Page 1
REGULAR COUNCIL MEETING
The Regular Council Meeting was held on November 12, 2013 at 7:30 p.m. with Councilwoman
Williams presiding in the absence of Council President Bonar. Council members present were
Mr. Dixon, Mr. Lynn, Mr. Perza, Mr. Slavin, Mr. Hare, and Mr. Hutchison. Mr. Anderson was
absent.
Council staff members present were Police Chief Hosfelt, Mrs. Mitchell, Mr. Koenig,
Mrs. Townshend, City Solicitor Rodriguez, and Mrs. McDowell. Mayor Carey was absent.
OPEN FORUM
The Open Forum was held at 7:15 p.m., prior to commencement of the Official Council Meeting.
Councilwoman Williams declared the Open Forum in session and reminded those present that
Council was not in official session and could not take formal action.
There was no one present wishing to speak during the Open Forum.
The invocation was given by Reverend Theodore Henderson, followed by the Pledge of Allegiance.
AGENDA ADDITIONS/DELETIONS
Mr. Hare noted the absence of Mayor Carey and suggested that the Geographic Information Systems
(GIS) Day and Geographic Awareness Week and Pancreatic Cancer Awareness Month
Proclamations be deferred until the next Council Meeting.
Mr. Hutchison moved for approval of the agenda as amended, seconded by Mr. Dixon and
unanimously carried.
Mr. Hare moved for approval of the consent agenda as presented, seconded by Mr. Hutchison
and carried by a unanimous roll call vote (Anderson and Bonar absent).
ADOPTION OF MINUTES - REGULAR COUNCIL MEETING OF OCTOBER 28, 2013
The Minutes of the Regular Council Meeting of October 28, 2013 were unanimously approved
by motion of Mr. Hare, seconded by Mr. Hutchison and bore the written approval of
Mayor Carey.
ADOPTION OF MINUTES - SPECIAL COUNCIL MEETING OF OCTOBER 30, 2013
The Minutes of the Regular Council Meeting of October 30, 2013 were unanimously approved
by motion of Mr. Hare, seconded by Mr. Hutchison and bore the written approval of
Mayor Carey.
UTILITY COMMITTEE REPORT - OCTOBER 28, 2013
The Utility Committee met on October 28, 2013 with Chairwoman Williams presiding.
Annexation Request - 508 Acorn Lane, Owned by Raul M. Juarez
Mr. Scott Koenig, City Manager, reviewed a Petition to Annex and Zone Property located at
508 Acorn Lane, consisting of 1.315+/- acres, owned by Raul M. Juarez. Mr. Koenig advised
members that the property owner had requested annexation, mainly for utility purposes. He
Page 2
CITY COUNCIL MEETING OF NOVEMBER 12, 2013 PAGE 2
explained that this property was designated as a Category 1 - High Priority Annexation Area in
accordance with the City’s Comprehensive Plan because it represents an in-fill area. Staff
recommended annexation of the property in order to further “square up” the City boundaries and
provide the sewer utility to this property in the future. He explained that a sewer line was installed
on Acorn Lane and that if the property owner connects to the sewer, he would be subject to the
assessment associated with that project and would also pay a connection fee as a per foot assessment.
Staff recommended that the City proceed with annexation of the subject property.
Responding to Mrs. Williams, Mr. Koenig stated that Fox Hall Drive was also a Category 1 - High
Priority Annexation Area and that the Acorn Lane situation would be similar, if there are failing
utility systems and City utilities are needed. He confirmed that the annexation would not only
capture an enclave but would eventually build customers.
In response to Mr. Bonar, Mr. Koenig stated that the City’s Comprehensive Plan includes an
annexation map that shows all Category 1, Category 2, and Category 3 areas that may be considered
for annexation. He noted that Category 1 areas, such as Fox Hall Drive, Acorn Lane, and some areas
of Governors Avenue, are in-fill areas; Category 2 areas are located at the borders of the City where
growth is anticipated; and that the Category 3 designation includes areas that are further out that may
potentially be annexed at an undetermined time in the future.
The Committee recommended annexation of the property located at 508 Acorn Lane, owned by
Raul M. Juarez.
By consent agenda, Mr. Hare moved for approval of the Committee’s recommendation,
seconded by Mr. Hutchison and carried by a unanimous roll call vote (Anderson and Bonar
absent).
Annexation Request - Westerly Side of Acorn Lane, Owned by City of Dover
Mr. Scott Koenig, City Manager, reviewed a Petition to Annex and Zone Property located on the
westerly side of Acorn Lane, consisting of .075+/- acres (3,264 SF), owned by the City of Dover.
Mr. Koenig advised members that the property was part of an enclave outside the City limits. He
noted that the property was currently vacant and was proposed to be zoned R-8, should it be annexed
into the City. He explained that anything built on this land and connected to the sewer would be
subject to a per foot charge.
Staff recommended that the City proceed with annexation of the subject property.
In response to Mr. Perza, Mr. Koenig confirmed that the City owns other properties outside of the
City, such as the Cartanza Substation and various wellheads. He stated that he was unsure of the
history of the property being discussed but advised members that it was immediately adjacent to City
limits.
Mrs. Williams questioned if enclaves within the City could be bundled and brought in all at one
time. Responding, Mr. Koenig stated that he would prefer to bundle them at one time but felt that
this would be a “hostile” approach; therefore, the City had adopted a “wait and see” strategy. He
Page 3
CITY COUNCIL MEETING OF NOVEMBER 12, 2013 PAGE 3
advised members that when residents in these areas need utilities, they must request annexation. He
estimated that there were at least 50 in-fill properties within the City.
The Committee recommended annexation of the property located on the westerly side of Acorn
Lane, owned by the City of Dover.
By consent agenda, Mr. Hare moved for approval of the Committee’s recommendation,
seconded by Mr. Hutchison and carried by a unanimous roll call vote (Anderson and Bonar
absent).
Request for Abandonment of Street (Improved) - Harmony Lane
Mr. Scott Koenig, City Manager, advised members that correspondence had been received from
Mr. Russell Huxtable, Vice President, Milford Housing Development Corporation (MHDC)
proposing to consolidate parcels within the Walker Woods subdivision and renovate this
development. The letter included a request for the abandonment of Harmony Lane for a number of
reasons, many beneficial to the developer but some beneficial to the City. He explained that
Harmony Lane was an improved public street. He referred members to the table previously provided
for information regarding the existing infrastructure and the easements associated with the property.
Staff recommended: 1) abandonment of the subject right-of-way with conveyance of sixty feet (60’)
of said right-of-way to Milford Housing Development Corporation. Abandonment shall be
conditioned upon the completion of the Site Development Plan and parcel consolidation plan. Cross
access and public utility easements will be required for the existing wastewater pump station and
associated force main infrastructure located therein. Ownership shall not be relinquished until such
time as the parcel consolidation plan is recorded; 2) abandonment of all stormwater, street,
wastewater, and water infrastructure to Milford Housing Development Corporation in conjunction
with the abandonment of Harmony Lane. The City shall retain ownership of the existing pump
station and associated force main only; and 3) adoption of a resolution by Council setting a public
hearing regarding the proposed abandonment for November 25, 2013.
