ATTACHMENT #1
Joint Committee Meeting of 12/11/2006
City of Dover
Electric Revenue Fund
Budget & Electric Rate Review and Recommendations
December 11, 2006
1
Page 2
2
Page 3
Electric Revenue Fund
Revenue, Expense & Margin Trends
3
Page 4
Electric Revenue Fund
Debt Requirements (in 000’s)
4
Page 5
Electric Revenue Fund
Transfers as a Percentage of Fund Revenue
5
Page 6
Electric Revenue Fund
Revenue & Transfer Trend – General & Electric Funds
6
Page 7
Electric Revenue Fund
Annual Kilowatt Hour Sales Trend
7
Page 8
Electric Revenue Fund
Monthly Kilowatt Hour Sales Trend
8
Page 9
9
Page 10
Electric Revenue Fund
Future Debt Requirement
Current Capital Project Plan $44.5M (excluding vehicles & plant)
Planned bond issue in 2008 - $20.0M
Increased debt service therefore increases margins to cover covenant
10
Page 11
Electric Revenue Fund
Assumptions Across All Alternatives
Net Margin positive in all years
Debt Service Coverage is greater than 1.25 in all years
2008 – 2011 includes $3.0M to partially fund capital
projects
2008 – 2011 includes 6.5% transfer to General Fund
2008 – 2011 assumes power supply and Pace
Management Fee stays at $84 megawatt hour
Pace Incentive Fee of $1.24 mgw in all years
Net Expense of Plant stays $3.9M in all years
11
Page 12
Electric Revenue Fund
Alternative 1
Rate increase in January 2007
– 21%; No rate increase in
July 2007;
Sales of emission credits as
estimated by PACE Global
Duke Rebate – estimate
provided by Duke
Interest on reserves not
included in earlier forecast
Plant budget reduction for
FY07 as provided by NAES
Additional Margin $3.4M
12
Page 13
Electric Revenue Fund
Alternative 1 – Revenue, Expense & Margin Projections
13
Page 14
Electric Revenue Fund
Alternative 2
Rate increase in January 2007
– 8%; Rate increase in July
2007 – 12%;
Sales of emission credits as
estimated by PACE Global
Duke Rebate – estimate
provided by Duke
Interest on reserves not
included in earlier forecast
Plant budget reduction for
FY07 as provided by NAES
Additional Margin $3.3M
14
Page 15
Electric Revenue Fund
Alternative 2 – Revenue, Expense & Margin Projections
15
Page 16
Electric Revenue Fund
Alternative 3
Rate Increase in January 2007
– 8%; Rate increase in July
2007 – 12%;
Budget reductions – Transfer
to General Fund $1.8M;
Operating Exp. $.9M;
Additional Revenue – Electric
Fund $2.7 (reserve interest,
FY06 Est. Duke Rebate, &
Emission Credits)
Net Margin Increase - $5.4M
16
Page 17
Electric Revenue Fund
Alternative 3 – Revenue, Expense & Margin Projections
17
Page 18
Electric Revenue Fund
Alternative 4
Rate increase in January 2007
– 3%; Rate increase in July
2007 – 17%
Budget reductions – Transfer
to General Fund $1.8M;
Operating Exp. $.9M;
Additional Revenue – Electric
Fund $2.7 (reserve interest,
FY06 Est. Duke Rebate, &
Emission Credits)
Net Margin Increase - $5.4M
18
Page 19
Electric Revenue Fund
Alternative 4 – Revenue, Expense & Margin Projections
19
Page 20
Electric Revenue Fund
Alternative 5
No rate increase January
2007; Rate increase July 2007
– 21%;
Budget reductions – Transfer
to General Fund $3.7M;
Operating Exp. $.9M;
Reductions in service and
layoffs;
Additional Revenue – Electric
Fund $2.7 (reserve interest,
FY06 Est. Duke Rebate, &
Emission Credits)
Net Margin Increase $7.3M
20
Page 21
Electric Revenue Fund
Alternative 5 – Revenue, Expense & Margin Projections
21
Page 22
Electric Revenue Fund
Recap of Alternatives – Covenant & Rate Increase
22
Page 23
23
Page 24
Electric Revenue Fund
Rate Impact – Samples by Customer Class
For Scenarios 2 & 3
24
Page 25
Electric Revenue Fund
Rate Impact – Samples by Customer Class
Scenario 4
Scenario 4 rates were not received from the
Consultant in time for inclusion in the packet.
We will forward this slide as soon as available.
25