs for Unit 3 were currently up to $1.6M, and she noted that when it is opened,
additional repairs may be required which would increase the costs.
In response to Mr. Perza, Mrs. Mitchell stated that staff’s recommendation would not include
bidding Units 1 and 2 in the PJM market beyond Fiscal Year 2017 since staff anticipated a joint
agreement with Calpine or another capacity agreement to pick up 34 MW. She confirmed that it
was staff’s recommendation not to fund capital improvements to bring the Units up to current
standards and not to fund these Units beyond the next three (3) years. If the Units began to fail in
the next year or two (2), she stated that the City would have the option to pull the Units out of the
PJM market instead of investing capital into them; however, the City would have to pay for the
capacity and pay a forced outage penalty if the Units went down when scheduled to run. In order
to meet the December 1, 2013 deadline, it was staff’s plan to bid the Units into the capacity auction
for the 2017/2018 planning year at $311per MWd to ensure they do not get called on and the City
recoups the money, as recommended by TEA.
Noting that the City was obligated to keep Units 1 and 2 operating since they have been included in
the auction for the next couple of years, Mr. Slavin questioned if the Units would be revenue positive
to the City based on the assumption that the market does not completely bottom out on the capacity
side. Responding, Mrs. Mitchell confirmed that they would be revenue positive through Fiscal
Year 2017 based on the analysis. She indicated that if the Units were unavailable to run when
required, the City would be able to decide whether or not to pay for repairs at that time.
Mr. Slavin questioned the net effect on the City’s revenue if it was decided not to keep Units 1 and
2 online beyond 2018. In response, Mrs. Mitchell stated that staff had only forecasted out to the
2018 PJM year; however, according to Mr. Betts, the replacement capacity costs would define
whether the City was “in the money or not” for those Units.
Responding to Mr. Blakeman, Mrs. Mitchell referred to the projected incremental operating costs
indicated on Page 19 of the presentation and indicated her opinion that the $1M amount could
decrease more since staff was currently negotiating contracts.
Staff recommended, for the short term, that Units 1 and 2 not be offered into PJM’s capacity auction
for the 2017/18 delivery year; that a comprehensive analysis be performed that lays out all the
decision options for the City of Dover; that a similar analysis on other parts of the generation
portfolio be completed; and that all supply options be surveyed, including new generation projects
in and around Dover and Power Purchase Agreement (PPA) opportunities.
Page 72
UTILITY COMMITTEE MEETING NOVEMBER 25, 2013 PAGE 4
Mr. Perza questioned the future impact on revenues if these Units are shut down, irrespective of how
much it would cost to get the turbines up and running, and how members could make an assessment
and final decision regarding this matter if staff had not planned beyond 2017. Responding,
Mrs. Mitchell stated that one (1) of the factors to consider in determining whether the Units should
be shut down or not would be the capacity auction, as well as the figures received from TEA. She
noted that if the City can obtain the capacity cheaper from Calpine, it may not be advantageous to
keep Units 1 and 2 running. Elaborating, Mr. Betts indicated that there were a lot of “moving
pieces,” one (1) of which was the renegotiation of the NAES Agreement, which may lower operating
costs. The other was whether the City would be able to have Garrison or some other entity buy
replacement capacity, noting that if the City were able to obtain a longer-term offer, it would provide
a benchmark price to compare with the cost to operate the Units. Both of these were on a relatively
“fast track,” which would allow for a longer-term budget analysis for members to review.
Mr. Betts stated that it is an imperfect system. In a dynamic market, no one knows what the energy
prices will be in four (4) years, but the hope is that energy will still be consumed at a consistent rate.
It is known that the capacity market is changing, so staff, including himself, must consider the best
case, examine the alternatives of keeping the Units running, and make projections based on historic
costs versus replacement capacity. It was his opinion that this would be the basis for the estimate
built into the City’s overall operating budget for the utility.
Mrs. Williams questioned whether Mr. Betts had any concern regarding negotiating an agreement
with Calpine since the City incurred great expense and gave land to them. Responding, Mr. Betts
stated that he and staff would do their best to hold Calpine to the terms of the contract, which
provided for at least 50 MW at a cost that was established as the actual construction costs less the
development costs. If Calpine is willing to abide by the contract terms, he believed there could be
an opportunity for negotiation that may be favorable for the City. As a competitive strategy, he
stated that the City should also consider other available capacity. He stated that the City not only
offered the benefit of the land provided to Calpine but can also provide constant cash flow, which
they cannot necessarily get from PJM. He also suggested that the City use its monopoly power as
a water supplier to encourage negotiation.
In response to Mrs. Williams, Mr. Betts confirmed that Calpine does not have internal “inside the
fence” capacity, which could also effect negotiations. Mr. Betts advised members to consider the
cost and value of the City’s reliability to “island” the City, notwithstanding occurrences in the region.
He stressed the importance of the comprehensive analysis proposed by TEA, and that consideration
be given to the reasons the City is in the municipal utility business, including reliability, costs, and
the attractiveness of the City to outside potential buyers. He stressed that reliability is critical and
if it were desired to bring in a data center, as was discussed in previous years, reliability must be at
99.9%. He stated that, with PJM, there had been huge investments in transmission that was not in
existence 10 years ago. He noted that there are many rules that apply to the City, in regard to
reliability under requirements with PJM and this zone, that have federal implications. The current
environment for reliability is very different than it was 10 - 15 years ago, which should be taken into
account when considering pricing and value for internal versus external generation.
Page 73
UTILITY COMMITTEE MEETING NOVEMBER 25, 2013 PAGE 5
In response to Mr. Perza, Mr. Koenig stated that, to his knowledge, the City had not had a negative
cash flow similar to what was projected for Fiscal Year 2017/2018 since contracting with PACE,
approximately 15 years ago.
Responding to Mr. Perza, Mr. Koenig stated that the Units would last as long as the City would be
willing to invest in maintenance, which would depend upon economic feasibility. It was staff’s
opinion that, at this point, maintaining the Units would probably not be in the City’s best interest
financially. Mr. Blakeman stated that prior to his retirement from the City of Dover, approximately
10 years ago, all similar units that were built in 1962 had been retired.
Mr. Betts suggested that a comparison of the costs to operate the Units (capital, operating, and gas)
with the amount purchased through the PJM power grid or TEA, would provide an indication as to
whether the Units should be maintained or not. He suggested that TEA be requested to provide this
information to members for their consideration in making a determination.
Mr. Blakeman moved to recommend approval of staff’s recommendations that, for the short
term, Units 1 and 2 not be offered into PJM's capacity auction for the 2017/18 delivery year;
that a comprehensive analysis be performed that lays out all the decision options for the City
of Dover; that a similar analysis on other parts of the generation portfolio be completed; and
that all supply options be surveyed, including new generation projects in and around Dover
and Power Purchase Agreement (PPA) opportunities. The motion was seconded by
Mr. Snaman and unanimously carried.
[City Clerk’s Office Note: Subsequent to the meeting, members were provided a memorandum dated
December 4, 2013, from Donna Mitchell, Controller Treasurer - Response to Questions, Utility
Committee Meeting November 25, 2013, relating to this matter, as well as an Outage Status Report -
Week 9, dated November 27, 2013 (Attachment #1).]
VanSant Generating Station Capacity Increase - Cost/Benefit Analysis
Mr. Scott Koenig, City Manager, reviewed a Presentation - Cost/Benefit Analysis for City of Dover -
Update on VanSant Generating Station Capacity Increase.
Staff recommended that staff be authorized to continue to proceed with project implementation and
reassess economics after bids for project installation are received and before submitting an offer into
PJM for the 2017/18 capacity auction on May 12, 2014, noting that PJM must be notified of intent
to bid in Units 1 & 2 by March 1, 2014.
Mr. Blakeman questioned whether staff had considered installing a waste heat recovery boiler to
create a combined cycle unit. Responding, Mr. Koenig stated that it had been discussed previously;
however, it was not included in the most recent reviews. He speculated that there must have been
a technical or regulatory issue associated with it.
Responding to Mrs. Williams regarding the Indian River Coal Plant, Mr. Koenig stated that it will
have an effect on the market, which may have an indirect effect on the City; however, he was not
aware of the time frame.
Page 74
UTILITY COMMITTEE MEETING NOVEMBER 25, 2013 PAGE 6
Mr. Slavin moved to recommend approval of staff’s recommendation, seconded by
Mr. Snaman and unanimously carried.
[City Clerk’s Office Note: Subsequent to the meeting, members were provided a memorandum dated
December 4, 2013, from Donna Mitchell, Controller Treasurer - Response to Questions, Utility
Committee Meeting November 25, 2013, relating to this matter, as well as an Outage Status Report -
Week 9, dated November 27, 2013 (Attachment #1).]
Purchase Power Agreement - Calpine
Mr. Scott Koenig, City Manager, advised members that staff intends to seek the assistance of
Mr. Kirk Betts, Betts & Holt LLP, the City’s Energy Attorney, for discussions regarding a mutually
beneficial contract arrangement for the potential Power Purchase Agreement (PPA) with Calpine.
He stated that this information was provided for informational purposes only and that no further
action was required at this time.
Discussion - Joint Agreement with the Delaware Municipal Electric Corporation (DEMEC) for New
Generation
Mr. Scott Koenig, City Manager, explained that as a part of staff’s due diligence to examine the
possibilities for replacing the capacity of Units 1 and 2, should they be taken out of service, staff
intends to meet with the Delaware Municipal Electric Corporation (DEMEC) and/or another partner
they may have, to discuss the potential for joint projects, such as capacity improvements, provided
a Purchase Power Agreement (PPA) with Calpine cannot be arranged. He stated his preference for
keeping the City’s options open moving forward and that he will keep Council updated in regard to
all discussions.
In response to Mr. Blakeman, Mr. Koenig stated that staff would complete financial analyses on all
of the available options, and the potential for DEMEC to own part of the City’s units would be open
for discussion.
Mr. Koenig stated that this information was provided for informational purposes only and that no
further action was required at this time.
Mr. Blakeman moved for adjournment, seconded by Mr. Snaman and unanimously carried.
Meeting adjourned at 5:57 p.m.
Beverly C. Williams
Chairwoman
BCW/TM/dd/js
S:\AGENDAS-MINUTES-PACKETS\Committee-Minutes\2013\11-25-2013 UTILITY.wpd
Attachment
Attachment #1 - Memorandum dated December 4, 2013, from Donna Mitchell, Controller Treasurer - “Response to
Questions, Utility Committee Meeting November 25, 2013” and Outage Status Report - Week 9 -
November 27, 2013
Page 75
ATTACHMENT #1
Utility Committee Meeting of 11/25/2013
Page 81
Outage Status Report--Week 9
Project Title: Units 1, 2, 3 and 11 Fall 2013 Planned Outage
Report Date: Wednesday, November 27, 2013
Perform outage related work that returns critical unit equipment to safe and reliable condition that supports maintaining unit availability in the most cost
Outage Objectives
effective manner. All work will be performed in accordance with safe work practices and without impact to the environment.
Major Work Activities Planned:
Boiler and drum insurance inspections. (Complete)
Boiler duct work inspection. (Complete)
Unit 1
Clean and inspect generator chokes and insulators. (Complete)
Throttle valve mechanism replacement. (Complete)
Boiler and drum insurance inspections. (Complete)
Unit 2 Boiler duct work inspection. (Complete)
Clean and inspect generator chokes and insulators. (Complete)
Boiler duct work inspection. (Complete)
Boiler and drum insurance inspections. (Complete)
Boiler reheater support repair scope development (Deferred to Spring Outage)
Drain, clean and inspect the Industrial Waste Water pit liner. (Complete)
Unit 3
Cooling tower basin water level reduction and closure of discharge point to Outfall 005. (Complete)
Cooling tower hot water basin decking replacement. (Complete)
Boiler drains header piping and valve replacements. (Complete)
Boiler main steam piping hanger adjustments. (Complete)
Inspect duct work and stack liner. (Complete)
Unit 11 Remove/inspect/replace fuel nozzles and fuel oil check valves.(Complete)
Planned Schedule: October 1, 2013 @ 0700 to November 27, 2013 @ 0700
The planned outage for Units 1, 2, 3 and 11 was cleared with PJM on Wednesday, November 27, 2013 at 0640 hours. TEA was also notified of the clearing of outage. Units were made
Week 9 -Schedule Update
available for dispatch commencing HE 8 on 11/16/13 by TEA.
Week 9 - Safety and Environ. There were no safety or environmental issues during the week.
Accomplishments/ Problems for the Report Period:
Week 9
Units 1 and 2
The NAES Operations Team cleared the PJM outage tickets Wednesday November 27, 2013 at 0640 hours. Units have been walked down and are now ready for service, if requested.
Week 9
Unit 3
The NAES Mechanics and APEX Power and Heat (mechanical contractor) completed the installation of Unit 3 Boiler drain piping and isolation valves to the expansion tank. New heat tracing, insulation and lagging
will need to be installed to complete this project.
The NAES Operations Team cleared the PJM outage ticket Wednesday November 27, 2013 at 0640 hours. Unit has been walked down and is now ready for service, if requested.
Week 9
Unit 11
The NAES Mechanics and ICE Technicians removed and replaced the AC lube oil pump. The Pump and motor were bump tested for proper rotation and then placed in service for further testing. With the pump and
motor coupled together, both operated properly and the unit was placed on ratchet. Lockout/tagout was removed and unit was made ready for dispatch.
The NAES Operations Team cleared the PJM outage ticket Wednesday November 27, 2013 at 0640 hours. Unit has been walked down and is now ready for service, if requested.
Week 9
Other Plant Activities:
During the week, the Plant Maintenance staff continued addressing monthly preventive maintenance (PM) work orders, while completing outage activities. PM's for November are being addressed as planned and on
schedule.
Page 82
Items requiring Immediate Management Attention and / or Support:
Week 9
There were no immediate attention or support items addressed this week.