Responding to Mr. Blakeman’s inquiries regarding trash pick-up and snow removal, Mr. Koenig
explained that trash pick-up currently takes place in the middle of the development. He noted that
there were approximately ten 330-gallon trash containers and staff had been struggling for 20 years
with collection in this area. Under the proposed re-development, trash pick-up would be converted
to private collection using larger dumpsters and more defined areas for collection. Snow collection
beyond the right-of-way of Walker Road would also be private.
In response to Mrs. Williams, Mr. Koenig stated that, in his opinion, there would not be confusion
or conflict caused by the operation of the Milford Housing Authority in the City of Dover, where the
Dover Housing Authority also operates.
The Committee recommended: 1) abandonment of Harmony Lane with conveyance of sixty feet
(60’) of said right-of-way to Milford Housing Development Corporation. Abandonment shall be
conditioned upon the completion of the Site Development Plan and parcel consolidation plan. Cross
access and public utility easements will be required for the existing wastewater pump station and
associated force main infrastructure located therein. Ownership shall not be relinquished until such
Page 4
CITY COUNCIL MEETING OF NOVEMBER 12, 2013 PAGE 4
time as the parcel consolidation plan is recorded; 2) abandonment of all stormwater, street,
wastewater, and water infrastructure to Milford Housing Development Corporation in conjunction
with the abandonment of Harmony Lane. The City shall retain ownership of the existing pump
station and associated force main only; and 3) adoption of a resolution by Council setting a public
hearing regarding the proposed abandonment for November 25, 2013, as recommended by staff.
By consent agenda, Mr. Hare moved for approval of the Committee’s recommendation,
seconded by Mr. Hutchison and by a unanimous roll call vote (Anderson and Bonar absent),
Council adopted Resolution No. 2013-25 setting a public hearing for November 25, 2013
regarding the abandonment of Harmony Lane (Exhibit #1).
Public Notification - Power Outages
During the Utility Meeting held on September 9, 2013, members considered the existing Electric
Outage Public Notification Procedure and the Internal Standing Orders for the City’s Electric
Department. Members recommended that this matter be referred back to staff for their consideration
in implementing the comments and suggestions made by members of the Committee. During the
City Council meeting held on September 23, 2013, Council approved the Committee’s
recommendation.
During the Utility Committee meeting of October 28, 2013, Mr. Scott Koenig, City Manager,
explained that staff had investigated several options to try to remedy members’ concerns. He
indicated that staff did not recommend implementing outage management software at this time due
to the costs associated with this option but noted that it might be a viable option in the future. He
felt that the City’s system was extremely reliable and reported that the City’s annual outage statistics
for FY 2009 through FY 2013 exceeded the Delaware standard of 295 minutes per customer, set by
the Public Service Commission. He indicated that most of the outages were the result of car
accidents or animal intrusions rather than wires “burning up.”
Mr. Koenig explained that staff did not recommend using Facebook to notify customers of outages
as this would involve additional staff resources and the number of customers using this medium was
unknown. Current postings on Facebook are done by Kay Dietz-Sass, Public Affairs/Emergency
Management Coordinator, whose normal work hours are 8:00 a.m. - 5:00 p.m., Monday through
Friday; therefore, after-hours posting would incur costs through compensatory time or overtime for
her services, and at this point having Systems Operators post to Facebook had not been discussed
because they are a major part of system restoration. Mr. Koenig explained that staff would make an
effort to bring in additional staff to answer phone calls and update the phone message system when
it is believed that this is needed and that specific thresholds needed to be developed as to how this
would occur. Staff would also be evaluating the costs associated with an automated phone/push
notification system in future budgets if Council indicated an interest. He noted that reverse 911
calling had been researched previously and recalled that the installation cost was approximately
$30,000; however, he cautioned members that the electric system was extensive (approximately
50 square miles) and extends outside of the City limits. Mr. Koenig was unsure if the City should
be investing funds in this type of project, reminding members that he and staff were very proud of
the reliability of the City’s system. He wanted to be sure that information posted was accurate if
such a system were installed because inaccurate information may be worse than no information. He
indicated that staff would be looking at these types of notification systems in future budgets, but
would not plan to include it in the FY15 budget unless asked to do so by Council.
Page 5
CITY COUNCIL MEETING OF NOVEMBER 12, 2013 PAGE 5
Staff recommended authorization to call in additional resources during outages to assist with phone
calls and new phone messages to address the concerns identified by the Committee and to evaluate
an automated phone/push notification system to be considered in future budgets.
Mr. Slavin stated that notification via social media could be as easy as directing an email that is
already going to be sent out to a Twitter or Facebook account and that this could be sent from a cell
phone inside the plant and posted automatically. He suggested that very low-cost solutions that are
currently available be considered. He indicated that he would not recommend reverse 911. It was
his belief that Capital School District was using those types of calls in abundance and that people
were beginning to ignore the calls because they are receiving so many of them.
Responding to Mr. Koenig regarding the level of detail for information to be conveyed during an
outage, Mr. Slavin confirmed he was simply looking for a statement that there is an outage in a
particular area and an estimate of when it was anticipated that power would be restored.
In response to Mrs. Williams, Steven Enss, Interim Electric Director, indicated that the City’s
electric system had better reliability than both of its local counterparts.
Mr. Bonar stated that a reliability study for Delmarva Power was being conducted at the State level
and that when Delmarva Power’s forward-looking rate plan becomes effective, their threshold for
outages would drop to 175 minutes per year. He felt that the City was well ahead of the curve
compared to other commercial providers.
Mr. Slavin inquired what the costs would be to bring in additional staff and if they would be paid
an overtime rate. Mr. Koenig stated that if staff were called in they would receive overtime pay or
compensatory time at a reimbursement rate of 1.5 hours per hour. He was unsure of what the dollar
value would be.
The Committee recommended acceptance of staff’s recommendation to authorize staff to call in
additional resources during outages to assist with phone calls and new phone messages to address
the concerns identified by the Committee and to evaluate an automated phone/push notification
system to be considered in future budgets.
Mr. Blakeman noted that, in previous years, Council members had volunteered to man phones during
outages and were not compensated for their service.
Mrs. Williams stated that Council members and other City staff had worked on a volunteer basis
during several emergencies.
By consent agenda, Mr. Hare moved for approval of the Committee’s recommendation to
authorize staff to call in additional resources during outages to assist with phone calls and new
phone messages to address the concerns identified by the Committee and to evaluate an
automated phone/push notification system to be considered in future budgets. The motion was
seconded by Mr. Hutchison and carried by a unanimous roll call vote (Anderson and Bonar
absent).
