Page 2
City Clerk Report – 2003 Update
Space Plan for City Buildings
Update on Space Plan Performed
Council Minutes 11/10/2003
By Cornerstone Partners, Inc.
1991
Exhibit 2
Page 3
City Hall - Police - Warehouse - Weyandt Hall
Included in 1991 Study
• Lots of Information was provided in 1991 Study:
• Current and Projected Requirements;
• Structural Soundness and Adaptability;
• Flexibility and Viability of Mechanical and Electrical Systems;
• And Code and Special Regulatory Requirements.
• Program of Space Requirements To Meet:
» Current Needs
» The needs in 5-10 Years
» And needs for 25 Years in the Future
• Analyzed Options, Costs, and Plan for Phasing to Meet the
City’s Requirements (costs inflated to mid 1993)
Page 4
Recommendations (1991)
Police Station
• Police Station √
– Total gsf Needed: 36,100
– Current Available: (16,500)
– Total New gsf: 19,600
• Estimated Cost $3.6 Million
» COMPLETED PROJECT
Page 5
Recommendations (1991)
City Hall/Administrative Annex
• City Hall/Administrative Annex
– Total gsf Needed: 36,400
– Current Available: (17,800)
– Total New gsf: 18,200
• Estimated Cost $2.9 Million
– Includes $1.6 M for new wing. New
wing would not be necessary if all of
Weyandt Hall (2nd and 3rd floors) was
utilized by City.
Page 6
Recommendations (1991)
Warehouse
• Warehouse √
– Total gsf Needed: 8,300
– Current Available: (4,700)
– Total New gsf: 3,700
• Estimated Cost $529,000
– Needs have been met with
purchase of “Pear Street
Warehouse”
Page 7
Recommendations (1991)
Weyandt Hall
• Weyandt Hall
– Total gsf: 24,000
• 6,000 gsf per floor (4 floors –
including basement)
• Estimated Cost $412,000
Page 8
Space Needs – Status of Projects
• √ Police Station - Space Needs Completed
• City Hall/Administrative Annex
• Problems found at City Hall:
– Overcrowding
– Age
– Code Deviations
» Elevator does not meet handicap standards
» Single fire stair does not meet current codes
– Unsuitability of Buildings for Current Tasks
» Caucus Room inadequate for any but small meetings
• √ Warehouse - Space Needs Completed
• Weyandt Hall
Page 9
Total Space Requirement
City Administration
• 36,400 gsf Projected Requirement for City
Hall/Administrative Annex Building. With
acquisition of Weyandt Hall, the City’s
resources are as follows:
• City Hall 7,300
• Administrative Annex 10,500
• Weyandt Hall 24,000
• TOTAL AREA 41,800
Page 10
Disposition of Departments
Study Recommendations
• CITY HALL
– First Floor
• Council Chambers
• Council Library/Small Conference Room
(existing Caucus Room)
– Second Floor
• Mayor’s Office
• City Manager’s Office
• Assistant City Manager
Page 11
Disposition of Departments
(continued)
• CITY HALL ADMINISTRATIVE ANNEX
– First Floor
• City Council Large Caucus Room
• City Clerk
• Human Resources
Page 12
Disposition of Departments
(continued)
• WEYANDT HALL
– Basement √
• Information Technology Department
• General Storage
• Employee’s Lunch Room
– First Floor √
• Administrative Services
• Tax Assessor’s Office
Page 13
Disposition of Departments
(continued)
• WEYANDT HALL • WEYANDT HALL
– Second Floor (Alt 1) – Second Floor (Alt 2)
• Planning • Public Works
• Shared Spaces (except Inspectors)
(Conference Rooms) • Planning
• Expansion Area (except Fire Marshall and
– Third Floor (Alt 1) Inspectors)
• Public Works – Third Floor (Alt 2)
• Finance • Finance
• Shared Spaces • Public Works Inspectors
(Conference Rooms) • Planning Fire Marshall and
Inspectors
Page 14
Weyandt Hall Leases
Second and Third Floors
– Second Floor
– State of Delaware – Coastal Mgmt (Suite 201)
» Lease Renewed 2/1/2002 - Expires 1/2005
– State of Delaware – DNREC (Suite 200)
» Lease Renewed 2/1/2003 - Expires 1/2005
– Third Floor
– Delaware Bankers Association (Suite 300)
» Lease Renewed 7/1/2003 - Expires 6/2005
– Holfeld Becker (Suite 315)
» Lease Renewed 3/1/2000 - Expires 2/2005
– State of Delaware – Soil & Water District (Suite 305)
» Lease Renewed 2/1/2002 - Expires 1/2005
»Leases of Weyandt Hall Managed through Finance Director/Treasurer
Page 15
Cost Analysis
(utilizing study costs – mid 1993)
• City Hall
• $2.9M less $1.6M for new wing no longer needed if Second
and Third Floors of Weyandt Hall utilized
» REVISED TOTAL FOR CITY HALL - $1.3
• Weyandt Hall
• $412,000 which included costs for reconstruction, paint,
carpet, modifications to HVAC system, wiring, electrical
improvements, etc. of First Floor and Basement Area which
has been accomplished.
(It should be noted that the estimated costs include items that may have been upgraded
– also, there may be additional upgrades necessary since the study was completed.)