Actions to Problems/ Changes to Plan:
Week 9
There were no problems/changes to planned activities conducted during the week.
Major upcoming activities (two week look ahead):
Unit 1-
Resolution to the leakage problem on the expansion joint. Continuing to investigate and locate proper sealant. (No outage required)
NAES Mechanics to remove and install new continuous blowdown piping to the lab. (No outage required)
Unit 2- A1
Resolution to the leakage problem on the expansion joint. Continuing to investigate and locate proper sealant. (No outage required)
Unit 3-
NAES Mechanics to install framing for neutralization pit once parts are received. Cover material has yet to be ordered. as staff is waiting for material quotes.(No outage required)
County Scaffolding to remove scaffolding once plant repair projects (hanger adjustments and insulation repairs) have been completed. (No outage required)
NAES Mechanics to install "A" Industrial Waster Water pump once it is received. (No outage required)
Unit 11-
There are no upcoming activities.
Budget Update: As of 11-27-2013 Week 9
Additional Expected
Budgeted Committed to Expenses to Total at
O&M Account Number Description Amount Date Complete Completion Variance Comments
480-8101-591-30-31 Contractual Services $31,200 $18,565 $5,000 $23,565 $7,635
Note: Negative variance for the outage time frame due
to ordering items and services that are budgeted for
during the spring outage such as insulation repairs, chart
Auxiliary Systems Repairs - recorder replacement, and air compressor maintenance
480-8101-591-30-80 Maintenance $15,700 $44,341 $2,500 $46,841 -$31,141 kits.
480-8101-591-30-81 Boiler Repairs $10,000 $13,346 $0 $13,346 -$3,346
480-8101-591-30-82 Continuous Emission Monitors $9,000 $5,209 $1,800 $7,009 $1,991
Cooling Tower Systems
480-8101-591-30-85 Maintenance $3,000 $872 $2,128 $3,000 $0
Note: Negative variance for the outage time frame due
to performing an unscheduled borescope inspection
480-8101-591-30-87 Combustion Turbine Maintenance $5,000 $6,158 $1,500 $7,658 -$2,658 prior to replacing Van Sant fuel nozzles.
480-8101-591-30-88 Power Distribution Repairs $3,000 $1,383 $900 $2,283 $717
Turbine Generator Repairs-
480-8101-591-30-89 Maintenance $4,000 $3,291 $709 $4,000 $0
Total O&M $80,900 $93,165 $14,537 $107,702 -$26,802
Page 83
Capital Projects
Additional Expected
Budgeted Committed to Expenses to Total at
Capital Project Number Description Amount Date Complete Completion Variance Comments
Bid awarded for Inspection - Repair Services,
EG1212 Unit #3 Turbine Inspection $1,149,800 $764,138 $385,662 $1,149,800 $0 Consumables have been purchased with some parts
being received. Work to be done in the spring outage
EG1402 Unit #3 Cooling Tower Repairs $42,000 $31,575 $10,425 $42,000 $0 Major Work completed 10-24-2013
Unit #3 Auxiliary Component Waste Water Pump Repairs to Date, Unit #3 Boiler
EG1404 $116,000 $75,559 $40,441 $116,000 $0
Replacement - Repairs Header Drain Repairs
Fuel Nozzle Parts from Inventory - Nozzles, Check
Van Sant Component Valves, Gaskets, Flex Lines. Lube oil pump replacement
EG1405 $32,000 $30,245 $1,755 $32,000 $0
Replacement - Repairs costs to be determined next week. Expect this job to be
overspent.
McKee Run High Energy Piping Planning ongoing, No expenditures to date this FY.
EG1406 $80,000 $0 $80,000 $80,000 $0
Repairs Work to be performed in the spring overhaul
Project meeting held, planning ongoing, no expenditures
to date, work not scheduled this outage. Have received
EG1407 Metering System Upgrades $25,000 $0 $25,000 $25,000 $0
quote form COD vendor. Getting clarification from
vendor on several items.
McKee Run and Van Sant Safety
EG1408 $86,000 $0 $86,000 $86,000 $0 Work not scheduled this outage.
and Compliance
McKee Run Natural Gas Block
EG1409 $65,000 $0 $65,000 $65,000 $0 Planning ongoing, No expenditures to date this FY.
and Bleed Valve Replacement
McKee Run - Van Sant Structural
EG1413 $42,000 $0 $42,000 $42,000 $0 Bids received. Project on hold due to budget restraints.
Preservation
McKee Run Units #1-#2 Unit #1 Boiler Tube Leak and Turbine Throttle Valve
EG1415 Component Repair - $105,000 $31,173 $73,827 $105,000 $0 Repairs. Balance of work to be performed in the spring
Replacement outage
Permitting and Engineering Support activities only to
EG1416 Van Sant Capacity Increase $250,000 $51,350 $198,650 $250,000 $0
date.
Total Capital $1,992,800 $984,040 $1,008,760 $1,992,800 $0
Page 84
Contractors on Site During On Site
Scope
Course of Outage Week 9
EVAPTECH No - Work is
Remove and install hot water basin cover.
(Cooling Tower Contractor) completed.
General Electric
Borescope inspection of fuel system combustion No - Work is
(Measurement and Control
internal parts. Complete
Solutions)
Hallaton Inc.
No - Work is
( Industrial Waste Pit Liner IWW pit liner inspection and repairs to liner.
Complete
Repair Company)
XL Insurance Company Inspection of internal steam drums for Units 1, 2, 3 No - Work is
(Boiler/Drum Inspector) and mud drums for Units 1 & 2. Complete
No - will need
to return at a
later time to
take down
County Scaffolding Company Install scaffolding for various projects on Units 1,2,3 scaffold once
insulation and
hangar
adjustments
are complete.
Install insulation and lagging for various projects on
County Insulation Company Yes
Units 1,2,3
Install root isolation valves for two projects on Unit
APEX Heat and Power LLC. Yes
3.
Page 85
LEGISLATIVE, FINANCE AND ADMINISTRATION COMMITTEE
The Legislative, Finance, and Administration Committee meeting was held on November 25, 2013,
at 6:00 p.m. with Chairman Lynn presiding. Members present were Mr. Hare, Mr. Slavin,
Mr. Rushe, and Mr. Shevock. Members of Council present were Council President Bonar (arrived
at 6:14 p.m.), Mr. Dixon (arrived at 6:03 p.m.), Mrs. Williams (arrived at 6:10 p.m.), and Mr. Hutchison.
Mayor Carey was also present.
AGENDA ADDITIONS/DELETIONS
Mr. Rushe moved for approval of the agenda, seconded by Mr. Shevock and unanimously
carried.
Vehicle Purchase/Transfer - Mayor
Police Chief James Hosfelt informed members that the Police Department currently had a new
Dodge Charger, and it was staff’s desire to replace the Mayor’s vehicle with the Dodge Charger and
bring the Mayor’s Crown Victoria back into the Police Department’s fleet of vehicles. He stated that
Crown Victorias were no longer made; therefore, as the City transitions from Crown Victorias to
Dodge Chargers, equipment used in the Crown Victorias would no longer be usable. Chief Hosfelt
stated that staff would like to bring the Mayor’s Crown Victoria back into the fleet while the
equipment needed to outfit the vehicle was still available in the Department. He noted that this
would cost less than equipping the Charger.
Staff recommended approval of the vehicle transfer.
Responding to Mr. Slavin, Mayor Carey stated that there were approximately 20,400 miles on the
Crown Victoria.
In response to Mr. Slavin, Chief Hosfelt stated that, according to normal procedure, the Crown
Victoria would be rotated out of active use when 80,000 - 85,000 miles were accumulated and that
the condition of the vehicle would also be taken into consideration. He advised members that he was
uncertain when this mileage would be reached. Chief Hosfelt stated that this depends on the
serviceability of the particular vehicle, noting that dependable vehicles are used quite often; however,
the average time span for a dependable vehicle to reach this mileage was approximately five (5) to
six (6) years. He reminded members that, unlike State Police vehicles that typically have one (1)
user, City vehicles are used 24/7 by multiple operators.
Responding to Mr. Hare, Chief Hosfelt confirmed that the requested action would save the Police
Department money in the long run as they would not have to buy new equipment for the Charger or
waste equipment that was already available.
In response to Mr. Slavin, Chief Hosfelt estimated that the cost of the equipment that would be
installed in the Charger, if it were outfitted, would be approximately $10,000.
Responding to Mr. Lynn, Chief Hosfelt stated that aftermarket equipment would be installed in the
vehicle after the Mayor’s use and would include police inserts used to separate prisoners from the
vehicle operator and light bars.
Page 86
LEGISLATIVE, FINANCE, AND ADMINISTRATION
COMMITTEE MEETING OF NOVEMBER 25, 2013 PAGE 2
Mr. Hare moved to accept staff’s recommendation to approve the vehicle transfer as
requested, seconded by Mr. Shevock and carried by a vote of four (4) yes (Hare, Lynn, Rushe,
and Shevock) and one (1) no (Slavin).
Request of Elizabeth W. Murphey School - Grant for Judo Mats
Mr. Scott Cook, 256 Holly Hill Drive, Smyrna, advised members that he was a black belt in judo at
the Elizabeth W. Murphey School in Dover, where children and adults are taught the art of judo
through the instruction of Mr. Tommie Little. He noted that this program had begun in April 2013
and the class was expanding. Mr. Cook explained that there were approximately 26 participants
using 20' x 30' mats in the Elizabeth W. Murphey Hall and there was not a great deal of mat space
for practice. Students were required to take turns using mats and he indicated that support was being
sought to purchase additional mats so that students could be trained properly. He noted
approximately six (6) Murphey School residents were involved in the class, as well as one (1) staff
member and the class was continuing to grow. He requested assistance from the City of Dover to
purchase mats for the School.
Mr. Thomas Little, 400 N. DuPont Highway, B-23, explained that he worked at Family Court for
the last eight (8) years and when he moved to the area last March, he received permission from the
Murphey School to use their hall for judo instruction. He noted that he initially purchased mats for
$3,000 and paid $1,200 for gis (uniforms) for the children. He indicated that the class had been very
successful, required no fees, and was open to the entire community, including police agencies. He
expressed the organization’s hope to expand the program.
Responding to Mr. Lynn, Mr. Cook stated that the cost of a two (2) inch thick, 5' x 10' mat was $239.
Mr. Little stated that10-12 mats were desired.
Mr. Slavin noted that the total cost would be approximately $2,500. He stated that he would recuse
himself from any vote on this request because he had financial dealings with the Murphey School
through his job with the State of Delaware but he would vet this matter with legal counsel to verify
his standing before the request would be considered by Council.
Mr. Hare inquired if it was possible for the City to make a $2,500 donation to the Murphey School.
Responding, Mr. Koenig suggested that perhaps the Council budget could be examined to determine
if there were funds available; however, Mrs. Traci McDowell, City Clerk, indicated that there were
not adequate funds within this budget.
Mr. Hare offered to donate $250 and noted that if each Council member donated the same, the
desired amount could be raised.
Mr. Lynn requested Mr. Koenig to provide a recommendation for funding the project at the next
meeting.
Page 87
LEGISLATIVE, FINANCE, AND ADMINISTRATION
COMMITTEE MEETING OF NOVEMBER 25, 2013 PAGE 3
Responding to Mr. Lynn regarding the status of a City grant-in-aid policy, Mrs. Donna Mitchell,
Controller/Treasurer, indicated that the City was in the process of developing such a policy. She
noted that the only contributions of this type made by the City each year were going to Kent County
Tourism and the Downtown Dover Partnership (DDP). She noted that she had drafted a grant-in-aid
policy for the City mirroring the State’s policy and this would be brought forward for the
Committee’s review at a subsequent meeting. Mrs. Mitchell expressed her belief that Council had
adopted policies regarding gifts and donations that would prohibit cash donations and offered to
provide this information to members. She explained that staff was in the process of preparing a
revised Budget Ordinance which was planned for presentation at the next Committee meeting that
would include project funding and budget balance carry-forwards and suggested that funding for this
matter could be incorporated if Council so chose.
Responding to Mr. Lynn regarding whether mats could be provided to the School, rather than a
donation of funds, and if this would comply with the policy, Mrs. Mitchell stated that she did not
believe that this would be in compliance.
In response to Mr. Shevock regarding the existing policy and procedure for grants in aid from the
City, Mrs. Mitchell stated that there was no grant-in-aid policy as yet; however, a gift policy had
been approved by Council some time ago. She indicated that this prohibited cash donations and
stated her belief that permitted donations were limited to items like City flags and shirts.
Mrs. Williams stated her opinion, as an executive of a private non-profit group and as a
Councilwoman, that opening a grant-in-aid type program for private non-profit organizations in the
City would result in the receipt of thousands of applications.
In response to Mr. Lynn regarding the auspices under which the City provides funds to Kent County
Tourism, Mrs. Mitchell stated that these funds were provided to support the Dover Days Festival.
Mr. Lynn inquired why this donation was not a violation of City policy. Responding, Mrs. Mitchell
stated that this had been approved in the past and was incorporated in the City’s budget because it
is a Dover festival.
In response to Mr. Lynn, Mr. Koenig indicated that the City had also provided funds in support of
the African American Festival.
Noting that Mr. Little was a lawyer, Mr. Rushe suggested that Mr. Little reach out to the Kent
County Bar Association for assistance. He offered to speak with Mr. Little after the meeting to
discuss other avenues for assistance.
Mrs. Williams suggested that Kent County Levy Court also be contacted since they have an
appropriate program and do make cash grants. She offered to provide contact information.
Page 88
LEGISLATIVE, FINANCE, AND ADMINISTRATION
COMMITTEE MEETING OF NOVEMBER 25, 2013 PAGE 4
Mr. Rushe moved to table the request until the next meeting so that more information could
be obtained regarding where the money may come from, seconded by Mr. Hare and carried
by a vote of four (4) yes (Hare, Lynn, Rushe, and Shevock) and one (1) abstention (Slavin).