Page 6
CITY COUNCIL MEETING OF NOVEMBER 12, 2013 PAGE 6
Rate Classification/Tariff Amendment for Churches
During the Utility Committee meeting held on September 23, 2013, Mr. Scott Koenig, City Manager,
reviewed a request from the Presbyterian Church of Dover (the Church) to consider a change in tariff
language for the C/C1 (Small Commercial) description. Specifically, he stated that the request was
to have the wording “or have instrument rated metering” removed from the C/C1 classification
description. At that time, members recommended that this matter be referred back to staff to
determine, if the requested change were granted, based on a possible amendment to the tariff that
would eliminate the phrase “or have instrument rated metering,” what impact it would have on the
City in terms of revenue or other unforeseen possibilities; how many customers would be impacted
(including other non-profits, churches, commercial customers, etc.); and, historically, how similar
changes had been made in the past, for a report back to the Utility Committee by no later than their
meeting scheduled for October 28, 2013. The Committee’s recommendation was approved by City
Council during their meeting held on October, 14, 2013.
During the Utility Committee meeting held on October 28, 2013, Mr. Koenig explained that the
request was related to the discussion of the C5 classification assigned to the Church. The demand
profile for the Church would allow it to be assigned to the C/C1 classification if it did not have an
instrument rated meter. Based on a “look back” period of one (1) year, it was staff’s belief that as
many as 51 customers could be reclassified if the above referenced language was removed from the
C/C1 classification. This was determined based on using an average demand of less than
3,500 kWh/month. He noted that electric use was dynamic; therefore, the actual number of
customers could vary from year to year, depending upon when the calculation was made. Using
these customers, it was estimated that such a change in the tariff language could result in a loss of
revenue of approximately $128,458.00 for this group of customers related to the demand charge.
Since electric usage is dynamic in nature, Mr. Koenig estimated the loss of revenue at between
$75,000 and $125,000 per year, based on the information available.
Staff indicated to the Church that the Green Energy Grant Fund could assist in making energy
efficiency improvements to the facility, such as replacement of the metering infrastructure. Using
the Green Energy Fund to improve the facility would achieve the same goal as amending the tariff.
The current estimate to improve the facility was less than $5,000.
Amending the tariff would have a direct financial impact on the City’s rate structure and could have
unanticipated consequences related to rates. Staff recommended against any alterations to the tariff,
unless they were altered in the context of a comprehensive rate review that was not scheduled to be
considered until future budgets.
Mr. Koenig explained that this information was relayed to Mr. Gary Patterson, Secretary of the
Trustees of the Presbyterian Church of Dover, who had asked to postpone action on this item and
was unable to attend the meeting. Mr. Koenig noted that staff offered to help church members to
fill out the grant application and shepherd them through the application process, as this would meet
the Church’s goal to become more efficient and would put the Church in a proper rate classification
for its demand profile.
Page 7
CITY COUNCIL MEETING OF NOVEMBER 12, 2013 PAGE 7
Mr. Slavin stated that he had also received a call from Mr. Patterson, who had asked for more time
for discussion between City staff and the Church. He told Mr. Patterson that he would ask for this
issue to be tabled until the first meeting in November.
The Committee tabled the matter until the Utility Committee meeting of November 12, 2013.
No further action was taken by City Council.
Quarterly Review of Utility Related to Capital Investment Plan (CIP) Electric and
Water/Wastewater (July, August, and September)
Mr. Scott Koenig, City Manager, reviewed the Capital Investment Plan (CIP) Project Tracking
Report - September 30, 2013. He noted that much work had been done to complete water, sewer and
electric projects. He assured members that staff was working diligently on these projects.
The Committee took no action.
By consent agenda, Mr. Hare moved for acceptance of the Utility Committee Report, seconded
by Mr. Hutchison and carried by a unanimous roll call vote (Anderson and Bonar absent).
LEGISLATIVE, FINANCE, AND ADMINISTRATION COMMITTEE REPORT -
OCTOBER 28, 2013
The Legislative, Finance, and Administration Committee met on October 28, 2013 with Chairman
Lynn presiding.
Request to General Assembly to Amend Title 29 - State Government - General Regulations for
State Agencies - Chapter 100 - Freedom of Information Act
Mayor Carey advised members that, in recent months, the City of Dover had been actively
negotiating the proposed sale of various pieces of land within the City limits and that, under current
law, the sale and/or lease of land owned by the City could not be discussed in executive session.
Mayor Carey indicated that he had worked with Senator Brian Bushweller to draft an amendment
to the Delaware Freedom of Information Act that would add language to allow preliminary
discussions regarding the sale or lease of publicly funded capital improvements in executive session.
Mayor Carey presented the proposed amendment to members for consideration.
In response to Mr. Shevock, Mayor Carey confirmed that the amendment would allow only
discussion of such sales and leases in executive session; however, any Council action would occur
in a public forum.
Mayor Carey reminded members that recent negotiations regarding Garrison Park were open to the
public, which restricted the City’s ability to negotiate the price for the property. He believed that this
restriction could have potentially cost the City a great deal of money.
Mr. Lynn thanked Mayor Carey for his efforts and concurred that publicly negotiating sales puts the
City in an inferior bargaining position; however, he expressed concern with the use of the term
“preliminary,” stating that this was not defined within the Code and was therefore open to
interpretation. In addition, Mr. Lynn noted his concern that the amendment would attach such sales
and leases to publicly funded capital improvements. He explained that this would not necessarily
Page 8
CITY COUNCIL MEETING OF NOVEMBER 12, 2013 PAGE 8
address situations similar to Garrison Park, as this was not a capital improvement project but a sale
of City property. Mr. Lynn suggested that the proposed amendment be sent to Deputy City
Solicitor Pepper for review and revision of the language.
Mr. Rushe questioned if other municipalities were facing this issue and whether they had addressed
Senator Bushweller. Responding, Mayor Carey indicated that no other municipalities had brought
this item forward. He stated that he brought this matter to the attention of the Delaware League of
Local Governments (DLLG) and its members were unanimously in favor of moving forward with
the amendment and were willing to write letters of support.
In response to Councilman Hutchison, Mayor Carey advised members that the DLLG had not
expressed concern regarding any other aspects of the Freedom of Information Act (FOIA).
Councilman Hutchison expressed his opinion that it would be helpful for Council to have the ability
to hold an executive session for preliminary discussion of a matter to determine a consensus for
support and to identify whether such matter warranted further discussion by Council. For example,
Mr. Hutchison stated his opinion that Council’s hands were tied with regard to discussing concerns
involving land, personnel matters, financial matters, etc. outside of a public meeting.
Mr. Bonar suggested approaching the legislature with the proposed amendments, with the DLLG’s
support, before the end of January when their session ends.
The Committee recommended supporting Mayor Carey’s efforts and issuing correspondence
endorsing the proposed request to the General Assembly to Amend Title 29 – State Government –
General Regulations for State Agencies – Chapter 100 - Freedom of Information Act, stipulating that
the proposed amendment be sent to the Deputy City Solicitor for review prior to consideration by
Council. [Clerk’s Office Note: Subsequent to the Deputy City Solicitor’s review, the proposed
Senate Bill was revised as recommended and a copy was provided to City Council.]
