Page 1
ATTACHMENT #1
SA&T Committee Meeting of 10/23/2007
DE 8 Concept Plan and
Operations Study
Dover Safety Advisory and
SA&T Committee Meeting of 10/23/2007
Transportation Committee
October 23, 2007
ATTACHMENT #1
Page 2
Purpose
Develop a concept plan describing the aesthetic qualities of
the corridor as a gateway to Dover
Analyze and recommend improvements to address current
and future operational problems
Create an action plan to address future growth in the
corridor and the associated transportation impacts.
Develop a document that DelDOT can use to start the
project development process for implementing
recommendations
Delaware 8 Concept Plan and Operations Study
Page 3
Study Limits
Delaware 8 Concept Plan and Operations Study
Page 4
Methodology
Establish Existing Conditions
Conduct Traffic Analysis
Develop a Purpose and Need Statement
Develop Concepts and Alternatives
Prepare a Technical Memorandum
Delaware 8 Concept Plan and Operations Study
Page 5
Steps Completed to Date
Establish Existing Conditions – Data
Collection
– Traffic Counts
– Transit Ridership
– Crash Data
– Environmental Resources
– Cultural Resources
– Land Use Inventory
Delaware 8 Concept Plan and Operations Study
Page 6
Traffic Analysis
Delaware 8 Concept Plan and Operations Study
Page 7
Crash Analysis
Delaware 8 Concept Plan and Operations Study
Page 8
Transit Needs
Delaware 8 Concept Plan and Operations Study
Page 9
Cultural Resources
Delaware 8 Concept Plan and Operations Study
Page 10
Future Land Development
Delaware 8 Concept Plan and Operations Study
Page 11
Future Traffic Analysis
Delaware 8 Concept Plan and Operations Study
Page 12
Alternatives Analysis
Improvements included in all alternatives:
– Realign Artis Dr. to 90º intersection
– Two access points to proposed high school
– New road connectors: to Hazlettville Rd., Artis Dr. and Chestnut
Grove Rd
– Change to protected-only left turn signals
– Add eastbound right turn storage lane at Mifflin Rd.
– Add on-road bike lane through all intersections
– Add six foot shoulders from Saulsbury Rd. to Gibbs Dr.
– Install cross walks, handicap ramps and pedestrian signals at all
signalized intersections
– Improve existing shared use path on north side of DE 8 and extend
from Kenton to Mifflin Rd.
– New connection McDonald’s and Arby’s
– Add outside shoulders on DE 8 from Mifflin to Saulsbury
– Incorporate landscaping and streetscaping elements into plan
Delaware 8 Concept Plan and Operations Study
Page 13
Alternatives Analysis
Improvements Considered – Two Alternatives:
– Shared-use path vs. sidewalks from Artis Dr. to Mifflin
Rd.
– Landscaped median vs. center turn lane from west of
Mifflin Rd to Saulsbury Rd.
– Widening the Kenton Rd. intersection vs. connector to
Independence Blvd.
– Widening the Saulsbury Rd. intersection vs. additional
connector roads on the south side of DE 8
– Roundabout vs. traffic signal at DE 8 and Weston Dr.
– Do nothing (no-build)
Delaware 8 Concept Plan and Operations Study
Page 14
Preferred Alternative
All common improvements
Reconfigure entrance to Brandywine Apartments
Pedestrian crossing at Forest Street
Shared-use path from Artis Dr. to Mifflin Rd.
Landscaped median from Mifflin Rd to Saulsbury Rd.
Connector Kenton Rd. to Independence Blvd.
Widening the Saulsbury Rd. intersection and additional
connector roads on the south side of DE 8
Traffic signal at DE 8 and Weston Dr
Delaware 8 Concept Plan and Operations Study
Page 15
Implementation Plan
Develop Memorandum of Understanding
between Dover, DelDOT and Kent County
Develop Early Action Contracts
Submit Projects to DelDOT for Funding
Delaware 8 Concept Plan and Operations Study
Page 16
Next Steps
Agency and Public Review
Incorporate Comments and Changes
Issue Report
Begin Implementation
Delaware 8 Concept Plan and Operations Study