By unanimous consent, the meeting adjourned at 6:17 p.m.
Sean M. Lynn
Chairman
SML/TM/js/dd
S:\AGENDAS-MINUTES-PACKETS\Committee-Minutes\2013\11-25-2013 LF&A.wpd
Page 89
Monthly Report
October 2013
Office of City Assessor
Page 90
Assessor’s Report
Number of Deeds Stamped for the Transfer Tax Dollar Amount for the
Month of October 2012/2013 Month of October 2012/2013
$50 $42
38 33
Thousands
40
$23
30 20 $20 $20 $11
16 $12
20 11 $7 $3
6 2013 2013
10 1 1 2 4
$0
0 2012 2012
First Time Buyer for Month of October 2012/2013 Realty
October 2012/2013 PropertySales in Dollars Received
20 Prior to Recording
20 16 $3 $3
Res. Non‐First $3
$1 $2
Millions
15 11 Time Buyers $2 $1 $1 $1
Res. First Time $1 $0
10 6 2013
Buyers $0
5 2012
0
2013 2012
Major Updates
August ‐ 13 September ‐ 13 October‐ 13
Assessment Change $98,900 $2,468,800 $390,500
Residential Sales Ratio Report
Sales in Study Total Assessed Total Sale Price Ratio PRD
Value
28 $4,810,200 $4,508,443 1.07 1.06
Page 1
Page 91
Assessor’s Report
Ratio – Assessed Value divided by Sale Price.
PRD – Mean – A PRD above 1.03 tends to indicate assessment regressivity – high valued properties are under
appraised relative to low valued properties. A PRD below .98 tends to indicate assessment progressivity – high
valued properties are relatively over appraised.
Points of Interest
Scanning & Filing
‐ All new deeds are being scanned and attached to the CAMA software for easy retrieval.
‐ All appeal documents and correspondence are being scanned and attached to the CAMA software for
easy retrieval.
‐All old property record cards are being scanned and indexed into Fortis.
2015 Revaluation
‐ The Assessor’s Office has started the 2015 Revaluation process by visiting various neighborhoods
and collecting data, if necessary.
Assessor’s Office
Supplemental Billing:
Supplemental bills were mailed out totaling $8,003.08
Delinquent Taxes:
First Sheriff Sale Notifications were mailed out October 14, 2013.
Page 2
Page 92
NOV 14, 2013 CITY OF DOVER PAGE: 1
09:12 AM SALES RATIO REPORT CA324
PARID NBHD LUC ADDRESS UNITS STYLE YRBLT STORIES SFLA GRADE CDU TOTAL APPR SALE DT PRICE ASR
ED05-067.01-01-41.00 26A R10 326 TOPAZ CIR 5 2013 2 2483 B GD 258,000 30-OCT-13 276,827
ED05-067.01-02-09.00 26A R10 15 GEMSTONE BLVD 1 2013 2 1941 B GD 241,900 18-OCT-13 202,980
ED05-067.12-03-18.00 8B R10 937 SILVER LAKE DR 1 13 1983 2 2120 B VG 203,700 31-OCT-13 212,000
ED05-067.14-02-07.00 2B R10 61 OLD FORGE DR 1 5 1974 2 1880 C AV 162,600 18-OCT-13 165,000
ED05-067.15-04-24.00 11 R10 814 WILSON DR 1 5 1967 2 1939 C GD 172,100 04-OCT-13 187,000
ED05-067.18-01-03.00 21 R10 1502 COLLEGE RD 1 14 1960 1 1348 D FR 82,000 04-OCT-13 30,000
ED05-068.10-03-21.00 13 R10 516 NIMITZ RD 1 16 1966 1 1436 C AV 154,100 04-OCT-13 123,500
ED05-068.13-01-04.28 53 R50 55 CHATHAM CT 1 13 1984 2 2112 B+ EX 143,600 03-OCT-13 152,000
ED05-068.14-01-27.00 13 R10 1105 WHITE OAK RD 1 14 1964 1 1040 C AV 160,800 11-OCT-13 129,000
ED05-068.14-02-36.00 13 R10 205 MACARTHUR DR 1 5 1965 2 1524 C+ AV 139,100 25-OCT-13 127,606
ED05-068.15-03-66.00 16G R10 1424 HOPKINS AVE 1 5 1996 2 2160 C+ AV 165,800 14-OCT-13 140,000
ED05-068.18-05-25.00 27 R10 606 SPRING GARDEN ST 1 14 1993 1 1276 C AV 142,400 24-OCT-13 122,000
ED05-075.08-01-38.00 24 R10 225 FALMOUTH WAY 1 14 1999 1 1905 B- GD 204,200 18-OCT-13 204,250
ED05-076.05-07-35.00 22 R10 219 PEBBLE VALLEY PL 1 5 1994 2 2770 A- VG 309,300 22-OCT-13 247,500
ED05-076.06-08-60.00 17A R10 39 PERIWINKLE CT 1 13 1995 2 1260 C+ AV 131,100 03-OCT-13 120,000
ED05-076.09-03-28.00 25 R10 360 NORTHDOWN DR 1 5 2008 2 1986 C+ AV 177,800 23-OCT-13 185,000
ED05-076.11-02-30.00 16 R10 1173 N FARMVIEW DR 1 5 1990 2 1916 C+ AV 171,400 15-OCT-13 145,000
ED05-076.20-03-16.00 30 R10 543 WOODSEDGE RD 1 5 1961 2 1987 B- AV 161,600 01-OCT-13 209,000
ED05-077.06-01-36.00 8 R10 534 GREENHILL RD 1 1 1941 2 1741 B- AV 160,000 15-OCT-13 189,000
ED05-077.11-02-57.00 13A R10 642 ROBERTA AVE 1 14 1967 1 1130 C GD 155,800 15-OCT-13 150,000
ED05-077.11-02-70.00 13A R10 631 ROBERTA AVE 1 5 1967 2 1483 C+ AV 156,500 21-OCT-13 160,000
ED05-077.11-05-28.00 16J R10 52 MER WAY 8 2013 2 2266 B- AV 216,200 04-OCT-13 195,000
ED05-077.17-02-14.00 5 R10 916 N SUNSET DR 1 14 1959 1 1633 C+ AV 196,700 08-OCT-13 130,000
ED05-077.17-03-36.00 32 R10 1051 S BRADFORD ST 1 3 1961 1.5 1696 C+ AV 154,400 25-OCT-13 130,000
ED05-077.17-05-41.00 34 R10 184 ORCHARD AVE 1 14 1952 1 1112 C FR 113,500 18-OCT-13 110,880
ED05-085.08-02-67.00 12 R10 411 DOGWOOD CT 1 16 1964 1 1766 C+ AV 157,500 16-OCT-13 145,000
ED05-085.12-01-27.00 12 R10 245 KESSELRING AVE 1 5 1964 2 1802 C+ AV 158,700 18-OCT-13 158,000
ED05-085.12-01-45.00 12 R10 252 KESSELRING AVE 1 5 1964 2 1550 C+ AV 159,400 18-OCT-13 161,900
Page 93
CITY MANAGER’S
MONTHLY REPORT
OCTOBER 2013
City Manager’s Monthly Report, October 2013
Page 94
Human Resources
Continued contract negotiations.
Library
326 attended 66 programs for adults.
412 attended 30 programs for teens.
1,026 attended 36 programs for children.
35 volunteers completed 356 hours of service.
113 attended 49 programs/classes coordinated through the Job Center.
Public Works
Working on CIP and additional funding for future street program and other projects.
2 City Manager’s Monthly Report, October 2013
Page 95
CUSTOMER SERVICES
Customer Service information was not available at the time of submission.
The information will be updated in next months report. Please call the
City Manager’s Office if you have any questions. Thank you.
City Manager’s Monthly Report, October 2013 3
Page 96
HUMAN RESOURCES
Oct Nov Dec Jan Feb Mar April May June July August Sept Oct
Category Total
12 12 12 13 13 13 13 13 13 13 13 13 13
Caucasian* 285 283 287 288 291 287 287 283 282 281 279 283 284 N/A
Minorities* 58 57 57 56 56 54 54 53 53 54 54 54 56 N/A
Hired 0 1 6 3 4 0 4 3 1 2 2 7 4 37
Terminated/
Resigned/ 0 4 2 3 1 7 4 8 2 1 3 2 1 38
Retired/Other
Transferred/
2 2 1 1 4 2 1 1 0 2 0 4 1 21
Promoted
Jobs Posted 2 4 0 4 1 5 5 5 8 5 5 3 2 49
Workers Comp. Inju-
5 0 4 3 1 2 1 4 3 4 3 7 2 39
ries
Workers Comp. Hours 66 138 341 363 315 259 62 28 0 119 62 384 110 2247
Insurance Claims 3 4 2 5 2 2 2 3 7 4 6 2 2 44
Full-time Employees: 326 Part-time Employees: 14 (4 Pitts Center, 1 Recreation, 9 Library)
-Numbers do not reflect, temporary, seasonal, relief fire dispatchers, committee or council members.
Positions Hired: Fleet and Facilities Supervisor, Laborer II, (2) Police Officers,
Positions Transferred/Promoted: Library Clerk II to Library Assistant
Resigned, Retired/Terminated: Lineman 1st Class
Positions Posted: Part-time Library Assistant (2), Storekeeper/Buyer I
Recruitment Information (Positions Closed in October)
American Un-
Blac Hispan- Asian/Pacific In Out
Position Total Female Male Unknown White Indian/Alaskan known
k ic Islander Dover Dover
Native
Library Assistant (part-time (2)) 59 47 7 5 21 28 1 4 - 5 27 32
Store/keeper Buyer I 40 20 16 4 6 27 1 1 1 4 12 28
Unfilled/Open Positions by Department*
Unfilled/Open Positions Oct Dec Jan Feb Mar April May June July Au- Sept Oct
Nov
By Department 12 12 13 13 13 13 13 13 13 gust 13 13
12
13
Electric 3 3 4 4 4 4 4 4 4 4 4 5
3
Public Works 12 14 11 13 17 19 22 22 20 20 16 15
12
Police 5 5 4 1 1 2 1 0 1 2 3 3 1
All Other Departments 6 7 5.5 6.5 7 7.5 5.5 6.5 6.5 6.5 6 8.5
7
Totals 26 26 21.5 24.5 30 30.5 31.5 33.5 32.5 33.5 29 29.5
27
*Not used for Budgeting Purposes
²
The following has been updated to reflected the Fiscal 2013-14 Budget
Electric: Electric Director, Electrical Engineer, Senior Lineman, Line Crew Superintendent, Lineman 1 st Class
Public Works: Utility Maintenance Mechanic II/Wastewater, Operations -Construction Manager, Building Craftsperson I , Motor Equipment Operator III
(Streets), (2) Motor Equipment Operators II (Grounds), Motor Equipment Operator I (Water), Motor Equipment Operator III (Sanitation), Public Works
Operation Manager, (3) Civil Engineer l, Utility Construction Worker, Crew Leader Streets, Nursery Worker II
Police: Communication Operator
All Other Departments: Fire Chief’s Assistant (Fire-Department), (3) Library Assistant (part-time), Library Clerk I (part-time), LAN Analyst, Customer
Service Collections (part-time), Planner, Storekeeper Buyer I, Fire Dispatcher
4 City Manager’s Monthly Report, October 2013
Page 97
HUMAN RESOURCES
continued
Workers Comp Injuries
20
15
10
5
0
Oct- Nov- Dec- Ja n- Feb- Ma r- Apr- Ma y- Jun- Jul - Aug- Sep- Oct-
12 12 12 13 13 13 13 13 13 13 13 13 13
Electric Public Works Police Others
Electric: 1 Public Works: 0 Police: 41 All Other Depts.: 0
Turnover Statistics
2013 *
2010 2011 2012* (CYD)
Total Turnover % 5.57 6.75 11.00 10.63
Termination Turnover % 0.27 1.08 0.29 1.48
Resignation Turnover % 2.12 4.05 5.21 4.72
Retirement Turnover % 3.18 1.62 5.50 4.43
* Healthcare cost sharing implemented
Average Employees
2010 2011 2012* 2013(YTD)
Total Number of Employees Separating from Service 21 25 38 36
Average Number of Full-time Employees 362 356 333 325
Average Number of Part-time Employees 16 15 12 14
* Healthcare cost sharing implemented
City Manager’s Monthly Report, October 2013 5
Page 98
INFORMATION TECHNOLOGY
Service Requests Resolved Citizen Action Center - Customers w/ New Issues
250 234
150
200 182 179 177
189 182 130
110
150 130 122
104 104
115 90
97 101
100 70
50 103 102 106
50 82 80 87
61
30 45 58 55 44 56 56
0 10
Oct- Nov- Dec- Jan- Feb- Mar- Apr- May- Jun- Jul- Aug- Sep- Oct- Oct- Nov- Dec- Jan- Feb- Mar- Apr- May- Jun- Jul- Aug- Sep- Oct-
12 12 12 13 13 13 13 13 13 13 13 13 13 12 12 12 13 13 13 13 13 13 13 13 13 13
Programming Requests Completed Page Views - City of Dover Web Page
25 23 35,000
30,000
20 17
25,000
14 15 15 14 15
Pages Viewed
14
15 12 13 13 20,000
10
27,002 29,413 29,435 27,721
25,196 25,562 25,827
8 15,000
23,956
10
23,096 21,716
19,308 19,853 19,936
10,000
5
5,000
0 0
Oct- Nov- Dec- Jan- Feb- Mar- Apr- May- Jun- Jul- Aug- Sep- Oct- Oct- Nov- Dec- Jan- Feb- Mar- Apr- May- Jun- Jul- Aug- Sep- Oct-
12 12 12 13 13 13 13 13 13 13 13 13 13 12 12 12 13 13 13 13 13 13 13 13 13 13
Current
Performance Indicators Last Month Same Month
Month
Last Year
iSeries Availability 100% 100% 100%
Server Availability 100% 100% 100%
AS/400 Connections
(concurrent/authorized users)
N/A N/A N/A
PCs Supported 365 351 358
Scheduled PCs Replaced - - -
Servers Supported 19 19 13
People Trained 18 16 2
Availability Statistics based on 7:00 AM until 5:00 PM Monday—Friday
6 City Manager’s Monthly Report, October 2013
Page 99
LIBRARY
Reference Transactions
1200
1000
800
600
400
200
0
Adult Teen Children
Oct 13
Adults – 1106 Teens – 499 Children – 539
Circulation October 13 FYTD 14 October 12 FYTD 13
Dover residents 22,905 90,133 21,073 64,638
Ebooks 1,369 5,344 867 3,194
Kent residents* 15,790 67,033 16,112 51,741
Non-county residents 2,249 10,308 2,139 7,393
Registrations
Dover residents 435 1,736 673 1,355
Kent residents* 38 466 154 350
Non-county residents 6 43 22 40
Other
Visiting Patrons 48,515 134,620 30,744 70,612
Meeting Room Usage 2,824 8,890 1,287 320
Photocopier Usage 1,215 5,873 1,179 2,971
Computer Printing Usage 3,091 11,664 2,319 2,891
Computer Users 5,126 20,476 4,542 8,227
Wireless Computer Users 1,196 5,088
Holds (Total) 6,698 29,702 5,964 20,720
*Breakout of Kent County Residential Statistics
Circulation Registrations
Harrington: 413 Harrington: 0
Milford: 119 Milford: 0
Smyrna: 1,052 Smyrna: 5
Outside City Limits: 14,206 Outside City Limits: 33
Total Registered Users: (Card Holders)
City: 21,779 Kent County: 12,930 Outside Kent County: 960
Other Points of Interest:
Inter/Interlibrary: 58 items loaned out Technical services: 2,094 items added
37 items borrowed 637 items deleted
Volunteers: 356 hours of service completed
City Manager’s Monthly Report, October 2013 7
Page 100
PUBLIC WORKS
Administration
Administrative review and inspection services continued on all residential and commercial developments.