Mr. Hare moved for approval of the Committee’s recommendation, seconded by
Mr. Hutchison and unanimously carried.
Establishment of an Ad Hoc Committee to Study the Future of City Hall, Weyandt Hall, and
the Former Dover Public Library
Council President Bonar stated that due to the age and condition of the City’s buildings, including
the former Dover Public Library, Weyandt Hall, and City Hall, it would cost a significant amount
of money to repair or renovate them. He noted that these buildings were not handicapped accessible,
had problems with the heating, ventilation and air conditioning (HVAC) systems, etc., and were not
currently drawing any tax revenue for the City.
Mr. Bonar explained that the purpose of this Committee would be to review these issues and develop
an unbiased but educated recommendation to Council on the most fiscally responsible way to remedy
them. He noted that members would consider whether to renovate or build new structures, keeping
in mind the concept of inviting private investors to pay for the repairs or construction of a new
building which would also put the buildings back on the tax rolls. Mr. Bonar noted additional
concerns regarding security in City Hall, citing a recent incident involving an individual who posed
Page 9
CITY COUNCIL MEETING OF NOVEMBER 12, 2013 PAGE 9
a potential threat and was able to make it into the City Manager’s and Mayor’s Office. He stated that
this person was taken into custody without incident; however, he felt that this indicated that security
at City Hall and in the City Council Chambers needed to be addressed.
Mr. Bonar recommended creating an objective group to review the options and provide a
recommendation to the Legislative, Finance, and Administration Committee and ultimately to
Council. He noted that the Committee would be of no expense to the City but would provide
valuable information.
In response to Mr. Shevock, Mr. Bonar advised that once the task of the Committee was complete
it would dissolve. It would not be a standing committee.
Responding to Mr. Shevock, Mr. Bonar stated that the Committee would consist of three (3)
members of Council, and three (3) members of the general public with a background in investments
and finance, and that he, as Council President, would appoint the members.
In response to Mr. Slavin, Mr. Bonar advised that if the recommendation were passed on to Council,
additional details and specific information concerning the formation of the Committee would be
provided, including the names and backgrounds of members, the scope of the committee, etc.
Responding to Mr. Lynn, Mr. Scott Koenig, City Manager, stated that the basic groundwork and
architectural design previously approved by Council for City Hall was currently on hold pending the
potential formation of the Committee. He reminded members that further discussion and possible
recommendations regarding public/private partnerships related to City-owned buildings was
scheduled for consideration during the Special Council Meeting of October 30, 2013.
The Committee recommended the establishment of an Ad Hoc Committee to Study the Future of
City Hall, Weyandt Hall, and the Former Dover Public Library.
Mr. Hare moved for approval of the Committee’s recommendation, seconded by Mr. Dixon
and carried with Mr. Lynn voting no.
Mr. Lynn moved for acceptance of the Legislative, Finance, and Administration Committee
Report, seconded by Mr. Hare and unanimously carried.
SAFETY ADVISORY AND TRANSPORTATION COMMITTEE REPORT -
OCTOBER 30, 2013
The Safety Advisory and Transportation Committee met on October 30, 2013 with Chairman
Hutchison presiding.
Discussion - Transportation Improvement District
Mr. Scott Koenig, City Manager, advised members that, in the spring of 2013, the Delaware
Department of Transportation (DelDOT) adopted new regulations that govern how DelDOT reviews
access to State-maintained roadways. He noted that the regulations require developers to conduct
large scope traffic impact studies and complete all necessary improvements for potential
redevelopment projects along U.S. 13, resulting in a paralyzing effect on redevelopment projects
along the U.S. 13 corridor. However, the regulations also allow for DelDOT to work with
Page 10
CITY COUNCIL MEETING OF NOVEMBER 12, 2013 PAGE 10
metropolitan planning organizations and local governments to create Transportation Improvement
Districts (TIDs). Once a district is defined, an agreement is put in place and DelDOT funds a
district-wide traffic study and implementation plan. Depending on the terms of the agreement,
developers within the TID would either pay their fair share of the improvements (which would be
determined by the agreement) or construct a portion of the improvement. He noted that the
improvements identified in the TID study would receive a higher priority in the ranking of projects
in the State’s Capital Transportation Plan.
Mrs. Ann Marie Townshend, Director Planning and Community Development, advised members
that staff was seeking support from the Committee and Council to work with DelDOT to begin to
lay out a Memorandum of Understanding (MOU) for a TID that would define the scope of the
district, the geographic area, and related items and then to begin the study. She reminded members
that DelDOT would pay for this study using a pool of funds that developers had paid into for
area-wide studies rather than performing a Traffic Impact Study (TIS) for their projects.
Mrs. Townshend indicated that staff had held one (1) meeting with DelDOT to discuss the possibility
of a TID. She stated that staff felt it was important to obtain the endorsement of City Council to
engage in the process since it would take significant staff time.
Responding to Mr. Hutchison regarding the amount of staff time that would be required,
Mrs. Townshend estimated that meetings would be held bi-monthly.
In response to Mr. Davis regarding potential negative implications, Mrs. Townshend noted that the
study would define the traffic problems and the price tag of solving them, which could be “a tough
pill to swallow.” She noted that moving forward was not mandated; however, she explained that
currently projects were being undertaken in a piecemeal fashion that could cause potential large-scale
development to halt due to the massive scope of the studies required. She advised members that
developers are now required to pay an engineer to perform a large scope study, including traffic
counts and modeling, that identifies improvements that must be done, and are then expected to
contribute significantly toward the road upgrades identified. She explained that a proposed
re-development project at the former Berry Van Lines property, located at 741N. DuPont Highway,
had caused immediate engagement in this discussion with DelDOT. At a scoping meeting for this
project between DelDOT, the prospective developer, and the developer’s engineer, it was determined
that, based on the new DelDOT regulations, the developer would be required to study the impact on
all of the U.S. 13 intersections between Scarborough Road and Division Street. She felt that
developers would likely walk away from areas that the City would like to see re-developed and
projects that would help economic growth because the regulations are so onerous.
Responding to Mr. Hutchison regarding the target area to be addressed, Mrs. Townshend stated that
the Route 13 corridor through the City from Denneys Road in the north to the intersection at State
Street in the south had been discussed with DelDOT, as well as Route 113 from its intersection with
Route 13 extending to Dover Air Force Base.
Mr. Koenig indicated that the intent of the regulations was good; however, that the scoping meeting
held in regard to the former Berry Van Lines property project had identified some unintended
consequences. According to the developer who was interested in purchasing and developing this
site, the required study would cost $100,000 - $200,000.