The following residential subdivisions are in various phases of construction:
Oak Shadows Farthing Woods Village of Cannon Mill
Patriot Village Clearview Meadows
Emerald Pointe Eden Hill (Residential)
Sanitation
Monthly Total Refuse (Tons) Sanitation Hours
1,500
1200
956 942 1000
1,000 911
862 840 845 855
788 810 790
764
698
800
675 600
559 568 530
600 476
500 383
330 298 315 400
250 238 263
118 131 123 130 160
99 109
200 40 46
- 0
Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Bulk Collection Mechanized Hand Trash Container
12 12 12 13 13 13 13 13 13 13 13 13 13 Collection Collection Repair/Delivery
Bulk Automated Oct 13 Oct 12
OCTOBER 13 FYTD 14 OCTOBER 12 FYTD 13
Trips to DSWA Sandtown Landfill 236 918 168 691
Total Tonnage to DSWA 1,117.91 4,642.06 906.78 2,873.36
90-Gallon Containers Delivered 24 79 31 120
300-Gallon Containers Delivered 14 16 2 13
Total Man Hours-containers Delivered 40 154 46 207
CURBSIDE RECYCLING TOTAL # OF TOTAL # OF
STATS HOUSEHOLDS ACCOUNTS WEIGHT/LBS. AVE. LBS.
COLLECTED
October 2013 20,314 8,790 308,220 15.17
8 City Manager’s Monthly Report, October 2013
Page 101
PUBLIC WORKS
continued
Streets OCTOBER 13 FYTD 14 OCTOBER 12 FYTD 13
Signed Installed 17 148 27 118
Signs Repaired 17 47 15 53
Curbs Painted Yellow (feet) 0 1,306 174 5,609
New Post Installed 2 31 5 24
Storm Catch Basins Repaired 4 13 0 1
Storm Catch Basin Repairing (Hrs.) 14 65 0 1
Storm Catch Basins Cleaned 30 130 304 361
Storm Catch Basins Cleaning (Hrs.) 12 66 76 187
Hot Mix Patching (Tons) 0 1 0 236
Hot Mix Patching (Hrs.) 0 0 0 283
Cold Mix Patching Hrs.) 4 12 33 197
Concrete Work (Hrs) 18 209 108 273
Concrete Patching (Cubic Yards) 0 21 0 0
Ditch Work (Hrs). 29.0 60 14 90
Street and Alley Maintenance (Hrs) 96 264 184 696
Street Sweeping (Miles) 287 5,192 703 5,092
Street Sweeping (Cubic Yards) 126 1,302 184 1,030
Leaves Collected (Cubic Yards) 1,038 1,038 1,300 1,300
Leaf Collection (Miles) 435 435 1,358 1,358
Grounds
Arborist Crew OCTOBER 2013 OCTOBER 2012
Trees Trimmed 15 27
Trees Removed 12 15
Winterized the irrigation systems including the Library root garden.
Began working on the Christmas lights.
Worked two days on the alleys in Edgehill area.
Cleaned up the ditch that runs thru Woodbrook to the pond.
Beautification Crew
Began pulling annual beds to get ready for planting tulips and other bulbs.
Took the hanging baskets down on October 15th.
Checked in the bulb order at the Warehouse on October 23rd.
Added the leaf compost to annual beds that needed it.
Began planting bulbs on October 28th after edging, tilling and raking.
The entire Grounds staff help plant 6,000 tulips in the gateway bed on October 29th.
Mowing Crew
Most of the mowing ended around October 22nd.
Boom Axe mowing at the following locations: Schutte Park ponds, Woodbrook ditch, Cartanza substation, Dover Park
ditch, Firehouse #2 pond.
Hauled 8 pickup loads of leaf compost to flower beds to till in before planting bulbs.
Hauled 5 pickup loads of weeds/brush/and trash collected from Silver Lake Park by volunteers for a Saturday Lake clean-
up sponsored by the Silver Lake Commission. Bill Cooper and Roger Ridgeway worked the ½ day event with 30-35 vol-
unteers.
Began planting bulbs in the flower beds on October 28th.
City Manager’s Monthly Report, October 2013 9
Page 102
PUBLIC WORKS
continued
Geographic Information Systems (GIS)
Printed multiple posters for DDP and Economic Development.
Created multiple Miss Utility maps.
Updated concrete repair list.
Printed multiple posters for the Library.
Collected GPS data for storm water infrastructure.
Created street abandonment map for the City Clerk’s office.
Created storm water outfall map for water/wastewater.
Jeremy Gibb, GIS Technician, attended four day HAZUS GIS training.
Fleet and Facilities Management
Fleet Maintenance
Work Orders: 100
Major Program Updates
Measure OCTOBER 2013 OCTOBER 2012 DIFFERENCE
27 out of 28
96.43%
9 - Unscheduled PM’s Vehicles
2 - Streets. Dept - (1) Couldn’t
get to before Leaf season-in use
every day now. (1) Couldn’t get
in shop, up for replacement-they
don’t use this truck.
Scheduled Preventative Maintenance appoint- 6 - T & D vehicles –Not able to 13 out of 25
+44.43 %
ments being kept (Quantity and Percentage) get in shop-due to trash trucks 52.00%
down/other PM’s blocking bays.
Vehicles to be reschedule for
November.
2 – Code Enforcement
– Were not dropped off
4 Code Enforcement – Haven’t
seen or heard from Dept.
Facilities Management
Routine work orders completed within 5 days 32 out of 32 33 out of 238 +13.16
(Quantity and Percentage) 100 % 85.19% %
Emergency work orders completed within 2 1 out of 1 0 out of 0
0%
days (Quantity and Percentage) 100 % 100 %
10 City Manager’s Monthly Report, October 2013
Page 103
PUBLIC WORKS
continued
Water/Wastewater
Water Production/Billed Consumption/Flow to Kent
County
255000000
205000000
155000000
105000000
55000000
5000000
Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct
12 12 12 13 13 13 13 13 13 13 13 13 13
Total Water Prod. Billed Consumpt.
Total Flow to County City Readings
Major Program Updates OCTOBER 2013 OCTOBER 2012 DIFF FY14 YTD FY13
State and Federal Violations 0 violations 0 violations - - -
Water Quality Complaints 10 42 -32 43 58
Plan Review Completed Within 13 plan 8 plan 42
+5 30
30 days of Submission 100% 100%
OPERATIONAL SUMMARY
Task OCTOBER 13 OCTOBER 12 CURRENT FY
Water Production - Daily Average 4,309,774 4,308,323 559,558,000
Average Field Response Time (goal is <30 minutes) 14.60 16.87
Water Mains Repaired 1 0 3
Water Service Lines Repaired 0 4 3
Wastewater Mains Repaired 0 0 0
Wastewater Service Lines Repaired 0 0 3
Sewer Lines Flushed - linear feet 82,066 54,054 700,927
Sewer Mains Videoed -linear feet 2,102 0 18,702
Total Fire Hydrants in Service 1,807 1,795 1,807
Total Water Meters in City Distribution System 14,162 14,072 14,162
City Manager’s Monthly Report, October 2013 11
Page 104
PUBLIC UTILITIES
Electric
System Peak Total System Load
100,000
200
164.2 80,225
150.9 156.8
141.5 144.8 70,462
67,058
80,000
61,952 60,085 60,871
123.6 57,915 58,635
118.4 111.22 56,336 55,973 57,155
150
55,238 52,890
102.9 104.7 102.3 107.1
99.2 60,000
100
40,000
50 20,000
Oct 12 Nov 12 Dec 12 Jan 13 Feb 13 Mar 13 Apr 13 May 13 Jun 13 Jul 13 Aug 13 Sep 13 Oct 13 Oct 12 Nov 12 Dec 12 Jan 13 Feb 13 Mar 13 Apr 13 May 13 Jun 13 Jul 13 Aug 13 Sep 13 Oct 13
Outages Customers of Gained/Lost
35 8,000
60 54
25 6,000 50
Customers
40
Outages
15 4,000 30 26
20 15
5 2,000 9 10 11 9 7
10 3 2 5 2 4
0
Oct 12 Nov 12 Dec 12 Jan 13 Feb 13 Mar 13 Apr 13 May 13 Jun 13 Jul 13 Aug 13 Sep 13 Oct 13
-5 0
Oct 12 Nov 12 Dec 12 Jan 13 Feb 13 Mar 13 Apr 13 May 13 Jun 13 Jul 13 Aug 13 Sep 13 Oct 13
Outages: 8 Customers:
Outages 1,550
Electric Monthly Outage Report
The annual outage goal will be less than 295 Controllable Outages Average Response Time
minutes per customer, which is a Delaware Annual goal is less than 40 Goal is less than 30 minutes
Standard. This will be measured by calculating
the System Average Interruption Duration Index. Month Year-to-date Month Year-to-date
FY 14 YTD FY 14 FY 13
2 12 24.25 Minutes 25.89 Minutes
63.83 50.74 39.44
OCT 13 OCT 12 FY14 YTD
PROGRAM UPDATES
Tree Trimming 224 221 946
Number of Oil Releases 0 0 5
Lost Time Accidents – All Electric Utility Divisions 1 1 1
New Services 4 54 24
Major Goals Completed in the Past Two Months
N/A
12 City Manager’s Monthly Report, October 2013
Page 105
City Planner’s Monthly Report
Planning, Inspections & Recreation
OCTOBER 2013
Planning, Inspections & Recreation Highlights
Bicycle Friendly Community - Announcing Honorable Mention recognition
from the League of American Bicyclist on October 24, the Bicycle/Pedestrian
Subcommittee and staff were pleased their application earned the acknowledge-
ment. Future efforts will focus on gaining a Bronze or other higher level of
recognition for the City.
Dover High School Jr. ROTC - - Schutte Park hosted the Dover High
School Raider Challenge on Saturday, October 12. Nine teams of 110
cadets participated. Physical Fitness, Land Navigation, First Aid/Litter Carry, Mayor Carey, Sec. Bha & Gov. Markell
Rope Bridge & 5K were the five events in the Raider Challenge. Bicycle Friendly Community Announcement
Royal Farms—The new Royal Farms opened a location at the corner of
Saulsbury Road and North Street.
New Royal Farms
Personnel and Training Updates
Several departmental staff attended webinars offered by SunGuard through the City’s contract.
Kristen Mullaney attended a two-day workshop on Excelling At Managing People presented by Skillpath
on October 17-18, 2013
Multiple departmental staff attended the IBC Fundamentals and IRC Fundamentals Training on October
30-31, 2013.
Jason Osika attended the Emergency Medical Responder 1011 training on October 14-18, 2013 that was
held at the Delaware State Fire School in Dover.
Sherwanda Rachal-Speaks and Carolyn Courtney attended a Constant Contact workshop. Both brought
home new ideas and techniques for making the Constant Contact outreach more productive and reader
friendly.
Internal Facebook training was held for Wayne Voshell, Sherwanda Speaks, Peggy O’Brien, Steve Pick-
ering and Carolyn Courtney.\
Ann Marie Townshend and Dawn Melson-Williams attended the APA Webcast Conference on October
9, 2013 that was held at the Kent County Building.
Page 106
Planning, Inspections & Recreation Revenue
FY '14 Budget FY '14 Actual
(YTD)
Revenue Stream
Business License $1,460,000 $ 1,421,555 97%
Trailer License $20,500 $ 20,523 100%
Building Permits $400,000 $ 233,159 58%
Looking Forward…..