Page 11
CITY COUNCIL MEETING OF NOVEMBER 12, 2013 PAGE 11
Mr. Koenig expressed his opinion that there was a need to define what level of traffic the City was
willing to accept as the cost of doing business. He felt that a healthy, economically vibrant City
would have traffic, especially at times when offices are closing and around large traffic areas such
as malls. He stated that if there were no cars present at 5:00 p.m. on Route 13, this would be a large
problem because it would indicate a lack of economic activity. Because an intersection fails for
30 minutes per day, he did not feel that it was appropriate to “build your way out of that,” noting that
he did not envision a fourth lane being built on U.S. 13. He questioned what would come of a
decision to “study 16 traffic signals” and wondered if all of these signals would be upgraded or if
they were being studied only because regulations direct that this occur.
Mr. Koenig advocated proceeding with the TID. He recalled that several years ago the State adopted
policies that channeled development into growth zones and that the State promised to funnel funds
to these areas. He noted that dollars had not matched up with these promises. Mr. Koenig felt that
the State should be spending money in the capital city and that this was an opportunity to engage the
State by creating a TID and using that policy framework to get the State to invest in the City. He
indicated that it was distressing for him to talk to developers who expressed interest in properties
but stated that DelDOT was preventing redevelopment. It was his belief that the TID could be a
mechanism that would overshadow some of the current DelDOT regulations and potentially help
drive dollars into the capital City, both from private investment and public dollars through DelDOT.
Mr. Koenig stated that TIDs were a relatively new concept in the State of Delaware and he was
unsure how long it would take to get through the process. He felt it important to move forward on
the re-development of U.S. 13 and other transportation corridors. He noted that a number of items
in the City’s budget were driven by growth and that revenues would not be at the levels needed for
current and future years unless growth was occurring.
Responding to Mr. Davis regarding the developer’s responsibility for funding transportation projects,
Mr. Koenig explained that currently a private developer must fund a study on the individual project’s
impact. If a TID is created, DelDOT would do a comprehensive study of the district. Developers
would then pay a fair share of related improvements that happen in the future.
In response to Mr. Davis regarding whether the City’s funds would be impacted, Mr. Koenig stated
that the City would not be committing to putting dollars into improvements or studies for private
developers since this was not the current practice.
In response to Mr. Keller, Mrs. Townshend indicated that there were approximately 18 - 20
intersections in the area proposed for the TID. She believed that if the entire corridor were not
included, there would be potential for a project just beyond the line selected and then the developer
would be required to complete a separate TIS. She noted that, as the economy was beginning to
rebound, she had talked to a number of developers who were looking at the former Playtex properties
(bound by Kings Highway, Route 8, and N. DuPont Highway); however, the traffic component of
those properties had continued to be an issue. It was her belief that any large property with good
development/re-development opportunity would encounter this problem.
Responding to Mr. Perza regarding the potential impact of the study on existing businesses,
Mrs. Townshend confirmed that it the study would be passive and involve traffic counts, modeling,
land use, etc.
Page 12
CITY COUNCIL MEETING OF NOVEMBER 12, 2013 PAGE 12
Mr. Hutchison suggested that the matter be brought before Council but that it not be placed on the
consent agenda in order to allow for discussion.
Responding to Mr. Dixon regarding the impact on Fairview Elementary School, Mrs. Townshend
stated that this location was west of the study area and would not be impacted.
Staff recommended that the City Manager and City Planner be authorized to begin negotiations with
DelDOT to create a Transportation Improvement District (TID), noting that any agreement related
to the TID would be brought before City Council in draft form prior to execution.
The Committee recommended acceptance of staff’s recommendation.
During the Council Meeting, Mrs. Townshend advised members that staff had identified the
US Route 13 and Bay Road corridors within the City limits as a potential TID and would like to
negotiate with DelDOT regarding an agreement for the District and initiate the study. She
introduced Mr. Bill Brockenbrough, representative of DelDOT’s Division of Planning.
Mr. Brockenbrough reviewed a Presentation - Transportation Improvement Districts (TIDs)
(Exhibit #2). He advised members that a TID is a geographic area defined for the purpose of
securing required improvements to transportation facilities in that area. He stated that Kent County
had identified 11 areas where it was desired to create TIDs in their comprehensive plan. In addition,
he noted that two (2) areas in northern New Castle County were operating somewhat like TIDs and
two (2) areas in southern New Castle County had been working for several years to create districts;
however, he stated that the only operating TID is in the Westown development, which is located on
the west side of Middletown. He explained that the TIDs that were proposed under the regulations
adopted this spring would differ from Westown in some ways.
Mr. Brockenbrough advised members that DelDOT created the TID regulations to serve as an
alternative to their standard TIS process. When a TID is created, a land use plan for an area is agreed
upon and a single TIS is conducted to address all expected development in that area rather than
having each development do their own. He stated that once the TID is in effect, developments that
conform to that plan will be able to skip the TIS process and pay a fee to cover their share of the
needed transportation improvements. It was estimated that this would save six (6) to 12 months over
having a TIS done, explaining that the TIS process is slow.
In addition, Mr. Brockenbrough stated that TIDs are more equitable since land use and transportation
are linked and all developments in the TID would pay based on the same formula. He stated that
with a TIS, improvements are required based on capacity available at a point in time. He explained
that a large development could use all of the available capacity at an intersection and not require any
additional improvements. A smaller development would then be required to make large
improvements to restore the capacity that was used by the previous developer. Mr. Brockenbrough
noted that such a scenario can create large inequities between adjacent developments and that the
TIDs level the playing field. He explained that once a TID is established, everyone pays the same
amount per unit, so a potential developer can estimate the infrastructure costs based on the size of
their development.
Page 13
CITY COUNCIL MEETING OF NOVEMBER 12, 2013 PAGE 13
Mr. Brockenbrough stated that the TIDs consider all aspects of transportation infrastructure, whereas
TISs are focused primarily on intersection capacity for automobiles. As such, he noted that TIDs
represent a more comprehensive approach by considering the entire streetscape, including bicycles,
pedestrians, and transit. Mr. Brockenbrough stated that TIDs have boundaries since they are
districts; however, by focusing on larger areas, TIDs will address the impact of the developments
within them more comprehensively. In addition, he stated that TIDs are more supportive of what
is often referred to as “smart growth.” TISs were created to solve the problems of an auto–oriented
suburbia and the solutions they identify often do not support walkable communities. The TID
process is much more adaptable to a specific area, so that the problems addressed and the solutions
developed are more likely to fit the area being studied.
Mr. Brockenbrough indicated that TIDs will be created in areas where the counties and
municipalities are planning for growth; Levels 1, 2 and 3 in the Strategies for State Policies and
Spending; and those locations identified in comprehensive plans. A TID begins with an agreement
between DelDOT and the local government that outlines how the parties will work together to create
and maintain the TID. Should the City of Dover be interested in creating a TID, he stated that it
would be necessary to amend the City’s Comprehensive Plan to indicate a general location of a TID
on the map.
Mr. Brockenbrough advised members that a more detailed presentation on the TID would be made
to the Delaware League of Local Governments during their meeting of November 21, 2013, at
7:30 p.m.
Responding to Mr. Hutchison, Mrs. Townshend confirmed that the areas identified by staff for a TID
included US Route 13, from the north boundary to the south boundary of the City, and Bay Road,
from the split off Route 13 to Dover Air Force Base.