Cert. of Occupancy $9,000 $ 2,490 28%
Dick’s Sporting Goods
Public Occupancy $10,000 $ 525 5%
Lodging House $14,000 $ 518 4%
Opens
Plumbing/Heating/Air $75,000 $ 24,340 32% Basketball and Field
Sprinkler $25,000 $ 8,946 36%
Rental Inspection Fee $345,000 $ 3,518
Hockey Leagues
1%
Miscellaneous $20,000 $ 11,726 59%
Fire Protection Fees $31,000 $ 9,490 31%
Vacant Building Reg. $60,000 $ 52,500 88%
Total P&I Revenue $2,469,500 $ 1,789,290 72%
Recreation $133,000 $38,348 29%
PLANNING OFFICE
The Planning Office is part of the review process for certain types of construction activity permits (Building
Permits, Sign Permits, etc.) and Certificate of Occupancy permits. For October 2013, Planning Staff was
involved with review of 85 Permits and 18 Certificates of Occupancy permits (2013 Year to Date total of
774 Permits and COs compared to 787 year-to-date in 2012). Planning Staff also reviews new applications
for Business Licenses and Rental Dwelling Permits.
COMPREHENSIVE PLAN IMPLEMENTATION
Planning Staff continues to focus on the various implementation items identified in the 2008 Comprehensive
Plan as amended.
On-going efforts of the Planning Office include participating in planning for the participating in the
planning and development design of Garrison Oak Technical Park, the pending updates to the FIRM
Maps (Flood Insurance Rate maps) issued by FEMA for flood plains, and research for future ordinance
amendments related to the commercial zoning classifications.
Planning Staff attended the Annual Meeting of the Delaware Population Consortium on October 31,
2013. The DPC provides 30-year population and employment projections for the State, counties, and
selected municipalities including the City of Dover. The meeting involved approval of the release of the
Annual Population Projection series. The final version of the projections is pending publication.
Page 107
New Dover High School Project (C-10-05/S-11-18)
Construction activities related to site improvements and the building construction activities continue at the
new Dover High School project site. The Planning Staff continues to work with the Capital School District
and DelDOT regarding pedestrian safety concerns for the school project. On October 21, 2013 the Planning
Commission granted conditional approval of a Revised Parking Justification for the school site setting the
required parking at 800 parking spaces. The Planning Commission also granted conditional approval of a
Waiver Request for a Parking Reduction allowing portions of Lots C and D to be grass parking for large
events only; to require the bus parking area to be dual striped for car parking at large events; and for a reduc-
tion of Lot G to 31 parking spaces (MI-13-18).On October 24th, Planning Staff held the monthly coordina-
tion meetings on the project with the various involved departments, agencies, and project design profession-
als and managers. The sidewalk improvement project for the north side of Route 8 is progressing through the
design process.
Garrison Energy Center (Master Plan S-12-03/ Phase 1 S-12-17)
The Planning Staff participates in weekly coordination conference calls with Calpine regarding the Garrison
Energy Center project at 450 Garrison Oak Drive (Lot 7 of the Garrison Oak Technical Park). The Final/
Final Administrative Site Plan approval for the Garrison Energy Center Phase 1 was granted on September
6, 2013 subject to conditions of approval. Additional Foundation Building Permits for the project continue
to be received for review and inspection.
BOARD AND COMMISSION ACTIVITY
Planning Commission
The Planning Commission met on October 21, 2013 and took the actions summarized listed below. The next
Planning Commission meeting is scheduled for November 18, 2013.
MI-13-10 Nottingham Meadows: Revised Active Recreation Area – Approval of the Revised Active
Recreation Area cash-in-lieu payment of $14,517.
C-13-11 Dover Christian Church at 1783 Forrest Avenue – Approval based on all of the DAC recom-
mendations and the Staff Report.
MI-13-16 Request for Street Abandonment: Harmony Lane – Approval to the City Council of MI-13
-16 Request for Street Abandonment: Harmony Lane, conditional to the Site Plan Development and the
Parcel Consolidation Plan as recorded in accordance with the DAC comments.
S-13-18 Redevelopment of Walker Woods: The Village of Sherwood —Approval with the requested
waiver of the partial elimination of curbing and the Active Recreation Area Plan. Also to recommend
approval to City Council on the waiver request for the elimination of the emergency rear access require-
ment.
S-13-19 Woodmill Apartment Storage Buildings and Garage Building and Revised Active Recrea-
tion Area at Woodmill Apartments —Approval of the Woodmill Apartment Storage Buildings, Garage
Building and Revised Active Recreation Area with the caveat that Staff be able to review the existing
tree buffer and make a determination about the appropriateness and to also include the DAC recommen-
dations.
MI-13-18 New Dover High School: Revised Parking Justification and Waiver Request for Parking
Reduction-Approval of the Waiver Request for Parking Reduction as specified in Table 3: Parking Lot
A and Parking Lot B - no changes; Lot C and Lot D – parking reduction still grassed and can be utilized
in that number for parking for events; Lot E the bus parking converted to car parking - one hundred sev-
enty (170) spaces; Parking Lot F - no changes; Parking Lot G – thirty-one (31) spaces; parallel parking -
no changes with a total number of eight hundred (800) spaces and the District having to designate the
bus area with lines as car parking as well, along with the DAC comments.
Page 108
Board of Adjustment
The Board of Adjustment did not meet on October 16, 2013. The next regular scheduled meeting of the Board
of Adjustment is scheduled for November 20, 2013.
Historic District Commission
The Historic District Commission did met on October 17, 2013. The next Historic District Commission meet-
ing is scheduled for November 21, 2013.
COMMUNITY DEVELOPMENT BLOCK GRANT PROGRAM
CDBG FY13 Projects
Contracts for FY13 projects have been executed and projects are underway.
Homeownership Assistance Program
CDBG funds will be used to provide settlement assistance to assist qualifying families purchase properties in
the City of Dover.
MHDC Homeowner Rehabilitation Program
CDBG funds will be used to rehabilitate owner occupied homes in the City of Dover found in violation of the
City’s housing code. The waiting list for this project opened on June 12th and this project is underway.
Dover Interfaith Mission to the Homeless
CDBG funds will be used for operations cost for the shelter.
MHDC Emergency Home Repair Project
CDBG funds will be used to assist very low income homeowners with emergency repairs to eliminate sever-
housing conditions that constitute health and safety hazards.
NCALL Research
CDBG funds were used for foreclosure prevention and pre-purchase homeownership counseling services for
ten (10) Dover residents.
Elizabeth W. Murphey School
CDBG funds will be used for minor renovations for one of the facilities that services children that are at risk
for homelessness.
Neighborhood Stabilization Program (NSP)
The City was awarded $1,426,740 for the acquisition and rehab of foreclosed properties to be sold to qualify-
ing families. A total of $2,030,529 including program income has been expended on the acquisition and reno-
vations for 11 properties. The remaining balance of $36,125 will be utilized for renovations, acquisition and
down payment assistance for eligible NSP properties. Nine properties have been sold, one is a lease purchase
and one is a rental that serves persons with disabilities. Nine (9) first time homebuyers have purchased homes
through the NSP Settlement Assistance Program.
218 Ann Avenue (sold) 337 N. Governors Avenue (sold)
343 Mimosa Avenue (sold) 254 Green Blade Drive (sold)
907 Woodcrest Avenue (sold) 302 Stone Brook Place (lease purchase)
1430 S. Hancock (group home rental) 11 Westover Drive (sold)
1415 S. Hancock (sold) 110 Thames Drive (sold)
4 Bennington Street (sold)
Page 109
Dangerous Buildings, Vacant Buildings & Demolitions
126 N. Ann Avenue – The owner is making repairs to the exterior of the property.
209 N. New Street – Owner obtained a structural engineering report and has submitted it to the City.
105 S Queen Street—A residential Renovation Permit has been obtained and a re-inspection to the home
shows that work continues to be made as finances provide.
238 Railroad Ave—The asbestos abatement for the 5 structures has been completed and demolition of
the structures will begin on October 29th.
123 Blue Beach Drive—An asbestos survey was completed for the pool pump-house and no asbestos was
found. Sunnyfield Contractors have been awarded the contractor for the pool and pump house demoli-
tion.
142 Brandywine Drive—An interior inspection of the property was conducted by City Staff and repre-
sentatives for the property owner. It was determined that repairs could be made to the home and the
property owner will be obtaining bids for the renovation work. Since no repairs were done through the
month of September, City staff took the property forward to City Council on October 28th to recom-
mend to Council to order the property dangerous and to have the owners make repairs within 15 days of
the Council Meeting.
710 Slaughter Street—The asbestos survey was completed on October 14th and asbestos was found in the
structure. Bids have been placed for the removal of the asbestos. Gateway Contracting has been award-
ed the demolition bid and have obtained a permit.
45 S Queen Street—The home has been demolished.
200 N West Street—The owner was sent notice that they had 15 days to make repairs to the structure or
City Staff would present the property to City Council in October as a dangerous building and request that
Council approve the demolition of the structure. Owners met with City Staff at the property and advised
that they will start repairs by the end of October.
67 S Queen St—City Council declared this building dangerous and ordered the owner to repair or demol-
ish the building by October 27th.
24 N New St—The property was inspected on October 10th and condemned as unfit for human occupan-
cy due to insanitary conditions and overcrowding. The property was taken forward to City Council on
October 28th , in which City Council declared the structure dangerous and ordered the occupants to va-
cate the structure and gave them two weeks to remove any items they wished to keep from the property.
An asbestos survey was conducted on October 31st and asbestos was found.
Vacant Buildings—During the month of October, 33 additional buildings were registered as vacant, and
$4,750.00 in vacant building registration fees were collected.
Page 110
Dangerous Buildings, Vacant Buildings & Demolitions
45 S Queen Street
106 Saulsbury Road
Page 111
Code Enforcement Activity—October
Case Type # cases current # cases % staff ini ated % staff ini ated
month YTD current month YTD
No valid Rental Permit 4 152 75% 96%
No valid Building Permit 3 57 100% 93%
Tall grass and weeds 24 775 83% 79%
Unregistered vehicle 4 55 75% 91%
Abandoned vehicle 6 89 67% 87%
Annual Housing Inspec on 70 345 86% 87%
Property Maintenance – 22 577 45% 67%
Exterior
Electric Termina on 36 255 100% 96%
Dover Code of Ordinances 52 544 85% 76%
Zoning 9 110 100% 75%
Total Cases 230 2713
Total # of Inspec ons For 317
Month
Page 112
Fire Marshal’s Office, Building Inspections & Licensing Summary
LIFE SAFETY
Inspec ons OCT 13 FYTD 14 OCT 12 FYTD 13
Fire Protec on Inspec ons (New &
Exis ng) 43 485 42 135
Fire Code Inspec ons
94 609 283 730
Inspec on Deficiencies 40 350 17 159
Cer ficate of Occupancy
3 76 5 14
Accidental $5,000 $137,450 $50.00 $450.00
Incendiary $0 $34,600.00 $100.00 $11,100.00
Undetermined $10,000 $281,000.0 $150.00 $1150.00
PERMITTING AND LICENSING
Permits Issued OCT 13 FYTD 14 OCT 12 FYTD 13
Administra ve Permit
1 4 2 12
Building Addi on/Renova on Permits
49 167 56 171
Building Permits
18 64 12 60
Demoli on Permits
5 21 3 21
Fence Permits 9 33 10 36
Fire Preven on Permits 13 44 7 24
Mechanical Permits
21 89 30 136
Plumbing Permits
29 127 43 119
Sign Permits 33 345 24 76
Swimming Pool Permits
1 6 0 10
Business Licenses
47 1209 94 874
Merchant Licenses
7 276 9 239
Contractor Licenses
32 785 32 542
Lodging House Licenses
2 2 0 1
Mobile Homes
87 286 5 157
Public Occupancy
6 26 6 28
Rental Dwelling 21 99 19 97
BUILDING INSPECTIONS
Inspec ons OCT 13 FYTD 14 OCT 12 FYTD 13
Building
384 1322 346 1,292
Plumbing/Mechanical
350 1214 284 1,329
Cer ficate of Occupancy 18 53 13 46
Page 113
Fire Marshal’s Office—At a Glance
Number of Fires Requiring FM Response for
September 2013 Juvenile for pulling fire alarm pull sta on.
3 Accidental
Failure to have city business license.
1 Incendiary
1 Undetermined
5 hours of inves ga on me
Number of Complaints – 1
Ac ve Fire Inves ga on
Pine Street
Two Arrest for Month
Recreation Division
Enrollment Summary
October 2012 verses October 2013
3 00
FY13
FY14
2 00
1 00
0
General Recreation Sports Trips Camps
Category FY13 FY14
General Recrea on 273 254
Sports 97 68
Trips Not Offered Not Offered
Camps Not Offered Not Offered
Page 114
Revenue Breakdown: October 2012 verses October 2013
G e n e r a l R e c re a tio n General Recreation
Sp o rts Sports
T ri p s Trips
L e a gu e s Leagues
B u ild in g & Fi e l d R e n t al s Building & Field Rentals
Camps
Camps
General Recreation 1,763.00 General Recreation 2,673.50
Sports 300.00 Sports 885.00
Camps 0.00 Trips 1227.00
Leagues 1550.00
Trips 2,214.00
Building & Field Rentals 180.00
Leagues 5,814.00
Camps 0.00
Building & Field Rentals 1,921.00
Page 115
John W. Pitts Recreation Center – October 2013
Total Program Attendance Facility Usage By The Hour
14,000 1,000
12,000 800
10,000
8,000 600
6,000 400
4,000
200
2,000
0 0 Oct 12
Oct 12
Nov 12
Dec 12 Nov 12
Dec 12
Jan 13
Feb 13 Jan 13
Feb 13
Mar 13
Apr 13 Mar 13
Apr 13
May 13
June 13 May 13
June 13
July 13
Aug 13 July 13
Aug 13
Sept 13
Oct 13 Sept 13
Oct 13
Facility Usage By The Hour OCT 13 FYTD 14 OCT 12 FYTD 13
Open Gym 595.5 1,690 495 1,874
Fitness Classes 62 190.5 53.5 169.5
Leagues 24 125 32 88
Camps 0 555 0 49
Sports Classes 13.5 53.5 13.5 59.5
Meetings & Rentals 8.5 40 27.5 94
Enrichment Classes 7 20.5 2 14.5
Total Facility Usage Hours 710.5 2,674.5 623.5 2,348.5
** Program Attendance figures includes daily participants, parents and spectators in the facility.
Daily Program Attendance** OCT 13 FYTD 14 OCT 12 FYTD 13
Total 1,428 7,418 2,090 7,238
Open Gym 472 1,194 610 2,499
Fitness Classes 330 1,027 500 1,272
Leagues 400 3,156 615 2,055
Camps 0 1,308 0 254
Sports Classes 145 326 93 493
Meetings & Rentals 71 370 268 628
Enrichment Classes 10 37 6 37
Since our opening in late April 2008, we have had 279,638 guests at the John W. Pitts Recreation Center.