Mr. Slavin moved for approval of the Committee’s recommendation to authorize the City
Manager and City Planner to begin negotiations with the Delaware Department of
Transportation (DelDOT) to create a Transportation Improvement District (TID), noting that
any agreement related to the TID would be brought before City Council in draft form prior
to execution. The motion was seconded by Mr. Lynn and unanimously carried.
Update - Dover High School Construction
Mrs. Ann Marie Townshend, Director of Planning and Community Development, advised members
that monthly coordination meetings continued regarding the construction of the new Dover High
School. She noted that those meetings had been very effective in identifying and resolving issues.
She stated that the Delaware Department of Transportation (DelDOT) was designing sidewalks on
the north side of Route 8 and would be would be acquiring related temporary or permanent
right-of-way easements. Discussions regarding the cost of the improvements were ongoing;
however, it was her belief that the Capital School District had not borne an unfair share of the cost
for transportation to access the school.
Responding to Mr. Hutchison regarding the school entrances, Mrs. Townshend stated that the School
District planned to construct the east entrance and had appeared before the Planning Commission
to obtain a waiver to allow reduction in parking areas. The parking areas would be curbed but would
Page 14
CITY COUNCIL MEETING OF NOVEMBER 12, 2013 PAGE 14
be grass so that they could be used for overflow parking. The Capital School District Board of
Education had stated that the east entrance was important to them.
Mr. Hutchison expressed appreciation for Mrs. Townshend’s efforts in this regard, as did Mr. Davis.
In response to Mr. Keller, Mrs. Townshend indicated that the east entrance would be designed and
built as a full entrance, but if the school wished to limit it to a right-in/right-out entrance they could
do so.
Mr. Keller noted his observation regarding difficulties being experienced by large vehicles coming
from the east and accessing the school at the west entrance. Responding, Mrs. Townshend explained
that the entrance and signal were designed to manage all traffic, including buses; however, issues
emerged during construction, and DelDOT and the School District were working together to see
what alterations might be needed to reconfigure this area. She was unsure if it was a design problem,
a construction issue, or a combination of both.
Briefing on Delaware Department of Transportation (DelDOT) Projects
DelDOT Repaving Project
No update was provided regarding this item.
West Dover Connector
Mr. John Gaines, Project Engineer, reviewed a rendering of the planned West Dover Connector. He
explained that the connector will start at the intersection of Route 13 and Charles Polk Road at
Rodney Village, travel in a northwesterly direction, traversing the two (2) Kesselring farms, and
terminate at the intersection of North Street and Saulsbury Road. DelDOT was currently acquiring
the right-of-way for the project. There were 14 total acquisitions on Charles Polk Road, all of which
had been purchased, 12 of the 14 properties had been razed, and a contract for the other two (2) was
awarded during the previous week, so all demolitions would be accomplished soon. Mr. Gaines
indicated that appraisals for the remaining parcels had been received and were being assigned to
acquisition agents. It was hoped that the entire right-of-way would be cleared by March. Final
construction plans were expected in approximately two (2) weeks and would be distributed through
DelDOT for comment. According to the remaining schedule, bids would be advertised in the
March/April time frame and it was hoped that construction would start late in the Summer of 2014.
Mr. Gaines noted that there were several outstanding issues with the City in regard to water/sewer
lines within Rodney Village. DelDOT was coordinating with the City to ensure that improvements
to these lines would be complete before DelDOT patches the roads and reconstructs the sidewalks
and curb line to avoid multiple disturbances in that area, and it was his understanding that the City
and DelDOT would be developing a contract in this regard. He noted that DelDOT would also be
moving fire hydrants in the area.
Mr. Gaines explained that he was also working with Mrs. Ann Marie Townshend, Director of
Planning and Community Development, on issues related to Federal Emergency Management
Agency (FEMA) mapping in connection with Puncheon Run flooding issues. He noted that, as part
of this project, DelDOT had updated the FEMA flood plain maps for the area north of New Burton
Page 15
CITY COUNCIL MEETING OF NOVEMBER 12, 2013 PAGE 15
Road and was working with the Department of Natural Resources and Environmental Control
(DNREC) in this effort. This would not increase any flows downstream where there were flooding
concerns.
Responding to Mr. Hutchison, Mr. Gaines stated that the construction that took place on South
Governors Avenue was never intended to be a cure-all for the flooding problems in that area. He
stated that the problem was that the houses were built in a flood plain. He indicated that DNREC
and the Kent Conservation District had been working with developers in the upper reaches of the
watershed on the current project. He noted that new developments, such as Eden Hill Farm and
Hidden Creek, were over-managing stormwater and were being forced to manage for 100-year
storms rather than ten-year storms. Mr. Gaines explained that this would ultimately decrease the
flow levels downstream.
The Committee recommended acceptance of the report.
By consent agenda, Mr. Hare moved for approval of the Committee’s recommendation,
seconded by Mr. Hutchison and carried by a unanimous roll call vote (Anderson and Bonar
absent).
Mr. Hare moved for acceptance of the Safety Advisory and Transportation Committee Report,
seconded by Mr. Slavin and unanimously carried.
UTILITY COMMITTEE REPORT - NOVEMBER 12, 2013
Councilwoman Williams reminded members that the Utility Committee met earlier in the evening.
Except for the following time sensitive issues, the Committee Report from November 12, 2013 will
be presented to Council during their Regular Meeting of November 25, 2013 for Council’s review
and consideration.
Engineering Design of Water Main Realignment - Denneys Road
Mr. Scott Koenig, City Manager, explained that the Delaware Department of Transportation
(DelDOT) had been upgrading a number of bridges around the State and had recently been doing
work within the City limits. He stated that an existing bridge, located on low land on Denneys Road
approaching Delaware Technical and Community College and northeast of the railroad tracks, was
installed in approximately the early 1990s and must be moved slightly to the east. He advised
members that this project would involve moving the existing water line outside of the project area.
The relocation would be necessary because of the work that DelDOT was doing to maintain a clear
zone between the utility and the new bridge work. Mr. Koenig noted that all of the engineering and
construction costs associated with the water main realignment would be reimbursable by DelDOT;
however, the City must pay costs up front. Mr. Koenig stated that this project was being brought
forward on a “fast track” to meet the State’s timeline for the bridge relocation. Staff expected the
work to move quickly and that construction would be performed in the Spring of 2014.
Staff recommended acceptance of the proposal from URS Corporation to perform engineering design
work necessary for the Water Main Realignment in Denneys Road in the amount of $33,200.
Page 16
CITY COUNCIL MEETING OF NOVEMBER 12, 2013 PAGE 16
Responding to Mr. Perza regarding the timetable on reimbursement, Mr. Koenig stated that
turnaround time is typically 90 days or less after bills are submitted to DelDOT.
In response to Mrs. Williams regarding the need for the City to pay for the project, Mr. Koenig stated
the City typically incurs these costs and then bills the State. He noted that this was in accordance
with DelDOT’s policies and that electric projects are handled the same way. He indicated that this
would be a City utility and that the City would like to control the contracts to ensure that design is
done properly.
The Committee recommended acceptance of the proposal from URS Corporation to perform
engineering design work necessary for the Water Main Realignment in Denneys Road in the amount
of $33,200, as recommended by staff.
During the Council meeting on November 12, 2013, in response to Mr. Perza, Mr. Koenig confirmed
that DelDOT would reimburse the City for both design and construction on this project once the
project is completed.
Mr. Lynn moved for approval of the Committee’s recommendation, seconded by Mr. Hare.
Noting that this issue was not an emergency, Mr. Slavin relayed concerns regarding this matter, as
well as the next agenda item, being presented to the Committee and City Council on the same night.
In addition, he noted that the work had already began by utilizing a different funding source and felt
that this should not be the City’s practice.
The motion for the acceptance of the proposal from URS Corporation to perform engineering
design work necessary for the water main realignment in Denneys Road in the amount of
$33,200 was carried by a roll call vote of six (6) yes (Dixon, Lynn, Perza, Hare, Hutchison, and
Williams), one (1) no (Slavin), and two (2) absent (Anderson and Bonar).
Kent Avenue Inflow and Infiltration Repair
Mr. Scott Koenig, City Manager, reviewed a request to authorize creation of a new Inflow and
Infiltration (I & I) project to correct issues in the Kent Avenue area. He explained that on
October 10, 2013, the City of Dover Department of Public Works received a call from the
Elizabeth W. Murphey School on Kent Avenue claiming a sanitary sewer back-up into their building.
City staff investigated the claim and found a disconnect between the sanitary sewer main in
Kent Avenue and the receiving sanitary sewer interceptor in Division Street, causing sediment to
build up and create a blockage in the Kent Avenue sewer main. The City secured a contractor to
remove the blockage at the main, allowing staff to clear the sanitary sewer lateral after considerable
effort. This allowed the customer on Kent Avenue to utilize their sanitary sewer lateral. After
additional research, staff concluded that the storm sewer was also connected to the sanitary sewer,
which is a violation of Section 110-231 of the City of Dover Code of Ordinances. The illicit
connection represents direct inflow into the sanitary sewer system. City staff further verified that
there was only one (1) customer connected to the sanitary sewer main in Kent Avenue. After
discussion with the property representative, staff provided a plan to alleviate the customer’s
problems and eliminate the illicit stormwater discharge into the sanitary sewer interceptor in
Division Street. Mr. Koenig indicated that staff estimated that the project could cost as much as
$75,000.
Page 17
CITY COUNCIL MEETING OF NOVEMBER 12, 2013 PAGE 17
Staff recommended authorizing the creation of a new Inflow/Infiltration Project to correct the issues
in Kent Avenue.
Mr. Perza inquired if the City had determined if the current property owner was responsible for the
improper hook-up. Responding, Mr. Koenig indicated that the illicit discharge resulted from the
catch basins in Kent Avenue discharging into the sewer system. He stated that the Murphey School
was not responsible and that this infrastructure was installed many years ago, probably by the City
of Dover. The problem with the sewer main was a disconnection caused by a joint that slipped out.
Mr. Koenig indicated that the only problem staff was having with the Murphey School was grease
in the line and that staff was working on correcting this with a new lateral.
The Committee recommended authorization for the creation of a new Inflow/Infiltration Project to
correct the issues in Kent Avenue.
Mr. Hare moved for approval of the Committee’s recommendation, seconded by Mr. Dixon
and carried by a roll call vote of six (6) yes (Dixon, Lynn, Perza, Hare, Hutchison, and
Williams), one (1) no (Slavin), and two (2) absent (Anderson and Bonar).
Mr. Hutchison moved for acceptance of the Utility Committee Report of November 12, 2013,
seconded by Mr. Hare and unanimously carried.
MONTHLY REPORTS - SEPTEMBER 2013
By motion of Mr. Hare, seconded by Mr. Hutchison, the following monthly reports were
accepted by consent agenda:
City Assessor’s Report
City Manager's Report
City Planner’s Report
Controller/Treasurer’s Budget Report
Economic Development Office Report
Police Chief’s Report
EVALUATION OF BIDS - MCKEE RUN UNIT 3 TURBINE REPAIRS - EG1212
At the request of Mr. Scott Koenig, City Manager, Mr. Vince Scire of NAES Corporation, Plant
Manager of McKee Run Generating Station, reviewed the evaluation of bids for the McKee Run Unit
3 Turbine Repairs. He advised members that the project was intended to perform inspections and
repairs to the McKee Run Unit 3 Turbine, to be completed during the scheduled upcoming spring
outage on that Unit. He advised members that the Unit had not been inspected since the year 2000;
therefore, it was imperative that an inspection be accomplished to make sure the condition is
acceptable for future operation. Included in the inspection would be a full disassembly and
inspection of the turbine. Replacement of the 9th stage turbine blades was recommended during the
last inspection in 2000 and was planned, with the blades and other materials being purchased in
advance. As part of that inspection, typical wear components such as seals, bearings, and stationary
steam flow path components would be inspected and evaluated for continued service. Ultrasonic
diagnostic testing of highly stressed components, such as rotors and flow nozzles, would be
Page 18
CITY COUNCIL MEETING OF NOVEMBER 12, 2013 PAGE 18
completed. This contract work represented the majority of work to be performed on this project with
the remaining scope to include procurement of materials and other specialty services such as
insulation repairs.
Mr. Scire indicated that a Request for Proposal (RFP) package was advertised according to the City
purchasing policy and NAES purchasing policy. The proposals were evaluated by NAES using cost,
experience, and bid completeness. It was determined that the bidder with the highest evaluated score
was HPI Mechanical Services. In addition, HPI Mechanical Services provided the lowest evaluated
bid. Members were provided a summary of the evaluation scores and pricing.
Based upon the evaluation prepared by NAES, staff recommended awarding the contract to the low
bidder (including price adjustments) to HPI Mechanical Services, for $769,227.17. It was noted that
the portion of the project budget for this work was $783,000.
Responding to Mr. Lynn, Mr. Scire explained that the evaluation scores and pricing of the proposals
included an adjustment, which represented additional man hours for the normal inspection findings
that would need to be resolved before putting the machine back together. He confirmed that it was
anticipated that an additional $49,000 may be necessary based on their assessment of the condition.
However, he advised members that there were no assurances regarding the condition of a machine
that had not been inspected since the year 2000.
Mr. Scire indicated that this project would involve a 12-week outage, noting that disassembling the
unit would take approximately seven (7) days. Should there be additional expenses over and above
the $49,000, he stated that it would be necessary to present the issues to City Council for
consideration within a very short timeframe.
In response to Mr. Slavin regarding the disparity in the bids, Mr. Scire stated that the bid from
General Electric was the most expensive in term of labor rates, particularly for technical staff, at a
rate of two (2) to three (3) times higher than their competitors. In regard to some of the other
proposals, he stated staff’s opinion that since the company lacked experience with this particular
style of machine, they may have escalated their bids based on the fact that they would be on a
learning curve.