October Open Gym Registrations and Packages Sold
Packages Sold: Oct. MTD YTD FYTD
Daily: 38 $ 114 129 $387
Individual Quarterly: 2 $ 30 7 $105
Individual Annual: 0 $0 0 $0
Family Quarterly: 1 $ 30 3 $ 90
Family Annual: 0 $ 0_ 0 __ $ 0 ____
Revenue: $174 $582
Page 116
CITY OF DOVER
FINANCE AND PROCUREMENT & INVENTORY DEPARTMENTS
OCTOBER 2013 - MONTHLY BUDGET REPORTS
LEASE NOTE – THIS REPORT PROVIDES TOP LINE INFORMATION ON THE OPERATING
FUNDS. IF YOU WOULD LIKE ADDITIONAL INFORMATION, PLEASE FEEL FREE TO
CONTACT THE FINANCE DEPARTMENT.
Page 117
Page 2 of 11
CITY OF DOVER
ACTIVITY REPORTS
October 2013
S
FINANCE DEPARTMENT ACTIVITY LEVELS
FY13 YTD FY14 YTD
BANK TRENDS
Number of Deposits Made (Hand, ACH & Wire, Lockbox) 1,947 2,107
Total Amount of All Deposits $ 58,140,374 $ 48,115,598
PAYROLL
Hours % Amount Hours % Amount
Gross wages per registers 263,671 100.0% $ 6,256,759 257,584 100.0% $ 6,033,040
Wages and Hours Worked
Regular 218,318 82.8% $ 4,827,264 216,584 84.1% $ 4,690,982
All over time 13,932 5.3% $ 633,265 12,176 4.7% $ 521,969
Other Paid or Unpaid Wages and Hours
Vacation 16,538 6.3% $ 430,094 16,889 6.6% $ 447,935
Sick 6,668 2.5% $ 167,221 5,087 2.0% $ 129,639
Terminal Leave - Retiree Vacation/Sick Payout 2,266 0.9% $ 51,480 797 0.3% $ 21,341
Comp Time 2,949 1.1% $ 82,602 2,593 1.0% $ 72,756
Personal 298 0.1% $ 7,802 353 0.1% $ 9,343
Leave Without Pay 2,073 0.8% $ - 1,626 0.6% $ -
Other (description below) 631 0.2% $ 57,031 1,481 0.6% $ 139,073
Other includes: pay adjustments, military differential pay, committee meetings, worker compensation tracking/adjustments, etc.
Other Activity
Number of Pay Periods 8 8
Number of Payroll Checks & Direct Deposits Issued 2,933 2,856
Number of Pension Checks Issued 982 1,035
Total Pension Benefits Paid - Defined Benefit Plan $ 4,063,547 $ 4,308,838
ACCOUNTS PAYABLE
Number of Check Vouchers 2,052 1,944
Number of EFT Vouchers 695 674
Vouchers Dollar Amount Disbursed $ 28,267,814 $ 24,719,690
PROCUREMENT & INVENTORY ACTIVITY LEVELS
Contingency & Warehouse Stock Items on Hand with No Usage
$2,600,000
2400 $630
$2,500,000
2200
$530
Total Dollar Value
$2,400,000
Total Line Items
2000
$2,300,000 $430
1800
Thousands
$2,200,000 1600 $330
$2,100,000 1400
$230
$2,000,000 1200
$130
Total Dollar Value Total Line Items $30
Oct‐12 Nov‐12 Dec‐12 Jan‐13 Feb‐13 Mar‐13 Apr‐13 May‐13 Jun‐13 Jul‐13 Aug‐13 Sep‐13 Oct‐13
Value: $2,536,771 Line Items: 1,458 Ele ctric Water General
Electric: $602,410 Water: $56,799 General: $35,478
S t o c k P urc ha s e s by F und
$ 3 5 0 ,0 0 0
$ 3 0 0 ,0 0 0
$ 2 5 0 ,0 0 0
Fuel Use
$ 2 0 0 ,0 0 0 Unleaded: 10,903.9 gallons
$ 15 0 ,0 0 0 Diesel: 6,993.5 gallons
$ 10 0 ,0 0 0
Total Cost: $ 51,421
$ 5 0 ,0 0 0
$0
Oct N o v D ec Jan F eb M ar A pr M a y J un J ul A ug S e p Oct
12 12 12 13 13 13 13 13 13 13 13 13 13
E le c t ric Wa t e r G e ne ra l
Electric $ (14,839) Water $ 7,423 General $ 3,612
Page 118
Page 3 of 11
City of Dover
Finance Department
Monthly Report – October 2013
General Fund Summary
33% of
Budget YTD Balance Budget
Beginning Balance (unaudited) $ 3,455,200 $ - $ 3,455,200 0.0%
Revenues
Court of Chancery Fees 863,200 237,100 626,100 27.5%
Fines & Police Revenues 1,316,000 404,716 911,284 30.8%
Franchise Fees 606,200 84,100 522,100 13.9%
Grants 623,500 71,000 552,500 11.4%
Intrafund Services 4,454,300 1,301,610 3,152,690 29.2%
Library & Recreation Revenues 599,600 296,295 303,305 49.4%
Licenses & Permits 2,627,500 1,859,476 768,024 70.8%
Property Taxes (Includes BID Revenue) (1) 11,169,500 11,042,322 127,178 98.9%
Miscellaneous Revenues 138,300 33,894 104,406 24.5%
Sanitation Revenues 2,676,500 868,571 1,807,929 32.5%
Garrison Farm Rent Revenue 118,500 28,892 89,608 24.4%
Transfers-In from Special Funds & Utilities
Municipal Street Aid Fund 527,400 - 527,400 0.0%
Civil Traffic Penalties 600,000 - 600,000 0.0%
Transfer Taxes 1,315,500 385,756 929,744 29.3%
Verizon, Contingency and CI Reserves 32,000 - 32,000 0.0%
Police Grants 110,000 16,373 93,627 14.9%
Water/Wastewater Fund 500,000 250,000 250,000 50.0%
Electric Fund 8,000,000 4,000,000 4,000,000 50.0%
Total Revenues 36,278,000 20,880,105 15,397,895 57.6%
Total Beginning Balance & Revenues $ 39,733,200 $ 20,880,105 $ 18,853,095 52.6%
Expenditures
City Clerk & Council $ 442,200 $ 132,329 $ 309,871 29.9%
Mayor, City Manager & Human Resources 874,900 297,663 577,237 34.0%
Police & Police Extra Duty 14,331,800 4,130,727 10,201,073 28.8%
Public Services 4,131,800 1,052,882 3,078,918 25.5%
Procurement & Inventory, Facilities Mgmt., Vehicle Maint. 1,870,900 497,313 1,373,587 26.6%
Planning & Inspections 2,045,600 628,631 1,416,969 30.7%
Finance, Info Tech & Customer Services 2,676,400 866,999 1,809,401 32.4%
Library & Recreation 2,038,600 615,945 1,422,655 30.2%
Fire Department 692,100 233,426 458,674 33.7%
Assessor 198,300 63,218 135,082 31.9%
Contribution to DDP 162,400 81,200 81,200 50.0%
Miscellaneous Grant Expense 25,000 - 25,000 0.0%
Other Employment Expenses 400,000 - 400,000 0.0%
Insurance 658,900 151,959 506,941 23.1%
OPEB - Retiree’s Health Care Contribution 1,636,500 409,125 1,227,375 25.0%
Police Pension Trust Contribution - State Grant 500,000 70,000 430,000 14.0%
Appropriation to Employee Pension Fund - Unfunded Liability 1,466,500 886,950 579,550 60.5%
Street Lights 836,000 260,709 575,291 31.2%
Debt Service 557,300 538,486 18,814 96.6%
Provision for Uncollectible 10,000 10,000 - 100.0%
Transfers Out
Capital Projects Fund 1,278,300 639,150 639,150 50.0%
Total Expenditures 36,833,500 11,566,712 25,266,788 31.4%
Budget Balance - Working Capital 2,899,700 - 2,899,700 0.0%
Total Budget Balance & Expenditures $ 39,733,200 $ 11,566,712 $ 28,166,488 29.1%
Reserve Balances
Contingency $ 723,600 $ 735,599
(1) Property Taxes are the taxes billed and not cash received. The outstanding receivable balance as of 10/31/13 is $591,84.55
as compared to $780,693.58 in October 2012.
Page 119
Page 4 of 11
City of Dover
Finance Department
Monthly Report – October 2013
Water/Wastewater Fund Summary
33% of
Budget YTD Balance Budget
Beginning Balance - Water (unaudited) $ 770,800 $ - $ 770,800 0.0%
Beginning Balance - Wastewater (unaudited) $ 412,600 $ - $ 412,600 0.0%
Beginning Balance - Kent County Treatment (unaudited) $ 141,600 $ - $ 141,600 0.0%
1,325,000 - 1,325,000 0.0%
Revenues
Water Fees 4,730,700 1,640,288 3,090,412 34.7%
Wastewater Fees 3,642,700 1,269,860 2,372,840 34.9%
Kent County Treatment Fees 2,980,300 1,048,261 1,932,039 35.2%
Ground Water Inflow Adjustment 1,324,600 470,482 854,118 35.5%
Water Tank Leases 333,800 64,493 269,307 19.3%
Miscellaneous Service Fee 105,100 25,656 79,444 24.4%
Impact Fees - Water 357,000 52,714 304,286 14.8%
Impact Fees - Wastewater 323,000 47,661 275,339 14.8%
Total Revenues 13,797,200 4,619,415 9,177,785 33.5%
Total Beginning Balance & Revenues $ 15,122,200 $ 4,619,415 $ 10,502,785 30.5%
Expenses
Water/Wastewater Operating Divisions
Engineering & Inspection $ 664,400 $ 108,091 $ 556,309 16.3%
Water 433,900 134,713 299,187 31.0%
Water Treatment Plant 1,501,800 412,323 1,089,477 27.5%
Wastewater 945,100 250,419 694,681 26.5%
Construction 351,400 73,554 277,846 20.9%
Kent County Treatment 3,524,800 990,865 2,533,935 28.1%
Intrafund Service Fees 1,233,400 367,530 865,870 29.8%
Pension Unfunded Liability 339,400 169,700 169,700 50.0%
OPEB - Retiree's Health Care Contributions 200,000 100,000 100,000 50.0%
Debt Service 1,019,500 187,220 832,280 18.4%
Other Employment Expenses 25,000 - 25,000 0.0%
Transfers Out
General Fund 500,000 250,000 250,000 50.0%
Water I & E Fund 1,200,000 600,000 600,000 50.0%
Wastewater I & E Fund 1,330,000 665,000 665,000 50.0%
Total Expenses 13,268,700 4,309,415 8,959,285 32.5%
Budget Balances
Budget Balance - Working Capital - Water 1,056,400 - 1,056,400 0.0%
Budget Balance - Working Capital - WW 797,100 - 797,100 0.0%
Total Budget Balances 1,853,500 - 1,853,500 0.0%
Total Budget Balances & Expenses $ 15,122,200 $ 4,309,415 $ 10,812,785 28.5%
Reserve Balances
Contingency-Water $ 105,600 $ 104,338
Contingency-Wastewater $ 191,500 $ 188,671
Impact Fee Reserve - Sewer NO BUDGET $ 3,764,350
Impact Fee Reserve - Water NO BUDGET $ 197,514
Bond Coverage Ratio (Covenant 1.20) 3.96 6.91
Page 120
Page 5 of 11
City of Dover
Finance Department
Monthly Report – October 2013
Electric Revenue Fund Summary
33% of
Budget YTD Balance Budget
Beginning Balance (unaudited) $ 7,152,400 $ - $ 7,152,400 0.0%
Revenues
Sales to Customers 76,286,700 28,365,468 47,921,232 37.2%
Utility Tax 1,492,200 465,745 1,026,455 31.2%
Weyandt Hall Rents 251,000 44,899 206,101 17.9%
Miscellaneous Revenues 737,800 234,600 503,200 31.8%
Interest Earned 119,400 554 118,846 0.5%
Transfer from Rate Stabilization 4,000,000 2,000,000 2,000,000 50.0%
Intrafund Service Receipts Water/Wastewater 98,500 30,107 68,393 30.6%
Total Revenues 82,985,600 31,141,373 51,844,227 37.5%
Total Beginning Balance & Revenues $ 90,138,000 $ 31,141,373 $ 58,996,627 34.5%
Expenses
Power Supply & Generation
Hedged Energy $ 23,832,000 $ 11,768,406 $ 12,063,594 49.4%
Power Supply Management 996,000 332,000 664,000 33.3%
Capacity Charges 15,787,200 5,409,985 10,377,215 34.3%
Dover Sun Park Energy 1,565,800 689,487 876,313 44.0%
Solar Renewal Energy Credits 300,000 124,415 175,585 41.5%
PJM Charges - Energy 12,812,900 3,163,727 9,649,173 24.7%
PJM Charges - Transmission & Fees 4,740,000 2,443,782 2,296,218 51.6%
Total Power Supply 60,033,900 23,931,802 36,102,098 39.9%
Plant Operations 6,015,800 1,852,210 4,163,590 30.8%
Generation Fuels - 919,951 (919,951) 0.0%
Capacity Credits (15,079,800) (5,273,625) (9,806,175) 35.0%
PJM Spot Market Energy (230,500) (43,541) (186,959) 18.9%
PJM Credits (397,000) (1,916,940) 1,519,940 482.9%
Total Generation (9,691,500) (4,461,945) (5,229,555) 46.0%
Total Power Supply & Plant 50,342,400 19,469,857 30,872,543 38.7%
Electric Operating Divisions:
Transmission/Distribution 3,302,500 918,107 2,384,393 27.8%
Electrical Engineering 1,192,200 305,820 886,380 25.7%
Administration 597,000 91,695 505,305 15.4%
Meter Reading 220,300 71,189 149,111 32.3%
Systems Operations 543,600 160,520 383,080 29.5%
Intrafund Services 3,319,400 964,187 2,355,213 29.0%
Utility Tax 1,492,200 465,745 1,026,455 31.2%
OPEB - Retirees Health Care Contribution 513,300 256,650 256,650 50.0%
Pension Trust Contribution - Unfunded liability 1,314,200 657,100 657,100 50.0%
Interest on Deposits 27,000 8,215 18,785 30.4%
Green Energy Payment to DEMEC 135,800 34,856 100,944 25.7%
Accounts Receivable Write-Offs 200,000 200,000 - 100.0%
Other Employee Expenses 150,000 - 150,000 0.0%
Contractual Services RFP's 100,000 - 100,000 0.0%
Debt Service 3,301,900 1,136,870 2,165,030 34.4%
Transfers Out:
General Fund 8,000,000 4,000,000 4,000,000 50.0%
Electric Improvement & Extension Fund 5,448,600 2,724,300 2,724,300 50.0%
Total Expenses 81,176,100 31,952,961 49,223,139 39.4%
Budget Balance - Working Capital 8,961,900 - 8,961,900 0.0%
Total Budget Balance & Expenses $ 90,138,000 $ 31,952,961 $ 58,185,039 35.4%
Reserve Balances
Contingency Reserve $ 826,500 $ 816,027
Insurance Reserve $ 739,000 $ 734,655
Rate Stabilization Reserve $ 13,644,000 $ 15,417,629
Bond Coverage Ratio (Covenant 1.25) 1.97 1.28
Megawatt Hours Sold & Purchased
Sales to Customers MWh (excluding Street Light MWh) 712,675 265,066 37.2%
Sales per MWh $ 107.04 $ 107.01 100.0%