Mr. Lynn moved for approval of staff’s recommendation to award the contract to the low
bidder (including price adjustments) to HPI Mechanical Services, for $769,227.17. The motion
was seconded by Mr. Slavin and carried by a unanimous roll call vote (Anderson and Bonar
absent).
EVALUATION OF BIDS - TRAILER MOUNTED STANDBY EMERGENCY GENERATOR
Mr. Scott Koenig, City Manager, reminded members that the 2006 Water Master Plan identified a
generator purchase in the water utility for emergency backup power to the City’s large water
production wells. He explained that the use of this generator would provide operational flexibility
when an emergency arises that causes power failure and that the generator had been sized to work
at three (3) different production wells throughout the City.
Page 19
CITY COUNCIL MEETING OF NOVEMBER 12, 2013 PAGE 19
Mr. Koenig advised members that bids were solicited and that only one (1) bid was received from
FM Generator, Inc., in the amount of $61,503 for the purchase of a trailer mounted generator, at a
cost of $58,968, and an optional 5-year warranty, at a cost of $2,535. He assured members that the
price was fair and consistent with the approved budget.
Staff recommended purchasing the Trailer Mounted Generator with the optional five (5) year
warranty from FM Generators, Inc. in the amount of $61,503.
Mr. Slavin moved for approval of staff’s recommendation, seconded by Mr. Dixon and carried
by a unanimous roll call vote (Anderson and Bonar absent).
APPOINTMENTS RECOMMENDED BY COUNCIL PRESIDENT BONAR - AD HOC
FINANCIAL AND OPERATIONAL ADVISORY COMMITTEE - ONE (1) YEAR TERM
TO EXPIRE NOVEMBER 10, 2014
Councilwoman Williams advised members that Council President Bonar had recommended the
appointment of Councilman James Hutchison, Mr. D. Wayne Holden, Mr. Russell T. Larson,
Dr. Cynthia Newton, and Mr. Chris Smith to the Ad Hoc Financial and Operational Advisory
Committee. These appointments would be for one (1) year terms to expire November 10, 2014. As
a reminder, Councilwoman Williams stated that the Committee would consist of five (5) members
that would advise the Legislative, Finance, and Administration Committee, who would in turn advise
City Council as a whole on operations, financial issues, and organizational structure within the City
of Dover. She noted that members need not be residents of the City of Dover, but must have
demonstrated financial, business, and organizational abilities that would enhance the operation of
the Committee and that the members shall serve without compensation.
Mr. Slavin moved for approval of the appointment of Councilman James Hutchison,
Mr. D. Wayne Holden, Mr. Russell T. Larson, Dr. Cynthia Newton, and Mr. Chris Smith, as
recommended by Council President Bonar. The motion was seconded by Mr. Hutchison and
unanimously carried.
Mr. Hutchison moved to hold discussion pertaining to the responsibilities and focus of the
committee, seconded by Mr. Hare.
Mr. Slavin suggested that this discussion take place following the return of Council President Bonar.
Concurring, Mr. Hare suggested that the Committee also be allowed the opportunity to have input.
Mrs. Williams suggested that those with suggestions or concerns regarding the structure or charge
of the ad hoc committee communicate them to Council President Bonar before the next meeting.
Mr. Hutchison withdrew the motion.
COUNCIL AND COMMITTEE MEETINGS - HOLIDAY SCHEDULE
Councilwoman Williams reminded members that, as members had done in the past due to the
holiday season, it was recommended that the Utility and Legislative, Finance, and Administration
Committee Meetings and the Council Meeting scheduled for December 23rd be cancelled, as well
as the Safety Advisory and Transportation Committee meeting scheduled for December 25th. She
assured members that should the need arise, Special Meetings would be called.
Page 20
CITY COUNCIL MEETING OF NOVEMBER 12, 2013 PAGE 20
Mr. Hare moved for approval of the recommendation to cancel the December 23, 2013 Utility
and Legislative, Finance, and Administration Committee Meetings and Council Meeting, as
well as the December 25, 2013 Safety Advisory and Transportation Committee Meeting. The
motion was seconded by Mr. Lynn and carried with Mr. Perza voting no.
COUNCIL MEMBERS’ ANNOUNCEMENTS
Mr. Hare announced that Parke Greene Galleries, a new art gallery, had opened at the old Golden
Fleece Tavern location earlier in the day and that during his visit there, the proprietors had invited
everyone to try to stop by after the meeting.
Mr. Slavin moved for adjournment, seconded by Mr. Hutchison and unanimously carried.
Meeting adjourned at 8:12 p.m.
TRACI A. McDOWELL
CITY CLERK
All orders, ordinances, and resolutions adopted by City Council during their Regular Meeting of
November 12, 2013, are hereby approved.
CARLETON E. CAREY, SR.
MAYOR
/TM/jg
S:\AGENDAS-MINUTES-PACKETS\Council-Minutes\2013\11-12-2013.wpd
Exhibit
Exhibit #1 - Resolution No. 2013-25 - Setting a Public Hearing - Abandonment of Harmony Lane
Exhibit #2 - Presentation - Transportation Improvement District
Page 21
EXHIBIT #1
Regular Council Meeting of 11/12/2013
Page 25
EXHIBIT #2
Regular Council Meeting of 11/12/2013
Transportation Improvement
Districts (TIDs)
EXHIBIT #2
Presentation to Dover City Council
November 12, 2013
Regular Council Meeting of 11/12/2013
1
Page 26
What is a TID?
“A geographic area defined for the purpose of
securing required improvements to
transportation facilities in that area.”
- Section 1.5 of DelDOT’s Standards and Regulations for Subdivision Streets and State Highway Access
2
Page 27
Why Create TIDs?
• Desire to do Things Better
• More Equitable
• Predictable
• Link Land Use and Transportation
• Look at all aspects of Transportation
Infrastructure
• Comprehensive Approach
• Ability to Incorporate Smart Growth Principles
Page 28
Where will we create TIDs?
• Where the counties
and municipalities are
planning for growth
• Levels 1, 2 and 3 in the
Strategies for State
Policies and Spending
• Locations identified in
Comprehensive Plans
4
Page 29
How will TIDs work?
A TID will begin with an agreement, a “TID Agreement.”
5
Page 30
Next Steps
• Hear more at the League of Local
Governments meeting – November 21, 2013
• Commit to creating a TID by amending the
Comprehensive Plan
• Establish a TID Agreement with DelDOT
• Begin working with DelDOT staff to create a
Land Use and Transportation Plan
Page 31
Thank You!
Please contact Bill Brockenbrough at 760-2109
or thomas.brockenbrough@state.de.us with
questions or comments.
View DelDOT’s TID regulations at
http://www.deldot.gov/information/pubs_forms/revisi
ons_to_ASR/121115TrafficImpactStudiesDraftRegulatio
nAmendment.pdf
7