Purchased/Generated MWh 725,818 267,847 36.9%
All In MWh Supply & Generation $ 69.36 $ 72.69 104.8%
Page 121
Page 6 of 11
City of Dover
Finance Department
Monthly Report – October 2013
General Capital Project Fund Summary
33% of
Budget YTD Balance Budget
Beginning Balance - Projects (unaudited) $ 241,200 $ - $ 241,200 0.0%
Beginning Balance - Library (unaudited) $ (74,700) $ - $ (74,700) 0.0%
Revenues
State Grant - Other 15,000 - 15,000 0.0%
Interest Earnings - 6,049 (6,049) 0.0%
Transfer from General Fund for Projects 1,278,300 639,150 639,150 50.0%
Transfer from Parkland Reserve 95,000 - 95,000 0.0%
Subtotal Revenues 1,388,300 645,167 743,133
State Grant - Library - 107,674 (107,674) 0.0%
Library Construction Donations - 5,150 (5,150) 0.0%
Subtotal Library Project Receipts - 112,824 (112,824) 0.0%
Total Revenues 1,388,300 757,991 630,309 54.6%
Total Beginning Balance & Revenue $ 1,554,800 $ 757,991 $ 796,809 48.8%
Expenditures
Fire $ 238,500 $ 238,515 $ (15) 100.0%
Grounds Maintenance 50,100 - 50,100 0.0%
Library - 6,512 (6,512) 0.0%
Recreation 95,000 - 95,000 0.0%
Code Enforcement 30,000 - 30,000 0.0%
Police 257,300 32,668 224,632 12.7%
Streets 251,500 143,684 107,816 57.1%
Sanitation 402,100 - 402,100 0.0%
Information Technology 7,000 - 7,000 0.0%
Facilities Management 17,800 - 17,800 0.0%
Procurement & Inventory 55,000 - 55,000 0.0%
Total Expenditures 1,404,300 421,379 982,921 30.0%
Budget Balance - Projects 150,500 - 150,500 0.0%
Total Budget Balance & Expenditures $ 1,554,800 $ 421,379 $ 1,133,421 27.1%
Reserve Balances
Capital Asset Replacement Reserve $ 512,000 $ 508,424
Parkland/Recreation $ 110,000 $ 203,361
Page 122
Page 7 of 11
City of Dover
Finance Department
Monthly Report – October 2013
Water/Wastewater Improvement & Extension Fund Summary
33% of
Budget YTD Balance Budget
Beginning Balance - Water (unaudited) $ 1,620,000 $ - $ 1,620,000 0.0%
Beginning Balance - Wastewater (unaudited) $ 660,900 $ - $ 660,900 0.0%
Revenues
State Loan-Wastewater 2010 - 62,000 (62,000) 0.0%
Interest Earned 25,000 8,596 16,404 34.4%
Transfer from Operating Fund for Water 1,200,000 600,000 600,000 50.0%
Transfer from Operating Fund for Wastewater 1,330,000 665,000 665,000 50.0%
Transfer from Impact Fee Reserve - Water 390,000 - 390,000 0.0%
Total Revenues 2,945,000 5,341,556 (2,396,556) 181.4%
Total Beginning Balance & Revenues $ 5,225,900 $ 5,341,556 $ (115,656) 102.2%
Expenses
Water $ 1,476,800 $ 421,039 $ 1,055,761 28.5%
Wastewater 1,251,000 194,812 1,056,188 15.6%
Water Construction 90,000 - 90,000 0.0%
Total Expenses 2,817,800 615,851 2,201,949 21.9%
Budget Balance - Working Capital - Water 1,655,700 - 1,655,700 0.0%
Budget Balance - Working Capital - Wastewater 752,400 - 752,400 0.0%
Total Budget Balances 2,408,100 - 2,408,100 0.0%
Total Budget Balances & Expenses $ 5,225,900 $ 615,851 $ 4,610,049 11.8%
Reserve Balances
Capital Asset Replacement - Water $ 513,000 $ 506,553
Capital Asset Replacement - Wastewater $ 512,300 $ 505,394
Page 123
Page 8 of 11
City of Dover
Finance Department
Monthly Report – October 2013
Electric Improvement & Extension Fund Summary
33% of
Budget YTD Balance Budget
Beginning Balance (unaudited) $ 3,091,000 $ - $ 3,091,000 0.0%
Revenues
Interest Earnings 25,200 4,363 20,837 17.3%
Transfer from Electric Revenue Fund 5,448,600 2,724,300 2,724,300 50.0%
General Service Billing 440,000 101,153 338,847 23.0%
Total Revenues 5,913,800 2,829,816 3,083,984 47.9%
Total Beginning Balance & Revenues $ 9,004,800 $ 2,829,816 $ 6,174,984 31.4%
Expenses
Electric Generation $ 2,117,800 $ 92,922 $ 2,024,878 4.4%
Transmission/Distribution 1,100,000 70,535 1,029,465 6.4%
Electrical Engineering 2,405,800 412,250 1,993,550 17.1%
Total Expenses 5,623,600 575,707 5,047,893 10.2%
Budget Balance - Working Capital 3,381,200 - 3,381,200 0.0%
Total Budget Balance & Expenses $ 9,004,800 $ 575,707 $ 8,429,093 6.4%
Reserve Balances
Depreciation Reserve $ 9,977,100 $ 9,877,384
Future Capacity Reserve $ 10,131,400 $ 10,026,197
City of Dover
Finance Department
Monthly Report – October 2013
Community Transportation Improvement Fund
33% of
Budget YTD Balance Budget
Beginning Balance (unaudited) $ - $ - $ - 0.0%
Revenues
Grants Revenue 500,000 (2) 500,002 0.0%
Interest Earned 500 158 342 31.6%
Total Revenues 500,500 156 500,344 0.0%
Total Beginning Balance & Revenues $ 500,500 $ 156 $ 500,344 0.0%
Expenses
Program Expenses $ 500,000 $ 228,427 $ 271,573 45.7%
Budget Balance - Working Capital 500 - 500 0.0%
Total Budget Balances & Expenses $ 500,500 $ 228,427 $ 272,073 45.6%
Page 124
Page 9 of 11
City of Dover
Finance Department
Monthly Report – October 2013
Police Grant Funds
33% of
Budget YTD Balance Budget
Beginning Balance (unaudited) $ 100 $ - $ 100 0.0%
Revenues
Grants Received 413,000 81,620 331,380 19.8%
Interest Earned - 182 (182) 0.0%
Total Revenues 413,000 81,802 331,198 19.8%
Total Beginning Balance & Revenues $ 413,100 $ 81,802 $ 331,298 19.8%
Expenses
Program Expenses/Supplies $ 191,000 $ 3,700 $ 187,300 1.9%
Computer Hardware 60,000 - 60,000 0.0%
Telephone/Fax 15,000 3,647 11,353 24.3%
Training/Conference/Food/Travel 36,000 - 36,000 0.0%
Consulting/Audit Fees 1,000 - 1,000 0.0%
Contractual services - 2,075 (2,075) 0.0%
Operating Transfers - Out 110,000 6,442 103,558 5.9%
Total Expenses 413,000 15,864 397,136 3.8%
Budget Balance - Working Capital 100 - 100 0.0%
Total Budget Balances & Expenses $ 413,100 $ 15,864 $ 397,236 3.8%
Page 125
Page 10 of 11
City of Dover
Finance Department
Monthly Report – October 2013
Library Grant Fund
33% of
Budget YTD Balance Budget
Beginning Balance (unaudited) $ - $ - $ - 0.0%
Revenues
Grants Received 270,100 2,130 267,970 0.8%
Total Revenues 270,100 2,130 267,970 0.8%
Total Beginning Balance & Revenues $ 270,100 $ 2,130 $ 267,970 0.8%
Expenses
Program Expenses/Supplies-State Grants $ 28,000 $ 1,507 $ 26,493 5.4%
Program Expenses/Supplies-Federal Grants - 989 (989) 0.0%
Office Supplies 24,000 3,089 20,911 12.9%
Printing/Duplicating 8,900 879 8,021 9.9%
Postage 100 - 100 0.0%
Books 124,900 - 124,900 0.0%
Furniture 2,000 - 2,000 0.0%
Audio Visual Supplies 74,000 4,701 69,299 6.4%
Training/Conference/Food/Travel 3,500 210 3,290 6.0%
Office Equipment/Repairs & Maintenance 2,000 1,811 189 90.6%
Computer Hardware 2,700 - 2,700 0.0%
Total Expenses 270,100 13,186 256,914 4.9%
Budget Balance - Working Capital - - - 0.0%
Total Budget Balances & Expenses $ 270,100 $ 13,186 $ 256,914 4.9%
City of Dover
Finance Department
Monthly Report – October 2013
Girls Circle of Dover/Aid
33% of
Budget YTD Balance Budget
Beginning Balance (unaudited) $ - $ - $ - 0.0%
Revenues
Grants Received 31,800 - 31,800 0.0%
Interest Earnings - - - 0.0%
Total Revenues 31,800 - 31,800 0.0%
Total Beginning Balance & Revenues $ 31,800 $ - $ 31,800 0.0%
Expenses
Contractual Services $ 31,800 $ 5,287 $ 26,513 16.6%
Budget Balance - Working Capital - - - 0.0%
Total Budget Balances & Expenses $ 31,800 $ 5,287 $ 26,513 16.6%
Page 126
Page 11 of 11
City of Dover
Finance Department
Monthly Report – October 2013
CDBG Fund
33% of
Budget YTD Balance Budget
Beginning Balance (unaudited) $ - $ - $ - 0.0%
Revenues
Grants Received 223,600 2,639 220,961 1.2%
Interest Earnings - 15 (15) 0.0%
Total Revenues 223,600 2,654 220,946 1.2%
Total Beginning Balance & Revenues $ 223,600 $ 2,654 $ 220,946 1.2%
Expenses
Current Year Closing Cost/Down Payment Program $ 40,000 $ - $ 40,000 0.0%
Current year Dover Interfaith Ministry 27,500 5,275 22,225 19.2%
Current Year MHDC Emergency Home Repair 40,000 - 40,000 0.0%
Current Year Elizabeth W Murphy School 32,700 - 32,700 0.0%
Current Year NCALL Research Inc. 6,000 - 6,000 0.0%
Current Year Milford Housing H/O Rehabilitation 32,700 - 32,700 0.0%
Current Year Salaries 44,700 - 44,700 0.0%
NSP Expense - 486 (486) 0.0%
Total Expenses 223,600 5,761 217,839 2.6%
Budget Balance - Working Capital - - - 0.0%
Total Budget Balances & Expenses $ 223,600 $ 5,761 $ 217,839 2.6%
City of Dover
Finance Department
Monthly Report – October 2013
After School Program/Substance Abuse Prevention Fund
33% of
Budget YTD Balance Budget
Beginning Balance (unaudited) $ - $ - $ - 0.0%
Revenues
Grants Received 55,630 7,008 48,622 12.6%
Recreation Revenue 33,000 3,150 29,850 9.5%
Total Revenues 88,630 10,158 78,472 11.5%
Total Beginning Balance & Revenues $ 88,630 $ 10,158 $ 78,472 11.5%
Expenses
Temporary Help/Benefits $ 33,000 $ 8,769 $ 24,231 26.6%
Program Expenses/Supplies 55,630 9,649 45,981 17.3%
Total Expenses 88,630 18,418 70,212 20.8%
Budget Balance - Working Capital - - - 0.0%
Total Budget Balances & Expenses $ 88,630 $ 18,418 $ 70,212 20.8%
Page 127
Monthly Report
October 2013
Economic Development Office
Page 128
2013 _10 Economic Development
Calpine Weekly Conference Calls
Provided response to DEDO with regard to Biogas power generation
Teleconference with Congressman Carney’s office with regard to site visit to Proctor & Gamble
Met with Campus Director at Delaware Technical Community College to discuss Food Innovation
District and representation on the planning committee
Follow-up with Ferguson Plumbing regarding location in Dover
Hosted a tour of Garrison Energy Center with Calpine, Mayor Carey, Councilwoman Williams,
Councilman Bonar, Councilman Hutchison and Judy Diogo
Provided Calpine information on local nurseries to handle tree mitigation
Teleconference with Vice-President of Marketing of the Onix Group to discuss EDU concerns at
Compass Pointe
Follow-up meeting with City Manager to discuss Onix’ concerns
Met with Secretary Levin to discuss the possibility of the Data Center coming to Dover
Follow-up meeting with Sharon Duca regarding Compass Pointe and discussed solutions
for the EDU problem
Attended Chamber Board Meeting
Toured Dover Garden Suites
Met with owner of The Greene Turtle and discussed fire suppression issue
Attended Leads Group meeting at R&R Commercial Realty
Discussed agricultural lease extension with city solicitor and provided him with copies of past
leases
Reviewed sign concerns with Chris Smith from Edward Jones
Follow-up with Ed Perez regarding Councilman Anderson’s referral of Splash Design
Updated COSTAR listing information on Garrison Tract
Discussed “waters of the US” issues on Lot 12 with Philipp Utz and set-up follow-up meeting for
Friday, October 18th
Reviewed FERC Environmental Assessment for White Oak lateral
Attended Bayhealth Business & Investment Committee meeting
Reviewed Chesapeake Utilities proposal for gas delivery to Garrison Tract, made wording
changes and returned proposal to Chesapeake
Discussion with Becker Morgan regarding “waters of the US” issue at Garrison Tract and follow-
up phone call with Philipp Utz regarding discussion with Becker Morgan
Attended DDP Economic Development Committee meeting and provided economic update
Attended Tourism Board Meeting and gave an Economic Development overview
Attended Food Innovation District Steering Committee meeting
Discussed Food Innovation District in teleconference with Mike Casson and the Director of Food
Innovation District of the Finger Lakes project
Attended Delawareans for Economic and Environmental Development meeting
Meeting with Uzin Utz, City Manager, Mayor, and engineer for Uzin Utz to discuss timeframe for
infrastructure construction
Attended MILCON Breakfast
Met with owner of The Greene Turtle and did tour of the new facility
Reviewed Health Facility Authority Tax-Exempt Post Issuance Compliance Policy
Follow-up discussion with Sharon Duca for Compass Pointe and provided an acceptable solution
to the Onix Group
Page 129
Attended Mayor’s Prayer Breakfast
Attended DDP Board Meeting and provided economic development overview
Attended Kent County Economic Summit Debriefing
Provided Delaware State News information on the redevelopment of former Wal-Mart building
Follow-up with Congressman Carney’s office regarding tour dates for Proctor & Gamble visit
Provided contact information to Simplex Grinnell regarding fire suppression and monitoring at
DDP Building
Discussed with president of DDP the importance of selecting local contractors for work on the
DDP Building
Attended meeting with Gregg Moore, City Manager, Public Works Director, and Greg Scott from
Scott Engineering to discuss issues regarding Lot 12 and permits for crossing “waters of the US”
and flood plain delineation
Prepared CAF for additional engineering services at Garrison Tract
Reviewed wording for agricultural lease extension and forwarded to City Manager and City
Finance Director for their review
Forwarded wording of the Garrison Tract agricultural lease to the farmer after review by City
Manager and Finance Director
Reviewed final version of Chesapeake Utilities agreement, approved it and forwarded to City
Manager and Mayor for comments
Requested DEDO assistance and participation with ribbon-cutting at Parke-Green Galleries
Reviewed DAC comments regarding Lot 12 at Garrison Tract
Attended Tourism Annual Luncheon
Measures:
1 Maintain an unemployment rate for the City of Dover that is lower than national and
state averages
2011-2012 Actual 2012-2013 Actual 2013 - 2014 Projected
Results <10% unemployment rate in < 10% unemployment rate in <10% unemployment rate in
June 2012 June 2013 June 2014
82% - US Rate 76% - US Rate 73% - US Rate
68 % - DE Rate 73% - DE Rate 68 % - DE Rate
86% - City of Dover Rate 98% - City of Dover Rate 8% - City of Dover Rate
June 2012 – Actual June 2013 Actual October 2013 Actual
Page 130
2 Monitor number of contacts with small businesses and with out-of-town companies
interested in locating in Dover
2011-2012 Actual 2012-2013 Actual 2013 - 2014 Projected
Results ≥20 contacts with potential >20 contacts with potential >20 contacts with potential
small businesses; small businesses; small businesses;
10 contacts YTD 18 Contacts YTD 8 Contacts YTD
≥11 contacts with out-of-town >11 contacts with out-of-town >11 contacts with out-of-town
companies interested in companies interested in companies interested in
locating in Dover locating in Dover locating in Dover
9 Contacts YTD 7 Contacts YTD 7 Contacts YTD
Economic Development Activities (Perez)
Provided technical assistance to eight (8) prospective small business individuals on overall
business development within the City of Dover and the Downtown Dover Business District
Provided technical assistance to four (4) prospective small business individuals on locating
available space within the City of Dover and Downtown Business District to lease
In collaboration with the YWCA Delaware conducted two (2) small business development
training sessions on Business Basics for eight (8) participants
In collaboration with the SCORE Delaware conducted one (1) small business development
training workshop on Business Plan Development-Writing a Business Plan for three (3)
participants
Represented the Economic Development Office and provided Technical Assistance to the
Delaware Black Chamber of Commerce on the Capacity Building Committee on review of
Assessment Outcomes on October 30th
Provided Post Evaluation technical assistance, as part of the Planning Committee, to Delaware
Technical & Community College on Kent County Economic Summit held on September 24th
Disseminated via email, DDP website and Facebook Small Business Development workshops
provided by our network partners and special events to the Business Community in Dover
Attended the DE Office of Supplier Diversity Vendor Day Workshop held on October 16th
Provided Staff Support in designing materials for the Mayor’s Prayer Breakfast held on October
23rd
Downtown Dover Partnership Activities
Coordinated media (newspaper announcement), website, social media press releases and
logistics of series of Special Events which occurred during this reporting period which included:
Pressley Ridge 5k Run
Wesley College Homecoming Parade
Delaware State University Homecoming Parade (Cancelled due to inclement weather)
Merchant’s Second Saturday Sidewalk Sale
Safe and Spooky Halloween Parade
First Friday in October’ 13
Page 131
Ongoing projects with the DDP Executive Director:
Development of the Program Annual Report’ 13- Phase IV
Development of DDP’s new Website Update
Working with the Marketing Committee on the coordination of
Capital Holiday Celebration, First Friday, and Home for the Holidays
Working with DEDO on providing Small Business Development Technical Assistance to
the selected POP-UP Project candidate
Identification of Sites to be used for the Central Dover Open House Project
Working with representative from the USDA Office to identify grant opportunities
Page 197
Dover Police Department
Monthly Report
To
Mayor and City Council
“To Protect and Serve”
October 2013
Page 198
November 25, 2013
Honorable Carleton E. Carey, Sr., Mayor
Members of Dover City Council
City Hall
Dover, DE 19901
Mayor Carey and Council Members:
The following is the monthly report for Dover Police Department activities for the month of October 2013:
COMPLAINTS
Total complaints received through October 31st, numbered 30,234. This is an increase of 40 complaints over the
same time period last year.
35,000
34,000
33,000
32,000 30,194 30,234
31,000
30,000 28,428 28,822
29,000
28,000
27,000
26,000
25,000 23,767
24,000
23,000
22,000
21,000
20,000
2009 2010 2011 2012 2013
CRIMINAL
INVESTIGATIONS
20
18 Cases Reported in
16 October
13 12
14
12 Cases Cleared in
10 6 October
8 6
6 3 Cases Cleared
4 2 2 from Previous
1 Months
2 0
0
Burglary Robbery Rape
Page 199
Report to Mayor and Council
October 2013
Page 3
COMMUNITY POLICING/QUALITY OF LIFE SECTION
ENFORCEMENT ACTION Contacts
ABANDONED VEHICLES 5
ALCOHOL VIOLATIONS/DUI’S 11
ASSIST OTHER 0
WARRANTS ON FILE 0
BIKE ON SIDEWALK 0
CITY PARK VIOLATIONS 1
CRIMINAL ARRESTS 21
DRUG RELATED ARRESTS 6
LOUD MUSIC 0
MISCELLANEOUS VIOLATIONS 7
PARKING VIOLATIONS 54
PEDDLER 0
MEETINGS 150
PROSTITUTION 0
COLLECTION OF DELINQUENT 0
DCO’S
WANTED CHECKS/CPC’S 32
TRAFFIC ARRESTS 66
WARNINGS 21
FUGITIVE 6
TOTAL CONTACTS 380
TRAFFIC ARRESTS
20,000
The department issued 14,809 traffic citations 19,000
18,000 16,781 17,303
through this reporting period. This is an increase 16,173
of 1,306 citations over the number issued during 17,000
16,000 14,809
the same period last year.
15,000
13,503
14,000
13,000
12,000
11,000
10,000
2009 2010 2011 2012 2013
TRAFFIC CRASHES
Through October 31st, Dover Police investigated 1,800
1,623 1,647
1,647 traffic crashes. This is an increase of 24 1,700 1,564 1,527
crashes investigated during the same period last 1,600
1,452
year. 1,500
1,400
1,300
1,200
1,100
1,000
2009 2010 2011 2012 2013
Page 200
Report to Mayor and Council
October 2013
Page 4
911 CENTER
During the month of October, the Dover Police
Department handled a total of 9,897 calls
24% averaging 320 calls per day. Dispatchers handled
2,339 calls on the 911 wireless lines, 602 calls on
the 911 landlines, and 209 calls on the Voice Over
911 Wireless Internet Protocol lines, the remaining 6,747 were
911 Landline administrative calls.
6% VolP
68% 2%
Administrative
CITY ORDINANC E SUMMONS
7,238
7,169
6,834
Through October 31st, we issued 6,380 7,300
7,100 6,380
6,900 6,276
City ordinance summons, a increase of 6,700
6,500
104 summonses over the same period last 6,300
6,100
5,900
year. *Note: Of those summonses issued 5,700
5,500
in September, 26 DCO’s were issued for 5,300
5,100 4,649
4,682 4,905
handicapped parking violations, 6 for fire 4,900 4,584
4,700
4,500 3,948
lane parking violations, 50 for false 4,300
4,100
alarms (0, for 1-2, 36, for 3-5 alarms, 9, 3,900
3,700
3,500
for 6-9 alarms, 3, for 10-15 alarms, and 2 3,300
3,100
for 16 or more alarms) and 18 for noise 2,900
2,700
violations (8 for vehicle violations and 10 2,500
2009 2010 2011 2012 2013
for residence violations).
ISSUED PAID
Please visit our new website at www.doverpolice.org for up to date information on crimes and activities in the City
of Dover.
Respectfully Submitted,
James E. Hosfelt, Jr.
Chief of Police
Page 201
ACTION FORM
PROCEEDING: City Council
DEPARTMENT OF ORIGIN: Electric DATE SUBMITTED: 11/25/13
PREPARED BY: Steve Enss, Interim Electric Director
SUBJECT: Evaluation of Bids – Cable Puller (Equipment Purchase, Replacing 2002 Cable Puller #758)
REFERENCE: N/A
REVIEWED BY: City Manager, Controller/Treasurer
EXHIBITS: Vendor Quote
EXPENDITURE REQUIRED: $152,584.00 AMOUNT BUDGETED: $125,000
FUNDING SOURCE (Dept./Page in CIP & Budget): Electric T&D / Page 134 FY 2014
TIME TIMETABLE: Order will be placed following Council approval
RECOMMENDED ACTION: Staff recommends purchasing the replacement Cable Puller from Sherman &
Reilly for a total cost of $152,584.00
BACKGROUND AND ANALYSIS
The purpose of the Cable Puller purchase is to replace the ageing 2002 Sherman & Reilly equipment. The
department has one cable puller typically used every day for installing main electric feeders, distribution lines
and house services. Cable pullers are similar to bucket truck use and should be replaced every ten (10) years to
minimize break downs and repairs.
The Electric department budgeted $125,000 based on a quote received 1/11/13. Since the time of the quote, the
cable puller has been redesigned for proper ergonomics and safety. The last of the vintage models were sold in
June 2013. Due to the changes in the design, the overall cost for the cable puller exceeds the budgeted amount
of $125,000.
The Controller/Treasurer is recommending covering the difference of $27,584.00 through the budget balance to
be included in the December 9, 2013 budget ordinance. (In reviewing the I & E Fund budget, it was determined
that the Miscellaneous Revenues are not tracking sufficiently to cover the equipment overages.)
Bids were advertised and received using the City of Dover purchasing policy. Bid Number 14-0005EL was
opened on September 26, 2013. Two bids were received; Sherman & Reilly and Condux. The specifications
were based on the components equal to that of the Sherman & Reilly. Our specifications were developed based
on safety, pulling capabilities and operator ergonomics. The Sherman & Reilly machine was developed to help
improve employee safety and reduce workman’s comp claims with the use of hydraulic pulling and lifting
devices including the machines ability to maneuver over transformers, pull box’s and man holes. Prior to
writing the specifications, staff evaluated and demonstrated both machines. The Sherman & Reilly machine met
all safety and operational requirements of the department. The Condux machine required additional components
to meet the pulling requirements. The machine failed the demonstration as the machine bent while trying to pull
our feeder cable. Additionally the Condux machine did not meet all of our safety requirements by not having
proper grounding components or US DOT approved lighting.